CN113417402A - Ceiling system capable of being installed quickly and installation method thereof - Google Patents

Ceiling system capable of being installed quickly and installation method thereof Download PDF

Info

Publication number
CN113417402A
CN113417402A CN202110794077.0A CN202110794077A CN113417402A CN 113417402 A CN113417402 A CN 113417402A CN 202110794077 A CN202110794077 A CN 202110794077A CN 113417402 A CN113417402 A CN 113417402A
Authority
CN
China
Prior art keywords
fixing
plate
fixed
ceiling
plates
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110794077.0A
Other languages
Chinese (zh)
Inventor
曾庆俊
陈昌春
伏波
李荣义
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Aizhi Technology Co ltd
Original Assignee
Guangzhou Aizhi Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Aizhi Technology Co ltd filed Critical Guangzhou Aizhi Technology Co ltd
Priority to CN202110794077.0A priority Critical patent/CN113417402A/en
Publication of CN113417402A publication Critical patent/CN113417402A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/18Means for suspending the supporting construction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/04Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like
    • E04B9/0428Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation comprising slabs, panels, sheets or the like having a closed frame around the periphery
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
    • E04B9/12Connections between non-parallel members of the supporting construction
    • E04B9/14Connections between non-parallel members of the supporting construction all the members being discontinuous and laying at least partly in the same plane
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/18Means for suspending the supporting construction
    • E04B9/20Means for suspending the supporting construction adjustable

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention provides a ceiling system capable of being quickly installed and an installation method thereof. According to the invention, the section structure is skillfully designed, so that the module ceiling board can be quickly assembled, and the module ceiling board has the characteristics of firm structure and convenience in installation. According to the invention, all the components are tightly combined with each other, the firmness and stability of connection among the components are ensured in all directions, the whole ceiling system can be assembled by clamping, splicing and inserting the components, excessive additional tools are not needed, and the installation efficiency is greatly improved.

Description

Ceiling system capable of being installed quickly and installation method thereof
Technical Field
The invention relates to the field of architectural decoration, in particular to a ceiling capable of being installed quickly and an installation method thereof.
Background
The traditional building industry is greatly promoted to be upgraded in China, and the building industry is greatly developed into green buildings and green construction, so that the building industrialization and splicing trends are formed. Suspended ceilings are one of the most common decorative structures in interior decoration, and suspended ceiling structures generally comprise a suspended ceiling connection structure and a suspended ceiling plate, and the suspended ceiling connection device is fixed on a building body and provides a fixing place of the suspended ceiling plate.
However, in the existing ceiling structure, the adopted connection mode has low construction efficiency, is greatly limited in installation and production, cannot adapt to the future development direction of the building industry, and is contrary to the rapid assembly advocated in the building industry and the standardization and nodularization trend of ceiling structure products. Particularly, the connection and fixation between the ceiling plates mostly have the problems of complicated installation, poor firmness and low seismic performance, and need to be further improved.
Disclosure of Invention
The invention aims to provide a ceiling system capable of being quickly installed and an installation method thereof aiming at the defects in the prior art, and the ceiling system has the characteristics of convenience in installation and firm structure.
In order to achieve the purpose, the invention adopts the following technical scheme:
a ceiling system capable of being quickly installed comprises a plurality of flower basket screws and a plurality of module ceiling boards, wherein the module ceiling boards are fixedly hoisted on a ceiling through the flower basket screws, and the module ceiling boards are mutually spliced and connected through fixing clamps;
the module ceiling board comprises a plate and fixed sectional materials, the four fixed sectional materials are sequentially connected end to form a rectangular fixed frame, and the plate is supported and connected in the fixed frame;
the top of fixed section bar is equipped with the spout, the bottom of flower basket screw rod is fixed with the slider that matches with the spout, and the slider joint of flower basket screw rod bottom is in the spout at fixed section bar top, and the top fixed connection of flower basket screw rod is on the ceiling.
Furthermore, the cross section of the fixed profile comprises a rectangular main body, the edges of two sides above the rectangular main body are respectively connected with a side plate which is vertically arranged, the middle part above the rectangular main body is connected with two chute plates which are vertically arranged in parallel, the upper ends of the chute plates are connected with chute limiting plates which are horizontally arranged, and the chute plates and the chute limiting plates are mutually vertically connected to form a T shape, so that a chute is formed in a space between the two chute plates; a hook plate is connected to one side below the rectangular main body, and the tail end of the hook plate is bent to form a rectangle;
in the fixed frame formed by sequentially connecting the four fixed sectional materials end to enclose a rectangle, the plate is supported and connected in the hook-shaped plates of the four fixed sectional materials; the sliding block at the bottom of the flower basket screw rod is slidably clamped in the sliding groove at the top of the fixed sectional material.
Furthermore, the two fixed section bars are connected through a right-angle connecting piece, the right-angle connecting piece comprises two square pipes which are vertically connected with each other, and the tail ends of the two square pipes are respectively inserted into the rectangular main bodies of the two fixed section bars;
the upper wall of the inner cavity of the rectangular main body is provided with two fixing plates which vertically protrude downwards, the lower wall of the inner cavity of the rectangular main body is provided with a platform which protrudes upwards, and the platform is positioned right below the two fixing plates; spacing slots are formed between the two fixing plates and above the platform, and the tail ends of the square tubes of the right-angle connecting pieces are inserted into the spacing slots.
Furthermore, among the fixed section bar, the bottom surface of rectangle main part is equipped with the tooth that is used for increasing with panel frictional force, the tooth sets up in the below of platform.
Furthermore, the fixing clamp comprises a first clamping plate and a second clamping plate which are parallel to each other, the upper ends of the first clamping plate and the second clamping plate are connected through a connecting plate, the outer side of the upper end and the outer side of the lower end of the first clamping plate are respectively and vertically connected with a first transverse plate and a second transverse plate which extend outwards, and the tail end of the first transverse plate is provided with a clamping plate which is bent outwards vertically;
in the fixed section, a fixing clamp limiting plate bent downwards is arranged at the outer side end of the chute limiting plate;
adjacent fixing profiles are connected through the fixing clamps between the adjacent spliced module ceiling boards; the fixing clamp is connected to one of the fixing profiles, wherein a first clamping plate, a first transverse plate and a second transverse plate of the fixing clamp are arranged between a side plate and a sliding groove plate of the fixing profile, and the clamping plate is clamped between a limiting plate of the fixing clamp and the sliding groove plate; the second clamping plate is clamped on the inner side of the side plate of the other fixed profile.
Further, the lower end of the second clamping plate is provided with a guide part which is bent outwards and obliquely.
Further, the length of the slider at the bottom of the screw rod of the flower basket is matched with the distance between the two sliding groove plates in the fixed section bar, and the width of the slider is matched with the distance between the two sliding groove limiting plates.
Furthermore, the flower basket screw is connected with a fixing nut in a threaded mode, and the fixing nut is arranged above the sliding block.
A method of installing a quick-install ceiling system as described above, comprising the steps of:
s1, installing the fixing clamp from the end part of the fixing section bar;
s2, splicing the fixed profiles into a fixed frame through a right-angle connecting piece, simultaneously installing plates in the fixed frame, fixing the plates through glue or screws, and pre-installing the plates into a plurality of module ceiling boards;
s3, arranging the module ceiling board below the basket screw, inserting the sliding block of the basket screw into the sliding groove of the fixed section bar from the upper side, and then rotating the basket screw by 90 degrees to clamp the sliding block in the sliding groove; the fixing nut is fastened at the opening of the sliding groove by rotating the fixing nut on the screw rod of the flower basket downwards.
Further, still include:
s4, when the adjacent module ceiling tiles are installed, the edge of the fixed section bar of the next module ceiling tile is clamped in the fixed clamp on the previous module ceiling tile, so that the adjacent module ceiling tiles are fixed in the horizontal direction.
According to the ceiling system capable of being installed quickly and the installation method thereof, provided by the invention, the module ceiling boards can be assembled quickly by skillfully designing the section structure and can be hung on the ceiling quickly through the flower basket screw, the installation process is convenient and quick, and the module ceiling boards are tightly connected with each other through the fixing clamps, so that the module ceiling boards are fused with each other, and are not easy to move relatively after being fixed, and the ceiling system has the characteristics of firm structure and convenience in installation. According to the invention, all the components are tightly combined with each other, the firmness and stability of connection among the components are ensured in all directions, the whole ceiling system can be assembled by clamping, splicing and inserting the components, excessive additional tools are not needed, and the installation efficiency is greatly improved.
Drawings
Fig. 1 is a schematic diagram of an overall structure of a ceiling system capable of being installed quickly according to an embodiment of the present invention.
Fig. 2 is an exploded view of a ceiling system that may be quickly installed according to an embodiment of the present invention.
Figure 3 is an exploded view of the modular ceiling tile in an embodiment of the present invention.
Fig. 4 is a schematic view of a connection structure between the flower basket screw and the fixing section bar in the embodiment of the invention.
Fig. 5 is a sectional view of a fixing profile in an embodiment of the present invention.
Fig. 6 is a cross-sectional view of a retaining clip in an embodiment of the present invention.
Fig. 7 is a schematic diagram of the splicing structure of the fixing profile and the fixing clip in the embodiment of the invention.
Detailed Description
The technical solution of the present invention will be described in detail with reference to the accompanying drawings and specific embodiments.
As shown in fig. 1 and 2, the ceiling system capable of being quickly installed provided by the invention comprises a plurality of flower basket screws 1 and a plurality of module ceiling boards 2, wherein the module ceiling boards 2 are hoisted and fixed on a ceiling through the flower basket screws 1, and the module ceiling boards 2 are spliced with each other and connected through fixing clamps 3.
Referring to fig. 3, the module ceiling plate 2 includes a plate 5 and fixed sectional materials 4, the four fixed sectional materials 4 are sequentially connected end to form a rectangular fixed frame, and the plate 5 is supported and connected in the fixed frame.
Referring to fig. 4, the top of the fixed section bar 4 is provided with a sliding groove 40, the bottom of the flower basket screw rod 1 is fixed with a sliding block 10 matched with the sliding groove 40, the sliding block 10 at the bottom of the flower basket screw rod 1 is clamped in the sliding groove 40 at the top of the fixed section bar 4, and the top of the flower basket screw rod 1 is fixedly connected to a ceiling.
Specifically, as shown in fig. 5, the cross-sectional shape of the fixed profile 4 includes a rectangular main body 41, the upper two side edges of the rectangular main body 41 are respectively connected with a vertically arranged side plate 42, the upper middle part of the rectangular main body 41 is connected with two vertically parallel chute plates 43, the upper end of the chute plate 43 is connected with a horizontally arranged chute limiting plate 44, and the chute plate 43 and the chute limiting plate 44 are mutually and vertically connected in a T shape, so that a chute 40 is formed in a space between the two chute plates 43; a hook plate 47 is connected to one side of the lower part of the rectangular main body 41, and the end of the hook plate 47 is bent to form a rectangle for providing a supporting and installing space for the plate 5.
In the fixed frame which is formed by connecting the four fixed section bars 4 end to end in sequence and enclosing a rectangle, the plate 5 is supported and connected in the hook-shaped plates 47 of the four fixed section bars 4; the sliding block 10 at the bottom of the flower basket screw rod 1 can be slidably clamped in the sliding groove 40 at the top of the fixed section bar 4. The length of a sliding block 10 at the bottom of the flower basket screw rod 1 is matched with the distance between two sliding chute plates 43 in the fixed sectional material 4, and the width of the sliding block 10 is matched with the distance between two sliding chute limiting plates 44; when the flower basket screw rod fixing device is installed, the length direction of the sliding block 10 and the extending direction of the fixing section bar 4 can be set to be consistent, the sliding block 104 is placed into the sliding groove 0, then the flower basket screw rod 1 is rotated by 90 degrees, and then the fixing section bar 4 and the flower basket screw rod 1 can be fixed.
As an improvement, a fixing nut 11 is connected to the turnbuckle 1 in a threaded manner, and the fixing nut 11 is arranged above the sliding block 10. After the sliding block 10 is installed in place, the fixing nut 11 can be screwed downwards to be fastened at the opening of the sliding chute 40, so that the connection tightness of the flower basket screw 1 and the fixing section bar 4 is enhanced.
The junction of slider 10 and the basket of flowers screw 1 main part still has one bellied step portion 100 that makes progress, the width of step portion 100 and the opening part width phase-match of spout 40 for when slider 10 is connected in spout 40, step portion 100 just protrudes and blocks at the opening part from the opening part of spout 40, plays certain limiting displacement, strengthens basket of flowers screw 1 and fixed section bar 4's stability of being connected.
Further, as shown in fig. 3, the two fixing profiles 4 are connected by a right-angle connector 6, the right-angle connector 6 includes two square pipes perpendicularly connected to each other, and ends of the two square pipes are respectively inserted into the rectangular main bodies 41 connected to the two fixing profiles 4. Specifically, as shown in fig. 5, the upper wall of the inner cavity of the rectangular main body 41 has two fixing plates 46 protruding vertically downward, and the lower wall of the inner cavity of the rectangular main body 41 has a platform 49 protruding upward, and the platform 49 is located right below the two fixing plates 46; spacing slots are formed between the two fixing plates 46 and above the platform 49, and the tail ends of the square tubes of the right-angle connecting pieces 6 are inserted into the spacing slots.
As a modification, in the fixing profile 4, the bottom surface of the rectangular main body 41 is provided with teeth 48 for increasing the friction force with the plate 5, and the teeth 48 are disposed below the platform 49. So, when right angle connector 6 inserted in the spacing slot of rectangle main part 41, can suitably push down platform 49 for tooth 48 and the panel 5 of platform 49 below closely laminate, increase the frictional force between fixed section bar 4 and the panel 5, improve the stability of structure, prevent that panel 5 from sliding. Meanwhile, fixing glue can be filled in the gaps of the teeth 48, so that the connection firmness between the fixing section 4 and the plate 5 is further improved.
As shown in fig. 6, the fixing clip 3 includes a first clamping plate 31 and a second clamping plate 32 which are parallel to each other, the upper ends of the first clamping plate 31 and the second clamping plate 32 are connected by a connecting plate 35, a first horizontal plate 33 and a second horizontal plate 34 which extend outwards are respectively vertically connected to the outer side of the upper end and the outer side of the lower end of the first clamping plate 31, and a clamping plate 36 which is bent outwards vertically is arranged at the end of the first horizontal plate 33.
Correspondingly, the outer end of the chute limiting plate 44 in the fixed profile 4 is provided with a downward bent fixing clip limiting plate 45.
As shown in fig. 7, adjacent fixing profiles 4 are connected between the adjacent spliced module ceiling boards 2 through the fixing clips 3; the fixing clamp 3 is connected to one of the fixing profiles 4, wherein a first clamping plate 31, a first transverse plate 33 and a second transverse plate 34 of the fixing clamp 3 are arranged between a side plate 42 and a chute plate 43 of the fixing profile 4, and a clamping plate 36 is clamped between a fixing clamp limiting plate 45 and the chute plate 43; the second clamping plate 32 is clamped inside a side plate 42 of the other fixing profile 4.
As a modification, the lower end of the second clamping plate 32 of the fixing frame 3 is provided with a guide part 37 which is bent obliquely outward. When two module furred ceiling board 2 splice each other, guide portion 37 can play certain guide effect, makes the concatenation more smooth and easy.
The installation method of the ceiling system capable of being installed quickly provided by the embodiment of the invention comprises the following steps:
s1, the fixing clip 3 is installed from the end part of the fixing section bar 4 and slides to the middle part of the fixing section bar 4;
s2, splicing the fixed profiles 4 into a fixed frame through right-angle connectors 6, simultaneously installing plates 5 in the fixed frame, fixing the plates through glue or screws, and pre-installing the plates into a plurality of module ceiling boards 2;
s3, arranging the module ceiling board 2 below the flower basket screw 1, inserting the sliding block 10 of the flower basket screw 1 into the sliding groove 40 of the fixed section bar 4 from the upper side, and then rotating the flower basket screw 1 for 90 degrees to enable the sliding block 10 to be clamped in the sliding groove 40; the fixing nut 11 is fastened to the opening of the chute 40 by rotating the fixing nut 11 on the turnbuckle 1 downward.
S4, when the adjacent module ceiling tiles 2 are installed, the edge of the fixed section 4 of the next module ceiling tile 2 is clamped in the fixed clamp 3 on the previous module ceiling tile 2, so that the adjacent module ceiling tiles 2 are fixed in the horizontal direction.
According to the ceiling system capable of being installed quickly and the installation method thereof, provided by the invention, the module ceiling boards can be assembled quickly by skillfully designing the section structure and can be hung on the ceiling quickly through the flower basket screw, the installation process is convenient and quick, and the module ceiling boards are tightly connected with each other through the fixing clamps, so that the module ceiling boards are fused with each other, and are not easy to move relatively after being fixed, and the ceiling system has the characteristics of firm structure and convenience in installation. According to the invention, all the components are tightly combined with each other, the firmness and stability of connection among the components are ensured in all directions, the whole ceiling system can be assembled by clamping, splicing and inserting the components, excessive additional tools are not needed, and the installation efficiency is greatly improved.
The above-mentioned embodiments only express several embodiments of the present invention, and the description thereof is more specific and detailed, but not construed as limiting the scope of the present invention. It should be noted that, for a person skilled in the art, several variations and modifications can be made without departing from the inventive concept, which falls within the scope of the present invention. Therefore, the protection scope of the present patent shall be subject to the appended claims.

Claims (10)

1. A ceiling system capable of being quickly installed is characterized by comprising a plurality of flower basket screws and a plurality of module ceiling boards, wherein the module ceiling boards are hoisted and fixed on a ceiling through the flower basket screws, and the module ceiling boards are mutually spliced and connected through fixing clamps;
the module ceiling board comprises a plate and fixed sectional materials, the four fixed sectional materials are sequentially connected end to form a rectangular fixed frame, and the plate is supported and connected in the fixed frame;
the top of fixed section bar is equipped with the spout, the bottom of flower basket screw rod is fixed with the slider that matches with the spout, and the slider joint of flower basket screw rod bottom is in the spout at fixed section bar top, and the top fixed connection of flower basket screw rod is on the ceiling.
2. The ceiling system capable of being quickly installed according to claim 1, wherein the cross-sectional shape of the fixed profile comprises a rectangular main body, the edges of two sides of the upper part of the rectangular main body are respectively connected with a side plate which is vertically arranged, the middle part of the upper part of the rectangular main body is connected with two chute plates which are vertically arranged in parallel, the upper ends of the chute plates are connected with chute limiting plates which are horizontally arranged, and the chute plates and the chute limiting plates are mutually vertically connected to form a T shape, so that a chute is formed in a space between the two chute plates; a hook plate is connected to one side below the rectangular main body, and the tail end of the hook plate is bent to form a rectangle;
in the fixed frame formed by sequentially connecting the four fixed sectional materials end to enclose a rectangle, the plate is supported and connected in the hook-shaped plates of the four fixed sectional materials; the sliding block at the bottom of the flower basket screw rod is slidably clamped in the sliding groove at the top of the fixed sectional material.
3. The ceiling system capable of being quickly installed according to claim 2, wherein the two fixing profiles are connected with each other through a right-angle connector, the right-angle connector comprises two square pipes which are vertically connected with each other, and the tail ends of the two square pipes are respectively inserted into the rectangular main bodies connected with the two fixing profiles;
the upper wall of the inner cavity of the rectangular main body is provided with two fixing plates which vertically protrude downwards, the lower wall of the inner cavity of the rectangular main body is provided with a platform which protrudes upwards, and the platform is positioned right below the two fixing plates; spacing slots are formed between the two fixing plates and above the platform, and the tail ends of the square tubes of the right-angle connecting pieces are inserted into the spacing slots.
4. A ceiling system capable of being installed quickly as set forth in claim 3, wherein the bottom surface of the rectangular body of the fixing profile is provided with teeth for increasing friction with the panel, the teeth being provided below the platform.
5. The ceiling system capable of being quickly installed according to claim 4, wherein the fixing clip comprises a first clamping plate and a second clamping plate which are parallel to each other, the upper ends of the first clamping plate and the second clamping plate are connected through a connecting plate, a first transverse plate and a second transverse plate which extend outwards are respectively and vertically connected to the outer side of the upper end and the outer side of the lower end of the first clamping plate, and a clamping plate which is bent outwards vertically is arranged at the tail end of the first transverse plate;
in the fixed section, a fixing clamp limiting plate bent downwards is arranged at the outer side end of the chute limiting plate;
adjacent fixing profiles are connected through the fixing clamps between the adjacent spliced module ceiling boards; the fixing clamp is connected to one of the fixing profiles, wherein a first clamping plate, a first transverse plate and a second transverse plate of the fixing clamp are arranged between a side plate and a sliding groove plate of the fixing profile, and the clamping plate is clamped between a limiting plate of the fixing clamp and the sliding groove plate; the second clamping plate is clamped on the inner side of the side plate of the other fixed profile.
6. The quick installable ceiling system of claim 5, wherein the lower end of the second clamp plate has an outwardly angled guide.
7. The ceiling system capable of being quickly installed of claim 6, wherein the length of the slider at the bottom of the turnbuckle matches the distance between the two chute plates in the fixed profile, and the width of the slider matches the distance between the two chute limit plates.
8. The quick-installable ceiling system of claim 7, wherein the threaded screw is threadably connected to a retaining nut disposed above the slider.
9. A method of installing a quick-install ceiling system according to claim 8, comprising the steps of:
s1, installing the fixing clamp from the end part of the fixing section bar;
s2, splicing the fixed profiles into a fixed frame through a right-angle connecting piece, simultaneously installing plates in the fixed frame, fixing the plates through glue or screws, and pre-installing the plates into a plurality of module ceiling boards;
s3, arranging the module ceiling board below the basket screw, inserting the sliding block of the basket screw into the sliding groove of the fixed section bar from the upper side, and then rotating the basket screw by 90 degrees to clamp the sliding block in the sliding groove; the fixing nut is fastened at the opening of the sliding groove by rotating the fixing nut on the screw rod of the flower basket downwards.
10. The method of installation according to claim 9, further comprising:
s4, when the adjacent module ceiling tiles are installed, the edge of the fixed section bar of the next module ceiling tile is clamped in the fixed clamp on the previous module ceiling tile, so that the adjacent module ceiling tiles are fixed in the horizontal direction.
CN202110794077.0A 2021-07-14 2021-07-14 Ceiling system capable of being installed quickly and installation method thereof Pending CN113417402A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110794077.0A CN113417402A (en) 2021-07-14 2021-07-14 Ceiling system capable of being installed quickly and installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110794077.0A CN113417402A (en) 2021-07-14 2021-07-14 Ceiling system capable of being installed quickly and installation method thereof

Publications (1)

Publication Number Publication Date
CN113417402A true CN113417402A (en) 2021-09-21

Family

ID=77720944

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110794077.0A Pending CN113417402A (en) 2021-07-14 2021-07-14 Ceiling system capable of being installed quickly and installation method thereof

Country Status (1)

Country Link
CN (1) CN113417402A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114753545A (en) * 2022-04-01 2022-07-15 中建八局第二建设有限公司 Water-drop-shaped aluminum hammer sheet suspended ceiling and installation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114753545A (en) * 2022-04-01 2022-07-15 中建八局第二建设有限公司 Water-drop-shaped aluminum hammer sheet suspended ceiling and installation method thereof

Similar Documents

Publication Publication Date Title
CN108086627B (en) Quick installation structure and installation method of composite wallboard
CN113417402A (en) Ceiling system capable of being installed quickly and installation method thereof
CN109763596B (en) Assembled light steel keel gypsum thistle board ceiling system and construction method thereof
CN216428740U (en) Ceiling system capable of being installed quickly
CN210622072U (en) Suspended ceiling structure
CN211200822U (en) Partition plate's installation clamping device
CN210685133U (en) Mounting member for assembled ladder suspended ceiling
CN111663706A (en) Mounting structure and mounting method of suspended ceiling
CN208473060U (en) A kind of metal curtain wall
CN115977279A (en) Partition wall structural system and construction method thereof
CN216810718U (en) Artificial quartz stone plate with structure convenient to hang
CN210622073U (en) Grade-falling suspended ceiling system
CN215977911U (en) Assembled wallboard top corner binding off structure
CN210622074U (en) Suspended ceiling side plate system
CN211037504U (en) Concatenation formula building backup pad for building
CN210563000U (en) Net rack board convenient to installation
CN210316330U (en) Assembled is exterior wallboard keel structure for building
CN209384510U (en) A kind of wallboard for assembled architecture convenient for splicing
CN213682714U (en) Heat-insulating energy-saving curtain wall template
CN112554415A (en) Buckle type ceiling closing-in structure and installation method thereof
CN213509302U (en) Wall veneer dry hanging structure
CN215484338U (en) Decorative wallboard for indoor design
CN211369222U (en) Whole bathroom smallpox mosaic structure
CN210622180U (en) Simple wall board decorative line structure
CN212836443U (en) Fixing structure for wrapping vertical pipe ceramic tile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination