CN114753545A CN202210338523.1A CN202210338523A CN114753545A CN 114753545 A CN114753545 A CN 114753545A CN 202210338523 A CN202210338523 A CN 202210338523A CN 114753545 A CN114753545 A CN 114753545A
Authority
CN
China
Prior art keywords
drop
plate
shaped
hanging
blind plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210338523.1A
Other languages
Chinese (zh)
Inventor
刘鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Second Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202210338523.1A priority Critical patent/CN114753545A/en
Publication of CN114753545A publication Critical patent/CN114753545A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/34Grid-like or open-work ceilings, e.g. lattice type box-like modules, acoustic baffles
    • E04B9/36Grid-like or open-work ceilings, e.g. lattice type box-like modules, acoustic baffles consisting of parallel slats
    • E04B9/366Grid-like or open-work ceilings, e.g. lattice type box-like modules, acoustic baffles consisting of parallel slats the principal plane of the slats being vertical
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/006Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation with means for hanging lighting fixtures or other appliances to the framework of the ceiling
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Abstract

The invention relates to the technical field of suspended ceilings, in particular to a water-drop-shaped aluminum hammer sheet suspended ceiling and an installation method thereof. The drop-shaped aluminum hammer piece suspended ceiling comprises a plurality of groups of supports and a plurality of drop-shaped hanging pieces which are arranged side by side, wherein the bottom of each group of supports is provided with a plurality of connecting claws; the hanging plate comprises a blind plate and two side plates, the two side plates are fixedly connected to two sides of the upper surface of the blind plate, the water drop-shaped hanging pieces are respectively provided with a connecting portion at the tops of the side plates, and the connecting portions are detachably connected with the connecting claws. The bottom end of a blind plate of the hanging plate is flush with the bottom end of the drop-shaped hanging piece, various devices are arranged on the blind plate, the mounting, the maintenance and the replacement are convenient and quick, and the normal use of the devices is not influenced; a reinforcing structure is arranged, the reinforcing structure is directly connected with the blind plate, the other end of the reinforcing structure is fixed with the bracket, and the bearing capacity of the blind plate can be enhanced through the reinforcing structure; the side plates and the upper parts of the water drop-shaped hanging pieces are provided with connecting parts, the water drop-shaped hanging pieces are disassembled, and the hanging plates with the blind plates can be replaced easily for installing equipment, so that the use is convenient.

