CN113557506A - 一种用于建筑施工的多塔吊布置方法 - Google Patents
一种用于建筑施工的多塔吊布置方法 Download PDFInfo
- Publication number
- CN113557506A CN113557506A CN201980093616.9A CN201980093616A CN113557506A CN 113557506 A CN113557506 A CN 113557506A CN 201980093616 A CN201980093616 A CN 201980093616A CN 113557506 A CN113557506 A CN 113557506A
- Authority
- CN
- China
- Prior art keywords
- tower crane
- building
- contour line
- discretization
- tower
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
- G06F17/40—Data acquisition and logging
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Computer Hardware Design (AREA)
- Data Mining & Analysis (AREA)
- Databases & Information Systems (AREA)
- Mathematical Physics (AREA)
- Software Systems (AREA)
- General Physics & Mathematics (AREA)
- Jib Cranes (AREA)
- Control And Safety Of Cranes (AREA)
Abstract
本发明提供一种用于建筑施工的多塔吊布置方法,包括步骤:获取建筑轮廓线,设定禁止布置塔吊区域和塔吊基本参数;离散化建筑轮廓线,得到建筑离散化点;将建筑轮廓线向外偏移预设距离,得到塔吊布置轮廓线,离散化所述塔吊布置轮廓线,得到塔吊离散化点;根据禁止布置塔吊区域和塔吊基本参数,删除不可用的塔吊离散化点,得到塔吊可布置点;根据塔吊数量,确定塔吊可布置工况。本发明的方法首次提出通过将建筑轮廓线和塔吊布置轮廓线进行离散化,能够量化地计算获得建筑施工过程中的多塔吊可布置工况以及最佳布置工况,该方法简单可靠、耗时短、计算效率高,精确性好。
Description
PCT国内申请,说明书已公开。
Claims (8)
- PCT国内申请,权利要求书已公开。
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PCT/CN2019/113072 WO2021077370A1 (zh) | 2019-10-24 | 2019-10-24 | 一种用于建筑施工的多塔吊布置方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113557506A true CN113557506A (zh) | 2021-10-26 |
CN113557506B CN113557506B (zh) | 2022-04-26 |
Family
ID=75619574
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201980093616.9A Active CN113557506B (zh) | 2019-10-24 | 2019-10-24 | 一种可量化、程序化的建筑施工群塔优化布置方法 |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN113557506B (zh) |
WO (1) | WO2021077370A1 (zh) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113128077B (zh) * | 2021-05-25 | 2024-04-23 | 上海建工四建集团有限公司 | 一种群塔竖向爬升策划数字仿真优化方法 |
CN113449401B (zh) * | 2021-07-27 | 2023-01-20 | 哈尔滨工业大学(深圳) | 一种塔吊反力识别方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103967040A (zh) * | 2014-05-19 | 2014-08-06 | 中国建筑第八工程局有限公司 | 塔吊基础结构及其施工方法 |
CN105731262A (zh) * | 2016-04-01 | 2016-07-06 | 中国建筑第八工程局有限公司 | 基于bim技术的塔吊平面布置系统及方法 |
CN106986275A (zh) * | 2017-03-13 | 2017-07-28 | 同济大学 | 一种基于bim的装配式建筑塔吊平面布置及选型方法 |
CN109086490A (zh) * | 2018-07-04 | 2018-12-25 | 中国二十冶集团有限公司 | 一种装配式工程基于bim技术的塔吊选型布置方法 |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2943961C2 (de) * | 1979-10-31 | 1983-03-24 | Aka Aufbereitung-Konstruktion-Anlagen Gesellschaft Fuer Kohle-Erz-Schlamm-Und Muellaufbereitung Mbh, 4350 Recklinghausen | Anlage zur Aufbereitung von Kohle, Erz o.dgl. |
CN103791894A (zh) * | 2014-02-18 | 2014-05-14 | 北京恒华伟业科技股份有限公司 | 用于架空输电线路的杆塔定位方法和装置 |
CN108038265A (zh) * | 2017-11-17 | 2018-05-15 | 上海二十冶建设有限公司 | 一种基于bim的山地建筑群施工临时道路布置方法 |
CN108319741A (zh) * | 2017-12-12 | 2018-07-24 | 上海建工五建集团有限公司 | 基于bim的塔吊布置比选方法及系统 |
-
2019
- 2019-10-24 WO PCT/CN2019/113072 patent/WO2021077370A1/zh active Application Filing
- 2019-10-24 CN CN201980093616.9A patent/CN113557506B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103967040A (zh) * | 2014-05-19 | 2014-08-06 | 中国建筑第八工程局有限公司 | 塔吊基础结构及其施工方法 |
CN105731262A (zh) * | 2016-04-01 | 2016-07-06 | 中国建筑第八工程局有限公司 | 基于bim技术的塔吊平面布置系统及方法 |
CN106986275A (zh) * | 2017-03-13 | 2017-07-28 | 同济大学 | 一种基于bim的装配式建筑塔吊平面布置及选型方法 |
CN109086490A (zh) * | 2018-07-04 | 2018-12-25 | 中国二十冶集团有限公司 | 一种装配式工程基于bim技术的塔吊选型布置方法 |
Non-Patent Citations (2)
Title |
---|
沈蔚等: "基于LIDAR数据的建筑轮廓线提取及规则化算法研究", 《遥感学报》 * |
童礼华等: "地面LiDAR数据中建筑轮廓和角点提取", 《中国图象图形学报》 * |
Also Published As
Publication number | Publication date |
---|---|
WO2021077370A1 (zh) | 2021-04-29 |
CN113557506B (zh) | 2022-04-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113557506B (zh) | 一种可量化、程序化的建筑施工群塔优化布置方法 | |
CN103162671B (zh) | 异型建筑物测量施工方法 | |
CN110485737A (zh) | 一种基于bim技术的钢网架定位安装施工方法 | |
CN201402324Y (zh) | 高压架空输电线路机载三维激光雷达检测系统 | |
CN109138446A (zh) | 一种大跨度管桁架吊装方法 | |
CN108169769B (zh) | 一种群塔防碰撞的方法 | |
CN110182303B (zh) | 一种挂舵臂的总组方法 | |
CN205537756U (zh) | 一种基于北斗的监测系统 | |
CN109064037A (zh) | 基坑施工风险管控方法、系统和设备 | |
CN105484299A (zh) | 用于确定桩基中心的收缩定位支架及其施工方法 | |
CN107367711A (zh) | 一种井下人员定位算法的仿真实验方法 | |
CN108277882A (zh) | 恶劣条件下特大型钢结构雨棚施工工艺 | |
CN107066748B (zh) | 一种用于桥梁风致振动监测的无线传感器布设方法 | |
Hasan et al. | Integrated building information model to identify possible crane instability caused by strong winds | |
Du et al. | GIS, GPS, and BIM-based risk control of subway station construction | |
CN104236618A (zh) | 泵车间臂架姿态防碰撞检测方法及系统 | |
CN104964674A (zh) | 用于大型结构物建造尺寸的控制网 | |
CN104021266A (zh) | 一种适用于海洋工程船的风载荷计算方法 | |
CN113671585B (zh) | 一种掘进巷道智能化瞬变电磁探测与实时预警方法 | |
CN103628511B (zh) | 一种用于桩基护筒的放样投点方法 | |
CN111561918B (zh) | 一种圆形结构微网监测方法 | |
CN212375857U (zh) | 一种深水桩基钢护筒位姿定位装置 | |
CN108510589A (zh) | 二维管线到三维模型的转换方法及装置 | |
CN107724689A (zh) | 一种建筑工程钢结构测量施工方法 | |
CN113987614A (zh) | 一种基于Revit平台的地下室支承点网自动生成装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |