CN113592107B - Bypass simulation method and system of power transmission line, intelligent terminal and storage medium - Google Patents
Bypass simulation method and system of power transmission line, intelligent terminal and storage medium Download PDFInfo
- Publication number
- CN113592107B CN113592107B CN202110815467.1A CN202110815467A CN113592107B CN 113592107 B CN113592107 B CN 113592107B CN 202110815467 A CN202110815467 A CN 202110815467A CN 113592107 B CN113592107 B CN 113592107B
- Authority
- CN
- China
- Prior art keywords
- simulation
- bypass
- circuit
- sequence
- rheostat
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000004088 simulation Methods 0.000 title claims abstract description 207
- 230000005540 biological transmission Effects 0.000 title claims abstract description 33
- 238000000034 method Methods 0.000 title claims abstract description 32
- 238000003860 storage Methods 0.000 title claims abstract description 15
- 238000012423 maintenance Methods 0.000 claims abstract description 55
- 238000012806 monitoring device Methods 0.000 claims abstract description 15
- 238000012544 monitoring process Methods 0.000 claims abstract description 11
- 238000004590 computer program Methods 0.000 claims description 11
- 238000005520 cutting process Methods 0.000 claims description 2
- 238000010586 diagram Methods 0.000 description 8
- 238000012360 testing method Methods 0.000 description 6
- 230000001360 synchronised effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/20—Administration of product repair or maintenance
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Theoretical Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Human Resources & Organizations (AREA)
- Economics (AREA)
- Health & Medical Sciences (AREA)
- Marketing (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Entrepreneurship & Innovation (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- Geometry (AREA)
- General Engineering & Computer Science (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Direct Current Feeding And Distribution (AREA)
Abstract
The embodiment of the application discloses a bypass simulation method of a power transmission line, which comprises the following steps: obtaining a target maintenance circuit, constructing a bypass simulation circuit according to the target maintenance circuit, wherein the bypass simulation circuit comprises two groups of simulation varistor groups, each group of simulation varistor groups comprises at least two simulation varistors with adjustable resistance values, which are connected in series, and two ends of each group of simulation varistor groups are connected with a simulation power supply; monitoring the change of the current and/or the voltage of the bypass simulation circuit through a monitoring device connected to the bypass simulation circuit; sequentially changing the resistance value of each simulation rheostat according to a preset sequence, and obtaining the real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each simulation rheostat is changed; and acquiring the safety sequence of the change simulation rheostat according to the real-time numerical value. The application also discloses a bypass simulation system of the power transmission line, an intelligent terminal and a storage medium. The application can effectively improve the maintenance safety of the transmission line.
Description
Technical Field
The application relates to the technical field of power transmission line maintenance, in particular to a bypass simulation method, a system, an intelligent terminal and a storage medium of a power transmission line.
Background
Modern economic construction development, the demand for electric energy is continuously increased, and electric power is completely integrated into daily life of people as conventional energy, and stable electric power can be provided for social production and people's life only by ensuring stable operation of an electric power system. Currently, a 35kV power transmission line system bears an important power transmission task, daily operation and maintenance are required to be comprehensively carried out, good operation of a power transmission line is guaranteed, and daily power facility maintenance is very important.
When the 35kV power transmission line is overhauled, the disconnection treatment is needed, and in order to ensure the normal power utilization of residents, a bypass is generally connected in parallel, and power is supplied through the bypass. Risks may occur in the actual overhaul process, so that normal power supply cannot be performed.
Disclosure of Invention
Based on the above, it is necessary to provide a bypass simulation method, a system, an intelligent terminal and a storage medium for a power transmission line.
A bypass simulation method of a power transmission line comprises the following steps: obtaining a target maintenance circuit, and constructing a bypass simulation circuit according to the target maintenance circuit, wherein the bypass simulation circuit comprises two groups of simulation varistor groups, each group of simulation varistor groups comprises at least two simulation varistors with adjustable resistance values, which are connected in series, and two ends of each group of simulation varistor groups are connected with a simulation power supply; monitoring the change of the current and/or the voltage of the bypass simulation circuit through a monitoring device connected to the bypass simulation circuit; sequentially changing the resistance value of each simulation rheostat according to a preset sequence, and obtaining the real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each simulation rheostat is changed; and acquiring and changing the safety sequence of the simulation rheostat according to the real-time numerical value.
Wherein, after the step of obtaining the safety sequence of the simulated varistor according to the real-time value, the method comprises the following steps: and constructing an actual bypass circuit of the target maintenance circuit according to the bypass simulation circuit, and cutting off and/or connecting the target maintenance circuit and the actual bypass circuit according to the safety sequence so as to maintain the target maintenance circuit.
The two ends of the two groups of simulation varistor groups are connected with the same simulation power supply voltage.
The voltage of the simulation power supply is 35kV.
The step of sequentially changing the resistance value of each simulation rheostat according to a preset sequence comprises the following steps: and adjusting the resistance value of each simulation rheostat from 0 to infinity and/or from infinity to 0 in preset time.
The step of obtaining the safety sequence of the simulation rheostat according to the real-time numerical value comprises the following steps: judging whether the real-time value of the current and/or the voltage of the bypass simulation circuit is in a safe state or not when the resistance value of the simulation rheostat is changed according to the preset sequence; if the real-time numerical value is in the safety state, the preset sequence is used as the safety sequence; and if the real-time value is not in the safe state, generating an adjustment sequence according to a preset sequence adjustment scheme, taking the adjustment sequence as the preset sequence, and executing the step of judging whether the real-time value of the current and/or the voltage of the bypass simulation circuit is in the safe state or not when the resistance value of the simulation rheostat is changed according to the preset sequence.
The step of constructing a bypass simulation circuit according to the target maintenance circuit comprises the following steps: and obtaining the number of the preset maintenance sections of the target maintenance circuit, and setting the number of the varistors of the simulation varistors included in each group of simulation varistors to be the same as the number of the sections.
A bypass simulation system of a power transmission line, comprising: the device comprises an acquisition module, a control module and a control module, wherein the acquisition module is used for acquiring a target maintenance circuit, constructing a bypass simulation circuit according to the target maintenance circuit, wherein the bypass simulation circuit comprises two groups of simulation varistor groups, each group of simulation varistor groups comprises at least two simulation varistors with adjustable resistance values, and two ends of each group of simulation varistor groups are connected with a simulation power supply; the monitoring module is used for monitoring the change of the current and/or the voltage of the bypass simulation circuit through a monitoring device connected to the bypass simulation circuit; the change module is used for sequentially changing the resistance value of each simulation rheostat according to a preset sequence and obtaining the real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each simulation rheostat is changed; and the safety module is used for acquiring and changing the safety sequence of the simulation rheostat according to the real-time numerical value.
An intelligent terminal, comprising: a processor, a memory, the processor coupled to the memory, the memory having a computer program stored therein, the processor executing the computer program to implement the method as described above.
A storage medium storing a computer program executable by a processor to implement a method as described above.
The embodiment of the application has the following beneficial effects:
constructing a bypass simulation circuit according to the target maintenance circuit, wherein the bypass simulation circuit comprises two groups of simulation varistor groups, and monitoring the change of current and/or voltage of the bypass simulation circuit through a monitoring device connected into the bypass simulation circuit; sequentially changing the resistance value of each simulation rheostat according to a preset sequence, and obtaining the real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each simulation rheostat is changed; according to the real-time numerical value, the safety sequence of the change simulation rheostat is obtained, so that the safety maintenance sequence can be obtained without actual tests, and the safety of maintenance personnel is effectively ensured.
Drawings
In order to more clearly illustrate the embodiments of the application or the technical solutions in the prior art, the drawings that are required in the embodiments or the description of the prior art will be briefly described, it being obvious that the drawings in the following description are only some embodiments of the application, and that other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
Wherein:
fig. 1 is a schematic flow chart of a first embodiment of a bypass simulation method of a power transmission line provided by the present application;
FIG. 2 is a schematic diagram of a bypass emulation circuit according to an embodiment of the present application;
FIG. 3 is a schematic diagram illustrating a bypass simulation system for a power transmission line according to an embodiment of the present application;
fig. 4 is a schematic structural diagram of a first embodiment of an intelligent terminal provided by the present application;
fig. 5 is a schematic structural diagram of an embodiment of a storage medium according to the present application.
