CN113585560A - Construction method of assembled embedded energy-saving curtain wall system - Google Patents

Construction method of assembled embedded energy-saving curtain wall system Download PDF

Info

Publication number
CN113585560A
CN113585560A CN202110887103.4A CN202110887103A CN113585560A CN 113585560 A CN113585560 A CN 113585560A CN 202110887103 A CN202110887103 A CN 202110887103A CN 113585560 A CN113585560 A CN 113585560A
Authority
CN
China
Prior art keywords
glass
construction
aluminum
curtain wall
keel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110887103.4A
Other languages
Chinese (zh)
Inventor
徐凤
龚登颛
冷凯
蒋昇廷
周颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Jianan Group Co ltd
Original Assignee
Zhuhai Jianan Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Jianan Group Co ltd filed Critical Zhuhai Jianan Group Co ltd
Priority to CN202110887103.4A priority Critical patent/CN113585560A/en
Publication of CN113585560A publication Critical patent/CN113585560A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • E04B1/68Sealings of joints, e.g. expansion joints
    • E04B1/6801Fillings therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/885Curtain walls comprising a supporting structure for flush mounted glazing panels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B1/00Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
    • E06B1/56Fastening frames to the border of openings or to similar contiguous frames
    • E06B1/58Fastening frames to the border of openings or to similar contiguous frames by filling up the joints, e.g. by cementing
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B1/00Border constructions of openings in walls, floors, or ceilings; Frames to be rigidly mounted in such openings
    • E06B1/56Fastening frames to the border of openings or to similar contiguous frames
    • E06B1/60Fastening frames to the border of openings or to similar contiguous frames by mechanical means, e.g. anchoring means
    • E06B1/6015Anchoring means

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

The invention discloses a construction method of an assembled embedded energy-saving curtain wall system, which comprises the following steps: construction preparation, namely after the main structure is finished, installing equipment such as a winch and embedded parts on beams in place; the invention is composed of two systems through the curtain wall: an embedded window unit system, a beam wrapping system and a column unit system. The embedded window system adopts a unit curtain wall form, and the embedded window main body is completely prefabricated in a factory; the package roof beam, package post system adopt half unit curtain form preparation, and the scene is independently assembled and is accomplished, and system's preparation installation industrialization degree is high, and the embedded window system plate is big, adopts jumbo size overall structure formula installation during the construction, has avoided middle and small component, repeated construction in the curtain installation in the past, and the installation is simple and convenient, and the efficiency of construction is higher, and package roof beam, package post system adopt hidden frame installation, and its metal frame component is whole not to show at the surface, and the wholeness of curtain is good, and decorative effect is pleasing to the eye.