Description

Water-drop-shaped aluminum hammer sheet suspended ceiling and installation method thereof
Technical Field
The invention relates to the technical field of suspended ceilings, in particular to a water-drop-shaped aluminum hammer sheet suspended ceiling and an installation method thereof.
Background
An aluminum hammer piece ceiling is mostly adopted in a public corridor area of a large public building, so that the appearance is attractive and convenient; the drop-shaped aluminum hammer piece suspended ceiling is simple in structure, is formed by extrusion of aluminum materials, is good in product hardness and straightness effect, and is connected with the top support through the inserting and buckling type structure, so that the drop-shaped aluminum hammer piece suspended ceiling is widely applied.
But because the structural feature of water droplet shape aluminium hammer leaf furred ceiling, the corridor top above the furred ceiling must all be installed to the control ball machine that needs the installation on the corridor, air conditioning equipment, communication network equipment and lighting apparatus etc. or install in corridor one side, and the mode construction of installing like this, maintenance change difficulty, influence the use of equipment, can't satisfy the engineering demand, influence the holistic aesthetic property of furred ceiling.
Disclosure of Invention
The invention provides a water-drop-shaped aluminum hammer sheet suspended ceiling and an installation method thereof, aiming at the technical problems that other equipment is difficult to construct, maintain and replace after the water-drop-shaped aluminum hammer sheet suspended ceiling is installed in the prior art and the integral attractiveness of the suspended ceiling is influenced.
In order to achieve the purpose, the invention adopts the technical scheme that: a drop-shaped aluminum hammer piece suspended ceiling comprises a plurality of groups of supports and a plurality of drop-shaped hanging pieces which are arranged side by side, wherein the bottom of each group of supports is provided with a plurality of connecting claws; the hanging plate comprises a blind plate and two side plates, the side plates are fixedly connected to two sides of the upper surface of the blind plate, the water drop-shaped hanging piece is connected with the tops of the side plates, and the connecting portions are detachably connected with the connecting claws.
Preferably, the bottom end of the blind plate is flush with the bottom end of the drop-shaped hanging piece.
Preferably, the bottoms of the two side plates are respectively provided with an arc-shaped plate, the cross section of each arc-shaped plate is in a quarter circle shape, and the upper part of each arc-shaped plate is fixedly connected with the bottom end of each side plate and is tangent to the plane where the side plate is located; the lower part of the arc-shaped plate is fixedly connected with the blind plate and is tangent to the plane of the blind plate.
Preferably, the hanger plate is provided in plurality.
Preferably, the bracket is provided with a plurality of fixing holes, and the plurality of fixing holes are respectively arranged in the middle of two adjacent connecting claws one by one.
Preferably, the device further comprises a reinforcing structure, wherein the reinforcing structure comprises a sliding rail, a sliding block, a hollow rod, a screw rod and a nut; the sliding rail is fixed on the upper surface of the blind plate and positioned between two adjacent connecting claws, and the sliding rail is arranged along the length direction of the blind plate; the sliding block is matched with the sliding rail, and a threaded hole is formed in the top end of the sliding block; the bottom end of the hollow rod is provided with threads, and the threads at the bottom end of the hollow rod are matched with threaded holes at the top end of the sliding block; the lower end of the screw rod is sleeved in the hollow rod, and the upper end of the screw rod penetrates through the fixing hole in the support and is matched with the nut.
The invention also provides an installation method of the water-drop-shaped aluminum hammer sheet ceiling, which comprises the following steps:
Step one, installing a bracket: a plurality of brackets are arranged at the top end of the corridor side by side;
step two, mounting a hanging plate: according to the position of the hanging plate designed according to the drawing, two connecting parts at the top of the hanging plate penetrate through a plurality of groups of connecting claws which are arranged in the same row below the bracket along the transverse direction of the bracket;
step three, installing a water drop-shaped hanging piece: connecting parts at the tops of the drop-shaped hanging pieces penetrate through a plurality of groups of connecting claws which are arranged in the same row along the transverse direction of the bracket and below the bracket; sequentially enabling a plurality of water drop-shaped hanging pieces to penetrate through the connecting claws which are not installed with the hanging plates in the second step;
and fourthly, installing a dome camera, sound equipment, a ceiling lamp and a mobile communication line box on the lower surface of the blind plate.
Preferably, in the second step, a plurality of hanging plates are installed.
Preferably, the method further comprises the step of installing a reinforcing structure: the sliding block is connected to the sliding rail in a sliding mode, the hollow rod is fixed to the sliding block through threads, the screw rod which is pulled out and sleeved with the hollow rod penetrates through the fixing hole, and the nut is screwed up to the upper end of the screw rod.
Compared with the prior art, the invention has the advantages and positive effects that: (1) the hanging plate is arranged below the support and comprises a blind plate and two side plates, the bottom end of the blind plate is flush with the bottom end of the water drop-shaped hanging piece, equipment such as a dome camera, sound equipment, a ceiling lamp, a mobile communication line box and the like is arranged on the blind plate, the installation and the maintenance are convenient and quick, and the normal use of the equipment is not influenced; (2) the reinforcing structure is arranged, when more equipment is arranged on the blind plate, the strength of a connecting part at the top of the side plate connected with the blind plate is insufficient, the reinforcing structure is directly connected with the blind plate, the other end of the reinforcing structure is fixed with the bracket, and the bearing capacity of the blind plate can be enhanced through the reinforcing structure; (3) the upper parts of the side plates and the upper parts of the water drop-shaped hanging pieces are provided with connecting parts which can be detachably connected with the connecting claws of the support, when mounting equipment needs to be temporarily added, the water drop-shaped hanging pieces are detached, and the hanging plates with the blind plates can be easily replaced for mounting the equipment, so that the use is convenient.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments will be briefly introduced,
FIG. 1 is a schematic view of the suspended ceiling structure;
FIG. 2 is a side view of the suspended ceiling;
FIG. 3 is an enlarged view of the present ceiling at the hanger plate;
FIG. 4 is a schematic view of the connection of the hollow bar to the screw;
fig. 5 is a schematic view of the suspended ceiling in use.
1-bracket, 11-connecting claw, 12-fixing hole;
2-a connecting part;
3-drop-shaped hanging pieces;
4-hanging plate, 41-blind plate, 42-side plate, 43-arc plate;
5-reinforcing the structure; 51-slide rail, 52-slide block, 53-hollow rod, 54-screw rod, 55-nut, 56-thread;
6-dome camera; 7-sound equipment, 8-ceiling lamp and 9-mobile communication line box.
Detailed Description
In order that the above objects, features and advantages of the present invention can be more clearly understood, the present invention will be further described with reference to the accompanying drawings and examples.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention, however, the present invention may be practiced in other ways than those specifically described herein, and thus the present invention is not limited to the specific embodiments of the present disclosure.
Example 1
The invention is further explained by combining with the attached figures 1-5, and the drop-shaped aluminum hammer piece suspended ceiling comprises a plurality of groups of brackets 1 and a plurality of drop-shaped hanging pieces 3 which are arranged side by side, wherein the bottom of each group of brackets 1 is provided with a plurality of connecting claws 11; the hanging plate 4 comprises a blind plate 41 and two side plates 42, and the two side plates 42 are fixedly connected to two sides of the upper surface of the blind plate 41; the water drop-shaped hanging piece 3 and the top of the side plate 42 are both provided with a connecting part 2, and the connecting part 2 is detachably connected with the connecting claw 11.
By arranging the hanging plate 4, the bottom of the hanging plate 4 is provided with the blind plate 41, equipment such as a dome camera 6, sound equipment 7, a ceiling lamp 8, a mobile communication line box 9 and the like can be arranged below the blind plate 41, the two side plates 42 are fixedly connected with the blind plate 41, the top parts of the two side plates are provided with the connecting parts 2, and the two side plates are arranged on the connecting claws 11 at the bottom of the bracket 1 through the connecting parts 2; meanwhile, the connecting part 2 is detachably connected with the connecting claw 11, so that the installation, the maintenance and the replacement are convenient and quick, and the normal use of the equipment is not influenced;
meanwhile, when installation equipment needs to be temporarily added, the drop-shaped hanging piece 3 is detached, and the hanging plate 4 with the blind plate 41 can be easily replaced for installing the equipment, so that the use is convenient; or after the equipment under the hanging plate 4 is removed, the hanging plate 4 can be replaced by the drop-shaped hanging piece 3.
As shown in fig. 2, the bottom end of the blind plate 41 is flush with the bottom end of the drop-shaped hanging piece 3.
The bottom end of the blind plate 41 is higher than the bottom end of the drop-shaped hanging piece 3, so that the installation and the use of equipment under the blind plate 41 are not facilitated, the visual field of the hemispherical camera 6 is narrowed, and the illumination area of the ceiling lamp 8 is reduced; the bottom end of the blind plate 41 is lower than the bottom end of the drop-shaped hanging piece 3, so that the integral attractiveness of the suspended ceiling is influenced; the bottom end of the blind plate 41 is flush with the bottom end of the drop-shaped hanging piece 3, so that the use of equipment is ensured, and the attractiveness is also considered.
As shown in fig. 3, the bottom of each of the two side plates 42 is provided with an arc-shaped plate 43, the cross section of each arc-shaped plate 43 is in a quarter circle shape, and the upper part of each arc-shaped plate 43 is fixedly connected with the bottom end of each side plate 42 and is tangent to the plane of the side plate 42; the lower part of the arc-shaped plate 43 is fixedly connected with the blind plate 41 and is tangent to the plane of the blind plate 41.
The connection part of the blind plate 41 and the side plate 42 is provided with the arc-shaped plate 43 as a transition, so that the problem of stress concentration of the hanging plate 4 is reduced, the appearance of the hanging plate 4 is not greatly different from that of the drop-shaped hanging piece 3 from the side, and the attractiveness is considered.
As shown in fig. 5, there are two hanger plates 4.
As shown in fig. 1, a plurality of fixing holes 12 are formed in the bracket 1, and the plurality of fixing holes 12 are respectively arranged at the middle positions of two adjacent connecting claws 11 one by one.
As shown in fig. 3 and 4, the reinforcing structure 5 further comprises a slide rail 51, a slide block 52, a hollow rod 53, a screw 54 and a nut 55;
the slide rail 51 is fixed on the upper surface of the blind plate 41 and is positioned between two adjacent connecting claws 11, and the slide rail 51 is arranged along the length direction of the blind plate 41; the sliding block 52 is matched with the sliding rail 51, and the top end of the sliding block is provided with a threaded hole; the bottom end of the hollow rod 53 is provided with threads 56, and the threads 56 at the bottom end of the hollow rod 53 are matched with threaded holes at the top end of the sliding block 52; the lower end of the screw rod 54 is sleeved in the hollow rod 53, and the upper end of the screw rod 54 penetrates through the fixing hole 12 on the support 1 and is matched with the nut 55.
When the reinforcing structure 5 is used, the sliding block 52 is matched with the sliding rail 51, the hollow rod 53 is matched in the threaded hole of the sliding block 52 through the thread 56, then the sliding block 52 is slid to the position of the fixing hole 12, the screw rod 54 is drawn out of the hollow rod 53 and penetrates through the fixing hole 12, the nut 55 is installed at the other end, and the nut 55 is screwed until the screw rod 54 slides to the top end of the hollow rod 53.
The slide block 52 may be provided in plurality on the slide rail 51 while also mounting a plurality of hollow bars 53, threaded rods 54 and nuts 55.
A method for installing a drop-shaped aluminum hammer piece ceiling comprises the following steps:
Step one, mounting a bracket 1: a plurality of brackets 1 are arranged at the top end of the corridor side by side;
step two, mounting a hanging plate 4: the position of a hanging plate 4 is designed according to a drawing, the position of the hanging plate 4 is determined by the installation position of each device in a corridor, and two connecting parts 2 at the top of the hanging plate 4 penetrate through connecting claws 11 which are arranged in the same row below a plurality of groups of brackets 1 along the transverse direction of the brackets 1;
two hanging plates 4 are arranged;
step three, installing a water drop-shaped hanging piece 3: the connecting part 2 at the top of the drop-shaped hanging piece 3 penetrates through a plurality of groups of connecting claws 11 which are arranged in the same row along the transverse direction of the bracket 1 and below the bracket 1; sequentially enabling the plurality of water drop-shaped hanging pieces 3 to penetrate through the connecting claws 11 which are not installed on the hanging plate 4 in the second step;
fourthly, installing the dome camera 6, the acoustic equipment 7, the ceiling lamp 8 and the mobile communication line box 9 on the lower surface of the blind plate 41;
step five, installing a reinforcing structure 5: the slide block 52 is slidably connected to the slide rail 51, the hollow rod 53 is fixed to the slide block 52 by the screw 56, the screw 54 sleeved with the hollow rod 53 is pulled out to pass through the fixing hole 12, and the nut 55 is screwed on the upper end of the screw 54 until the screw 54 slides to the top end of the hollow rod 53.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the present invention in other forms, and any person skilled in the art may apply the above-mentioned technical details to other fields by using the equivalent embodiments with equivalent changes or modifications, but any simple modification and equivalent changes made to the above embodiments according to the technical spirit of the present invention may still fall within the protection scope of the technical solution of the present invention.

Claims (9)

1. A drop-shaped aluminum hammer piece suspended ceiling comprises a plurality of groups of supports (1) and a plurality of drop-shaped hanging pieces (3) which are arranged side by side, wherein the bottom of each group of supports (1) is provided with a plurality of connecting claws (11); it is characterized in that the preparation method is characterized in that,
the hanging plate (4) comprises a blind plate (41) and two side plates (42), and the two side plates (42) are fixedly connected to two sides of the upper surface of the blind plate (41);
the water drop-shaped hanging piece (3) and the top of the side plate (42) are both provided with connecting parts (2), and the connecting parts (2) are detachably connected with the connecting claws (11).
2. A drop-shaped aluminum hammer sheet suspended ceiling according to claim 1, wherein the bottom end of the blind plate (41) is flush with the bottom end of the drop-shaped hanging sheet (3).
3. The drop-shaped aluminum hammer sheet suspended ceiling according to claim 1, wherein the bottom of each of the two side plates (42) is provided with an arc-shaped plate (43), the cross section of each arc-shaped plate (43) is in a quarter-circle shape, and the upper part of each arc-shaped plate (43) is fixedly connected with the bottom end of each side plate (42) and is tangent to the plane of each side plate (42); the lower part of the arc-shaped plate (43) is fixedly connected with the blind plate (41) and is tangent to the plane of the blind plate (41).
4. A drop shaped aluminum hammer leaf ceiling according to any one of claims 1-3, wherein the hanging plate (4) is provided in plurality.
5. The drop-shaped aluminum hammer sheet suspended ceiling according to claim 4, wherein the bracket (1) is provided with a plurality of fixing holes (12), and the plurality of fixing holes (12) are respectively arranged in the middle of two adjacent connecting claws (11).
6. The drop-shaped aluminum hammer sheet suspended ceiling according to claim 5, further comprising a reinforcing structure (5), wherein the reinforcing structure (5) comprises a sliding rail (51), a sliding block (52), a hollow rod (53), a screw rod (54) and a nut (55);
the sliding rail (51) is fixed on the upper surface of the blind plate (41) and is positioned between two adjacent connecting claws (11), and the sliding rail (51) is arranged along the length direction of the blind plate (41); the sliding block (52) is matched with the sliding rail (51), and the top end of the sliding block is provided with a threaded hole; the bottom end of the hollow rod (53) is provided with a thread (56), and the thread (56) at the bottom end of the hollow rod (53) is matched with a threaded hole at the top end of the sliding block (52); the lower end of the screw rod (54) is sleeved in the hollow rod (53), and the upper end of the screw rod (54) penetrates through the fixing hole (12) in the support (1) and is matched with the nut (55).
7. A method for installing a drop-shaped aluminum hammer piece ceiling is characterized by comprising the following steps:
step one, mounting a bracket (1): a plurality of brackets (1) are arranged at the top end of the corridor side by side;
step two, mounting a hanging plate (4): according to the position of a hanging plate (4) designed according to a drawing, two connecting parts (2) at the top of the hanging plate (4) penetrate through connecting claws (11) which are arranged in the same row below a plurality of groups of brackets (1) along the transverse direction of the brackets (1);
step three, installing a water drop-shaped hanging piece (3): connecting parts (2) at the tops of the drop-shaped hanging pieces (3) penetrate through a plurality of groups of connecting claws (11) which are arranged in the same row along the transverse direction of the bracket (1) and below the bracket (1); sequentially enabling a plurality of water drop-shaped hanging pieces (3) to penetrate through connecting claws (11) which are not installed on the hanging plates (4) in the second step;
fourthly, a dome camera (6), sound equipment (7), a ceiling lamp (8) and a mobile communication line box (9) are arranged on the lower surface of the blind plate (41).
8. The method for installing the drop-shaped aluminum hammer sheet suspended ceiling according to claim 7, wherein a plurality of the hanging plates (4) are installed in the second step.
9. The method for installing a drop-shaped aluminum hammer sheet suspended ceiling according to claim 8, further comprising the step of installing a reinforcing structure (5): the sliding block (52) is connected to the sliding rail (51) in a sliding mode, the hollow rod (53) is fixed to the sliding block (52) through the threads (56), the screw rod (54) sleeved with the hollow rod (53) is pulled out to penetrate through the fixing hole (12), and the nut (55) is screwed at the upper end of the screw rod (54).
CN202210338523.1A 2022-04-01 2022-04-01 Water-drop-shaped aluminum hammer sheet suspended ceiling and installation method thereof Pending CN114753545A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210338523.1A CN114753545A (en) 2022-04-01 2022-04-01 Water-drop-shaped aluminum hammer sheet suspended ceiling and installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210338523.1A CN114753545A (en) 2022-04-01 2022-04-01 Water-drop-shaped aluminum hammer sheet suspended ceiling and installation method thereof

Publications (1)

Publication Number Publication Date
CN114753545A true CN114753545A (en) 2022-07-15

Family

ID=82329432

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210338523.1A Pending CN114753545A (en) 2022-04-01 2022-04-01 Water-drop-shaped aluminum hammer sheet suspended ceiling and installation method thereof

Country Status (1)

Country Link
CN (1) CN114753545A (en)

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130047541A1 (en) * 2011-08-26 2013-02-28 Hunter Douglas Inc. Suspension ceiling with parallel vanes for building structures
CN205024927U (en) * 2015-09-09 2016-02-10 广东华途仕建材实业有限公司 Multi -functional suspended ceiling
CN106149953A (en) * 2015-04-16 2016-11-23 北新集团建材股份有限公司 A kind of sound-absorbing ceiling suspension system
CN205976178U (en) * 2016-08-15 2017-02-22 杭州臻万建筑装饰工程有限公司 Ceiling structure
CN206607737U (en) * 2017-02-24 2017-11-03 上海博丽铝幕墙材料制造有限公司 A kind of flash batten furred ceiling
CN206607732U (en) * 2017-02-24 2017-11-03 上海博丽铝幕墙材料制造有限公司 A kind of U-shaped hang type furred ceiling
CN207277661U (en) * 2017-09-20 2018-04-27 天津市东泽天润建筑有限公司 A kind of side leads to ceiling structure
CN108118818A (en) * 2017-12-27 2018-06-05 骆诚 It is a kind of to build hold court from behind a screen steel construction and installation method
CN208918108U (en) * 2018-07-24 2019-05-31 上海六奇装饰工程有限公司 A kind of use should be in the package assembly and integrated suspended ceiling device of Integral ceiling
CN209457232U (en) * 2018-11-23 2019-10-01 合肥澳达环境艺术设计工程有限公司 A kind of U-shaped aluminium Fang Tongyu downlight combination furred ceiling
CN110469031A (en) * 2019-09-18 2019-11-19 杨烨 A kind of cracking resistance plasterboard
CN210288852U (en) * 2019-05-17 2020-04-10 上海丰丽集团有限公司 Hanging piece vertical curtain ceiling structure
CN213741834U (en) * 2020-05-11 2021-07-20 中铁电气化局集团北京建筑工程有限公司 Special hanger device capable of sliding and resisting wind uncovering for high-speed rail passenger station house and subway artistic ceiling
CN113417402A (en) * 2021-07-14 2021-09-21 广州市爱智造科技有限公司 Ceiling system capable of being installed quickly and installation method thereof
CN214739194U (en) * 2020-10-28 2021-11-16 上海宝冶建筑装饰有限公司 Hoisting structure of suspended ceiling swing blade

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130047541A1 (en) * 2011-08-26 2013-02-28 Hunter Douglas Inc. Suspension ceiling with parallel vanes for building structures
CN106149953A (en) * 2015-04-16 2016-11-23 北新集团建材股份有限公司 A kind of sound-absorbing ceiling suspension system
CN205024927U (en) * 2015-09-09 2016-02-10 广东华途仕建材实业有限公司 Multi -functional suspended ceiling
CN205976178U (en) * 2016-08-15 2017-02-22 杭州臻万建筑装饰工程有限公司 Ceiling structure
CN206607737U (en) * 2017-02-24 2017-11-03 上海博丽铝幕墙材料制造有限公司 A kind of flash batten furred ceiling
CN206607732U (en) * 2017-02-24 2017-11-03 上海博丽铝幕墙材料制造有限公司 A kind of U-shaped hang type furred ceiling
CN207277661U (en) * 2017-09-20 2018-04-27 天津市东泽天润建筑有限公司 A kind of side leads to ceiling structure
CN108118818A (en) * 2017-12-27 2018-06-05 骆诚 It is a kind of to build hold court from behind a screen steel construction and installation method
CN208918108U (en) * 2018-07-24 2019-05-31 上海六奇装饰工程有限公司 A kind of use should be in the package assembly and integrated suspended ceiling device of Integral ceiling
CN209457232U (en) * 2018-11-23 2019-10-01 合肥澳达环境艺术设计工程有限公司 A kind of U-shaped aluminium Fang Tongyu downlight combination furred ceiling
CN210288852U (en) * 2019-05-17 2020-04-10 上海丰丽集团有限公司 Hanging piece vertical curtain ceiling structure
CN110469031A (en) * 2019-09-18 2019-11-19 杨烨 A kind of cracking resistance plasterboard
CN213741834U (en) * 2020-05-11 2021-07-20 中铁电气化局集团北京建筑工程有限公司 Special hanger device capable of sliding and resisting wind uncovering for high-speed rail passenger station house and subway artistic ceiling
CN214739194U (en) * 2020-10-28 2021-11-16 上海宝冶建筑装饰有限公司 Hoisting structure of suspended ceiling swing blade
CN113417402A (en) * 2021-07-14 2021-09-21 广州市爱智造科技有限公司 Ceiling system capable of being installed quickly and installation method thereof

Similar Documents

Publication Publication Date Title
CN114753545A (en) Water-drop-shaped aluminum hammer sheet suspended ceiling and installation method thereof
CN213062596U (en) Suspended ceiling mounting structure with stable structure
CN215484010U (en) Aluminum square tube assembled design mounting structure who subsides of preapring for an unfavorable turn of events shape
CN212271379U (en) Keel capable of being hung for secondary time
CN212670973U (en) Building light steel grid suspended ceiling
CN212129637U (en) Hanging piece type suspended ceiling
CN113356448A (en) Installation device and installation method of curved surface metal ceiling
CN111009862B (en) Extrusion-molded bracket arm and production method thereof
CN102943542A (en) Large-span metal ceiling suspension structure
CN210947375U (en) Assembled furred ceiling structure
CN219992857U (en) Assembled furred ceiling structure
CN220318927U (en) Integrated furred ceiling antidetonation construction structures
CN204826366U (en) Indoor suspended ceiling
CN215330865U (en) Double-hook type keel for suspended ceiling
CN219808571U (en) Pipe curtain ceiling device
CN210291606U (en) Parlor ceiling lamp convenient to install
CN215888812U (en) Installation device of curved surface metal furred ceiling
CN215716472U (en) Decorative suspended ceiling
CN211499405U (en) High-stereoscopic ceiling
CN220747240U (en) Metal net rack support with adjusting function
CN215368142U (en) Hang and draw formula furred ceiling access hole structure
CN215106482U (en) Assembled furred ceiling convenient to dismouting
CN220353444U (en) Composite board curtain wall mounting system
CN218952560U (en) Locate inside modularization spatial structure of building
CN218091565U (en) Anti-strutting arrangement of furred ceiling and furred ceiling

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination