CN113445511A - Deep foundation pit assembled type safety channel reinforcing method and construction steps - Google Patents

Deep foundation pit assembled type safety channel reinforcing method and construction steps Download PDF

Info

Publication number
CN113445511A
CN113445511A CN202110322435.8A CN202110322435A CN113445511A CN 113445511 A CN113445511 A CN 113445511A CN 202110322435 A CN202110322435 A CN 202110322435A CN 113445511 A CN113445511 A CN 113445511A
Authority
CN
China
Prior art keywords
parts
bottom plate
pouring
templates
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110322435.8A
Other languages
Chinese (zh)
Inventor
吴潮丰
练建平
蒙亮灼
张驰
吕智强
史勤来
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Shenan Enterprise Co ltd
Original Assignee
Shenzhen Shenan Enterprise Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Shenan Enterprise Co ltd filed Critical Shenzhen Shenan Enterprise Co ltd
Priority to CN202110322435.8A priority Critical patent/CN113445511A/en
Publication of CN113445511A publication Critical patent/CN113445511A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes

Abstract

The invention discloses a deep foundation pit assembled type safety channel reinforcing method and construction steps, and particularly relates to the field of building construction, wherein the method comprises the following steps: s1, job face processing: roughening the bottom plate and the side wall of the safety channel, and cleaning by adopting high-pressure water; s2, unit steel bar binding: dividing the length of the safety channel into N sections, and binding a side wall and a bottom plate steel bar of a first section along one side of the safety channel in the length direction; s3, building a unit bracket: and erecting a first section of support above the bottom plate of the first section to serve as a foundation for the pressure casting working platform and the later unit template support. According to the invention, through the assembly of the unit templates, the bottom and the side walls of the safety channel can be poured, and the concrete reinforcing layers can be formed on the side walls and the bottom of the safety channel, so that the safety channel is reinforced, the construction is simple, and the period is short.

Description

Deep foundation pit assembled type safety channel reinforcing method and construction steps
Technical Field
The invention relates to the technical field of building construction, in particular to a method for reinforcing a deep foundation pit assembled type safety channel and a construction step.
Background
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, and also can be a process of changing various lines on a design drawing into a real object at a specified place. The method comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like.
In recent years, with the rapid development of the building industry, the number of deep foundation pits is more and more, a safety channel is dug in the deep foundation pit, a steel pipe scaffold is mostly adopted for temporarily setting up the vertical safety channel of the deep foundation pit for supporting, meanwhile, the foundation pit is always in a digging state, the rigidity of the temporary channel set up by the steel pipe scaffold is small, the deformation is large, the potential safety hazard is great, a large amount of labor and materials are consumed, and the economic benefit is poor; or after the foundation pit is constructed to the bottom of the pit, the foundation of the vertical safety channel is designed and manufactured, and then the foundation is installed from bottom to top for supporting, so that potential safety hazards exist during use, and therefore the deep foundation pit assembly type safety channel reinforcing method and the construction steps are provided.
Disclosure of Invention
In order to overcome the above-mentioned defects in the prior art, embodiments of the present invention provide a method and a construction step for reinforcing an assembled security tunnel of a deep foundation pit, so as to solve the above-mentioned problems in the background art.
In order to achieve the purpose, the invention provides the following technical scheme: a deep foundation pit fabricated safety channel reinforcing method and construction steps comprise the following steps:
s1, job face processing: roughening the bottom plate and the side wall of the safety channel, and cleaning by adopting high-pressure water;
s2, unit steel bar binding: dividing the length of the safety channel into N sections, and binding a side wall and a bottom plate steel bar of a first section along one side of the safety channel in the length direction;
s3, building a unit bracket: erecting a first section of support above the bottom plate of the first section to serve as a foundation for a pressure casting working platform and a later unit template support;
s4, unit template installation: the safety channel comprises two side walls and a bottom plate, wherein the closed templates are erected on the two side walls and the bottom plate, the closed templates comprise side wall templates and bottom plate templates, lateral pouring openings are reserved at the upper parts of the two side wall templates respectively, a plurality of pouring openings and grout outlets close to the bottom plate are reserved at the lateral sides of the bottom plate templates, and grouting pipes which vertically penetrate through the bottom plate templates and extend to the bottom plate are reserved in the middle of the bottom plate templates;
s5, preparing concrete: mixing and stirring concrete raw materials uniformly by a stirrer, wherein the concrete raw materials comprise, by weight, 20-60 parts of fine sand, 5-10 parts of broken stone, 35-65 parts of cement, 1-3 parts of a water reducing agent, 4-7 parts of gypsum powder, 1-2 parts of an early strength agent, 3-6 parts of a slow release agent, 3-5 parts of a defoaming agent, 3-5 parts of composite fibers and 35-55 parts of water;
s6, pouring concrete: respectively pouring the side walls and the bottom plate;
s7, grouting: performing pressure grouting from an opening at the lower end of the grouting pipe; the grouting material is cement slurry, and the cement slurry comprises, by weight, 40-80 parts of cement, 150-250 parts of fly ash, 30-90 parts of bentonite, 700-1000 parts of fine sand, 200-300 parts of water and 0-40 parts of an additive; the grouting pressure is 0.25-0.55 Mpa, and the pressurizing time is 10-12 seconds;
s8, repeating the construction process of the side wall in the steps S2 to S7, and constructing the rest sections of the side wall in sequence until the pouring of the whole safe channel is completed;
s9, concrete curing: and after the whole safe channel is poured for 12 hours, spraying and maintaining the poured surface for 3-5 days.
Further, the side wall pouring is to symmetrically pour two side walls from the lateral pouring openings at the same time respectively, the lateral pouring openings are plugged after concrete is poured to the lateral pouring openings, then the side walls are symmetrically poured from the bottom plate pouring openings at the two ends of the bottom plate template at the same time until the concrete flows out of the grout outlet openings at the two ends of the bottom plate template, and the pouring of the two side walls is completed.
Further, the bottom plate pouring is that the bottom plates are poured from the bottom plate pouring openings in the middle of the bottom plate formwork to the two sides respectively until the concrete flows out of the corresponding grout outlet, and finally, the bottom plate pouring openings on the two sides of the bottom plate formwork are poured symmetrically at the same time until the concrete flows out of the corresponding grout outlet, so that the bottom plate pouring is completed.
Further, the concrete material in the step S5 comprises the following raw materials, by weight, 40 parts of fine sand, 8 parts of gravel, 50 parts of cement, 2 parts of a water reducing agent, 5 parts of gypsum powder, 1.5 parts of an early strength agent, 4 parts of a slow release agent, 4 parts of a defoaming agent, 4 parts of composite fiber and 45 parts of water.
Further, the cement slurry in the step S7 includes, by weight, 60 parts of cement, 200 parts of fly ash, 60 parts of bentonite, 900 parts of fine sand, 250 parts of water, and 10 parts of an additive.
Further, in step S4, the joints are bonded by using a sponge tape when the unit templates are mounted, and the joints are flat.
Furthermore, the granularity of the fine sand is 120-180 meshes, and the particle size of the broken stone is smaller than 8 mm.
Further, in step S6, the pouring pipe is inserted from the bottom plate pouring opening during the bottom plate pouring, the pouring condition is observed from the adjacent bottom plate pouring opening, and the pouring pipe is slowly pulled out to the bottom plate pouring opening while pouring.
The invention has the technical effects and advantages that:
according to the invention, through the assembly of the unit templates, the bottom and the side walls of the safety channel can be poured, and the concrete reinforcing layers can be formed on the side walls and the bottom of the safety channel, so that the safety channel is reinforced, the construction is simple, and the period is short.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The invention provides a deep foundation pit assembled type safe channel reinforcing method and a construction step, wherein the method comprises the following steps:
s1, job face processing: roughening the bottom plate and the side wall of the safety channel, and cleaning by adopting high-pressure water;
s2, unit steel bar binding: dividing the length of the safety channel into N sections, and binding a side wall and a bottom plate steel bar of a first section along one side of the safety channel in the length direction;
s3, building a unit bracket: erecting a first section of support above the bottom plate of the first section to serve as a foundation for a pressure casting working platform and a later unit template support;
s4, unit template installation: the safety channel comprises two side walls and a bottom plate, wherein the closed templates are erected on the two side walls and the bottom plate, the closed templates comprise side wall templates and bottom plate templates, lateral pouring openings are reserved at the upper parts of the two side wall templates respectively, a plurality of pouring openings and grout outlets close to the bottom plate are reserved laterally in the bottom plate templates, grouting pipes which vertically penetrate through the bottom plate templates and extend to the bottom plate are reserved in the middle of the bottom plate templates, and joints are bonded by sponge adhesive tapes when the unit templates are installed and are smooth;
s5, preparing concrete: mixing and stirring concrete raw materials uniformly by a stirrer, wherein the concrete raw materials comprise, by weight, 20-60 parts of fine sand, 5-10 parts of broken stone, 35-65 parts of cement, 1-3 parts of a water reducing agent, 4-7 parts of gypsum powder, 1-2 parts of an early strength agent, 3-6 parts of a slow release agent, 3-5 parts of a defoaming agent, 3-5 parts of composite fibers and 35-55 parts of water;
s6, pouring concrete: respectively pouring the side walls and the bottom plate;
s7, grouting: performing pressure grouting from an opening at the lower end of the grouting pipe; the grouting material is cement slurry, and the cement slurry comprises, by weight, 40-80 parts of cement, 150-250 parts of fly ash, 30-90 parts of bentonite, 700-1000 parts of fine sand, 200-300 parts of water and 0-40 parts of an additive; the grouting pressure is 0.25-0.55 Mpa, and the pressurizing time is 10-12 seconds;
s8, repeating the construction process of the side wall in the steps S2 to S7, and constructing the rest sections of the side wall in sequence until the pouring of the whole safe channel is completed;
s9, concrete curing: and after the whole safe channel is poured for 12 hours, spraying and maintaining the poured surface for 3-5 days.
The side wall pouring is characterized in that two side walls are symmetrically poured from the side pouring openings at the same time respectively, the side pouring openings are plugged after concrete is poured to the side pouring openings, then bottom plate pouring is symmetrically poured from the bottom plate pouring openings at two ends of the bottom plate template at the same time until the concrete flows out of the grout outlet at two ends of the bottom plate template, pouring of the two side walls is completed, the bottom plate pouring is that bottom plates are poured from the bottom plate pouring openings at the middle part of the bottom plate template to two sides respectively until the concrete flows out of the corresponding grout outlet, finally, the bottom plate pouring is simultaneously and symmetrically poured from the bottom plate pouring openings at two sides of the bottom plate template until the concrete flows out of the corresponding grout outlet, pouring of the bottom plate is completed, pouring pipes are inserted from the bottom plate pouring openings when the bottom plate is poured, pouring conditions are observed from the adjacent bottom plate pouring openings, and the pouring pipes are slowly pulled out to the bottom plate pouring openings while pouring.
Wherein the particle size of the fine sand is 120-180 meshes, and the particle size of the broken stone is less than 8 mm.
Example 1
The invention provides a deep foundation pit assembled type safe channel reinforcing method and a construction step, wherein the method comprises the following steps:
s1, job face processing: roughening the bottom plate and the side wall of the safety channel, and cleaning by adopting high-pressure water;
s2, unit steel bar binding: dividing the length of the safety channel into N sections, and binding a side wall and a bottom plate steel bar of a first section along one side of the safety channel in the length direction;
s3, building a unit bracket: erecting a first section of support above the bottom plate of the first section to serve as a foundation for a pressure casting working platform and a later unit template support;
s4, unit template installation: the safety channel comprises two side walls and a bottom plate, wherein the closed templates are erected on the two side walls and the bottom plate, the closed templates comprise side wall templates and bottom plate templates, lateral pouring openings are reserved at the upper parts of the two side wall templates respectively, a plurality of pouring openings and grout outlets close to the bottom plate are reserved laterally in the bottom plate templates, grouting pipes which vertically penetrate through the bottom plate templates and extend to the bottom plate are reserved in the middle of the bottom plate templates, and joints are bonded by sponge adhesive tapes when the unit templates are installed and are smooth;
s5, preparing concrete: mixing and stirring concrete raw materials uniformly by a stirrer, wherein the concrete raw materials comprise, by weight, 60 parts of fine sand, 10 parts of broken stone, 65 parts of cement, 3 parts of a water reducing agent, 7 parts of gypsum powder, 2 parts of an early strength agent, 6 parts of a slow release agent, 5 parts of a defoaming agent, 5 parts of composite fiber and 55 parts of water;
s6, pouring concrete: respectively pouring the side walls and the bottom plate;
s7, grouting: performing pressure grouting from an opening at the lower end of the grouting pipe; the grouting adopts cement slurry, and the cement slurry comprises 80 parts of cement, 250 parts of fly ash, 90 parts of bentonite, 1000 parts of fine sand, 300 parts of water and 40 parts of additive in parts by weight; the grouting pressure is 0.25-0.55 Mpa, and the pressurizing time is 10-12 seconds;
s8, repeating the construction process of the side wall in the steps S2 to S7, and constructing the rest sections of the side wall in sequence until the pouring of the whole safe channel is completed;
s9, concrete curing: and after the whole safe channel is poured for 12 hours, spraying and maintaining the poured surface for 3-5 days.
The side wall pouring is characterized in that two side walls are symmetrically poured from the side pouring openings at the same time respectively, the side pouring openings are plugged after concrete is poured to the side pouring openings, then bottom plate pouring is symmetrically poured from the bottom plate pouring openings at two ends of the bottom plate template at the same time until the concrete flows out of the grout outlet at two ends of the bottom plate template, pouring of the two side walls is completed, the bottom plate pouring is that bottom plates are poured from the bottom plate pouring openings at the middle part of the bottom plate template to two sides respectively until the concrete flows out of the corresponding grout outlet, finally, the bottom plate pouring is simultaneously and symmetrically poured from the bottom plate pouring openings at two sides of the bottom plate template until the concrete flows out of the corresponding grout outlet, pouring of the bottom plate is completed, pouring pipes are inserted from the bottom plate pouring openings when the bottom plate is poured, pouring conditions are observed from the adjacent bottom plate pouring openings, and the pouring pipes are slowly pulled out to the bottom plate pouring openings while pouring.
Wherein the particle size of the fine sand is 120-180 meshes, and the particle size of the broken stone is less than 8 mm.
Example 2
The invention provides a deep foundation pit assembled type safe channel reinforcing method and a construction step, wherein the method comprises the following steps:
s1, job face processing: roughening the bottom plate and the side wall of the safety channel, and cleaning by adopting high-pressure water;
s2, unit steel bar binding: dividing the length of the safety channel into N sections, and binding a side wall and a bottom plate steel bar of a first section along one side of the safety channel in the length direction;
s3, building a unit bracket: erecting a first section of support above the bottom plate of the first section to serve as a foundation for a pressure casting working platform and a later unit template support;
s4, unit template installation: the safety channel comprises two side walls and a bottom plate, wherein the closed templates are erected on the two side walls and the bottom plate, the closed templates comprise side wall templates and bottom plate templates, lateral pouring openings are reserved at the upper parts of the two side wall templates respectively, a plurality of pouring openings and grout outlets close to the bottom plate are reserved laterally in the bottom plate templates, grouting pipes which vertically penetrate through the bottom plate templates and extend to the bottom plate are reserved in the middle of the bottom plate templates, and joints are bonded by sponge adhesive tapes when the unit templates are installed and are smooth;
s5, preparing concrete: mixing and stirring concrete raw materials uniformly by a stirrer, wherein the concrete raw materials comprise, by weight, 20 parts of fine sand, 5 parts of gravel, 35 parts of cement, 1 part of a water reducing agent, 4 parts of gypsum powder, 1 part of an early strength agent, 3 parts of a slow release agent, 3 parts of a defoaming agent, 3 parts of composite fibers and 35 parts of water;
s6, pouring concrete: respectively pouring the side walls and the bottom plate;
s7, grouting: performing pressure grouting from an opening at the lower end of the grouting pipe; the grouting adopts cement slurry, and the cement slurry comprises, by weight, 40 parts of cement, 150 parts of fly ash, 30 parts of bentonite, 700 parts of fine sand, 200 parts of water and 5 parts of an additive; the grouting pressure is 0.25-0.55 Mpa, and the pressurizing time is 10-12 seconds;
s8, repeating the construction process of the side wall in the steps S2 to S7, and constructing the rest sections of the side wall in sequence until the pouring of the whole safe channel is completed;
s9, concrete curing: and after the whole safe channel is poured for 12 hours, spraying and maintaining the poured surface for 3-5 days.
The side wall pouring is characterized in that two side walls are symmetrically poured from the side pouring openings at the same time respectively, the side pouring openings are plugged after concrete is poured to the side pouring openings, then bottom plate pouring is symmetrically poured from the bottom plate pouring openings at two ends of the bottom plate template at the same time until the concrete flows out of the grout outlet at two ends of the bottom plate template, pouring of the two side walls is completed, the bottom plate pouring is that bottom plates are poured from the bottom plate pouring openings at the middle part of the bottom plate template to two sides respectively until the concrete flows out of the corresponding grout outlet, finally, the bottom plate pouring is simultaneously and symmetrically poured from the bottom plate pouring openings at two sides of the bottom plate template until the concrete flows out of the corresponding grout outlet, pouring of the bottom plate is completed, pouring pipes are inserted from the bottom plate pouring openings when the bottom plate is poured, pouring conditions are observed from the adjacent bottom plate pouring openings, and the pouring pipes are slowly pulled out to the bottom plate pouring openings while pouring.
Wherein the particle size of the fine sand is 120-180 meshes, and the particle size of the broken stone is less than 8 mm.
Example 3
A deep foundation pit fabricated safety channel reinforcing method and construction steps comprise the following steps:
s1, job face processing: roughening the bottom plate and the side wall of the safety channel, and cleaning by adopting high-pressure water;
s2, unit steel bar binding: dividing the length of the safety channel into N sections, and binding a side wall and a bottom plate steel bar of a first section along one side of the safety channel in the length direction;
s3, building a unit bracket: erecting a first section of support above the bottom plate of the first section to serve as a foundation for a pressure casting working platform and a later unit template support;
s4, unit template installation: the safety channel comprises two side walls and a bottom plate, wherein the closed templates are erected on the two side walls and the bottom plate, the closed templates comprise side wall templates and bottom plate templates, lateral pouring openings are reserved at the upper parts of the two side wall templates respectively, a plurality of pouring openings and grout outlets close to the bottom plate are reserved laterally in the bottom plate templates, grouting pipes which vertically penetrate through the bottom plate templates and extend to the bottom plate are reserved in the middle of the bottom plate templates, and joints are bonded by sponge adhesive tapes when the unit templates are installed and are smooth;
s5, preparing concrete: mixing and stirring concrete raw materials uniformly by a stirrer, wherein the concrete raw materials comprise, by weight, 40 parts of fine sand, 8 parts of broken stone, 50 parts of cement, 2 parts of a water reducing agent, 5 parts of gypsum powder, 1.5 parts of an early strength agent, 4 parts of a slow release agent, 4 parts of a defoaming agent, 4 parts of composite fiber and 45 parts of water;
s6, pouring concrete: respectively pouring the side walls and the bottom plate;
s7, grouting: performing pressure grouting from an opening at the lower end of the grouting pipe; the grouting adopts cement slurry, and the cement slurry comprises, by weight, 60 parts of cement, 200 parts of fly ash, 60 parts of bentonite, 900 parts of fine sand, 250 parts of water and 10 parts of an additive;
s8, repeating the construction process of the side wall in the steps S2 to S7, and constructing the rest sections of the side wall in sequence until the pouring of the whole safe channel is completed;
s9, concrete curing: and after the whole safe channel is poured for 12 hours, spraying and maintaining the poured surface for 3-5 days.
The side wall pouring is characterized in that two side walls are symmetrically poured from the side pouring openings at the same time respectively, the side pouring openings are plugged after concrete is poured to the side pouring openings, then bottom plate pouring is symmetrically poured from the bottom plate pouring openings at two ends of the bottom plate template at the same time until the concrete flows out of the grout outlet at two ends of the bottom plate template, pouring of the two side walls is completed, the bottom plate pouring is that bottom plates are poured from the bottom plate pouring openings at the middle part of the bottom plate template to two sides respectively until the concrete flows out of the corresponding grout outlet, finally, the bottom plate pouring is simultaneously and symmetrically poured from the bottom plate pouring openings at two sides of the bottom plate template until the concrete flows out of the corresponding grout outlet, pouring of the bottom plate is completed, pouring pipes are inserted from the bottom plate pouring openings when the bottom plate is poured, pouring conditions are observed from the adjacent bottom plate pouring openings, and the pouring pipes are slowly pulled out to the bottom plate pouring openings while pouring.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that are within the spirit and principle of the present invention are intended to be included in the scope of the present invention.

Claims (8)

1. A deep foundation pit fabricated safety channel reinforcing method and construction steps are characterized by comprising the following steps:
s1, job face processing: roughening the bottom plate and the side wall of the safety channel, and cleaning by adopting high-pressure water;
s2, unit steel bar binding: dividing the length of the safety channel into N sections, and binding a side wall and a bottom plate steel bar of a first section along one side of the safety channel in the length direction;
s3, building a unit bracket: erecting a first section of support above the bottom plate of the first section to serve as a foundation for a pressure casting working platform and a later unit template support;
s4, unit template installation: the safety channel comprises two side walls and a bottom plate, wherein the closed templates are erected on the two side walls and the bottom plate, the closed templates comprise side wall templates and bottom plate templates, lateral pouring openings are reserved at the upper parts of the two side wall templates respectively, a plurality of pouring openings and grout outlets close to the bottom plate are reserved at the lateral sides of the bottom plate templates, and grouting pipes which vertically penetrate through the bottom plate templates and extend to the bottom plate are reserved in the middle of the bottom plate templates;
s5, preparing concrete: mixing and stirring concrete raw materials uniformly by a stirrer, wherein the concrete raw materials comprise, by weight, 20-60 parts of fine sand, 5-10 parts of broken stone, 35-65 parts of cement, 1-3 parts of a water reducing agent, 4-7 parts of gypsum powder, 1-2 parts of an early strength agent, 3-6 parts of a slow release agent, 3-5 parts of a defoaming agent, 3-5 parts of composite fibers and 35-55 parts of water;
s6, pouring concrete: respectively pouring the side walls and the bottom plate;
s7, grouting: performing pressure grouting from an opening at the lower end of the grouting pipe; the grouting material is cement slurry, and the cement slurry comprises, by weight, 40-80 parts of cement, 150-250 parts of fly ash, 30-90 parts of bentonite, 700-1000 parts of fine sand, 200-300 parts of water and 0-40 parts of an additive; the grouting pressure is 0.25-0.55 Mpa, and the pressurizing time is 10-12 seconds;
s8, repeating the construction process of the side wall in the steps S2 to S7, and constructing the rest sections of the side wall in sequence until the pouring of the whole safe channel is completed;
s9, concrete curing: and after the whole safe channel is poured for 12 hours, spraying and maintaining the poured surface for 3-5 days.
2. The deep foundation pit assembled type safe channel reinforcing method and construction steps according to claim 1 are characterized in that: the side wall pouring is to symmetrically pour two side walls from the side pouring openings at the same time respectively, the side pouring openings are plugged after concrete is poured to the side pouring openings, then the side pouring openings at two ends of the bottom plate template are symmetrically poured at the same time until the concrete flows out of the grout outlet at two ends of the bottom plate template, and the pouring of the two side walls is completed.
3. The deep foundation pit assembled type safe channel reinforcing method and construction steps according to claim 2 are characterized in that: and the bottom plate pouring is that the bottom plates are poured from the bottom plate pouring openings in the middle of the bottom plate template to two sides respectively until the concrete flows out of the corresponding grout outlet, and finally, the bottom plate pouring openings on the two sides of the bottom plate template are symmetrically poured simultaneously until the concrete flows out of the corresponding grout outlet, so that the pouring of the bottom plates is completed.
4. The deep foundation pit assembled type safe channel reinforcing method and construction steps according to claim 3 are characterized in that: the concrete material in the step S5 comprises the following raw materials, by weight, 40 parts of fine sand, 8 parts of broken stone, 50 parts of cement, 2 parts of a water reducing agent, 5 parts of gypsum powder, 1.5 parts of an early strength agent, 4 parts of a slow release agent, 4 parts of a defoaming agent, 4 parts of composite fiber and 45 parts of water.
5. The deep foundation pit assembled type safe channel reinforcing method and construction steps according to claim 4 are characterized in that: the cement slurry in the step S7 comprises, by weight, 60 parts of cement, 200 parts of fly ash, 60 parts of bentonite, 900 parts of fine sand, 250 parts of water and 10 parts of an additive.
6. The deep foundation pit assembled type safe channel reinforcing method and construction steps according to claim 5 are characterized in that: in step S4, the joints are bonded by sponge tapes when the unit templates are installed, and the joints are flat.
7. The deep foundation pit assembled type safe channel reinforcing method and construction steps according to claim 6 are characterized in that: the particle size of the fine sand is 120-180 meshes, and the particle size of the broken stone is smaller than 8 mm.
8. The deep foundation pit assembled type safe channel reinforcing method and construction steps according to claim 7 are characterized in that: in step S6, the pouring pipe is inserted from the bottom plate pouring opening during the bottom plate pouring, the pouring condition is observed from the adjacent bottom plate pouring opening, and the pouring pipe is slowly pulled out to the bottom plate pouring opening while pouring.
CN202110322435.8A 2021-03-25 2021-03-25 Deep foundation pit assembled type safety channel reinforcing method and construction steps Pending CN113445511A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110322435.8A CN113445511A (en) 2021-03-25 2021-03-25 Deep foundation pit assembled type safety channel reinforcing method and construction steps

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110322435.8A CN113445511A (en) 2021-03-25 2021-03-25 Deep foundation pit assembled type safety channel reinforcing method and construction steps

Publications (1)

Publication Number Publication Date
CN113445511A true CN113445511A (en) 2021-09-28

Family

ID=77809440

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110322435.8A Pending CN113445511A (en) 2021-03-25 2021-03-25 Deep foundation pit assembled type safety channel reinforcing method and construction steps

Country Status (1)

Country Link
CN (1) CN113445511A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2824541A1 (en) * 1977-06-10 1978-12-21 Jean Marie Gerard Rene Koehl DEVICE FOR STRENGTHENING THE WALLS OF BUILDING DITCHES, PIPE DITCHES, etc.
CN206800484U (en) * 2017-04-01 2017-12-26 周兆弟 Ruggedized construction for underpass
CN110468744A (en) * 2019-08-26 2019-11-19 北京奥科瑞检测技术开发有限公司 A kind of channel bridge reinforced construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2824541A1 (en) * 1977-06-10 1978-12-21 Jean Marie Gerard Rene Koehl DEVICE FOR STRENGTHENING THE WALLS OF BUILDING DITCHES, PIPE DITCHES, etc.
CN206800484U (en) * 2017-04-01 2017-12-26 周兆弟 Ruggedized construction for underpass
CN110468744A (en) * 2019-08-26 2019-11-19 北京奥科瑞检测技术开发有限公司 A kind of channel bridge reinforced construction method

Similar Documents

Publication Publication Date Title
CN105317137B (en) Precast wall body, wallboard and its construction method and prefabricated panel production method
CN103615053B (en) Monolithic reinforced concrete structure post empiricism engineering method
CN103469825B (en) The prefabricated water resistant template in ater-casting and mounting method
CN108005387B (en) Synchronous construction method for cast-in-place main body of assembled wallboard and short-limb shear wall
CN102116061A (en) Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN104405062A (en) Integrated column-equipped heat preservation wallboard, production and building techniques and matched equipment
CN108343148B (en) A kind of frame structure system and its construction method
CN109853956A (en) Residential building construction method
CN105780992B (en) A kind of orthogonal spatial Rc Open-web Sandwich Plates floor construction engineering method
CN101302783A (en) Building cast-in-situ roof
CN205224332U (en) Prefabricated wall body and prefabricated wallboard
CN106894538A (en) Filling wall and agent structure concrete integral shaping method
CN102535841A (en) Construction technology of prefabricated wall panel
CN106988319A (en) A kind of rapid constructing method of large deep foundation pit agent structure side wall
CN114164977A (en) Method for combining construction of aluminum template and laminated slab
CN107237330B (en) A kind of reinforced concrete inner support beam construction method of no bed die
CN110468744B (en) Channel bridge reinforcement construction method
CN210117716U (en) Trapezoidal foundation ditch lateral wall concrete typical forms of elevartor shaft
CN108130889B (en) Manufacturing method of stepped construction joint between main bottom plate of pump brake and side wall of runner layer
CN113445511A (en) Deep foundation pit assembled type safety channel reinforcing method and construction steps
US20220234248A1 (en) Solid waste large-mixing-amount concrete prefabricated laminated slab and preparation method thereof
CN205476468U (en) Non - design, can all rotary die plate bodys be prefabricated staircase bench template
CN109944265A (en) The method for carrying out foundation construction using concrete light scutum
CN104790565A (en) Cast-in-site ardealite load bearing wall composite structure main building construction method
CN211172565U (en) A ram for argil brick facade

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210928