Detailed Description
The following description of the embodiments of the present application will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present application, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the application without making any inventive effort, are intended to be within the scope of the application.
Referring to fig. 1 in combination, fig. 1 is a schematic flow chart of a first embodiment of a bypass simulation method for a power transmission line according to the present application. The bypass simulation method of the power transmission line provided by the application comprises the following steps:
s101: the method comprises the steps of obtaining a target maintenance circuit, constructing a bypass simulation circuit according to the target maintenance circuit, wherein the bypass simulation circuit comprises two groups of simulation varistor groups, each group of simulation varistor groups comprises at least two simulation varistors with adjustable resistance values, and two ends of each group of simulation varistor groups are connected with a simulation power supply.
In one particular implementation scenario, a target repair circuit is obtained, which may be a section of a transmission line or an entire section of a transmission line. And constructing a bypass simulation circuit according to the target maintenance circuit. Referring to fig. 2 in combination, fig. 2 is a schematic structural diagram of an embodiment of a bypass simulation circuit according to the present application. As shown in fig. 2, the bypass circuit 10 includes two simulated varistor groups 11 and 12, one on each leg of the bypass circuit.
The simulated varistor group 11 comprises two simulated varistors 111 and 112 of adjustable resistance connected in series, the simulated varistor group 12 comprises two simulated varistors 111 and 112 of adjustable resistance, in other implementation scenarios the simulated varistor groups 11 and 12 may comprise a greater number of simulated varistors, but the number of simulated varistors in the simulated varistor groups 11 and 12 is equal. In other implementations, each set of simulated varistors includes the same number of simulated varistors as the number of preset repair segments of the repair target repair circuit. The number of the preset maintenance sections of the target maintenance circuit can be obtained in advance, and the number of the varistors of each group of the simulated varistors is set to be the same as the number of the sections
Two ends of the two groups of simulated varistors 11 and 12 are connected to a simulated power supply, and in this embodiment, two ends of the two groups of simulated varistors 11 and 12 are connected to a 35kV power supply. In other implementation scenarios, the voltage of the simulation power supply is designed according to the actual application requirements, and the simulation power supplies connected to the two ends of the two groups of simulation varistor groups 11 and 12 may be equal or unequal.
S102: the change in current and/or voltage of the bypass simulation circuit is monitored by a monitoring device connected to the bypass simulation circuit.
In a specific implementation scenario, a monitoring device is connected to the bypass simulation circuit, where the monitoring device may be a device for measuring circuit parameters such as current, voltage, resistance, and the like, and the monitoring device may measure circuit parameters corresponding to each simulation varistor, or measure circuit parameters corresponding to each group of simulation varistors, and may also measure circuit parameters of the bypass simulation circuit, and may be set according to practical application requirements.
S103: and sequentially changing the resistance value of each simulation rheostat according to a preset sequence, and obtaining the real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each simulation rheostat is changed.
In a specific implementation scenario, the resistance of each simulated varistor is sequentially changed according to a preset sequence. The preset sequence may be plural, for example, plural kinds of sequences such as 111, 112, 121, 122, 121, 111, 121, 122, 111, 112, 122, 121, and the like will be preset. Further, the preset sequence further includes two sequences of changing the resistance value of each simulated varistor from 0 to infinity and from infinity to 0, for example, first changing 111 and 112 from 0 to infinity and then changing 121 and 122 from infinity to 0. The specific preset sequence is designed according to the actual maintenance requirement.
When the resistance value of each simulation rheostat is adjusted to change, the resistance value needs to be adjusted within preset time, the preset time is determined according to actual maintenance requirements, and the preset time is less than or equal to 5s in the application because the simulation rheostat needs to be quickly connected or disconnected during daily maintenance.
S104: and acquiring the safety sequence of the change simulation rheostat according to the real-time numerical value.
In a specific implementation scenario, the real-time value of each simulated varistor is detected and whether the real-time value is within a safe range is determined, and the safe range can be preset. And if the real-time numerical value is in the safety state, taking the preset sequence as the safety sequence. And if the real-time value is not in the safety state, generating an adjustment sequence according to a preset sequence adjustment scheme, taking the adjustment sequence as the preset sequence, and executing the step of judging whether the real-time value of the current and/or the voltage of the bypass simulation circuit is in the safety state or not when the resistance value of the simulation rheostat is changed according to the preset sequence until the real-time value is in the safety state, and obtaining the safety sequence.
For example, in the application scenario shown in fig. 2, the preset sequences are 111, 112, 121, and 122, if the real-time value is in the safety range when the resistance value of 111 is adjusted, the resistance value of 112 is adjusted according to the preset sequence, if the real-time value exceeds the safety range when the resistance value of 112 is adjusted, the test is stopped, the adjustment sequence is generated according to the preset sequence adjustment scheme, for example, 112, 121, and 122, the steps are repeated according to the new adjustment sequence until all the simulated varistors are adjusted, and the real-time value is always in the safety range, and the preset sequence is used as the safety sequence. The preset sequence adjustment scheme can be to exchange the front-back sequence of at least two simulation varistors in the original preset sequence, and ensure that the generated adjustment sequence is different from all the previous preset sequences. For example, the preset sequence is 111, 112, 121, 122, the real-time value is in unsafe state, the adjustment sequence is 112, 121, 122, the real-time value corresponding to the adjustment sequence is still in unsafe state, and if the adjustment sequence is 111, 112, 121, 122, the preset sequence is the same as the previous preset sequence, the adjustment sequence is not used, and the adjustment sequence is 112, 122, 121 different from the previous preset sequence.
When the power transmission line is maintained actually, the preset maintenance sections of the power transmission line are disconnected or connected according to the safety sequence, so that the safety of maintenance personnel is ensured.
In other implementations, after the safety sequence is acquired, an actual bypass circuit of the target repair circuit is constructed according to the bypass simulation circuit, and the target repair circuit and the actual bypass circuit are cut off and/or connected according to the safety sequence to repair the target repair circuit. Specifically, if the resistance value of the simulation rheostat is adjusted from 0 to infinity, the corresponding operation of disconnecting the preset maintenance section corresponding to the simulation rheostat is performed, and if the resistance value of the simulation rheostat is adjusted from infinity to 0, the corresponding operation of connecting the preset maintenance section corresponding to the simulation rheostat is performed.
As can be seen from the above description, in this embodiment, a bypass simulation circuit is constructed according to a target maintenance circuit, the bypass simulation circuit includes two groups of simulation varistor groups, and a monitoring device is connected to the bypass simulation circuit to monitor the current and/or voltage variation of the bypass simulation circuit; sequentially changing the resistance value of each simulation rheostat according to a preset sequence, and obtaining the real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each simulation rheostat is changed; according to the real-time numerical value, the safety sequence of the change simulation rheostat is obtained, so that the safety maintenance sequence can be obtained without actual tests, and the safety of maintenance personnel is effectively ensured.
Referring to fig. 3, fig. 3 is a schematic structural diagram of an embodiment of a bypass simulation system for a power transmission line according to the present application. The bypass simulation system 20 of the power transmission line comprises an acquisition module 21, a monitoring module 22, a change module 23 and a safety module 24.
The obtaining module 21 is configured to obtain a target maintenance circuit, and construct a bypass simulation circuit according to the target maintenance circuit, where the bypass simulation circuit includes two groups of simulation varistor groups, each group of simulation varistor groups includes at least two simulation varistors with adjustable resistance values, and two ends of the two groups of simulation varistor groups are connected with a simulation power supply; the monitoring module 22 is used for monitoring the change of the current and/or the voltage of the bypass simulation circuit through a monitoring device connected into the bypass simulation circuit; the change module 23 is configured to sequentially change the resistance value of each of the simulated varistors according to a preset sequence, and obtain a real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each of the simulated varistors changes; the safety module 24 is used for acquiring the safety sequence of the variable simulation varistors according to the real-time value.
The safety module 24 is also used to construct an actual bypass circuit of the target repair circuit from the bypass emulation circuit, and to disconnect and/or connect the target repair circuit and the actual bypass circuit according to a safe sequence for repairing the target repair circuit.
The two ends of the two groups of simulation varistors are connected with the same simulation power supply voltage.
The voltage of the simulation power supply is 35kV.
The variation module 23 is further configured to adjust the resistance of the simulated varistor from 0 to infinity and/or from infinity to 0 within a preset time.
The safety module 24 is further configured to determine whether a real-time value of the current and/or the voltage of the bypass simulation circuit is in a safe state when the resistance of the simulation varistor is changed according to a preset sequence; if the real-time numerical value is in a safe state, taking the preset sequence as a safe sequence; if the real-time value is not in the safe state, generating an adjustment sequence according to a preset sequence adjustment scheme, taking the adjustment sequence as a preset sequence, and executing the step of judging whether the real-time value of the current and/or the voltage of the bypass simulation circuit is in the safe state or not when the resistance value of the simulation rheostat is changed according to the preset sequence.
The obtaining module 21 is further configured to obtain a number of segments of a preset repair segment of the target repair circuit, and set a number of varistors of the simulated varistors included in each group of simulated varistors to be the same as the number of segments.
As can be seen from the above description, in the bypass simulation system of the power transmission line in this embodiment, a bypass simulation circuit is constructed according to a target maintenance circuit, the bypass simulation circuit includes two groups of simulation varistor groups, and a monitoring device is connected to the bypass simulation circuit to monitor the current and/or voltage variation of the bypass simulation circuit; sequentially changing the resistance value of each simulation rheostat according to a preset sequence, and obtaining the real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each simulation rheostat is changed; according to the real-time numerical value, the safety sequence of the change simulation rheostat is obtained, so that the safety maintenance sequence can be obtained without actual tests, and the safety of maintenance personnel is effectively ensured.
Referring to fig. 4, fig. 4 is a schematic structural diagram of a first embodiment of an intelligent terminal according to the present application. The intelligent terminal 30 includes a processor 31, a memory 32. The processor 31 is coupled to the memory 32. The memory 32 has stored therein a computer program which is executed by the processor 31 in operation to implement the method as shown in fig. 1. The detailed method can be referred to above, and will not be described here.
As can be seen from the above description, in this embodiment, the intelligent terminal constructs a bypass simulation circuit according to the target maintenance circuit, the bypass simulation circuit includes two groups of simulation varistor groups, and a monitoring device is connected to the bypass simulation circuit to monitor the current and/or voltage variation of the bypass simulation circuit; sequentially changing the resistance value of each simulation rheostat according to a preset sequence, and obtaining the real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each simulation rheostat is changed; according to the real-time numerical value, the safety sequence of the change simulation rheostat is obtained, so that the safety maintenance sequence can be obtained without actual tests, and the safety of maintenance personnel is effectively ensured.
Referring to fig. 5, fig. 5 is a schematic structural diagram of a storage medium according to an embodiment of the application. The computer-readable storage medium 40 stores at least one computer program 41, and the computer program 41 is used for being executed by a processor to implement the method shown in fig. 1, and the detailed method is referred to above and will not be repeated here. In one embodiment, the computer readable storage medium 30 may be a memory chip, a hard disk or a removable hard disk in a terminal, or other readable and writable storage means such as a flash disk, an optical disk, etc., and may also be a server, etc.
As is apparent from the above description, the computer program in the storage medium in this embodiment may be used to construct a bypass simulation circuit according to the target maintenance circuit, where the bypass simulation circuit includes two sets of simulation varistor groups, and a monitoring device is connected to the bypass simulation circuit to monitor a change in current and/or voltage of the bypass simulation circuit; sequentially changing the resistance value of each simulation rheostat according to a preset sequence, and obtaining the real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each simulation rheostat is changed; according to the real-time numerical value, the safety sequence of the change simulation rheostat is obtained, so that the safety maintenance sequence can be obtained without actual tests, and the safety of maintenance personnel is effectively ensured.
Those skilled in the art will appreciate that the processes implementing all or part of the methods of the above embodiments may be implemented by a computer program for instructing relevant hardware, and the program may be stored in a non-volatile computer readable storage medium, and the program may include the processes of the embodiments of the methods as above when executed. Any reference to memory, storage, database, or other medium used in embodiments provided herein may include non-volatile and/or volatile memory. The nonvolatile memory can include Read Only Memory (ROM), programmable ROM (PROM), electrically Programmable ROM (EPROM), electrically Erasable Programmable ROM (EEPROM), or flash memory. Volatile memory can include Random Access Memory (RAM) or external cache memory. By way of illustration and not limitation, RAM is available in a variety of forms such as Static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double Data Rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous Link DRAM (SLDRAM), memory bus direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM), among others.
The technical features of the above embodiments may be arbitrarily combined, and all possible combinations of the technical features in the above embodiments are not described for brevity of description, however, as long as there is no contradiction between the combinations of the technical features, they should be considered as the scope of the description.
The foregoing examples illustrate only a few embodiments of the application, which are described in detail and are not to be construed as limiting the scope of the application. It should be noted that it will be apparent to those skilled in the art that several variations and modifications can be made without departing from the spirit of the application, which are all within the scope of the application. Accordingly, the scope of protection of the present application is to be determined by the appended claims.
Claims (10)
1. The bypass simulation method of the power transmission line is characterized by comprising the following steps of:
obtaining a target maintenance circuit, and constructing a bypass simulation circuit according to the target maintenance circuit, wherein the bypass simulation circuit comprises two groups of simulation varistor groups, each group of simulation varistor groups comprises at least two simulation varistors with adjustable resistance values, which are connected in series, and two ends of each group of simulation varistor groups are connected with a simulation power supply;
monitoring the change of the current and/or the voltage of the bypass simulation circuit through a monitoring device connected to the bypass simulation circuit;
sequentially changing the resistance value of each simulation rheostat according to a preset sequence, and obtaining the real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each simulation rheostat is changed;
and acquiring and changing the safety sequence of the simulation rheostat according to the real-time numerical value.
2. The bypass simulation method of the power transmission line according to claim 1, wherein after the step of obtaining a safety sequence for changing the simulated varistors according to the real-time value, the method comprises:
and constructing an actual bypass circuit of the target maintenance circuit according to the bypass simulation circuit, and cutting off and/or connecting the target maintenance circuit and the actual bypass circuit according to the safety sequence so as to maintain the target maintenance circuit.
3. The bypass simulation method of a power transmission line according to claim 1, wherein the simulated power supply voltages connected to both ends of the two simulated varistor groups are equal.
4. A bypass simulation method of a power transmission line according to claim 3, wherein the voltage of the simulation power supply is 35kV.
5. The bypass simulation method of a power transmission line according to claim 1, wherein the step of sequentially varying the resistance value of each of the simulated varistors in a preset order comprises:
and adjusting the resistance value of each simulation rheostat from 0 to infinity and/or from infinity to 0 in preset time.
6. The bypass simulation method for a power transmission line according to claim 1, wherein,
the step of obtaining the safety sequence of the simulated rheostat according to the real-time numerical value comprises the following steps:
judging whether the real-time value of the current and/or the voltage of the bypass simulation circuit is in a safe state or not when the resistance value of the simulation rheostat is changed according to the preset sequence;
if the real-time numerical value is in the safety state, the preset sequence is used as the safety sequence;
and if the real-time value is not in the safe state, generating an adjustment sequence according to a preset sequence adjustment scheme, taking the adjustment sequence as the preset sequence, and executing the step of judging whether the real-time value of the current and/or the voltage of the bypass simulation circuit is in the safe state or not when the resistance value of the simulation rheostat is changed according to the preset sequence.
7. The bypass simulation method of an electric power transmission line according to claim 1, wherein the step of constructing a bypass simulation circuit from the target maintenance circuit includes:
and obtaining the number of the preset maintenance sections of the target maintenance circuit, and setting the number of the varistors of the simulation varistors included in each group of simulation varistors to be the same as the number of the sections.
8. A bypass simulation system of a power transmission line, comprising:
the device comprises an acquisition module, a control module and a control module, wherein the acquisition module is used for acquiring a target maintenance circuit, constructing a bypass simulation circuit according to the target maintenance circuit, wherein the bypass simulation circuit comprises two groups of simulation varistor groups, each group of simulation varistor groups comprises at least two simulation varistors with adjustable resistance values, and two ends of each group of simulation varistor groups are connected with a simulation power supply;
the monitoring module is used for monitoring the change of the current and/or the voltage of the bypass simulation circuit through a monitoring device connected to the bypass simulation circuit;
the change module is used for sequentially changing the resistance value of each simulation rheostat according to a preset sequence and obtaining the real-time value of the current and/or the voltage of the bypass simulation circuit when the resistance value of each simulation rheostat is changed;
and the safety module is used for acquiring and changing the safety sequence of the simulation rheostat according to the real-time numerical value.
9. An intelligent terminal, characterized by comprising: a processor, a memory, the processor being coupled to the memory, the memory having a computer program stored therein, the processor executing the computer program to implement the method of any of claims 1-7.
10. A storage medium storing a computer program executable by a processor to implement the method of any one of claims 1-7.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110815467.1A CN113592107B (en) | 2021-07-19 | 2021-07-19 | Bypass simulation method and system of power transmission line, intelligent terminal and storage medium |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110815467.1A CN113592107B (en) | 2021-07-19 | 2021-07-19 | Bypass simulation method and system of power transmission line, intelligent terminal and storage medium |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113592107A CN113592107A (en) | 2021-11-02 |
CN113592107B true CN113592107B (en) | 2023-11-07 |
Family
ID=78248140
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110815467.1A Active CN113592107B (en) | 2021-07-19 | 2021-07-19 | Bypass simulation method and system of power transmission line, intelligent terminal and storage medium |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113592107B (en) |
Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04203976A (en) * | 1990-11-30 | 1992-07-24 | Hitachi Ltd | Electronic type reactor |
JP2001099883A (en) * | 1999-10-04 | 2001-04-13 | Kinkei System Corp | Method for locating fault on transmission line |
WO2010043014A1 (en) * | 2008-10-13 | 2010-04-22 | Universidade Estadual De Campinas - Unicamp | Fast three-phase reclosing method in shunt reactor compensated transmission lines |
CN103729502A (en) * | 2013-12-19 | 2014-04-16 | 南京南瑞继保电气有限公司 | Method for increasing electromagnetic transient simulation speed of power system |
JP2017174398A (en) * | 2016-03-18 | 2017-09-28 | ローム株式会社 | Computer simulation method, and method for generating transmission line model |
CN107291981A (en) * | 2017-05-17 | 2017-10-24 | 国网北京市电力公司 | The emulation mode and device of transmission line of electricity |
CN108151771A (en) * | 2017-12-20 | 2018-06-12 | 哈尔滨广瀚燃气轮机有限公司 | A kind of gas turbine throttle position transmitter |
CN108509712A (en) * | 2018-03-29 | 2018-09-07 | 南方电网科学研究院有限责任公司 | A kind of the over-voltage simulation analysis method and system of cable run |
CN110543739A (en) * | 2019-09-11 | 2019-12-06 | 南方电网科学研究院有限责任公司 | Circuit simulation model of overhead power transmission line |
CN110632495A (en) * | 2018-06-25 | 2019-12-31 | 联合汽车电子有限公司 | Circuit fault simulation system and method |
CN110927528A (en) * | 2019-12-12 | 2020-03-27 | 广西电网有限责任公司电力科学研究院 | Transmission line fault simulation test device |
CN111736091A (en) * | 2020-05-27 | 2020-10-02 | 湖南省湘电试验研究院有限公司 | Unstable high-resistance ground fault simulation circuit based on RTDS platform and application method thereof |
CN111879786A (en) * | 2020-07-31 | 2020-11-03 | 广东电网能源发展有限公司 | Method for carrying out nondestructive testing on power transmission line clamp by applying flexible memory phosphor plate |
-
2021
- 2021-07-19 CN CN202110815467.1A patent/CN113592107B/en active Active
Patent Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH04203976A (en) * | 1990-11-30 | 1992-07-24 | Hitachi Ltd | Electronic type reactor |
JP2001099883A (en) * | 1999-10-04 | 2001-04-13 | Kinkei System Corp | Method for locating fault on transmission line |
WO2010043014A1 (en) * | 2008-10-13 | 2010-04-22 | Universidade Estadual De Campinas - Unicamp | Fast three-phase reclosing method in shunt reactor compensated transmission lines |
CN103729502A (en) * | 2013-12-19 | 2014-04-16 | 南京南瑞继保电气有限公司 | Method for increasing electromagnetic transient simulation speed of power system |
JP2017174398A (en) * | 2016-03-18 | 2017-09-28 | ローム株式会社 | Computer simulation method, and method for generating transmission line model |
CN107291981A (en) * | 2017-05-17 | 2017-10-24 | 国网北京市电力公司 | The emulation mode and device of transmission line of electricity |
CN108151771A (en) * | 2017-12-20 | 2018-06-12 | 哈尔滨广瀚燃气轮机有限公司 | A kind of gas turbine throttle position transmitter |
CN108509712A (en) * | 2018-03-29 | 2018-09-07 | 南方电网科学研究院有限责任公司 | A kind of the over-voltage simulation analysis method and system of cable run |
CN110632495A (en) * | 2018-06-25 | 2019-12-31 | 联合汽车电子有限公司 | Circuit fault simulation system and method |
CN110543739A (en) * | 2019-09-11 | 2019-12-06 | 南方电网科学研究院有限责任公司 | Circuit simulation model of overhead power transmission line |
CN110927528A (en) * | 2019-12-12 | 2020-03-27 | 广西电网有限责任公司电力科学研究院 | Transmission line fault simulation test device |
CN111736091A (en) * | 2020-05-27 | 2020-10-02 | 湖南省湘电试验研究院有限公司 | Unstable high-resistance ground fault simulation circuit based on RTDS platform and application method thereof |
CN111879786A (en) * | 2020-07-31 | 2020-11-03 | 广东电网能源发展有限公司 | Method for carrying out nondestructive testing on power transmission line clamp by applying flexible memory phosphor plate |
Non-Patent Citations (2)
Title |
---|
N. Fujiwara et al..《IEEE Transactions on Power Delivery》Development of a Pin-Post Insulator with Built-in Metal Oxide Varistors for Distribution Lines.1996,第11卷(第2期),第824-833页. * |
史志强 等.《高压电器》750 kV 同塔双回输电线路感应电压和电流的研究.2018,第54卷(第8期),第120-126页. * |
Also Published As
Publication number | Publication date |
---|---|
CN113592107A (en) | 2021-11-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9570909B2 (en) | Devices and methods for decentralized power loss reduction control | |
US8838284B2 (en) | Devices and methods for decentralized Volt/VAR control | |
US8838285B2 (en) | Devices and methods for decentralized power factor control | |
JP2017158418A (en) | Dynamic adjustment method and system for battery under-voltage protection | |
CN111581191B (en) | Nuclear safety data verification method, device, computer equipment and storage medium | |
US10283961B2 (en) | Voltage and reactive power control system | |
CN106655201A (en) | Security domain-based safe optimization and control method for electric power thermal stability | |
CN113592107B (en) | Bypass simulation method and system of power transmission line, intelligent terminal and storage medium | |
CN106501734B (en) | The voltage acquisition fault handling method and device of battery management system | |
Marggraf et al. | U-Control-Recommendations for Distributed and Automated Voltage Control in Current and Future Distribution Grids | |
CN110910275A (en) | Basic electricity utilization data acquisition method and device, computer equipment and storage medium | |
CN109212451B (en) | Voltage loss fault monitoring method and device based on three-phase four-wire meter measuring equipment | |
CN110350513B (en) | Online strategy fixed value checking method for safety and stability control system | |
Xiao et al. | Research on intelligent diagnosis method of oil temperature defect in distribution transformer based on machine learning | |
WO2021115694A1 (en) | Method, apparatus, system, electric vehicle, computer program and storage medium for charging or discharging a cell of an electric energy store | |
CN117374986B (en) | Power grid thermal stability quota calculation method, device, equipment and medium | |
CN112484920A (en) | System and method for monitoring rotational inertia of power system | |
CN112444718A (en) | Chip aging monitoring method, device and system | |
Vancells et al. | Analysis of importance of components in power systems using time sequential simulation | |
Su et al. | Online Reliability Assessment of Distribution Feeder Considering Time Sequential Load Transfer Procedure | |
CN108418239A (en) | Flexible direct current power transmission system Poewr control method and device | |
CN110649634B (en) | Converter station cooperative control method and device, computer equipment and storage medium | |
CN117353312A (en) | Power grid thermal stability quota checking method, device, equipment and medium | |
CN116937670A (en) | Method for establishing new energy station model based on field test | |
Wang et al. | A dynamic probabilistic load flow method considering random distribution of the unbalance power |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |