JP2016000941A - Reinforcing bar arrangement jig - Google Patents

Reinforcing bar arrangement jig Download PDF

Info

Publication number
JP2016000941A
JP2016000941A JP2014121616A JP2014121616A JP2016000941A JP 2016000941 A JP2016000941 A JP 2016000941A JP 2014121616 A JP2014121616 A JP 2014121616A JP 2014121616 A JP2014121616 A JP 2014121616A JP 2016000941 A JP2016000941 A JP 2016000941A
Authority
JP
Japan
Prior art keywords
bar arrangement
bar
roller
arrangement jig
jig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2014121616A
Other languages
Japanese (ja)
Other versions
JP6238075B2 (en
Inventor
大伍 岡本
Daigo Okamoto
大伍 岡本
喜英 杉本
Yoshihide Sugimoto
喜英 杉本
哲哉 池谷
Tetsuya Iketani
哲哉 池谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2014121616A priority Critical patent/JP6238075B2/en
Publication of JP2016000941A publication Critical patent/JP2016000941A/en
Application granted granted Critical
Publication of JP6238075B2 publication Critical patent/JP6238075B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a reinforcing bar arrangement jig capable of efficiently arranging a main reinforcement of a half PCa beam and other reinforced concrete members, for curtailing a construction period and reducing man-hours.SOLUTION: A reinforcing bar arrangement jig A is used for arranging a main reinforcement of a reinforced concrete member, and includes: a shaft bearing part 10 extending in a vertical direction A; a roller part 11 having an end connected to the shaft bearing part 10, the connection being rotatable around a rotation axis O1 extending in a horizontal direction T2; a lifting holding part 13 connected directly or indirectly to the shaft bearing part 10 and extended upward, the lifting holding part having a grip 12 to be held by an operator; and a locking part 14 installed integrally with the shaft bearing part 10 or the lifting holding part 13, above the roller part 11 leaving an interval, the locking part being hooked on a shear reinforcement for locking the reinforcing bar arrangement jig A.

Description

本発明は、主筋を配筋する際に用いる治具に関する。   The present invention relates to a jig used when arranging main bars.

従来、施工の合理化、生産性、工期短縮などの多くの利点を有することから、予め下筋をコンクリートに埋設して形成し、PCa化したハーフPCa梁(鉄筋コンクリート部材)が高層建物などを構築する際に多用されている。   Conventionally, it has many advantages such as rationalization of construction, productivity, and shortening of construction period. Therefore, the half PCa beam (reinforced concrete member) that has been pre-embedded in concrete under concrete and made into PCa constructs high-rise buildings. It is often used.

また、このハーフPCa梁は、上筋(上側の主筋)を仮留めした状態で柱上に架け渡すように設置され、柱上の所定位置に設置した状態で、上筋を外し、横引きしながら所定位置に配筋する(例えば、特許文献1、特許文献2参照)。そして、型枠を設置し、上筋を埋設し下側コンクリートと一体化するように上側コンクリートを打設することにより、梁部材が形成される。   In addition, this half PCa beam is installed so as to be bridged on the column with the upper bar (upper main bar) temporarily fixed, and in the state where it is installed at a predetermined position on the column, the upper bar is removed and laterally pulled. However, the bar is arranged at a predetermined position (see, for example, Patent Document 1 and Patent Document 2). Then, the beam member is formed by installing the formwork and placing the upper concrete so that the upper reinforcement is embedded and integrated with the lower concrete.

特公昭49−44723号公報Japanese Patent Publication No.49-44723 特開2005−188076号公報JP 2005-1888076 A

しかしながら、従来、上記のようにハーフPCa梁1を柱上に設置し、梁主筋の上筋2を配筋する際に、例えば、図5に示すように、4、5人の作業者が150mmピッチ程度で配設されたスターラップ(せん断補強筋)3の中に手を入れ、上筋2をスライドさせて配筋する必要があった。このため、常に鉄筋を保持しつつ作業者全員が息を合わせ、大重量の上筋2を人力で移動させる必要があり、作業者に大きな負担が生じ、この上筋2の配筋作業に多くの時間と労力を要していた。   However, conventionally, when the half PCa beam 1 is installed on the column as described above and the upper bar 2 of the beam main bar is arranged, for example, as shown in FIG. It was necessary to place a hand in the stirrup (shear reinforcement) 3 arranged at a pitch and slide the upper reinforcement 2 to arrange the bars. For this reason, it is necessary for all workers to breathe while always holding the reinforcing bar, and to move the heavy upper muscle 2 by human power. This causes a heavy burden on the worker, and this is often involved in the work of arranging the upper muscle 2. Time and effort.

本発明は、上記事情に鑑み、ハーフPCa梁などの鉄筋コンクリート部材の主筋を効率的に配筋することができ、工期の短縮、人工の削減を図ることを可能にする配筋用治具を提供することを目的とする。   In view of the above circumstances, the present invention provides a bar arrangement jig that can efficiently arrange main bars of a reinforced concrete member such as a half PCa beam, shorten the work period, and reduce artificial man-hours. The purpose is to do.

上記の目的を達するために、この発明は以下の手段を提供している。   In order to achieve the above object, the present invention provides the following means.

本発明の配筋用治具は、鉄筋コンクリート部材の主筋を配筋する際に用いる配筋用治具であって、上下方向に延びる軸受け部と、水平方向に延びる回転軸周りに回転自在に一端を前記軸受け部に接続して設けられたローラー部と、前記軸受け部に直接的あるいは間接的に繋がって上方に延設されるとともに、作業者が把持する取っ手を備えた引上げ把持部と、前記ローラー部の上方に間隔をあけ、前記軸受け部あるいは前記引上げ把持部に一体に設けられ、せん断補強筋に引っ掛けて配筋用治具を係止するための係止部とを備えていることを特徴とする。   The bar arrangement jig of the present invention is a bar arrangement jig used when the main reinforcing bar of a reinforced concrete member is arranged, and has a bearing portion extending in the vertical direction and an end that is rotatable around a rotation axis extending in the horizontal direction. A roller part provided by connecting to the bearing part, a pulling grip part provided with a handle that is directly or indirectly connected to the bearing part and extends upward, and gripped by an operator, There is an interval above the roller portion, and is provided integrally with the bearing portion or the pulling grip portion, and includes a locking portion that is hooked on a shear reinforcing bar to lock the bar arrangement jig. Features.

また、本発明の配筋用治具においては、前記軸受け部の下端側に前記ローラー部から所定の長さで下方に突出する突出部が設けられ、前記ローラー部の他端に水平方向に延びる回転軸周りに回転可能に接続して下方に突出する突出支持部が設けられていることが望ましい。   Further, in the bar arrangement jig according to the present invention, a protruding portion that protrudes downward from the roller portion by a predetermined length is provided on the lower end side of the bearing portion, and extends in the horizontal direction at the other end of the roller portion. It is desirable to provide a projecting support portion that is rotatably connected around the rotation axis and projects downward.

本発明の配筋用治具においては、鉄筋コンクリート部材の主筋を配筋する際に、ローラー部と係止部の間の鉄筋挿入開口を通じ、主筋がローラー部上に配されるように配筋用治具を設置する。   In the bar arrangement jig of the present invention, when the main reinforcing bar of the reinforced concrete member is arranged, the main reinforcing bar is arranged on the roller part through the reinforcing bar insertion opening between the roller part and the locking part. Install the jig.

ローラー部上に主筋を配置した後に、作業者が引上げ把持部の取っ手を持って配筋用治具を引き上げたり、下げることで、主筋を容易に上下に移動させることができる。そして、作業者が配筋用治具を主筋とともに引き上げ、係止部をせん断補強筋に係止させると、主筋を所定の高さ位置に配した状態で配筋用治具を保持することができる。   After the main bar is arranged on the roller part, the main bar can be easily moved up and down by the operator pulling up or lowering the bar arrangement jig with the handle of the pull-up grip part. Then, when the operator pulls the bar arrangement jig together with the main bar and locks the locking portion to the shear reinforcement bar, the bar arrangement jig can be held in a state where the main bar is arranged at a predetermined height position. it can.

また、主筋がローラー部上に設けられているため、作業者が主筋を一方向に押し引きすることにより、容易に且つ円滑に主筋を横引きして所定位置に配置することができる。   In addition, since the main bar is provided on the roller portion, the operator can easily and smoothly pull the main bar horizontally and arrange it at a predetermined position by pushing and pulling the main bar in one direction.

これにより、この配筋用治具の鉄筋コンクリート部材の主筋の配筋時に使用することで、例えば、配筋作業を2、3人の作業者で行うことが可能になり、従来と比較し、人工を減らすことができる。   As a result, it is possible to perform, for example, two or three workers by arranging the main reinforcement of the reinforced concrete member of this reinforcing bar jig. Can be reduced.

また、ローラー部が回転するため、押し引きする単純動作で主筋を所定位置に移動することができ、且つ少ない作業者で作業を行えるため、息を合わせやすく、容易に且つ円滑に配筋作業を行うことが可能になる。さらに、せん断補強筋に係止部を引っ掛けるだけで主筋を保持でき、従来のように、持ち上げた主筋を作業者が保持している必要がない。また、配筋時に上下に動く力が必要ない、あるいは少なくすることができるため、作業者が体勢を乱すことがなく、効率的に配筋作業を行うことができる。   In addition, since the roller part rotates, the main bar can be moved to a predetermined position with a simple operation of pushing and pulling, and the work can be performed with a small number of workers, so that the breathing is easy to adjust, and the bar arrangement work can be performed easily and smoothly. It becomes possible to do. Furthermore, it is possible to hold the main bar simply by hooking the locking portion on the shear reinforcement bar, and there is no need for the operator to hold the lifted main bar as in the prior art. Moreover, since the force to move up and down is not necessary or can be reduced at the time of the bar arrangement, the operator can perform the bar arrangement work efficiently without disturbing the posture.

よって、本発明の配筋用治具によれば、鉄筋コンクリート部材の主筋を効率的に配筋することができ、且つ作業者の負担を大幅に低減することができ、工期の短縮、人工の削減を図ることを可能になる。   Therefore, according to the bar arrangement jig of the present invention, the main reinforcement of the reinforced concrete member can be efficiently arranged, and the burden on the operator can be greatly reduced, the construction period is shortened, and the artificial reduction is achieved. It becomes possible to plan.

本発明の一実施形態に係る配筋用治具を示す正面図である。It is a front view which shows the jig for bar arrangement which concerns on one Embodiment of this invention. 本発明の一実施形態に係る配筋用治具を示す斜視図である。It is a perspective view which shows the jig for bar arrangement which concerns on one Embodiment of this invention. 本発明の一実施形態に係る配筋用治具を示す斜視図である。It is a perspective view which shows the jig for bar arrangement which concerns on one Embodiment of this invention. 本発明の一実施形態に係る配筋用治具を用いてハーフPCa梁の上筋(鉄筋コンクリート部材の主筋)を配筋している状態を示す図である。It is a figure which shows the state which has arranged the upper reinforcement (the main reinforcement of a reinforced concrete member) of a half PCa beam using the reinforcement jig | tool which concerns on one Embodiment of this invention. ハーフPCa梁の上筋を配筋する従来の配筋作業を示す図である。It is a figure which shows the conventional bar arrangement work which arranges the upper bar of a half PCa beam.

以下、図1から図4を参照し、本発明の一実施形態に係る配筋用治具について説明する。ここで、本実施形態は、ハーフPCa梁を柱上に設置した段階で、このハーフPCa梁の上筋を少ない作業者で効率的に配筋することを可能にする配筋用治具(ハーフPCa梁の上筋配筋用治具)に関するものである。   Hereinafter, with reference to FIGS. 1 to 4, a bar arrangement jig according to an embodiment of the present invention will be described. Here, in the present embodiment, at the stage where the half PCa beam is installed on the column, the bar arrangement jig (half half) that enables the upper bar of the half PCa beam to be efficiently arranged by a small number of workers. This relates to the upper bar arrangement jig for the PCa beam.

そして、本実施形態の配筋用治具Aは、図1から図3に示すように、上下方向T1に延びる軸受け部10と、水平方向T2に延びる回転軸O1周りに回転自在に一端11aを軸受け部10に接続して設けられたローラー部11と、軸受け部10に直接的あるいは間接的に繋がって上方に延設されるとともに、作業者が把持する取っ手12を備えた引上げ把持部13と、ローラー部11の上方に所定の間隔をあけ、軸受け部10あるいは引上げ把持部13に一体に設けられ、ハーフPCa梁のスターラップ(せん断補強筋)に引っ掛けて配筋用治具Aを係止するための係止部14とを備えて形成されている。   As shown in FIGS. 1 to 3, the bar arrangement jig A of the present embodiment has one end 11a that is rotatable around a bearing portion 10 extending in the vertical direction T1 and a rotation axis O1 extending in the horizontal direction T2. A roller portion 11 provided connected to the bearing portion 10; a pulling and holding portion 13 provided with a handle 12 which is connected to the bearing portion 10 directly or indirectly and extends upward; , With a predetermined space above the roller part 11, provided integrally with the bearing part 10 or the pulling grip part 13, and hooked on the half PCa beam stirrup (shear reinforcement) to lock the bar arrangement jig A And a locking portion 14 for doing so.

また、本実施形態では、ローラー部11がその一端11aを軸受け部10の上端と下端の間に接続して配設されている。さらに、軸受け部10は、下端側に、ローラー部11から所定の長さで下方に突出する突出部10aを備えて形成されている。また、ローラー部11の他端11bに上端を水平方向T2に延びる回転軸O1周りに回転可能に接続し、軸受け部10の突出部10aと同じ長さで下方に突出する突出支持部15が設けられている。そして、軸受け部10と突出支持部15の下端を接地面に当接させることにより、これら軸受け部10と突出支持部15によってローラー部11が回転軸O1を水平に配した状態で安定的に支持される。   Further, in the present embodiment, the roller portion 11 is disposed with its one end 11 a connected between the upper end and the lower end of the bearing portion 10. Furthermore, the bearing part 10 is provided with the protrusion part 10a which protrudes below by the predetermined length from the roller part 11 in the lower end side. Further, a protruding support portion 15 is provided which is connected to the other end 11b of the roller portion 11 so as to be rotatable around a rotation axis O1 extending in the horizontal direction T2 and protrudes downward with the same length as the protruding portion 10a of the bearing portion 10. It has been. And the roller part 11 supports stably in the state which has arrange | positioned the rotating shaft O1 horizontally by these bearing parts 10 and the protrusion support part 15 by making the lower end of the bearing part 10 and the protrusion support part 15 contact | abut to a grounding surface. Is done.

また、本実施形態の配筋用治具Aは、係止部14が軸受け部10の上端に一端部を接続し、ローラー部11の上方に所定の間隔をあけて対向するように、且つローラー部11の回転軸O1に沿う水平方向T2に延設されている。これにより、本実施形態の配筋用治具Aは、軸受け部10とローラー部11と係止部14が略コ字状に配設され、ローラー部11の他端11bと係止部14の他端部との間に鉄筋を挿入してローラー部11上に設置するための鉄筋挿入開口16が形成されている。   Further, the bar arrangement jig A of the present embodiment is such that the locking portion 14 has one end connected to the upper end of the bearing portion 10 and is opposed to the upper portion of the roller portion 11 with a predetermined interval. The portion 11 extends in the horizontal direction T2 along the rotation axis O1. Accordingly, in the bar arrangement jig A of the present embodiment, the bearing portion 10, the roller portion 11, and the locking portion 14 are arranged in a substantially U shape, and the other end 11b of the roller portion 11 and the locking portion 14 A reinforcing bar insertion opening 16 for inserting a reinforcing bar between the other end and installing it on the roller part 11 is formed.

さらに、係止部14には、他端部に下方に突出する第1係止片17が設けられている。また、係止部14には、一側端部と他側端部にそれぞれ、下方に突出する第2係止片18と第3係止片19が設けられている。そして、第2係止片18と第3係止片19はそれぞれ、軸受け部10と第1係止片17とのローラー部11の回転軸O1に沿う水平方向T2の間に隙間をあけて配設されており、この隙間がスターラップを係合させて引っ掛けるための係止溝20を形成している。   Furthermore, the latching | locking part 14 is provided with the 1st latching piece 17 which protrudes below in the other end part. Moreover, the latching | locking part 14 is provided with the 2nd latching piece 18 and the 3rd latching piece 19 which protrude below at the one side edge part and the other side edge part, respectively. The second locking piece 18 and the third locking piece 19 are arranged with a gap between the bearing portion 10 and the first locking piece 17 in the horizontal direction T2 along the rotation axis O1 of the roller portion 11. This gap forms a locking groove 20 for engaging and hooking the stirrup.

本実施形態の引上げ把持部13は、下端を係止部14の上面に接続し、上方に延設された軸部21と、軸部21の上端に接続してローラー部11の回転軸O1に沿う水平方向T2に延設された取っ手12とを備えて略T字状に形成されている。さらに、本実施形態では、軸部21の下端が係止部14の上面の略中央に接続され、且つ軸部21の中心軸O2の延長線上にローラー部11の回転軸O1が配されるようにして引上げ把持部13が設けられている。   The pulling and gripping portion 13 of this embodiment has a lower end connected to the upper surface of the locking portion 14, a shaft portion 21 extending upward, and an upper end of the shaft portion 21 connected to the rotation axis O <b> 1 of the roller portion 11. And a handle 12 extending in the horizontal direction T <b> 2 that extends along the horizontal direction T <b> 2. Furthermore, in the present embodiment, the lower end of the shaft portion 21 is connected to the approximate center of the upper surface of the locking portion 14, and the rotation axis O <b> 1 of the roller portion 11 is disposed on the extension line of the central axis O <b> 2 of the shaft portion 21. Thus, a pulling grip 13 is provided.

次に、上記構成からなる本実施形態の配筋用治具Aの作用効果について説明する。
図4(及び図1から図3)に示すように、本実施形態の配筋用治具Aを用いて上筋(主筋)2を配筋する際には、上筋2を仮留めした状態で柱上に架け渡すようにハーフPCa梁(鉄筋コンクリート部材の一部)1を設置し、上筋2を外す。そして、鉄筋挿入開口16を通じて上筋2がローラー部11上に配されるように配筋用治具Aを設置する。
Next, the effect of the bar arrangement jig A of the present embodiment having the above-described configuration will be described.
As shown in FIG. 4 (and FIGS. 1 to 3), when the upper reinforcement (main reinforcement) 2 is arranged using the reinforcement arrangement jig A of the present embodiment, the upper reinforcement 2 is temporarily fixed. The half PCa beam (part of the reinforced concrete member) 1 is installed so as to be bridged on the column, and the upper bar 2 is removed. Then, the bar arrangement jig A is installed so that the upper bar 2 is arranged on the roller part 11 through the reinforcing bar insertion opening 16.

このとき、軸受け部10の下端側にローラー部11から所定の長さで下方に突出する突出部10aが設けられ、ローラー部11の他端に上端を接続し、軸受け部10の突出部10aと同じ長さで下方に突出する突出支持部15が設けられている。このため、軸受け部10と突出支持部15の下端をハーフPCa梁1の下側コンクリートの上面(接地面)に当接させると、これら軸受け部10と突出支持部15によってローラー部11上で上筋2が安定した状態で支持されるとともに、下側コンクリートとの間に隙間を設けた状態で支持される。これにより、作業者が上筋2と下側コンクリートの間の隙間に指を入れて上筋2を掴み、容易に移動させることができる。   At this time, a protruding portion 10a protruding downward from the roller portion 11 with a predetermined length is provided on the lower end side of the bearing portion 10, and the upper end is connected to the other end of the roller portion 11, and the protruding portion 10a of the bearing portion 10 A protruding support portion 15 that protrudes downward with the same length is provided. For this reason, when the lower ends of the bearing portion 10 and the protruding support portion 15 are brought into contact with the upper surface (grounding surface) of the lower concrete of the half PCa beam 1, the bearing portion 10 and the protruding support portion 15 are moved upward on the roller portion 11. The streak 2 is supported in a stable state, and is supported in a state where a gap is provided between the lower side concrete. Thereby, an operator can put a finger in the gap between the upper reinforcement 2 and the lower concrete to grasp the upper reinforcement 2 and move it easily.

また、ローラー部11上に上筋2を配設した後に、作業者が引上げ把持部13の取っ手12を持って配筋用治具Aを引き上げたり、下げることで、上筋2を容易に上下に移動させることができる。そして、作業者が配筋用治具Aを上筋2とともに引き上げ、係止溝20にスターラップ3を嵌め込んで係止部14をスターラップ3に係止させると、上筋2を所定の高さに配した状態で配筋用治具Aを保持することができる。   Further, after the upper barb 2 is arranged on the roller part 11, the operator pulls up and down the bar arrangement jig A by holding the handle 12 of the pull-up grip part 13 so that the upper barb 2 can be easily moved up and down. Can be moved to. Then, when the operator raises the bar arrangement jig A together with the upper reinforcement 2, the star wrap 3 is fitted in the engagement groove 20 and the engagement portion 14 is engaged with the star wrap 3, the upper reinforcement 2 is The bar arrangement jig A can be held in a state of being arranged at a height.

また、上筋2がローラー部11上に設けられているため、作業者が上筋2を一方向に押し引きすることにより、容易に且つ円滑に上筋2を横引きして所定位置に配置することができる。   Further, since the upper muscle 2 is provided on the roller portion 11, when the operator pushes and pulls the upper muscle 2 in one direction, the upper muscle 2 is easily and smoothly pulled horizontally and arranged at a predetermined position. can do.

したがって、本実施形態の配筋用治具Aにおいては、ハーフPCa梁1の上筋2の配筋時に使用することで、例えば、配筋作業を2、3人の作業者で行うことが可能になり、従来と比較し、人工を減らすことができる。   Therefore, in the bar arrangement jig A according to the present embodiment, for example, the bar arrangement work can be performed by two or three workers by using the upper barb 2 of the half PCa beam 1 for bar arrangement. Therefore, compared with the conventional case, the artificial can be reduced.

また、ローラー部11が回転するため、押し引きする単純動作で上筋2を所定位置に移動することができ、且つ少ない作業者で作業を行えるため、息を合わせやすく、容易に且つ円滑に配筋作業を行うことが可能になる。また、スターラップ3に係止部14を引っ掛けるだけで上筋2を保持でき、従来のように、持ち上げた上筋2を作業者が保持している必要がない。さらに、配筋時に上下に動く力が必要ない、あるいは少なくすることができるため、作業者が体勢を乱すことがなく、効率的に配筋作業を行うことができる。   In addition, since the roller portion 11 rotates, the upper muscle 2 can be moved to a predetermined position by a simple operation of pushing and pulling, and work can be performed by a small number of workers, so that breathing is easy and easy and smooth arrangement. It is possible to perform muscle work. Further, the upper muscle 2 can be held only by hooking the locking portion 14 on the stirrup 3, and it is not necessary for the operator to hold the raised upper muscle 2 as in the prior art. Furthermore, since the force to move up and down is not necessary or can be reduced at the time of the bar arrangement, the operator can perform the bar arrangement work efficiently without disturbing the posture.

よって、本実施形態の配筋用治具Aによれば、ハーフPCa梁1の上筋2を効率的に配筋することができ、且つ作業者の負担を大幅に低減することができ、工期の短縮、人工の削減を図ることを可能になる。   Therefore, according to the bar arrangement jig A of the present embodiment, the upper bar 2 of the half PCa beam 1 can be arranged efficiently, and the burden on the operator can be greatly reduced. It becomes possible to aim at shortening and artificial reduction.

以上、本発明に係る配筋用治具の一実施形態について説明したが、本発明は上記の一実施形態に限定されるものではなく、その趣旨を逸脱しない範囲で適宜変更可能である。   As mentioned above, although one Embodiment of the bar arrangement jig which concerns on this invention was described, this invention is not limited to said one Embodiment, In the range which does not deviate from the meaning, it can change suitably.

例えば、本実施形態では、本発明に係る配筋用治具AがハーフPCa梁1の上筋2を配筋するための治具であるものとして説明を行ったが、本発明に係る配筋用治具Aは必ずしもハーフPCa梁1の上筋2の配筋に用いることに限定しなくてもよく、梁や床などの主筋が横方向に配設され、せん断補強筋を備えたあらゆる鉄筋コンクリート部材の主筋の配筋に適用可能である。   For example, in the present embodiment, the bar arrangement jig A according to the present invention has been described as a jig for arranging the upper barb 2 of the half PCa beam 1, but the bar arrangement according to the present invention is described. The jig A does not necessarily have to be used to arrange the upper reinforcement 2 of the half PCa beam 1. Any reinforced concrete in which main reinforcements such as beams and floors are arranged in the horizontal direction and have shear reinforcements. It is applicable to the reinforcement of the main reinforcement of the member.

また、本実施形態では、配筋用治具Aが軸受け部10の突出部10aと突出支持部15を備え、これら軸受け部10と突出支持部15の下端を接地面に当接させた状態でローラー部11上に上筋(主筋)2を設置するものとした。
これに対し、係止部14をスターラップ(せん断補強筋)3に係合させて先に配筋治具Aを設置し、この状態の配筋治具Aのローラ部11に後から主筋2を設置して配筋作業を行うようにしてもよい。
In the present embodiment, the bar arrangement jig A includes the protruding portion 10a and the protruding support portion 15 of the bearing portion 10, and the lower ends of the bearing portion 10 and the protruding support portion 15 are in contact with the grounding surface. The upper muscle (main muscle) 2 was installed on the roller part 11.
On the other hand, the engaging portion 14 is engaged with the stirrup (shear reinforcing bar) 3 and the bar arrangement jig A is set first, and the main bar 2 is later placed on the roller portion 11 of the bar arrangement jig A in this state. The bar arrangement work may be carried out by installing.

さらに、本実施形態では、上筋2を仮留めした状態でハーフPCa梁(鉄筋コンクリート部材)1を柱上の所定位置に搬送し、所定位置に設置し段階で上筋2を取り外し、配筋用治具Aを用いて配筋するものとして説明を行った。
これに対し、ハーフPCa梁1を設置した後、上筋2のみを別途搬送し、スラータップの横から差し込んで配筋するようにしてもよい。この場合、例えば、上筋2を差し込む挿入側の近い部分に2つの配筋用治具Aを近接配置しておき、上筋2を挿入し、ある程度(例えば半分以上)挿入した段階で、1つの配筋用治具Aの位置を移動(あるいは、あらたな配筋用治具Aを上筋2の先端付近に設置)して、上筋2の挿入(移動)作業を行うようにしてもよい。
Further, in the present embodiment, the half PCa beam (reinforced concrete member) 1 is transported to a predetermined position on the column in a state where the upper bar 2 is temporarily fixed, and the upper bar 2 is removed at a stage where it is installed at a predetermined position. The description was made assuming that the bars are arranged using the jig A.
On the other hand, after the half PCa beam 1 is installed, only the upper bar 2 may be separately conveyed and inserted from the side of the slur tap to be arranged. In this case, for example, at the stage where two bar arrangement jigs A are arranged close to the insertion side where the upper bar 2 is inserted and the upper bar 2 is inserted and inserted to some extent (for example, half or more), 1 The position of the two bar arrangement jigs A is moved (or a new bar arrangement jig A is installed near the tip of the upper barb 2), and the upper barb 2 is inserted (moved). Good.

1 ハーフPCa梁(鉄筋コンクリート部材)
2 上筋(主筋)
3 スターラップ(せん断補強筋)
10 軸受け部
10a 突出部
11 ローラー部
11a 一端
11b 他端
12 取っ手
13 引上げ把持部
14 係止部
15 突出支持部
16 鉄筋挿入開口
17 第1係止片
18 第2係止片
19 第3係止片
20 係止溝
21 軸部
A 配筋用治具
O1 回転軸
O2 引上げ把持部の中心軸
T1 上下方向
T2 水平方向
1 Half PCa beam (Reinforced concrete member)
2 Upper muscle (main muscle)
3 Stirrup (shear reinforcement)
DESCRIPTION OF SYMBOLS 10 Bearing part 10a Protrusion part 11 Roller part 11a One end 11b Other end 12 Handle 13 Pulling grip part 14 Locking part 15 Protrusion support part 16 Reinforcing bar insertion opening 17 1st locking piece 18 2nd locking piece 19 3rd locking piece 20 Locking groove 21 Shaft part A Arrangement jig O1 Rotating shaft O2 Center axis T1 of pulling gripping part Vertical direction T2 Horizontal direction

Claims (2)

鉄筋コンクリート部材の主筋を配筋する際に用いる配筋用治具であって、
上下方向に延びる軸受け部と、
水平方向に延びる回転軸周りに回転自在に一端を前記軸受け部に接続して設けられたローラー部と、
前記軸受け部に直接的あるいは間接的に繋がって上方に延設されるとともに、作業者が把持する取っ手を備えた引上げ把持部と、
前記ローラー部の上方に間隔をあけ、前記軸受け部あるいは前記引上げ把持部に一体に設けられ、せん断補強筋に引っ掛けて配筋用治具を係止するための係止部とを備えていることを特徴とする配筋用治具。
A reinforcing jig used for reinforcing the main reinforcement of a reinforced concrete member,
A bearing portion extending in the vertical direction;
A roller part provided with one end connected to the bearing part so as to be rotatable around a rotation axis extending in the horizontal direction;
A pulling and holding portion that is directly or indirectly connected to the bearing portion and extends upward, and has a handle that an operator holds,
There is an interval above the roller portion, provided integrally with the bearing portion or the pulling grip portion, and provided with a locking portion for hooking on a shear reinforcing bar to lock the bar arrangement jig. Reinforcing bar jig characterized by
請求項1記載の配筋用治具において、
前記軸受け部の下端側に前記ローラー部から所定の長さで下方に突出する突出部が設けられ、
前記ローラー部の他端に水平方向に延びる回転軸周りに回転可能に接続して下方に突出する突出支持部が設けられていることを特徴とする配筋用治具。
The bar arrangement jig according to claim 1,
A protrusion that protrudes downward at a predetermined length from the roller part is provided on the lower end side of the bearing part,
A bar arrangement jig characterized in that a protruding support portion protruding downward is connected to the other end of the roller portion so as to be rotatable around a rotation axis extending in the horizontal direction.
JP2014121616A 2014-06-12 2014-06-12 Bar arrangement jig Active JP6238075B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014121616A JP6238075B2 (en) 2014-06-12 2014-06-12 Bar arrangement jig

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014121616A JP6238075B2 (en) 2014-06-12 2014-06-12 Bar arrangement jig

Publications (2)

Publication Number Publication Date
JP2016000941A true JP2016000941A (en) 2016-01-07
JP6238075B2 JP6238075B2 (en) 2017-11-29

Family

ID=55076662

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014121616A Active JP6238075B2 (en) 2014-06-12 2014-06-12 Bar arrangement jig

Country Status (1)

Country Link
JP (1) JP6238075B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113719133A (en) * 2021-08-06 2021-11-30 中国一冶集团有限公司 Steel bar laying device and using method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0659538U (en) * 1993-02-01 1994-08-19 戸田建設株式会社 Roller jig for moving rebar
JPH0678505U (en) * 1993-04-15 1994-11-04 大成建設株式会社 Rebar insertion device
JP2000017840A (en) * 1998-07-03 2000-01-18 Sato Kogyo Co Ltd Roller type reinforcing bar insertion equipment
US20110302880A1 (en) * 2010-06-14 2011-12-15 Dipietro Michael Rebar Sleeve Unit

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0659538U (en) * 1993-02-01 1994-08-19 戸田建設株式会社 Roller jig for moving rebar
JPH0678505U (en) * 1993-04-15 1994-11-04 大成建設株式会社 Rebar insertion device
JP2000017840A (en) * 1998-07-03 2000-01-18 Sato Kogyo Co Ltd Roller type reinforcing bar insertion equipment
US20110302880A1 (en) * 2010-06-14 2011-12-15 Dipietro Michael Rebar Sleeve Unit

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113719133A (en) * 2021-08-06 2021-11-30 中国一冶集团有限公司 Steel bar laying device and using method thereof

Also Published As

Publication number Publication date
JP6238075B2 (en) 2017-11-29

Similar Documents

Publication Publication Date Title
JP4546949B2 (en) Insulator attachment method, insulator removal method and split pin attachment used therefor
KR101552536B1 (en) Falling object protective apparatus
KR101457114B1 (en) Pre-fabrication method for steel reinforcement
JP6238075B2 (en) Bar arrangement jig
KR102328181B1 (en) Wire grippers and live wire distribution tools using the wire grippers
KR101461473B1 (en) Apparatus for transfering wire-roll
KR101643398B1 (en) Breast wall sleeve
JP2016219168A (en) Apparatus for manufacturing twisted wire and method for manufacturing twisted wire
KR200478647Y1 (en) clamping device
JP6776026B2 (en) Slinging hand hook stick
JP3179014U (en) Scaffolding retainer
JP6285826B2 (en) Arrangement apparatus, operation tool, and operation method
CN205341735U (en) Instrument is restoreed with simple and easy nail to construction
JP2011259547A (en) Flexible conduit guiding device
JP2005350228A (en) Long item storage rack
CN205334113U (en) Electromagnetic type straightness controller that hangs down
JP2016148182A (en) Reinforcement material for temporary scaffold
KR101170038B1 (en) Wall sc clip and installation method of wall structure using the same
JP3145303U (en) Ceiling board auxiliary support
KR200466226Y1 (en) Clamp for fixing wire tube by one touch
CN106760208B (en) Hoisting device and hoisting method for concrete filled steel tubular column
JP2020007785A (en) Handrail device
CN204715754U (en) A kind of side template ruggedized construction
JP2013013186A (en) Auxiliary apparatus for cable extension and renewal construction method
JP2010083616A (en) Roll suspender

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20161207

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170912

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170926

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20171018

R150 Certificate of patent or registration of utility model

Ref document number: 6238075

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150