Description

Construction method of assembled embedded energy-saving curtain wall system
Technical Field
The invention relates to the technical field of building engineering, in particular to a construction method of an assembled embedded energy-saving curtain wall system.
Background
The traditional glass curtain wall construction achieves the facade effect of concave-convex of the outer facade by installing an aluminum alloy window in a window opening and decorating a beam column with paint, face bricks and the like. Nowadays, in order to meet wider functional and technological requirements, a fabricated embedded energy-saving curtain wall system combining a large plate embedded window system with a small unit beam-wrapping system and a column-wrapping system is produced. The curtain wall system has the advantages of good heat insulation and sound insulation performance of Low-E hollow glass, the construction characteristics of large volume and high efficiency of a novel curtain wall are combined, a better vertical face combination effect can be achieved, and in order to solve the problems, an assembly type embedded energy-saving curtain wall system construction method is provided.
Disclosure of Invention
The invention aims to provide a construction method of an assembled embedded energy-saving curtain wall system, which has the advantages of good heat insulation and sound insulation performance and excellent vertical surface combination effect and solves the problems of poor heat insulation and sound insulation performance and poor vertical surface combination effect.
In order to achieve the purpose, the invention provides the following technical scheme: the construction method of the assembled embedded energy-saving curtain wall system comprises the following steps:
step 1: construction preparation, namely after the main structure is finished, installing equipment such as a winch and embedded parts on beams in place;
step 2: measuring and paying off, namely measuring and positioning according to a site construction drawing and then determining an installation datum line;
and step 3: processing the embedded part, checking whether the installation position of the embedded part is correct, and cleaning up dust on the surface of the embedded part;
and 4, step 4: the connecting angle code is placed, the connecting angle code is welded on the embedded part through a bolt or welded on the embedded part, and the adapter aluminum bracket is fixed on the connecting piece through the bolt;
and 5: mounting the keel, namely mounting the wrap beam steel keel, mounting a wrap beam aluminum plate, mounting galvanized iron sheets on the periphery outside the mounting chamber, mounting the wrap column aluminum keel and finally mounting the wrap beam aluminum keel;
step 6: mounting the patterned glass, namely firstly erecting the column-wrapped glass indoors, then moving the column-wrapped glass to a mounting position, and lifting the column-wrapped glass to mount on a wall;
and 7: sealing and caulking by structural adhesive, namely cleaning a base material at an adhesive injection position, adhering by using a double-sided adhesive tape, injecting the adhesive, standing and maintaining for a period of time after the adhesive injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength;
and 8: the installation of the outer decorative cover plate comprises the steps of firstly determining the arrangement line of keels, then connecting the cover plates by using connecting pieces, then leveling the cover plates, and finally fixing the cover plates;
and step 9: weather-resistant glue caulking, namely cleaning a base material at a glue injection position, adhering the base material by using a double-sided adhesive tape, injecting glue, standing and maintaining for a period of time after the glue injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength;
step 10: cleaning the surface of a curtain wall, wiping and cleaning by using rag in the installation process, cleaning the whole curtain wall after the curtain wall is installed, cleaning by using clean water and a special detergent for the curtain wall from top to bottom in sequence, and formulating a cleaning scheme after the glass curtain wall is installed;
step 11: and (4) checking and accepting construction quality, checking whether the glass is firmly installed or not, checking the installation direction and the like, and checking the caulking of the sealant and the appearance of the curtain wall.
Preferably, in the step 1, the material entering work is finished, all components are in place, the construction of the main body structure is finished and meets the requirement of construction acceptance standards, operating equipment such as a winch is installed in place, operation platforms such as scaffolds are erected, the material variety, specification, color and performance of all components and accessories meet the design requirement, all embedded parts on all beams and columns are installed in place, construction schedule is arranged according to the field condition before construction and installation, subsection partition construction is organized, meanwhile, technical cross-bottom work is done, and installers are trained.
Preferably, in the step 2, the measurement and positioning are specifically performed according to a site construction drawing, the deviation of the civil engineering structure is measured, preparation is made for construction, an installation datum line is determined after the measurement, the installation datum line comprises a connecting piece positioning datum, a keel arrangement datum and horizontal marking lines of all parts of the curtain wall, and the datum lines in three directions are determined for the curtain walls at different positions.
Preferably, in the step 4, after the embedded part is installed to be qualified after inspection, construction of a connecting piece can be performed, the connecting piece can be connected to the embedded part through bolts or welding, the adapter aluminum bracket is fixed on the connecting piece through the bolts, the position of the connecting piece is aligned to the ink line, the horizontal position and the verticality of the connecting piece are controlled at a repeated point, the number of the connecting pieces for wrapping beams and wrapping columns is large, the connecting pieces need to be treated differently, one part of the connecting pieces is installed on the aluminum keel in advance and installed together with the aluminum keel, and the other part of the connecting pieces needs to be installed on the main body and then fixed with the aluminum keel.
Preferably, in step 5, before the aluminum alloy keel is installed, firstly, the straightness is checked, the checking method adopts a drawing method, if the straightness is not satisfactory, the aluminum keel is installed on the wall after being corrected, the error is controlled within an allowable range, and the installation sequence of the aluminum keel is as follows: the method comprises the steps of installing a steel keel of a wrap beam, installing an aluminum plate of the wrap beam, installing an aluminum keel of a wrap column, installing the aluminum keel of the wrap beam, assembling the aluminum frame by assembling the aluminum keel, installing an aluminum keel assembling working room on site, specially assembling the aluminum keel of the wrap beam and the aluminum keel of the wrap column, connecting the aluminum keel with a support by using stainless steel bolts, fixing the support with an embedded part by using bolts, continuously adjusting the verticality and the levelness of the keel in the installation process, finally tightening a nut for fixing, and after the keel is in place, carrying out installation and inspection according to steel wires and comprehensive construction drawings arranged during measurement to ensure that the axis of the keel has no deviation.
Preferably, when the package beam and the package column glass are installed in the step 6, all keels of the workshop section are installed, the package column glass is erected indoors, the package column glass is manually moved to an installation position and then directly lifted and installed on a wall for fixing, a scaffold is erected at the bottom of the hanging bottom glass to serve as a construction platform, a working platform on a manual station is used for installing the package beam glass, the package beam and the package column glass are installed on the same floor immediately after being installed, and the package beam, the package column glass and the embedded window on the same floor are all installed and then moved to the previous floor for installing a glass panel.
Preferably, in step 7, in particular, the cleaning of the base material at the injection site, all construction surfaces related to the injection site must be cleaned, kept clean, ashless, non-fouling and dry, and for non-oily contaminants, an isopropanol solvent (50% isopropanol: water 1: 1) is used; xylene solvent is usually used for pollutants, and white or primary-color cotton cloth which is clean, soft and non-depilatory is used for cleaning cloth. When cleaning, the cleaning agent is poured on the cleaning cloth, the cloth cannot be dipped into a container containing the cleaning agent, so that the pollution of the whole solvent is avoided, the cleaning is carried out by adopting a 'twice wiping' process, and after the cleaning, the cleaned part is never allowed to contact with hands or other pollution sources; the double-sided adhesive tape is stuck, after the size and the shape of the aluminum frame are confirmed according to a design drawing, the double-sided adhesive tape is stuck at the center of the aluminum alloy keel according to the drawing requirement, when the double-sided adhesive tape is stuck, the adhesive tape is kept in a straight line, the adhesive tape is forcibly pressed down to be tightly attached to the aluminum alloy bracket, before glass is placed, the isolation paper of the adhesive tape is not required to be torn off so as to prevent the other sticking surface of the adhesive tape from being polluted, after the glass is fixed, the shape and the size of the glass are finally corrected, and when the glass is placed, the glass surface is guaranteed to be smooth, and the glass cannot be bent; before glue injection, carefully checking and checking whether the sealant is overdue or not, judging whether the mark of the used sealant is in accordance with a design drawing or not, flattening by using a scraper after glue injection, scraping redundant sealant, and finishing the exposed surface of the sealant, so as to protect the parts possibly causing the pollution of the aluminum alloy keel and glass in the glue injection and scraping processes and pasting a paper-based adhesive tape; standing and maintaining, wherein the glass component subjected to glue injection is required to be subjected to standing and maintaining in time, and the requirements of a standing and maintaining place are as follows: the temperature is 10-30 ℃, the relative humidity is 65-75%, the glass component is free of oil stain and a large amount of dust, the glass component which is not completely cured cannot be collided at will, the bonding force is prevented from being reduced, and the next construction operation can be carried out after the bonding force reaches the specified strength.
Preferably, in step 7 specifically be curtain wall glass, aluminium alloy before the mill dispatches from the factory, use protective film packing protection, in the installation, use the rag to clean, the curtain installation finishes the back, carry out whole cleanness, clean order is from top to bottom, clean with clear water and the special sanitizer of curtain, curtain in the construction adopts appropriate measure to protect, prevent to bump, the pollution, the phenomenon such as deformation, discolour and drain pipe jam, in the construction, the adherent that causes the influence to curtain and curtain component surface decoration in time clears away, resume its original state and original appearance, after the glass curtain wall engineering installation, formulate the scheme of cleaning, wash curtain surface and exposed component. The neutral cleaning agent for cleaning glass and aluminum alloy parts is used after corrosion test is carried out before cleaning, and the neutral cleaning agent is used after no corrosion effect on aluminum alloy and glass is proved.
Preferably, in step 11, before the aluminum profile is blanked, it is necessary to check whether the profile number, color difference, specification and model are consistent with those required by the actually processed workpiece, whether the oxide film on the surface of the aluminum profile is intact or not, the aluminum profile with too deep nicks and large-area scratches is removed, the distorted and bent aluminum profile is corrected and blanked, and the glass processing quality is rechecked before the glass plate is assembled. The method is characterized in that the method is carried out on the aspects of appearance, size deviation and the like, unqualified products are not allowed to be used, and correspondingly recorded, classified and stored, the unqualified products cannot be mixed with qualified products to be placed, the splicing seams of the curtain wall and the splicing seams of the glass lattices are vertical and horizontal, the seam width is uniform and meets the requirement of a drawing, the variety, the specification and the color of the glass conform to the design, the color is basically uniform, the phenomena of alkali precipitation and mildew and obvious color difference do not exist, the glass with the phenomenon of film coating falling is forbidden to be used, the surface of the aluminum alloy decorative gland is smooth, the defects of deformation ripple or local crushing and smashing and the like which can be detected by naked eyes do not exist, the seam position must strictly meet the design requirement, and the shielding seal of hidden nodes is neat and attractive.
Preferably, when the patterned glass plate is installed safely and protectively in the installation process, attention is paid to the protection of the integrity of the aluminum alloy keel without load collision deformation, the frame type curtain wall glass plate is installed, and the installation is carried out slowly by using a glass sucker; the safety measures of the special construction mechanical equipment are that construction equipment (such as a special lifting car, a winch and the like) for installing the curtain wall must be carried out before use, strict inspection is carried out, trial run tests are carried out on various safety protection devices, an electric hand drill, an electric screwdriver, a welding gun, an electric tool and the like must be carried out for insulation tests, a manual glass sucker and an electric glass sucker must be used for testing the adsorption weight and the adsorption duration, workers using a handheld electric tool according to operation rules need to be matched with protective tools, the mechanical workers wear the protective tools according to the rules, and mechanical operators and bench workers cannot wear gloves when using the electric drill or the grinding wheel.
Compared with the prior art, the invention has the beneficial effects that: the invention is composed of two systems through the curtain wall: an embedded window unit system, a beam wrapping system and a column unit system. The embedded window system adopts a unit curtain wall form, and the embedded window main body is completely prefabricated in a factory; the package roof beam, package post system adopt half unit curtain form preparation, and the scene is independently assembled and is accomplished, and system's preparation installation industrialization degree is high, and the embedded window system plate is big, adopts jumbo size overall structure formula installation during the construction, has avoided middle and small component, repeated construction in the curtain installation in the past, and the installation is simple and convenient, and the efficiency of construction is higher, and package roof beam, package post system adopt hidden frame installation, and its metal frame component is whole not to show at the surface, and the wholeness of curtain is good, and decorative effect is pleasing to the eye.
Detailed Description
The present invention will now be described in more detail by way of examples, which are given by way of illustration only and are not intended to limit the scope of the present invention in any way.
The invention provides a technical scheme that: the construction method of the assembled embedded energy-saving curtain wall system comprises the following steps:
step 1: construction preparation, namely after the main structure is finished, installing equipment such as a winch and embedded parts on beams in place;
step 2: measuring and paying off, namely measuring and positioning according to a site construction drawing and then determining an installation datum line;
and step 3: processing the embedded part, checking whether the installation position of the embedded part is correct, and cleaning up dust on the surface of the embedded part;
and 4, step 4: the connecting angle code is placed, the connecting angle code is welded on the embedded part through a bolt or welded on the embedded part, and the adapter aluminum bracket is fixed on the connecting piece through the bolt;
and 5: mounting the keel, namely mounting the wrap beam steel keel, mounting a wrap beam aluminum plate, mounting galvanized iron sheets on the periphery outside the mounting chamber, mounting the wrap column aluminum keel and finally mounting the wrap beam aluminum keel;
step 6: mounting the patterned glass, namely firstly erecting the column-wrapped glass indoors, then moving the column-wrapped glass to a mounting position, and lifting the column-wrapped glass to mount on a wall;
and 7: sealing and caulking by structural adhesive, namely cleaning a base material at an adhesive injection position, adhering by using a double-sided adhesive tape, injecting the adhesive, standing and maintaining for a period of time after the adhesive injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength;
and 8: the installation of the outer decorative cover plate comprises the steps of firstly determining the arrangement line of keels, then connecting the cover plates by using connecting pieces, then leveling the cover plates, and finally fixing the cover plates;
and step 9: weather-resistant glue caulking, namely cleaning a base material at a glue injection position, adhering the base material by using a double-sided adhesive tape, injecting glue, standing and maintaining for a period of time after the glue injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength;
step 10: cleaning the surface of a curtain wall, wiping and cleaning by using rag in the installation process, cleaning the whole curtain wall after the curtain wall is installed, cleaning by using clean water and a special detergent for the curtain wall from top to bottom in sequence, and formulating a cleaning scheme after the glass curtain wall is installed;
step 11: and (4) checking and accepting construction quality, checking whether the glass is firmly installed or not, checking the installation direction and the like, and checking the caulking of the sealant and the appearance of the curtain wall.
Example one
Construction preparation, namely after the main structure is finished, installing equipment such as a winch and embedded parts on beams in place; measuring and paying off, namely measuring and positioning according to a site construction drawing and then determining an installation datum line; processing the embedded part, checking whether the installation position of the embedded part is correct, and cleaning up dust on the surface of the embedded part; the connecting angle code is placed, the connecting angle code is welded on the embedded part through a bolt or welded on the embedded part, and the adapter aluminum bracket is fixed on the connecting piece through the bolt; mounting the keel, namely mounting the wrap beam steel keel, mounting a wrap beam aluminum plate, mounting galvanized iron sheets on the periphery outside the mounting chamber, mounting the wrap column aluminum keel and finally mounting the wrap beam aluminum keel; mounting the patterned glass, namely firstly erecting the column-wrapped glass indoors, then moving the column-wrapped glass to a mounting position, and lifting the column-wrapped glass to mount on a wall; sealing and caulking by structural adhesive, namely cleaning a base material at an adhesive injection position, adhering by using a double-sided adhesive tape, injecting the adhesive, standing and maintaining for a period of time after the adhesive injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; the installation of the outer decorative cover plate comprises the steps of firstly determining the arrangement line of keels, then connecting the cover plates by using connecting pieces, then leveling the cover plates, and finally fixing the cover plates; weather-resistant glue caulking, namely cleaning a base material at a glue injection position, adhering the base material by using a double-sided adhesive tape, injecting glue, standing and maintaining for a period of time after the glue injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; cleaning the surface of a curtain wall, wiping and cleaning by using rag in the installation process, cleaning the whole curtain wall after the curtain wall is installed, cleaning by using clean water and a special detergent for the curtain wall from top to bottom in sequence, and formulating a cleaning scheme after the glass curtain wall is installed; and (4) checking and accepting construction quality, checking whether the glass is firmly installed or not, checking the installation direction and the like, and checking the caulking of the sealant and the appearance of the curtain wall.
Example two
Construction preparation, namely after the main structure is finished, installing equipment such as a winch and embedded parts on beams in place; measuring and paying off, namely measuring and positioning according to a site construction drawing and then determining an installation datum line; processing the embedded part, checking whether the installation position of the embedded part is correct, and cleaning up dust on the surface of the embedded part; the connecting angle code is placed, the connecting angle code is welded on the embedded part through a bolt or welded on the embedded part, and the adapter aluminum bracket is fixed on the connecting piece through the bolt; mounting the keel, namely mounting the wrap beam steel keel, mounting a wrap beam aluminum plate, mounting galvanized iron sheets on the periphery outside the mounting chamber, mounting the wrap column aluminum keel and finally mounting the wrap beam aluminum keel; mounting the patterned glass, namely firstly erecting the column-wrapped glass indoors, then moving the column-wrapped glass to a mounting position, and lifting the column-wrapped glass to mount on a wall; sealing and caulking by structural adhesive, namely cleaning a base material at an adhesive injection position, adhering by using a double-sided adhesive tape, injecting the adhesive, standing and maintaining for a period of time after the adhesive injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; the installation of the outer decorative cover plate comprises the steps of firstly determining the arrangement line of keels, then connecting the cover plates by using connecting pieces, then leveling the cover plates, and finally fixing the cover plates; weather-resistant glue caulking, namely cleaning a base material at a glue injection position, adhering the base material by using a double-sided adhesive tape, injecting glue, standing and maintaining for a period of time after the glue injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; cleaning the surface of a curtain wall, wiping and cleaning by using rag in the installation process, cleaning the whole curtain wall after the curtain wall is installed, cleaning by using clean water and a special detergent for the curtain wall from top to bottom in sequence, and formulating a cleaning scheme after the glass curtain wall is installed; checking and accepting construction quality, checking whether the installation position and installation direction of glass are firm, checking the appearance of sealant caulking and curtain walls, specifically, performing material entering work in step 1, enabling all components to be in place, completing construction of a main body structure and meeting the requirements of construction checking and accepting specifications, installing operating equipment such as a winch in place, completing erection of operating platforms such as scaffolds and the like, enabling the material variety, specification, color and performance of all components and accessories to meet design requirements, completely installing embedded parts on all beam columns in place, performing construction schedule arrangement according to the field condition before construction and installation, performing subsection construction, simultaneously performing technology bottom-crossing work, and training installation personnel.
EXAMPLE III
Construction preparation, after a main body structure is completed, devices such as a winch and embedded parts on beams are installed in place, material entering work is well done, components are in place, the main body structure is constructed completely and meets the requirements of construction acceptance standards, operating devices such as the winch are installed in place, operation platforms such as scaffolds are completely erected, the material varieties, specifications, colors and performances of components and accessories meet the design requirements, the embedded parts on the beam columns are all installed in place, construction schedule is well arranged according to the field condition before construction and installation, subsection partition construction is organized, meanwhile, technology intersection work is well done, and installation personnel are trained; measuring and paying off, namely measuring and positioning according to a site construction drawing, and then determining an installation datum line, specifically, measuring deviation of a civil engineering structure according to the site construction drawing, preparing for construction, determining the installation datum line after measurement, wherein the installation datum line comprises a connecting piece positioning datum, a keel arrangement datum and horizontal marking lines of curtain walls of all parts, and determining three-direction datum for the curtain walls of all different parts; processing the embedded part, checking whether the installation position of the embedded part is correct, and cleaning up dust on the surface of the embedded part; the connecting angle code is placed, the connecting angle code is welded on the embedded part through a bolt or welded on the embedded part, and the adapter aluminum bracket is fixed on the connecting piece through the bolt; mounting the keel, namely mounting the wrap beam steel keel, mounting a wrap beam aluminum plate, mounting galvanized iron sheets on the periphery outside the mounting chamber, mounting the wrap column aluminum keel and finally mounting the wrap beam aluminum keel; mounting the patterned glass, namely firstly erecting the column-wrapped glass indoors, then moving the column-wrapped glass to a mounting position, and lifting the column-wrapped glass to mount on a wall; sealing and caulking by structural adhesive, namely cleaning a base material at an adhesive injection position, adhering by using a double-sided adhesive tape, injecting the adhesive, standing and maintaining for a period of time after the adhesive injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; the installation of the outer decorative cover plate comprises the steps of firstly determining the arrangement line of keels, then connecting the cover plates by using connecting pieces, then leveling the cover plates, and finally fixing the cover plates; weather-resistant glue caulking, namely cleaning a base material at a glue injection position, adhering the base material by using a double-sided adhesive tape, injecting glue, standing and maintaining for a period of time after the glue injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; cleaning the surface of a curtain wall, wiping and cleaning by using rag in the installation process, cleaning the whole curtain wall after the curtain wall is installed, cleaning by using clean water and a special detergent for the curtain wall from top to bottom in sequence, and formulating a cleaning scheme after the glass curtain wall is installed; and (4) checking and accepting construction quality, checking whether the glass is firmly installed or not, checking the installation direction and the like, and checking the caulking of the sealant and the appearance of the curtain wall.
Example four
Construction preparation, namely after the main structure is finished, installing equipment such as a winch and embedded parts on beams in place; measuring and paying off, namely measuring and positioning according to a site construction drawing and then determining an installation datum line; processing the embedded part, checking whether the installation position of the embedded part is correct, and cleaning up dust on the surface of the embedded part; the method comprises the following steps that connecting angle codes are placed, the connecting angle codes are bolted or welded to embedded parts, adapter aluminum brackets are fixed on connecting pieces through bolts, specifically, after the embedded parts are inspected and installed to be qualified, construction of the connecting pieces can be carried out, the connecting pieces can be bolted or welded to the embedded parts, the adapter aluminum brackets are fixed on the connecting pieces through bolts, the positions of the connecting pieces are necessarily aligned with ink lines, the horizontal positions and the verticality of the connecting pieces are controlled through repeated points, the number of connecting pieces for wrapping beams and wrapping columns is large, the connecting pieces need to be treated differently, one part of the connecting pieces are installed on an aluminum keel in advance and are installed together with the aluminum keel, and the other part of the connecting pieces need to be installed on a main body and then are fixed with the aluminum keel; mounting the keel, namely mounting the wrap beam steel keel, mounting a wrap beam aluminum plate, mounting galvanized iron sheets on the periphery outside the mounting chamber, mounting the wrap column aluminum keel and finally mounting the wrap beam aluminum keel; mounting the patterned glass, namely firstly erecting the column-wrapped glass indoors, then moving the column-wrapped glass to a mounting position, and lifting the column-wrapped glass to mount on a wall; sealing and caulking by structural adhesive, namely cleaning a base material at an adhesive injection position, adhering by using a double-sided adhesive tape, injecting the adhesive, standing and maintaining for a period of time after the adhesive injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; the installation of the outer decorative cover plate comprises the steps of firstly determining the arrangement line of keels, then connecting the cover plates by using connecting pieces, then leveling the cover plates, and finally fixing the cover plates; weather-resistant glue caulking, namely cleaning a base material at a glue injection position, adhering the base material by using a double-sided adhesive tape, injecting glue, standing and maintaining for a period of time after the glue injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; cleaning the surface of a curtain wall, wiping and cleaning by using rag in the installation process, cleaning the whole curtain wall after the curtain wall is installed, cleaning by using clean water and a special detergent for the curtain wall from top to bottom in sequence, and formulating a cleaning scheme after the glass curtain wall is installed; and (4) checking and accepting construction quality, checking whether the glass is firmly installed or not, checking the installation direction and the like, and checking the caulking of the sealant and the appearance of the curtain wall.
EXAMPLE five
Construction preparation, namely after the main structure is finished, installing equipment such as a winch and embedded parts on beams in place; measuring and paying off, namely measuring and positioning according to a site construction drawing and then determining an installation datum line; processing the embedded part, checking whether the installation position of the embedded part is correct, and cleaning up dust on the surface of the embedded part; the connecting angle code is placed, the connecting angle code is welded on the embedded part through a bolt or welded on the embedded part, and the adapter aluminum bracket is fixed on the connecting piece through the bolt; keel installation, at first installation package roof beam steel joist, then installation package roof beam aluminum plate, the installation of galvanized sheet around the installation room, then installation package post aluminum keel, at last installation package roof beam aluminum keel specifically is before installation aluminum alloy keel, at first carries out the inspection of straightness accuracy, and the method of inspection adopts the method of drawing in, if not conform to the requirement, installs on the wall again after correcting, with error control in the within range that allows, and the order of aluminum keel installation is: installing a steel keel of a wrap beam, installing an aluminum plate of the wrap beam, installing a galvanized iron sheet around the outside, installing an aluminum keel of a wrap column, installing the aluminum keel of the wrap beam, assembling the aluminum frame by assembling the aluminum keel, installing an aluminum keel assembling working room on site, specially assembling the aluminum keel of the wrap beam and the aluminum keel of the wrap column, connecting the aluminum keel with a support by using a stainless steel bolt, fixing the support with an embedded part by using a bolt, continuously adjusting the verticality and the levelness of the keel in the installation process, finally tightening a nut for fixing, and after the keel is in place, carrying out installation inspection according to a steel wire line and a comprehensive construction drawing arranged during measurement to ensure that the axis of the keel has no deviation; mounting the patterned glass, namely firstly erecting the column-wrapped glass indoors, then moving the column-wrapped glass to a mounting position, and lifting the column-wrapped glass to mount on a wall; sealing and caulking by structural adhesive, namely cleaning a base material at an adhesive injection position, adhering by using a double-sided adhesive tape, injecting the adhesive, standing and maintaining for a period of time after the adhesive injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; the installation of the outer decorative cover plate comprises the steps of firstly determining the arrangement line of keels, then connecting the cover plates by using connecting pieces, then leveling the cover plates, and finally fixing the cover plates; weather-resistant glue caulking, namely cleaning a base material at a glue injection position, adhering the base material by using a double-sided adhesive tape, injecting glue, standing and maintaining for a period of time after the glue injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; cleaning the surface of a curtain wall, wiping and cleaning by using rag in the installation process, cleaning the whole curtain wall after the curtain wall is installed, cleaning by using clean water and a special detergent for the curtain wall from top to bottom in sequence, and formulating a cleaning scheme after the glass curtain wall is installed; and (4) checking and accepting construction quality, checking whether the glass is firmly installed or not, checking the installation direction and the like, and checking the caulking of the sealant and the appearance of the curtain wall.
EXAMPLE six
Construction preparation, namely after the main structure is finished, installing equipment such as a winch and embedded parts on beams in place; measuring and paying off, namely measuring and positioning according to a site construction drawing and then determining an installation datum line; processing the embedded part, checking whether the installation position of the embedded part is correct, and cleaning up dust on the surface of the embedded part; the connecting angle code is placed, the connecting angle code is welded on the embedded part through a bolt or welded on the embedded part, and the adapter aluminum bracket is fixed on the connecting piece through the bolt; mounting the keel, namely mounting the wrap beam steel keel, mounting a wrap beam aluminum plate, mounting galvanized iron sheets on the periphery outside the mounting chamber, mounting the wrap column aluminum keel and finally mounting the wrap beam aluminum keel; the method comprises the steps of mounting embossed glass, namely firstly erecting column-wrapped glass indoors, then moving the column-wrapped glass to a mounting position, lifting and mounting the column-wrapped glass on a wall, specifically, when mounting the beam-wrapped glass and the column-wrapped glass, finishing mounting all keels of a workshop section, erecting the column-wrapped glass indoors, manually moving the column-wrapped glass to the mounting position, then directly lifting and mounting the wall for fixing, erecting a scaffold at the bottom of a hanging bottom glass as a construction platform, mounting the beam-wrapped glass on a working platform on a manual station, immediately mounting the embedded windows on the same floor after the beam-wrapped glass and the column-wrapped glass are mounted, and moving the column-wrapped glass and the embedded windows on the same floor to the previous floor after the beam-wrapped glass, the column-wrapped glass and the embedded windows are mounted; sealing and caulking by structural adhesive, namely cleaning a base material at an adhesive injection position, adhering by using a double-sided adhesive tape, injecting the adhesive, standing and maintaining for a period of time after the adhesive injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; the installation of the outer decorative cover plate comprises the steps of firstly determining the arrangement line of keels, then connecting the cover plates by using connecting pieces, then leveling the cover plates, and finally fixing the cover plates; weather-resistant glue caulking, namely cleaning a base material at a glue injection position, adhering the base material by using a double-sided adhesive tape, injecting glue, standing and maintaining for a period of time after the glue injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; cleaning the surface of a curtain wall, wiping and cleaning by using rag in the installation process, cleaning the whole curtain wall after the curtain wall is installed, cleaning by using clean water and a special detergent for the curtain wall from top to bottom in sequence, and formulating a cleaning scheme after the glass curtain wall is installed; and (4) checking and accepting construction quality, checking whether the glass is firmly installed or not, checking the installation direction and the like, and checking the caulking of the sealant and the appearance of the curtain wall.
EXAMPLE seven
Construction preparation, namely after the main structure is finished, installing equipment such as a winch and embedded parts on beams in place; measuring and paying off, namely measuring and positioning according to a site construction drawing and then determining an installation datum line; processing the embedded part, checking whether the installation position of the embedded part is correct, and cleaning up dust on the surface of the embedded part; the connecting angle code is placed, the connecting angle code is welded on the embedded part through a bolt or welded on the embedded part, and the adapter aluminum bracket is fixed on the connecting piece through the bolt; mounting the keel, namely mounting the wrap beam steel keel, mounting a wrap beam aluminum plate, mounting galvanized iron sheets on the periphery outside the mounting chamber, mounting the wrap column aluminum keel and finally mounting the wrap beam aluminum keel; mounting the patterned glass, namely firstly erecting the column-wrapped glass indoors, then moving the column-wrapped glass to a mounting position, and lifting the column-wrapped glass to mount on a wall; the structural adhesive sealing caulking is characterized in that a base material at the position of an adhesive injection is cleaned firstly, then double-sided adhesive tapes are used for pasting, then the adhesive injection is carried out, after the adhesive injection is finished, standing and maintaining are carried out for a period of time, the next construction operation can be carried out after the adhesive force reaches the specified strength, specifically, curtain wall glass and aluminum profiles are packaged and protected by a protective film before factory shipment, cleaning is carried out by rag in the installation process, after the curtain wall is installed, the integral cleaning is carried out, the cleaning sequence is from top to bottom, cleaning is carried out by clear water and a special cleaning agent for the curtain wall, the curtain wall in construction is protected by proper measures to prevent the phenomena of collision, pollution, deformation, color change, drain pipe blockage and the like, in the construction, adherends influencing the surface decoration of the curtain wall and the curtain wall components are removed in time, the original state and appearance are recovered, and after the engineering installation of the glass curtain wall is finished, a cleaning scheme is formulated, and cleaning the surface of the curtain wall and the exposed component. The neutral cleaning agent for cleaning glass and aluminum alloy parts is subjected to corrosivity inspection before cleaning, and is used after the aluminum alloy and the glass are proved to have no corrosion effect, specifically, a base material at a glue injection position is cleaned, all construction surfaces related to the glue injection position need to be cleaned and kept clean, ashless, pollution-free and dry, and for non-oily pollutants, an isopropanol solvent is adopted (50% isopropanol: water is 1: 1); xylene solvent is usually used for pollutants, and white or primary-color cotton cloth which is clean, soft and non-depilatory is used for cleaning cloth. When cleaning, the cleaning agent is poured on the cleaning cloth, the cloth cannot be dipped into a container containing the cleaning agent, so that the pollution of the whole solvent is avoided, the cleaning is carried out by adopting a 'twice wiping' process, and after the cleaning, the cleaned part is never allowed to contact with hands or other pollution sources; the double-sided adhesive tape is stuck, after the size and the shape of the aluminum frame are confirmed according to a design drawing, the double-sided adhesive tape is stuck at the center of the aluminum alloy keel according to the drawing requirement, when the double-sided adhesive tape is stuck, the adhesive tape is kept in a straight line, the adhesive tape is forcibly pressed down to be tightly attached to the aluminum alloy bracket, before glass is placed, the isolation paper of the adhesive tape is not required to be torn off so as to prevent the other sticking surface of the adhesive tape from being polluted, after the glass is fixed, the shape and the size of the glass are finally corrected, and when the glass is placed, the glass surface is guaranteed to be smooth, and the glass cannot be bent; before glue injection, carefully checking and checking whether the sealant is overdue or not, judging whether the mark of the used sealant is in accordance with a design drawing or not, flattening by using a scraper after glue injection, scraping redundant sealant, and finishing the exposed surface of the sealant, so as to protect the parts possibly causing the pollution of the aluminum alloy keel and glass in the glue injection and scraping processes and pasting a paper-based adhesive tape; standing and maintaining, wherein the glass component subjected to glue injection is required to be subjected to standing and maintaining in time, and the requirements of a standing and maintaining place are as follows: the temperature is 10-30 ℃, the relative humidity is 65-75%, the glass assembly which is not completely cured cannot be collided at will, so that the bonding force is prevented from being reduced, and the next construction operation can be carried out after the bonding force reaches the specified strength; the installation of the outer decorative cover plate comprises the steps of firstly determining the arrangement line of keels, then connecting the cover plates by using connecting pieces, then leveling the cover plates, and finally fixing the cover plates; weather-resistant glue caulking, namely cleaning a base material at a glue injection position, adhering the base material by using a double-sided adhesive tape, injecting glue, standing and maintaining for a period of time after the glue injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; cleaning the surface of a curtain wall, wiping and cleaning by using rag in the installation process, cleaning the whole curtain wall after the curtain wall is installed, cleaning by using clean water and a special detergent for the curtain wall from top to bottom in sequence, and formulating a cleaning scheme after the glass curtain wall is installed; and (4) checking and accepting construction quality, checking whether the glass is firmly installed or not, checking the installation direction and the like, and checking the caulking of the sealant and the appearance of the curtain wall.
Example eight
Construction preparation, namely after the main structure is finished, installing equipment such as a winch and embedded parts on beams in place; measuring and paying off, namely measuring and positioning according to a site construction drawing and then determining an installation datum line; processing the embedded part, checking whether the installation position of the embedded part is correct, and cleaning up dust on the surface of the embedded part; the connecting angle code is placed, the connecting angle code is welded on the embedded part through a bolt or welded on the embedded part, and the adapter aluminum bracket is fixed on the connecting piece through the bolt; mounting the keel, namely mounting the wrap beam steel keel, mounting a wrap beam aluminum plate, mounting galvanized iron sheets on the periphery outside the mounting chamber, mounting the wrap column aluminum keel and finally mounting the wrap beam aluminum keel; mounting the patterned glass, namely firstly erecting the column-wrapped glass indoors, then moving the column-wrapped glass to a mounting position, and lifting the column-wrapped glass to mount on a wall; sealing and caulking by structural adhesive, namely cleaning a base material at an adhesive injection position, adhering by using a double-sided adhesive tape, injecting the adhesive, standing and maintaining for a period of time after the adhesive injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; the installation of the outer decorative cover plate comprises the steps of firstly determining the arrangement line of keels, then connecting the cover plates by using connecting pieces, then leveling the cover plates, and finally fixing the cover plates; weather-resistant glue caulking, namely cleaning a base material at a glue injection position, adhering the base material by using a double-sided adhesive tape, injecting glue, standing and maintaining for a period of time after the glue injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength; cleaning the surface of a curtain wall, wiping and cleaning by using rag in the installation process, cleaning the whole curtain wall after the curtain wall is installed, cleaning by using clean water and a special detergent for the curtain wall from top to bottom in sequence, and formulating a cleaning scheme after the glass curtain wall is installed; the construction quality is checked, whether the installation position and installation of the glass are firm, the installation direction and the like are checked, sealant caulking and curtain wall impression is checked, specifically, whether the serial number, color difference and specification model of the section conform to those required by an actually processed workpiece or not before the aluminum section is blanked is checked, whether an oxide film on the surface of the aluminum section is intact or not is not damaged, the aluminum section with an over-deep nick and a large-area scratch is rejected, the aluminum section with distortion and bending deformation is corrected firstly and then blanked, and the glass processing quality is rechecked before the glass plate is assembled. The method is characterized in that the method is carried out on the aspects of appearance, size deviation and the like, unqualified products are not allowed to be used, and correspondingly recorded, classified and stored, the unqualified products cannot be mixed with qualified products to be placed, the splicing seams of the curtain wall and the splicing seams of the glass lattices are vertical and horizontal, the seam width is uniform and meets the requirement of a drawing, the variety, the specification and the color of the glass conform to the design, the color is basically uniform, the phenomena of alkali precipitation and mildew and obvious color difference do not exist, the glass with the phenomenon of film coating falling is forbidden to be used, the surface of the aluminum alloy decorative gland is smooth, the defects of deformation ripple or local crushing and smashing and the like which can be detected by naked eyes do not exist, the seam position must strictly meet the design requirement, and the shielding seal of hidden nodes is neat and attractive.
Side length tolerance (mm) of hollow glass
Length of Tolerance deviation
<1000 +0.1,-2.0
1000~2000 +1.0,-2.5
>2000~2500 +1.5,-3.0
Appearance quality of toughened and semi-toughened glass
Figure BDA0003194576580000151
Figure BDA0003194576580000161
Curtain wall installation quality inspection table
Figure BDA0003194576580000162
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (10)

1. An assembled embedded energy-saving curtain wall system construction method is characterized in that: the method comprises the following steps:
step 1: construction preparation, namely after the main structure is finished, installing equipment such as a winch and embedded parts on beams in place;
step 2: measuring and paying off, namely measuring and positioning according to a site construction drawing and then determining an installation datum line;
and step 3: processing the embedded part, checking whether the installation position of the embedded part is correct, and cleaning up dust on the surface of the embedded part;
and 4, step 4: the connecting angle code is placed, the connecting angle code is welded on the embedded part through a bolt or welded on the embedded part, and the adapter aluminum bracket is fixed on the connecting piece through the bolt;
and 5: mounting the keel, namely mounting the wrap beam steel keel, mounting a wrap beam aluminum plate, mounting galvanized iron sheets on the periphery outside the mounting chamber, mounting the wrap column aluminum keel and finally mounting the wrap beam aluminum keel;
step 6: mounting the patterned glass, namely firstly erecting the column-wrapped glass indoors, then moving the column-wrapped glass to a mounting position, and lifting the column-wrapped glass to mount on a wall;
and 7: sealing and caulking by structural adhesive, namely cleaning a base material at an adhesive injection position, adhering by using a double-sided adhesive tape, injecting the adhesive, standing and maintaining for a period of time after the adhesive injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength;
and 8: the installation of the outer decorative cover plate comprises the steps of firstly determining the arrangement line of keels, then connecting the cover plates by using connecting pieces, then leveling the cover plates, and finally fixing the cover plates;
and step 9: weather-resistant glue caulking, namely cleaning a base material at a glue injection position, adhering the base material by using a double-sided adhesive tape, injecting glue, standing and maintaining for a period of time after the glue injection is finished, and performing the next construction operation until the adhesive force reaches the specified strength;
step 10: cleaning the surface of a curtain wall, wiping and cleaning by using rag in the installation process, cleaning the whole curtain wall after the curtain wall is installed, cleaning by using clean water and a special detergent for the curtain wall from top to bottom in sequence, and formulating a cleaning scheme after the glass curtain wall is installed;
step 11: and (4) checking and accepting construction quality, checking whether the glass is firmly installed or not, checking the installation direction and the like, and checking the caulking of the sealant and the appearance of the curtain wall.
2. The construction method of the assembled embedded energy-saving curtain wall system according to claim 1, characterized in that: specifically, in the step 1, the finished material enters the field to work, all components are in place, the construction of a main body structure is finished and meets the requirement of construction acceptance standards, operating equipment such as a winch is installed in place, operating platforms such as scaffolds are erected completely, the material variety, specification, color and performance of all components and accessories meet the design requirement, all embedded parts on all beams and columns are installed in place, construction schedule is arranged according to the field condition before construction and installation, subsection and partition construction is organized, meanwhile, technical cross-bottom work is done, and installers are trained.
3. The construction method of the assembled embedded energy-saving curtain wall system according to claim 1, characterized in that: and in the step 2, specifically, the measurement and positioning are carried out according to the site construction drawing, the civil structure deviation is measured, the preparation is made for construction, the installation datum line is determined after the measurement, the installation datum line comprises a connecting piece positioning datum, a keel arrangement datum and horizontal mark lines of all parts of curtain walls, and the datum lines in three directions are determined for the curtain walls at different parts.
4. The construction method of the assembled embedded energy-saving curtain wall system according to claim 1, characterized in that: in the step 4, after the embedded part is installed to be qualified after inspection, construction of a connecting piece can be carried out, the connecting piece can be connected to the embedded part through bolts or welding, the switching aluminum bracket is fixed on the connecting piece through the bolts, the position of the connecting piece is aligned to the ink line, the horizontal position and the verticality of the connecting piece are controlled at the repeated point, the number of the connecting pieces of the wrapping beam and the wrapping column is large, the connecting pieces need to be treated differently, one part of the connecting pieces is installed on the aluminum keel in advance and installed together with the aluminum keel, and the other part of the connecting pieces needs to be installed on the main body and then fixed with the aluminum keel.
5. The construction method of the assembled embedded energy-saving curtain wall system according to claim 1, characterized in that: in the step 5, before the aluminum alloy keel is installed, firstly, the straightness is checked, the checking method adopts a drawing method, if the straightness is not satisfactory, the aluminum keel is installed on the wall after being corrected, the error is controlled within an allowable range, and the installation sequence of the aluminum keel is as follows: the method comprises the steps of installing a steel keel of a wrap beam, installing an aluminum plate of the wrap beam, installing an aluminum keel of a wrap column, installing the aluminum keel of the wrap beam, assembling the aluminum frame by assembling the aluminum keel, installing an aluminum keel assembling working room on site, specially assembling the aluminum keel of the wrap beam and the aluminum keel of the wrap column, connecting the aluminum keel with a support by using stainless steel bolts, fixing the support with an embedded part by using bolts, continuously adjusting the verticality and the levelness of the keel in the installation process, finally tightening a nut for fixing, and after the keel is in place, carrying out installation and inspection according to steel wires and comprehensive construction drawings arranged during measurement to ensure that the axis of the keel has no deviation.
6. The construction method of the assembled embedded energy-saving curtain wall system according to claim 1, characterized in that: when the package beam and the package column glass are installed in the step 6, all keels of the workshop section are installed, the package column glass is erected indoors, the package column glass is manually moved to an installation position and then directly lifted to be installed on a wall for fixing, a scaffold is erected at the bottom of the hanging bottom glass to serve as a construction platform, a working platform on a manual station is used for installing the package beam glass, the package beam and the package column glass are installed on the same floor immediately after the package beam and the package column glass are installed, and the package beam, the package column glass and the embedded window on the same floor are all installed and then moved to the previous floor to install a glass panel.
7. The construction method of the assembled embedded energy-saving curtain wall system according to claim 1, characterized in that: in step 7, specifically, cleaning of the base material at the injection site, all construction surfaces related to the injection site must be cleaned and kept clean, ashless, non-dirty and dry, and for non-oily pollutants, an isopropanol solvent (50% isopropanol: water 1: 1) is adopted; xylene solvent is usually used for pollutants, and white or primary-color cotton cloth which is clean, soft and non-depilatory is used for cleaning cloth. When cleaning, the cleaning agent is poured on the cleaning cloth, the cloth cannot be dipped into a container containing the cleaning agent, so that the pollution of the whole solvent is avoided, the cleaning is carried out by adopting a 'twice wiping' process, and after the cleaning, the cleaned part is never allowed to contact with hands or other pollution sources; the double-sided adhesive tape is stuck, after the size and the shape of the aluminum frame are confirmed according to a design drawing, the double-sided adhesive tape is stuck at the center of the aluminum alloy keel according to the drawing requirement, when the double-sided adhesive tape is stuck, the adhesive tape is kept in a straight line, the adhesive tape is forcibly pressed down to be tightly attached to the aluminum alloy bracket, before glass is placed, the isolation paper of the adhesive tape is not required to be torn off so as to prevent the other sticking surface of the adhesive tape from being polluted, after the glass is fixed, the shape and the size of the glass are finally corrected, and when the glass is placed, the glass surface is guaranteed to be smooth, and the glass cannot be bent; before glue injection, carefully checking and checking whether the sealant is overdue or not, judging whether the mark of the used sealant is in accordance with a design drawing or not, flattening by using a scraper after glue injection, scraping redundant sealant, and finishing the exposed surface of the sealant, so as to protect the parts possibly causing the pollution of the aluminum alloy keel and glass in the glue injection and scraping processes and pasting a paper-based adhesive tape; standing and maintaining, wherein the glass component subjected to glue injection is required to be subjected to standing and maintaining in time, and the requirements of a standing and maintaining place are as follows: the temperature is 10-30 ℃, the relative humidity is 65-75%, the glass component is free of oil stain and a large amount of dust, the glass component which is not completely cured cannot be collided at will, the bonding force is prevented from being reduced, and the next construction operation can be carried out after the bonding force reaches the specified strength.
8. The construction method of the assembled embedded energy-saving curtain wall system according to claim 1, characterized in that: step 7 specifically be curtain wall glass, the aluminium alloy is before the mill dispatches from the factory, use protective film packing protection, in the installation, use the rag to clean, the curtain installation finishes the back, carry out whole cleanness, clean order is from top to bottom, clean with clear water and the special sanitizer of curtain, curtain in the construction adopts appropriate measure to protect, prevent the collision, the pollution, warp, phenomenons such as discoloring and drain pipe jam, in the construction, the adhesion thing that causes the influence to curtain and curtain component surface decoration in time clears away, resume its original state and original appearance, after the installation of glass curtain wall engineering, formulate and clean the scheme, wash curtain surface and exposed component. The neutral cleaning agent for cleaning glass and aluminum alloy parts is used after corrosion test is carried out before cleaning, and the neutral cleaning agent is used after no corrosion effect on aluminum alloy and glass is proved.
9. The construction method of the assembled embedded energy-saving curtain wall system according to claim 1, characterized in that: in step 11, before the aluminum profile is fed, the number, color difference and specification model of the aluminum profile are checked to determine whether the aluminum profile conforms to the profile required by the actual workpiece, whether the oxide film on the surface of the aluminum profile is intact or not is not damaged, the aluminum profile with too deep nicks and large-area scratches is removed, the aluminum profile with distortion and bending deformation is corrected and then fed, and the glass processing quality is rechecked before the glass plate is assembled. The method is characterized in that the method is carried out on the aspects of appearance, size deviation and the like, unqualified products are not allowed to be used, and correspondingly recorded, classified and stored, the unqualified products cannot be mixed with qualified products to be placed, the splicing seams of the curtain wall and the splicing seams of the glass lattices are vertical and horizontal, the seam width is uniform and meets the requirement of a drawing, the variety, the specification and the color of the glass conform to the design, the color is basically uniform, the phenomena of alkali precipitation and mildew and obvious color difference do not exist, the glass with the phenomenon of film coating falling is forbidden to be used, the surface of the aluminum alloy decorative gland is smooth, the defects of deformation ripple or local crushing and smashing and the like which can be detected by naked eyes do not exist, the seam position must strictly meet the design requirement, and the shielding seal of hidden nodes is neat and attractive.
10. The construction method of the assembled embedded energy-saving curtain wall system according to claim 1, characterized in that: when the patterned glass plate is safely and protectively installed in the installation process, attention should be paid to the protection of the integrity of the aluminum alloy keel without load impact deformation, the frame type curtain wall glass plate is installed, and the installation is slowly carried out by using a glass sucker, so that the protection is paid attention to; the safety measures of the special construction mechanical equipment are that construction equipment (such as a special lifting car, a winch and the like) for installing the curtain wall must be carried out before use, strict inspection is carried out, trial run tests are carried out on various safety protection devices, an electric hand drill, an electric screwdriver, a welding gun, an electric tool and the like must be carried out for insulation tests, a manual glass sucker and an electric glass sucker must be used for testing the adsorption weight and the adsorption duration, workers using a handheld electric tool according to operation rules need to be matched with protective tools, the mechanical workers wear the protective tools according to the rules, and mechanical operators and bench workers cannot wear gloves when using the electric drill or the grinding wheel.
CN202110887103.4A 2021-08-03 2021-08-03 Construction method of assembled embedded energy-saving curtain wall system Pending CN113585560A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110887103.4A CN113585560A (en) 2021-08-03 2021-08-03 Construction method of assembled embedded energy-saving curtain wall system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110887103.4A CN113585560A (en) 2021-08-03 2021-08-03 Construction method of assembled embedded energy-saving curtain wall system

Publications (1)

Publication Number Publication Date
CN113585560A true CN113585560A (en) 2021-11-02

Family

ID=78254466

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110887103.4A Pending CN113585560A (en) 2021-08-03 2021-08-03 Construction method of assembled embedded energy-saving curtain wall system

Country Status (1)

Country Link
CN (1) CN113585560A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117803116A (en) * 2024-02-29 2024-04-02 山东铭城环保新材料科技有限公司 Assembled curtain wall structure and construction method thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102242554A (en) * 2010-05-10 2011-11-16 天津市圣方幕墙装饰工程有限公司 Four-bit embedded glass curtain window system
CN107489215A (en) * 2017-07-27 2017-12-19 温州建设集团有限公司 A kind of construction technology of new network type glass curtain wall

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102242554A (en) * 2010-05-10 2011-11-16 天津市圣方幕墙装饰工程有限公司 Four-bit embedded glass curtain window system
CN107489215A (en) * 2017-07-27 2017-12-19 温州建设集团有限公司 A kind of construction technology of new network type glass curtain wall

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
刘尧: "节能型建筑玻璃幕墙施工工法的研究及应用", 《中国科技信息》 *
沈建平: "隐框玻璃幕墙在高层建筑中的关键施工技术", 《江西建材》 *
豆丁网: "大型low-e玻璃嵌型窗和包梁包柱系统幕墙施工工法", 《豆丁网-HTTPS://WWW.DOCIN.COM/P-2401609568.HTML》 *
马丽: "浅谈建筑幕墙施工质量控制的技术措施", 《建筑设计管理》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117803116A (en) * 2024-02-29 2024-04-02 山东铭城环保新材料科技有限公司 Assembled curtain wall structure and construction method thereof
CN117803116B (en) * 2024-02-29 2024-05-07 山东铭城环保新材料科技有限公司 Assembled curtain wall structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN108331216B (en) Installation method of large carved stone curtain wall
CN104631668A (en) Connection construction method for composite keel double-layer decorative curtain wall
CN113585560A (en) Construction method of assembled embedded energy-saving curtain wall system
CN110306704B (en) Hollow aluminum plate and glass composite curtain wall structure and mounting method thereof
CN111364767B (en) Construction method of short-slot dry-hanging argil plate
CN107035042B (en) Stone-imitated curtain wall system and construction method thereof
CN112127529A (en) Half unit assembled stone curtain wall structure
CN210797981U (en) Stone-like curtain wall system
CN114776034A (en) Glass curtain wall mounting construction process
CN108177731B (en) Method for building main pipe platform of liquid cargo ship
CN101509291B (en) Point type glass curtain wall construction technique
CN115178975A (en) Production process of energy storage box
CN110761560A (en) Mounting and construction method for steel bracket-arch lifting composite structure of pseudo-classic architecture
CN114000626B (en) Construction method of hyperbolic aluminum plate curtain wall
CN108729580B (en) Wall manufacturing method
CN210948322U (en) Glass and copper plate combined facing door supported by steel skeleton
CN115030518A (en) Sectional integral hoisting method for steel structure coal conveying trestle
CN103334524A (en) Construction method for spherical glass curtain wall with aluminum alloy hidden frame
CN103628602A (en) Building curtain wall glass fiber reinforcement composite board mounting assembly and method
CN114108893A (en) Construction process of high-strength aluminum plate curtain wall
GB2436847A (en) Stained Glass Window Frame Manufacturing Method
CN114439244A (en) Construction method of electric shuttle-shaped sun-shading shutter outside daylighting roof
CN118187462A (en) Curtain wall installation construction method
CN211499838U (en) Safety protective guard for construction unloading platform
CN213653929U (en) Half unit assembled stone curtain wall structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211102

RJ01 Rejection of invention patent application after publication