CN113356889B - Box type reinforcing method for advanced drill pipe right above tunnel - Google Patents

Box type reinforcing method for advanced drill pipe right above tunnel Download PDF

Info

Publication number
CN113356889B
CN113356889B CN202110797109.2A CN202110797109A CN113356889B CN 113356889 B CN113356889 B CN 113356889B CN 202110797109 A CN202110797109 A CN 202110797109A CN 113356889 B CN113356889 B CN 113356889B
Authority
CN
China
Prior art keywords
pipe
subway tunnel
grouting
threads
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110797109.2A
Other languages
Chinese (zh)
Other versions
CN113356889A (en
Inventor
唐亮
唐文冲
陈宏伟
凌贤长
孔祥勋
丛晟亦
胡心雨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Harbin Institute of Technology Shenzhen
China Railway 17th Bureau Group Co Ltd
Chongqing Research Institute of Harbin Institute of Technology
Original Assignee
Harbin Institute of Technology Shenzhen
China Railway 17th Bureau Group Co Ltd
Chongqing Research Institute of Harbin Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Institute of Technology Shenzhen, China Railway 17th Bureau Group Co Ltd, Chongqing Research Institute of Harbin Institute of Technology filed Critical Harbin Institute of Technology Shenzhen
Priority to CN202110797109.2A priority Critical patent/CN113356889B/en
Publication of CN113356889A publication Critical patent/CN113356889A/en
Application granted granted Critical
Publication of CN113356889B publication Critical patent/CN113356889B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

A box type reinforcing method for an advance drill pipe right above a tunnel belongs to the technical field of foundation pit excavation and reinforcement. The drill pipe consists of a hollow drill bit and one or more connecting pipes; the hollow drill bit is composed of a conical head and a circular steel pipe which are manufactured into a whole, inner threads and outer threads are arranged on the inner wall and the outer wall of the conical head, the outer threads are positive threads, the inner threads are reverse threads, inner connecting threads I are arranged at the tail end of the inner wall of the circular steel pipe, inner connecting threads II are arranged at one end of the inner wall of the connecting pipe, and outer connecting threads are arranged at the other end of the outer wall of the connecting pipe; a plurality of first slurry outlet consolidation holes are formed in the cylinder and the connecting pipe; when the number of the connecting pipes is one, the hollow drill bit is in threaded connection with the connecting pipes; when the number of the connecting pipes is multiple, every two adjacent connecting pipes are connected through threads to form a splicing connecting pipe, and the splicing connecting pipe is connected with the hollow drill bit in a screwing manner; during grouting, the sleeve valve grouting pipe is arranged in the drill pipe and is in tight fit with the drill pipe. The method is used for reinforcing the right upper part of the existing subway tunnel.

Description

一种隧道正上方超前钻管的箱式加固方法A box-type reinforcement method for the advanced drilling pipe directly above the tunnel

技术领域technical field

本发明属于基坑开挖加固技术领域,具体涉及一种隧道正上方超前钻管的箱式加固方法。The invention belongs to the technical field of foundation pit excavation and reinforcement, and in particular relates to a box-type reinforcement method for an advanced drilling pipe directly above a tunnel.

背景技术Background technique

城市地下轨道交通的发展能够有效支撑和引领城市空间布局的扩展,带动地铁周边经济的发展,因此,在既有运营地铁隧道周边进行的各项工程活动将变得日益频繁,伴随而来的地铁临近深大基坑工程不可避免。为了确保地铁隧道的安全,很多国家和地区都给出了地铁隧道应力和变形的控制标准。关于既有地铁隧道结构的保护措施也缺乏较为系统的研究,目前多局限于减小基坑自身变形从而降低隧道变形过大的风险,如针对基坑分仓开挖的研究等。这类方法往往缺乏主动性,一旦地铁隧道在施工过程中发生较大变形,将难以补救并控制地铁隧道进一步的变形。故针对这样的问题有必要提出一种新型的地铁隧道上方开挖施工的加固工法。The development of urban underground rail transit can effectively support and lead the expansion of urban spatial layout and drive the economic development around the subway. Therefore, various engineering activities around the existing operating subway tunnels will become more and more frequent, and the accompanying subway Adjacent to the deep and large foundation pit project is inevitable. In order to ensure the safety of subway tunnels, many countries and regions have given control standards for the stress and deformation of subway tunnels. There is also a lack of systematic research on the protection measures of existing subway tunnel structures. At present, it is mostly limited to reducing the deformation of the foundation pit itself to reduce the risk of excessive tunnel deformation, such as the research on the excavation of the sub-silo of the foundation pit. Such methods often lack initiative, and once the subway tunnel is greatly deformed during the construction process, it will be difficult to remedy and control the further deformation of the subway tunnel. Therefore, it is necessary to propose a new reinforcement method for the excavation construction above the subway tunnel.

此外,现有的注浆装置注浆效果较为单一,且需要对注浆加固区域进行预先打设注浆孔洞。注浆效果不理想,容易出现漏浆或者注浆压力不能达到预期目的。此外,注浆后的注浆凝结体形态无法控制,甚至注浆凝结体出现集中结块或者细微松散,达不到均匀注浆的效果。对于一些特殊注浆加固的工程,无法实现定向注浆,只能进行环向注浆,容易造成浆液浪费,增加施工成本。In addition, the grouting effect of the existing grouting device is relatively simple, and grouting holes need to be pre-drilled in the grouting reinforcement area. The grouting effect is not ideal, and it is easy to leak grouting or the grouting pressure cannot achieve the expected purpose. In addition, the shape of the grouting aggregate after grouting cannot be controlled, and even the grouting aggregate appears concentrated and agglomerated or slightly loose, which cannot achieve the effect of uniform grouting. For some special grouting reinforcement projects, directional grouting cannot be achieved, and only circumferential grouting can be performed, which is likely to cause waste of grouting and increase construction costs.

发明内容SUMMARY OF THE INVENTION

本发明的目的之一是为解决现有技术存在的上述问题,提供一种隧道正上方超前钻管的箱式加固方法,它可有效的达到保护地铁隧道的目的。One of the objectives of the present invention is to solve the above-mentioned problems in the prior art, and provide a box-type reinforcement method for the advance drilling pipe just above the tunnel, which can effectively achieve the purpose of protecting the subway tunnel.

本发明的目的之二是为解决现有注浆装置存在的上述问题,提供一种隧道正上方超前钻管的注浆装置,以满足超前箱式加固工法的超前注浆加固效果。The second purpose of the present invention is to solve the above problems existing in the existing grouting device, and provide a grouting device for advancing the drill pipe just above the tunnel to meet the advanced grouting reinforcement effect of the advanced box reinforcement method.

本发明为解决上述技术问题,采取的技术方案如下:In order to solve the above-mentioned technical problems, the technical scheme adopted by the present invention is as follows:

一种隧道正上方超前钻管的注浆装置,包括袖阀注浆管及钻管;所述钻管由空心钻头及一根或多根连接管组成;所述空心钻头由制为一体的锥头和圆形钢管构成,所述锥头的内、外壁上设有内、外螺纹,设置在所述锥头外壁上的外螺纹为正旋螺纹,设置在锥头内壁上的内螺纹为反旋螺纹,所述圆形钢管内壁的尾端设有内连接螺纹一,所述连接管内壁的一端设有内连接螺纹二,所述连接管外壁的另一端设有外连接螺纹;圆形钢管和连接管上均设有数个出浆固结孔一;A grouting device for an advanced drilling pipe just above a tunnel, comprising a sleeve valve grouting pipe and a drill pipe; the drill pipe is composed of a hollow drill bit and one or more connecting pipes; the hollow drill bit is made of an integrated cone The head is composed of a round steel pipe, the inner and outer walls of the cone head are provided with inner and outer threads, the outer threads arranged on the outer wall of the cone head are positive spiral threads, and the inner threads arranged on the inner wall of the cone head are reversed screw thread, the rear end of the inner wall of the circular steel pipe is provided with an inner connection thread 1, one end of the inner wall of the connection pipe is provided with an inner connection thread 2, and the other end of the outer wall of the connection pipe is provided with an outer connection thread; and the connecting pipe are provided with a number of slurry consolidation holes;

当连接管数量为一根时,空心钻头的内连接螺纹一与连接管的外连接螺纹旋合连接;当连接管的数量为多根时,每相邻两根连接管通过内连接螺纹二和外连接螺纹旋合连接组成拼接连接管,所述拼接连接管中位于任意一端的连接管的外连接螺纹与空心钻头的内连接螺纹一旋合连接;注浆时,所述袖阀注浆管设置在钻管内且二者紧配合。When the number of connecting pipes is one, the inner connecting thread 1 of the hollow drill bit is screwed and connected with the outer connecting thread of the connecting pipe; The external connection thread is screwed and connected to form a spliced connection pipe, and the outer connection thread of the connection pipe at any end of the spliced connection pipe is screwed together with the inner connection thread of the hollow drill bit; when grouting, the sleeve valve grouting pipe It is arranged in the drill pipe and the two are tightly fitted.

一种利用隧道正上方超前钻管的注浆装置实现隧道正上方超前钻管的箱式加固方法,所述加固方法包括以下步骤:A box-type reinforcement method for realizing the advanced drilling pipe directly above the tunnel by utilizing a grouting device for the advanced drilling pipe directly above the tunnel, the reinforcement method comprises the following steps:

步骤一:首先依据地铁隧道保护红线,在地铁隧道保护红线以外打设基坑两侧围护桩,进行地铁隧道两侧的一期基坑开挖,并要求基坑两侧围护桩下端深入地铁隧道的底部;Step 1: First, according to the subway tunnel protection red line, build the fencing piles on both sides of the foundation pit outside the subway tunnel protection red line, carry out the excavation of the first stage foundation pit on both sides of the subway tunnel, and require the lower ends of the fencing piles on both sides of the foundation pit to go deep the bottom of a subway tunnel;

步骤二:在开挖地铁隧道保护红线以外的一期基坑时,同时施工地铁隧道两侧的隔离桩,所述隔离桩距地铁隧道最外侧的最小水平距离不小于3米,打设多排隔离桩,将地铁隧道有效地保护起来,以减小地铁隧道两侧基坑开挖导致的地铁隧道的侧向位移;Step 2: When excavating the first-stage foundation pit beyond the protection red line of the subway tunnel, construct the isolation piles on both sides of the subway tunnel at the same time. The minimum horizontal distance between the isolation piles and the outermost side of the subway tunnel is not less than 3 meters. The isolation pile effectively protects the subway tunnel to reduce the lateral displacement of the subway tunnel caused by the excavation of the foundation pits on both sides of the subway tunnel;

步骤三:当地铁隧道两侧的一期基坑开挖到结构标高并且完成底板浇筑后,利用所述钻管进行侧向长距离钻进施工,先是利用空心钻头钻进,空心钻头外壁上的正旋螺纹用于钻进土体,空心钻头内壁上的反旋螺纹用于将钻进过程中的土体旋转出管体,随着空心钻头的钻进,使得拼接连接管不断的连续钻入,钻至同侧隔离桩为终点;之后,清理钻管内的土,将袖阀注浆管紧固放入钻管内,同时随着袖阀注浆管注浆的进行,浆液通过袖阀注浆管的出浆固结孔二不断渗入到周围土体达到注浆加固的效果,同时渗入土体的浆液与连接管中的浆液连接为一个带有树状分支的钢管混凝桩,当钻管每完成一排钻进时,就建立相应的腰梁,这样使钻管与基坑两侧围护桩连接为一个整体,有效的防止地铁隧道的侧向位移;Step 3: When the first-phase foundation pits on both sides of the subway tunnel are excavated to the structural level and the bottom plate is poured, the drilling pipe is used to carry out lateral long-distance drilling construction. The positive screw thread is used to drill into the soil, and the reverse screw thread on the inner wall of the hollow drill bit is used to rotate the soil body during the drilling process out of the pipe body. , drill to the isolation pile on the same side as the end point; after that, clean the soil in the drill pipe, fasten the sleeve valve grouting pipe into the drill pipe, and at the same time as the sleeve valve grouting pipe is grouted, the slurry is grouted through the sleeve valve The grouting consolidation hole 2 of the pipe continuously penetrates into the surrounding soil to achieve the effect of grouting reinforcement. At the same time, the slurry infiltrated into the soil is connected with the slurry in the connecting pipe to form a steel pipe concrete pile with tree branches. Each time a row of drilling is completed, a corresponding waist beam is established, so that the drilling pipe and the retaining piles on both sides of the foundation pit are connected as a whole, which can effectively prevent the lateral displacement of the subway tunnel;

步骤四:当地铁隧道两侧的一期基坑底板浇筑完成,位于侧向的钻管完成钻进的情况下,进行一期结构施工,形成堆载效果;此后,对地铁隧道正上方的土体进行加固,先在地铁隧道正上方进行旋喷加固桩施工,然后进行地铁隧道正上方的土体开挖,采用分层分条跳仓对称式开挖,先进行基坑两侧围护桩与隔离桩之间土体的开挖,挖到地下负一层底板标高时进行放坡继续向下开挖,直至挖到旋喷加固桩的底部标高位置,进行设备停放临时平台的施工,开始钻管操作,顶钻到规定位置后,清理钻管内的土,将袖阀注浆管紧固放入钻管内进行注浆;当钻管施工结束后,进行放坡回填土,当回填到旋喷加固桩顶部后,进行设备停放临时平台操作,然后进行顶部的钻管施工,当顶部钻管施工完成后,自此,在地铁隧道上方形成了箱式加固结构;之后进行地下负一层底板的施工,将地下负一层底板与基坑两侧围护桩及隧道隔离桩连接为一个整体;Step 4: When the first-phase foundation pit floor on both sides of the subway tunnel has been poured and the lateral drilling pipes have been drilled, the first-phase structural construction will be carried out to form a stacking effect; First, the rotary spray reinforcement pile construction is carried out directly above the subway tunnel, and then the soil excavation is carried out directly above the subway tunnel. The soil between the isolation piles shall be excavated. When the level of the bottom floor of the negative layer is reached, the grading shall be carried out and the excavation shall be continued until the bottom level of the rotary spray reinforcement pile is excavated. The construction of the temporary platform for equipment parking shall be carried out, and the drilling shall be started. Pipe operation, after top drilling to the specified position, clean the soil in the drill pipe, fasten the sleeve valve grouting pipe into the drill pipe for grouting; after the construction of the drill pipe is completed, carry out grading and backfill soil, and when the backfill reaches the rotary injection After the top of the pile is reinforced, the equipment is parked on a temporary platform, and then the drill pipe construction on the top is carried out. When the top drill pipe construction is completed, a box-type reinforcement structure is formed above the subway tunnel; In construction, connect the base plate of the negative ground floor with the retaining piles on both sides of the foundation pit and the tunnel isolation piles as a whole;

步骤五:当局部分层分条跳仓对称式开挖完成地下负一层底板浇筑后,紧接着进行上部负一层结构顶板的施工,包括施作临时加固肋墙;当负一层结构顶板施工完成后,进行其他未开挖部分的分层分条跳仓对称式开挖,等基坑两侧围护桩与隔离桩之间的土体都开挖并完成结构施工后,所有结构件间连接为一个完整的整体。Step 5: After the government completes the pouring of the base plate of the first basement, the construction of the roof of the structure of the upper basement, including the temporary reinforcement of rib walls, is carried out after the symmetrical excavation of the partial floor and the silo. After the completion, carry out the symmetrical excavation of the other unexcavated parts in layered, striped and skipped warehouses. After the soil between the enclosure piles and the isolation piles on both sides of the foundation pit is excavated and the structural construction is completed, all the structural parts will be excavated. connected as a complete whole.

本发明相对于现有技术的有益效果是:The beneficial effects of the present invention relative to the prior art are:

传统地铁正上方开挖方法基本都为后加固措施或者加固施工成本过高,亦或防控加固效果不理想。本发明为超前加固,即在地铁隧道正上方土体开挖卸荷前对隧道上方预留土体进行超前防控加固,使得后期地铁隧道正上方进行正式开挖卸荷时,隧道结构已经处于安全防护状态。且采用了新的注浆装置,该注浆装置不仅可以在地铁隧道正上方土体开挖前进行超前钻进加固,而且可以结合袖阀管进行定向注浆,且注浆浆液可以从钻管出浆固结孔定向溢出,进行定向注浆加固,减少浆液使用,可降低施工成本,加固效果大大提升。The traditional excavation methods directly above the subway are basically post-reinforcement measures or the cost of reinforcement construction is too high, or the prevention and reinforcement effect is not ideal. The present invention is advanced reinforcement, that is, before the excavation and unloading of the soil directly above the subway tunnel, the advanced prevention and control reinforcement is carried out on the reserved soil above the tunnel, so that when the formal excavation and unloading are carried out directly above the subway tunnel in the later stage, the tunnel structure is already in Security status. And a new grouting device is adopted, which can not only carry out advance drilling and reinforcement before the excavation of the soil directly above the subway tunnel, but also perform directional grouting in combination with the sleeve valve pipe, and the grouting slurry can be injected from the drill pipe. The grouting consolidation hole overflows directionally, and directional grouting reinforcement is carried out to reduce the use of grout, which can reduce the construction cost and greatly improve the reinforcement effect.

附图说明Description of drawings

图1是空心钻头的轴测图一;Fig. 1 is the axonometric view 1 of the hollow drill bit;

图2是空心钻头的轴测图二;Fig. 2 is the axonometric view 2 of the hollow drill bit;

图3是连接管的轴测图一;Fig. 3 is the axonometric view 1 of the connecting pipe;

图4是连接管的轴测图二;Figure 4 is a second axonometric view of the connecting pipe;

图5是钻管组装前的示意图;Figure 5 is a schematic view of the drill pipe before assembly;

图6是箱式加固结构示意图;Figure 6 is a schematic diagram of a box-type reinforcement structure;

图7是分层分条跳仓对称式开挖结构示意图;7 is a schematic diagram of a layered, strip-hopping, and warehouse-hopping symmetrical excavation structure;

图8是设备停放临时平台施工中钻管操作的示意图;Fig. 8 is the schematic diagram of the drill pipe operation during the construction of the equipment parking temporary platform;

图9是袖阀注浆管的主剖视图。图中向下指引的箭头表示注浆方向。FIG. 9 is a front cross-sectional view of the sleeve valve grout pipe. The downward pointing arrow in the figure indicates the grouting direction.

上述附图中涉及的部件名称及标号如下:The names and labels of the components involved in the above drawings are as follows:

反旋螺纹1、正旋螺纹2、出浆固结孔一3、内连接螺纹一4、外连接螺纹5、内连接螺纹二6、地铁隧道7、定位圈8、旋喷加固桩9、地下负一层底板10、设备停放临时平台11、隔离桩12、围护桩18、临时加固肋墙20、放坡25、钻管26、6分钢管27、连接件一28、止浆圈一29、钢管开孔30、止浆圈二31、尖底32、连接件二33、注浆管开孔34、PVC注浆管35。Reverse rotation thread 1, positive rotation thread 2, slurry consolidation hole 1 3, inner connection thread 1 4, outer connection thread 5, inner connection thread 2 6, subway tunnel 7, positioning ring 8, rotary spray reinforcement pile 9, underground Bottom layer 10, equipment parking temporary platform 11, isolation pile 12, enclosure pile 18, temporary reinforcement rib wall 20, grading 25, drill pipe 26, 6-point steel pipe 27, connecting piece 1 28, slurry stop ring 1 29 , Steel pipe opening 30, grouting ring 2 31, pointed bottom 32, connecting piece 2 33, grouting pipe opening 34, PVC grouting pipe 35.

具体实施方式Detailed ways

具体实施方式一:如图1-图5及图9所示,本实施方式披露了一种隧道正上方超前钻管的注浆装置,包括袖阀注浆管(为现有技术)及钻管26;所述钻管26由空心钻头及一根或多根连接管组成;所述空心钻头由制为一体的锥头和圆形钢管构成,所述锥头的内、外壁上设有内、外螺纹,设置在所述锥头外壁上的外螺纹为正旋螺纹2,设置在锥头内壁上的内螺纹为反旋螺纹1,所述圆形钢管内壁的尾端设有内连接螺纹一4,所述连接管内壁的一端设有内连接螺纹二6,所述连接管外壁的另一端设有外连接螺纹5;圆形钢管和连接管上均设有数个出浆固结孔一3;Embodiment 1: As shown in Figures 1-5 and 9, the present embodiment discloses a grouting device for drilling pipe ahead of the tunnel directly above, including a sleeve valve grouting pipe (in the prior art) and a drilling pipe 26; the drill pipe 26 is composed of a hollow drill bit and one or more connecting pipes; the hollow drill bit is composed of a conical head and a circular steel pipe made as one body, and the inner and outer walls of the conical head are provided with inner and outer walls. External thread, the external thread arranged on the outer wall of the cone head is a forward thread 2, the inner thread arranged on the inner wall of the cone head is a reverse rotation thread 1, and the rear end of the inner wall of the circular steel pipe is provided with an inner connecting thread 1 . 4. One end of the inner wall of the connecting pipe is provided with an inner connecting thread 2 6, and the other end of the outer wall of the connecting pipe is provided with an external connecting thread 5; both the circular steel pipe and the connecting pipe are provided with several slurry consolidation holes 1 3 ;

当连接管数量为一根时,空心钻头的内连接螺纹一4与连接管的外连接螺纹5旋合连接;当连接管的数量为多根时,每相邻两根连接管通过内连接螺纹二6和外连接螺纹5旋合连接组成拼接连接管,所述拼接连接管中位于任意一端的连接管的外连接螺纹5与空心钻头的内连接螺纹一4旋合连接(采用开山KG420S履带式潜孔钻车将钻管26钻进);注浆时,所述袖阀注浆管(为现有技术)设置在钻管26内且二者紧配合(通过设置在袖阀注浆管的注浆管外壁上的定位圈8与钻管26的连接管内壁紧配合连接)。When the number of connecting pipes is one, the inner connecting thread 4 of the hollow drill bit is screwed and connected with the outer connecting thread 5 of the connecting pipe; when the number of connecting pipes is multiple, every two adjacent connecting pipes pass through the inner connecting thread. Two 6 and external connecting thread 5 are screwed and connected to form a spliced connecting pipe, and the external connecting thread 5 of the connecting pipe located at any end in the splicing connecting pipe is screwed and connected with the inner connecting thread 1 4 of the hollow drill bit (using Kaishan KG420S crawler type The down-the-hole drilling rig drills the drill pipe 26); during grouting, the sleeve valve grouting pipe (in the prior art) is arranged in the drill pipe 26 and the two are tightly matched (through the sleeve valve grouting pipe provided The positioning ring 8 on the outer wall of the grouting pipe is tightly connected with the inner wall of the connecting pipe of the drill pipe 26).

进一步的是,所述空心钻头和连接管均为钢管。Further, the hollow drill bit and the connecting pipe are both steel pipes.

进一步的是,所述数个出浆固结孔一3均为圆孔(圆孔的直径大小,开孔的数量及疏密程度都可依据实际需要进行更改)。Further, the plurality of pulping and consolidation holes-3 are all round holes (the diameter of the round holes, the number and density of the openings can be changed according to actual needs).

具体实施方式二:如图1-图9所示,本实施方式是利用具体实施方式一所述的注浆装置实现隧道正上方超前钻管的箱式加固方法,所述加固方法包括以下步骤:Embodiment 2: As shown in FIGS. 1-9 , this embodiment is a box-type reinforcement method for realizing the advanced drilling pipe directly above the tunnel by using the grouting device described in Embodiment 1. The reinforcement method includes the following steps:

步骤一:首先依据地铁隧道7保护红线,在地铁隧道7保护红线以外打设基坑两侧围护桩18,进行地铁隧道7两侧的一期基坑开挖,并要求基坑两侧围护桩18下端深入地铁隧道7的底部(可根据基坑的开挖深度适当的设置若干数量的腰梁);Step 1: First, according to the protection red line of the subway tunnel 7, build the supporting piles 18 on both sides of the foundation pit outside the protection red line of the subway tunnel 7, carry out the excavation of the first-stage foundation pit on both sides of the subway tunnel 7, and require the surrounding walls on both sides of the foundation pit. The lower end of the guard pile 18 goes deep into the bottom of the subway tunnel 7 (a number of waist beams can be appropriately set according to the excavation depth of the foundation pit);

步骤二:在开挖地铁隧道7保护红线以外的一期基坑时,同时施工地铁隧道7两侧的隔离桩12,所述隔离桩12距地铁隧道7最外侧的最小水平距离不小于3米,打设多排隔离桩12(优选打设四排隔离桩12),将地铁隧道7有效地保护起来,以减小地铁隧道7两侧基坑开挖导致的地铁隧道7的侧向位移;Step 2: When excavating the first-phase foundation pit beyond the protection red line of the subway tunnel 7, construct the isolation piles 12 on both sides of the subway tunnel 7 at the same time, and the minimum horizontal distance between the isolation piles 12 and the outermost side of the subway tunnel 7 is not less than 3 meters. , set up multiple rows of isolation piles 12 (preferably set up four rows of isolation piles 12), effectively protect the subway tunnel 7, to reduce the lateral displacement of the subway tunnel 7 caused by the excavation of the foundation pit on both sides of the subway tunnel 7;

步骤三:当地铁隧道7两侧的一期基坑开挖到结构标高并且完成底板(此处底板指地铁隧道7两侧的一期基坑底板)浇筑后,利用所述钻管26进行侧向长距离(侧向钻进距离可保持在20m-25m左右)钻进施工(钻管26的连接管外壁直径略小于基坑两侧围护桩18外壁直径或根据施工结构需要进行直径调整),先是利用空心钻头钻进,空心钻头外壁上的正旋螺纹2用于钻进土体,空心钻头内壁上的反旋螺纹1用于将钻进过程中的土体旋转出管体,随着空心钻头的钻进,使得拼接连接管不断的连续钻入,钻至同侧隔离桩12为终点;之后,清理钻管26内的土,将袖阀注浆管紧固放入钻管26内,同时随着袖阀注浆管注浆的进行(土质不同,注浆压力也不同。如在砂土中注浆时,考虑到劈裂注浆的注浆压力,通常应控制在0.2-0.5MPa内;如果在粘性土中时,其注浆压力则控制在0.2-0.3MPa;如果是选用水泥砂浆作为浆液时,其坍落度应控制在25-75mm内,而注浆压力则为1-7MPa。而如果其坍落度较为小数的话,注浆压力可以取上限值。如果采用的是水泥水玻璃双液快凝浆液时,那么注浆压力应该要小于1MPa),浆液通过袖阀注浆管的出浆固结孔二不断渗入到周围土体达到注浆加固的效果,同时渗入土体的浆液与连接管中的浆液连接为一个带有树状分支的钢管混凝桩,当钻管26每完成一排钻进时,就建立相应的腰梁,这样使钻管26与基坑两侧围护桩18连接为一个整体,有效的防止地铁隧道的侧向位移;Step 3: When the first-phase foundation pits on both sides of the subway tunnel 7 are excavated to the structural level and the bottom plate (here the bottom plate refers to the first-phase foundation pit floor on both sides of the subway tunnel 7) is poured, the drilling pipe 26 is used to carry out lateral Drilling to a long distance (the lateral drilling distance can be maintained at about 20m-25m) (the diameter of the outer wall of the connecting pipe of the drill pipe 26 is slightly smaller than the diameter of the outer wall of the enclosure piles 18 on both sides of the foundation pit, or the diameter can be adjusted according to the needs of the construction structure) , First use the hollow drill bit to drill, the positive spiral thread 2 on the outer wall of the hollow drill bit is used to drill into the soil, and the reverse spiral thread 1 on the inner wall of the hollow drill bit is used to rotate the soil during the drilling process out of the pipe body. The drilling of the hollow drill bit makes the splicing connection pipe continuously and continuously drilled until the isolation pile 12 on the same side is the end point; after that, the soil in the drill pipe 26 is cleaned, and the sleeve valve grouting pipe is fastened and put into the drill pipe 26 At the same time, with the grouting of the sleeve valve grouting pipe (different soil quality, the grouting pressure is also different. For example, when grouting in sand, considering the grouting pressure of split grouting, it should usually be controlled at 0.2-0.5 MPa; if it is in cohesive soil, the grouting pressure should be controlled within 0.2-0.3MPa; if cement mortar is used as the slurry, the slump should be controlled within 25-75mm, and the grouting pressure should be 1 -7MPa. If the slump is relatively small, the grouting pressure can take the upper limit. If the cement-water glass double-liquid fast-setting grout is used, the grouting pressure should be less than 1MPa), and the grout passes through the sleeve valve. The grouting consolidation hole 2 of the grouting pipe continuously penetrates into the surrounding soil to achieve the effect of grouting reinforcement. At the same time, the grouting infiltrated into the soil and the grouting in the connecting pipe are connected to form a steel pipe concrete pile with tree branches. Each time the drill pipe 26 completes a row of drilling, a corresponding waist beam is established, so that the drill pipe 26 is connected with the surrounding piles 18 on both sides of the foundation pit as a whole, effectively preventing the lateral displacement of the subway tunnel;

步骤四:当地铁隧道7两侧的一期基坑底板浇筑完成,位于侧向的钻管26完成钻进的情况下,进行一期结构施工(一期结构施工主要包括建筑主体结构的梁、柱、楼板、剪力墙等),形成堆载效果(这样有助缓解因基坑卸载导致的土体回弹滞后效应);此后,对地铁隧道7正上方的土体进行加固,先在地铁隧道7正上方进行旋喷加固桩9施工,然后进行地铁隧道7正上方的土体开挖,采用分层分条跳仓对称式开挖,先进行基坑两侧围护桩18与隔离桩12之间土体的开挖,挖到地下负一层底板10标高时进行放坡25继续向下开挖,直至挖到旋喷加固桩9的底部标高位置,进行设备停放临时平台11的施工,开始钻管26操作(钻管26外壁直径为500mm,也可根据基坑项目的自身情况进行适当大小的调整),顶钻到规定位置后,清理钻管26内的土,将袖阀注浆管紧固放入钻管26内进行注浆(土质不同,注浆压力也不同);当钻管26施工结束后,进行放坡25回填土(可选择较好土质的土体置换原来土体,也可直接将原来土体回填),当回填到旋喷加固桩9顶部后,进行设备停放临时平台11操作,然后进行顶部的钻管26施工,当顶部钻管26施工完成后,自此,在地铁隧道7上方形成了箱式加固结构;之后进行地下负一层底板10的施工,将地下负一层底板10与基坑两侧围护桩18及隧道隔离桩12连接为一个整体(这样形成大刚度的反压结构);Step 4: When the first-phase foundation pit floor casting on both sides of the subway tunnel 7 is completed, and the lateral drilling pipe 26 completes the drilling, the first-phase structural construction is carried out (the first-phase structural construction mainly includes the beams of the main structure of the building, Columns, floors, shear walls, etc.) to form a stacking effect (this will help alleviate the hysteresis effect of soil rebound caused by unloading of the foundation pit); after that, the soil directly above the subway tunnel 7 is reinforced, first in the subway Rotary spray reinforcement piles 9 are constructed just above the tunnel 7, and then the soil excavation is carried out directly above the subway tunnel 7. The layered and striped vaulting is used for symmetrical excavation. First, the enclosure piles 18 and isolation piles 12 on both sides of the foundation pit are carried out. During the excavation of the soil between, when the level of the bottom floor 10 is reached, the grading 25 is carried out and the excavation continues downward until the bottom level of the rotary spray reinforcement pile 9 is excavated, and the construction of the temporary platform 11 for equipment parking is carried out. Start the operation of the drill pipe 26 (the diameter of the outer wall of the drill pipe 26 is 500mm, and the appropriate size can also be adjusted according to the conditions of the foundation pit project). The pipe is fastened and put into the drill pipe 26 for grouting (the soil quality is different, the grouting pressure is also different); when the construction of the drill pipe 26 is completed, the grading 25 is backfilled (the soil with better soil quality can be selected to replace the original soil , can also directly backfill the original soil), when backfilling to the top of the rotary jet reinforcement pile 9, the equipment is parked on the temporary platform 11, and then the top drill pipe 26 construction is carried out, when the top drill pipe 26 construction is completed, since then , a box-type reinforcement structure is formed above the subway tunnel 7; the construction of the underground negative first floor 10 is carried out afterwards, and the underground negative first floor 10 is connected with the enclosure piles 18 on both sides of the foundation pit and the tunnel isolation pile 12 as a whole ( In this way, a back pressure structure with large stiffness is formed);

步骤五:当局部分层分条跳仓对称式开挖完成地下负一层底板10浇筑后,紧接着进行上部负一层结构顶板的施工,包括施作临时加固肋墙20(这样比传统的加固结构刚度都大,并且上部结构的自重也可以相当于有效的堆载,有效的防止地铁隧道7因开挖上浮);当负一层结构顶板施工完成后,进行其他未开挖部分的分层分条跳仓对称式开挖,等基坑两侧围护桩18与隔离桩12之间的土体都开挖并完成结构施工后,所有结构件(包括基坑两侧围护桩18、隔离桩12、地下负一层底板10)间连接为一个完整的整体。Step 5: After the government completes the pouring of the base plate 10 on the first floor of the ground, the construction of the top plate of the structure on the upper first floor is carried out, including the temporary reinforcement of the rib wall 20 (this is more than the traditional reinforcement. The rigidity of the structure is large, and the self-weight of the upper structure can also be equivalent to an effective stacking load, which can effectively prevent the subway tunnel 7 from floating due to excavation); when the construction of the roof of the negative layer structure is completed, the other unexcavated parts are layered. Symmetrical excavation is carried out in strips and vaults. After the soil between the enclosure piles 18 and the isolation piles 12 on both sides of the foundation pit is excavated and the structural construction is completed, all structural parts (including the enclosure piles 18 on both sides of the foundation pit, The connection between the isolation pile 12 and the base plate 10) of the negative ground floor is a complete whole.

以上仅为本发明较佳的具体实施方式,但本发明的保护范围,并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。The above are only preferred specific embodiments of the present invention, but the protection scope of the present invention is not limited thereto. Equivalent replacements or changes to the inventive concept shall all fall within the protection scope of the present invention.

Claims (2)

1. A box type reinforcing method of a forepoling pipe right above a tunnel is realized by utilizing a grouting device of the forepoling pipe right above the tunnel, wherein the grouting device comprises a sleeve valve grouting pipe and a drilling pipe (26); the drill pipe (26) consists of a hollow drill bit and one or more connecting pipes; the hollow drill bit is composed of a cone head and a round steel pipe which are manufactured into a whole, inner threads and outer threads are arranged on the inner wall and the outer wall of the cone head, the outer threads arranged on the outer wall of the cone head are positive-rotation threads (2), the inner threads arranged on the inner wall of the cone head are negative-rotation threads (1), inner connecting threads I (4) are arranged at the tail end of the inner wall of the round steel pipe, inner connecting threads II (6) are arranged at one end of the inner wall of the connecting pipe, and outer connecting threads (5) are arranged at the other end of the outer wall of the connecting pipe; a plurality of slurry outlet consolidation holes I (3) are respectively arranged on the round steel pipe and the connecting pipe; when the number of the connecting pipes is one, the internal connecting thread I (4) of the hollow drill bit is screwed with the external connecting thread (5) of the connecting pipe; when the number of the connecting pipes is multiple, every two adjacent connecting pipes are connected in a screwing mode through an inner connecting thread II (6) and an outer connecting thread (5) to form a splicing connecting pipe, and the outer connecting thread (5) of the connecting pipe positioned at any end in the splicing connecting pipe is connected with an inner connecting thread I (4) of the hollow drill bit in a screwing mode; during grouting, the sleeve valve grouting pipe is arranged in the drill pipe (26) and is tightly matched with the drill pipe; the method is characterized in that: the reinforcing method comprises the following steps:
the method comprises the following steps: firstly, according to the protection red line of the subway tunnel (7), arranging fender posts (18) at two sides of a foundation pit outside the protection red line of the subway tunnel (7), excavating the foundation pit at one stage at two sides of the subway tunnel (7), and requiring the lower ends of the fender posts (18) at two sides of the foundation pit to be deep into the bottom of the subway tunnel (7);
step two: when excavation of a first-stage foundation pit outside a protection red line of the subway tunnel (7) is carried out, isolation piles (12) on two sides of the subway tunnel (7) are simultaneously constructed, the minimum horizontal distance between the isolation piles (12) and the outermost side of the subway tunnel (7) is not less than 3m, a plurality of rows of isolation piles (12) are arranged, the subway tunnel (7) is effectively protected, and the lateral displacement of the subway tunnel (7) caused by excavation of the foundation pits on two sides of the subway tunnel (7) is reduced;
step three: after foundation pits at two sides of a subway tunnel (7) are excavated to a structural elevation and a bottom plate is poured, lateral long-distance drilling construction is carried out by using the drill pipe (26), firstly, a hollow drill bit is used for drilling, a forward thread (2) on the outer wall of the hollow drill bit is used for drilling a soil body, a reverse thread (1) on the inner wall of the hollow drill bit is used for rotating the soil body out of a pipe body in the drilling process, a splicing connecting pipe is continuously drilled in along with the drilling of the hollow drill bit, and the isolation pile (12) drilled to the same side is taken as a terminal point; then, cleaning soil in the drill pipe (26), fastening the sleeve valve grouting pipe into the drill pipe (26), simultaneously continuously infiltrating the grout into the surrounding soil body through the grout outlet consolidation holes of the sleeve valve grouting pipe along with the grouting of the sleeve valve grouting pipe to achieve the effect of grouting reinforcement, simultaneously connecting the grout infiltrating into the soil body with the grout in the connecting pipe to form a steel pipe concrete pile with tree branches, and establishing a corresponding waist beam when drilling the drill pipe (26) in each row, so that the drill pipe (26) and the fender posts (18) on two sides of the foundation pit are connected into a whole, and the lateral displacement of the subway tunnel is effectively prevented;
step four: when the first-stage foundation pit bottom plates on two sides of the subway tunnel (7) are poured and the lateral drill pipes (26) are drilled, first-stage structural construction is carried out to form a stacking effect; then, reinforcing the soil body right above the subway tunnel (7), constructing a rotary spraying reinforcing pile (9) right above the subway tunnel (7), excavating the soil body right above the subway tunnel (7), adopting layered strip skip symmetrical excavation, firstly excavating the soil body between a retaining pile (18) at two sides of a foundation pit and an isolation pile (12), continuously excavating a slope (25) when the soil body is excavated to the elevation of a bottom plate (10) at the underground negative layer until the bottom elevation of the rotary spraying reinforcing pile (9) is excavated, constructing an equipment parking temporary platform (11), starting the operation of a drill pipe (26), cleaning the soil in the drill pipe (26) after top drilling to the preset position, and tightly arranging a sleeve valve grouting pipe into the drill pipe (26) for grouting; after the construction of the drill pipe (26), carrying out slope releasing (25) backfill, after backfilling to the top of the jet grouting reinforcing pile (9), carrying out equipment parking temporary platform (11) operation, then carrying out the construction of the drill pipe (26) at the top, and after the construction of the drill pipe (26) at the top is finished, forming a box-type reinforcing structure above the subway tunnel (7); then, constructing an underground minus one-layer bottom plate (10), and connecting the underground minus one-layer bottom plate (10), the fender posts (18) at two sides of the foundation pit and the tunnel isolation piles (12) into a whole;
step five: after the underground negative layer bottom plate (10) is poured by local partial layer strip-by-strip skip symmetrical excavation, the construction of the upper negative layer structure top plate is carried out, including the construction of a temporary reinforcing rib wall (20); after the construction of the top plate with the negative layer of structure is finished, the layered strip-by-strip cabin-jumping symmetrical excavation of other non-excavated parts is carried out, after the soil between the fender piles (18) at the two sides of the foundation pit and the isolation piles (12) is excavated and the structure construction is finished, all the structural members are connected into a whole.
2. The box type reinforcing method for the advance drill pipe right above the tunnel according to claim 1, characterized in that: in the fourth step, the mode of reinforcing the soil body right above the subway tunnel (7) before excavation is as follows: the reinforcing method is characterized in that grouting reinforcement or deep mixing pile reinforcement is adopted, the reinforcing range is longitudinal reinforcement along the subway tunnel (7), and the reinforcing width is the area surrounded by the isolation piles (12) on the two sides of the subway tunnel (7).
CN202110797109.2A 2021-07-14 2021-07-14 Box type reinforcing method for advanced drill pipe right above tunnel Active CN113356889B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110797109.2A CN113356889B (en) 2021-07-14 2021-07-14 Box type reinforcing method for advanced drill pipe right above tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110797109.2A CN113356889B (en) 2021-07-14 2021-07-14 Box type reinforcing method for advanced drill pipe right above tunnel

Publications (2)

Publication Number Publication Date
CN113356889A CN113356889A (en) 2021-09-07
CN113356889B true CN113356889B (en) 2022-07-15

Family

ID=77539496

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110797109.2A Active CN113356889B (en) 2021-07-14 2021-07-14 Box type reinforcing method for advanced drill pipe right above tunnel

Country Status (1)

Country Link
CN (1) CN113356889B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112359980B (en) * 2020-12-03 2021-11-26 王光顺 Connecting method of building assembly structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669346A (en) * 2013-12-30 2014-03-26 湖南城市学院 Sleeve valve pipe and application to landslide control
CN105200978A (en) * 2015-10-12 2015-12-30 山东大学 Advancing type localized double-liquid grouting device and construction method
WO2017190397A1 (en) * 2016-05-03 2017-11-09 许国安 Segmented modular large deformation-resistant and impact-resistant combined anchor bolt and method for assembling same
CN110259386A (en) * 2019-07-18 2019-09-20 骆波清 A kind of high pressure jet grouting drill bit
CN112067347A (en) * 2020-09-07 2020-12-11 合肥巨步机械科技有限公司 A drilling equipment for soil layer soil sample

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103215952A (en) * 2013-04-11 2013-07-24 河南博特工程防护有限公司 High polymer anchoring grouting method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669346A (en) * 2013-12-30 2014-03-26 湖南城市学院 Sleeve valve pipe and application to landslide control
CN105200978A (en) * 2015-10-12 2015-12-30 山东大学 Advancing type localized double-liquid grouting device and construction method
WO2017190397A1 (en) * 2016-05-03 2017-11-09 许国安 Segmented modular large deformation-resistant and impact-resistant combined anchor bolt and method for assembling same
CN110259386A (en) * 2019-07-18 2019-09-20 骆波清 A kind of high pressure jet grouting drill bit
CN112067347A (en) * 2020-09-07 2020-12-11 合肥巨步机械科技有限公司 A drilling equipment for soil layer soil sample

Also Published As

Publication number Publication date
CN113356889A (en) 2021-09-07

Similar Documents

Publication Publication Date Title
WO2020173100A1 (en) Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
CN101736749B (en) Method for constructing soft soil foundation continuous caisson
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN111677520B (en) Construction method of excavating station structure by tunnel first and then station pipe curtain hole pile method
CN112502734B (en) Construction method for water-rich sand layer shield zone connecting channel
CN105064397A (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
CN107542108A (en) A kind of reverse construction method of building basement structure
CN111502696A (en) Dense mesh type advanced support system and construction method of underground tunnel
CN102410031B (en) Underground space structure constructed by pile wall construction method
CN112663625A (en) Construction and protection method for shallow-buried bias-pressure weak surrounding rock tunnel portal in alpine region
CN102660955A (en) Quick construction method for foundation pit slope support
CN112502717B (en) Construction method for excavating connecting channels between shield sections of water-rich sand layer
CN111173004B (en) A construction method for a special-shaped prefabricated pile zipper support structure
CN207261017U (en) Tunnel form prestressed pipe curtain system
CN112443331A (en) Disturbance sensitive stratum ultra-small clear distance large section group-hole parallel subway tunnel construction method
CN113356889B (en) Box type reinforcing method for advanced drill pipe right above tunnel
CN105386779B (en) The counterfort method of large underground structure is built in shallow embedding rock stratum
CN109695453B (en) Auxiliary excavation construction method for vertical shaft main tunnel three-dimensional intersection
CN110130361A (en) A foundation pit support structure and construction method for protecting subway tunnel structures
CN112483126A (en) Construction method of underground excavation air duct of composite stratum with upper soft part and lower hard part
CN209586373U (en) The support system of the lower rock compound cross-section stratum jacking construction inlet and outlet cave of upper soil
CN102330430A (en) Construction method for prefabricated building enclosure of deep foundation pit in low-temperature environment construction
CN107143149A (en) A kind of existing masonry structure building sets up the construction method of basement
CN218934444U (en) Tunnel reinforcement structure with high-pressure horizontal jet grouting piles in permafrost regions
CN106013168A (en) Slag trough structure and construction method for same

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant