CN113339059A - Maintainable tunnel intelligent water-proof and drainage system and method - Google Patents

Maintainable tunnel intelligent water-proof and drainage system and method Download PDF

Info

Publication number
CN113339059A
CN113339059A CN202110375440.5A CN202110375440A CN113339059A CN 113339059 A CN113339059 A CN 113339059A CN 202110375440 A CN202110375440 A CN 202110375440A CN 113339059 A CN113339059 A CN 113339059A
Authority
CN
China
Prior art keywords
drainage
tunnel
electronic valve
water
pipes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110375440.5A
Other languages
Chinese (zh)
Inventor
曾志凯
张鹏
徐平
肖治微
魏善平
李�佑
吴国荣
蔡汝一
杨军
李宏伟
屈建强
邓凯
陈陶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Urban Investment Infrastructure Construction Co ltd
Original Assignee
Chongqing Urban Investment Infrastructure Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Urban Investment Infrastructure Construction Co ltd filed Critical Chongqing Urban Investment Infrastructure Construction Co ltd
Priority to CN202110375440.5A priority Critical patent/CN113339059A/en
Publication of CN113339059A publication Critical patent/CN113339059A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a maintainable tunnel intelligent water-proof and drainage system and a maintainable tunnel intelligent water-proof and drainage method, wherein the maintainable tunnel intelligent water-proof and drainage system comprises a longitudinal drainage blind pipe, an annular drainage blind pipe, a vertical inspection well, a side drainage pipe, a drainage side ditch, a central drainage ditch, an electronic valve and a computer terminal, and the computer terminal is used for receiving and analyzing urban tunnel water pressure load data transmitted by the electronic valve, sending an instruction to the electronic valve and controlling the opening and closing of the electronic valve so as to achieve the balance of tunnel engineering water pressure-drainage amount. Compared with the prior art, the invention can complete the switching of 3 urban tunnel water-proof and drainage modes according to the actual requirements of tunnel water-proof and drainage, and realizes the electronic and information management of tunnel water-proof and drainage; can satisfy the waterproof and drainage demand during the operation of tunnel structure, but still possess the maintenance function, when the drainage function is obstructed, can get into vertical inspection shaft and operate the maintenance under the prerequisite that does not influence urban tunnel traffic.

Description

Maintainable tunnel intelligent water-proof and drainage system and method
Technical Field
The invention relates to the field of tunnel water prevention and drainage, in particular to a maintainable tunnel intelligent water prevention and drainage system and a maintainable tunnel intelligent water prevention and drainage method.
Background
The urban tunnel can effectively improve the urban traffic efficiency and reduce the environmental pollution, and also accords with the advocation of the current low-carbon life. Due to the particularity of the urban tunnel, the presence of buildings and vegetation on the ground makes the urban tunnel face a lot of challenges during operation and maintenance. The water hazard problem (groundwater, rainfall, etc.) has the most common impact on the safety of the tunnel project, with the safety problem caused by groundwater accounting for 58% of the total number of tunnels. When the urban tunnel has the water damage problem, the underground water level is generally reduced, so that surface water sources are exhausted, and water and soil loss, vegetation damage, ground collapse and the like occur. The method can effectively prolong the service life of the urban tunnel and has positive effect on the surrounding ecological environment by solving the problem of tunnel water, and becomes a key factor influencing the success or failure of tunnel engineering.
In order to reduce the probability of water damage, urban tunnels in China mainly adopt 3 water prevention and drainage systems: (1) by adopting a drainage type or drainage self-drainage type system mainly draining water and draining water, namely, the water pressure load borne by the urban tunnel supporting structure is reduced through drainage, the method can effectively reduce the underground water level, but the damage to ground vegetation caused by the method is difficult to recover; (2) the full-wrapping waterproof system isolates stratum seepage water outside a supporting structure of the urban tunnel, realizes the waterproof function of the urban tunnel by improving the waterproof capability of the supporting structure, but the supporting structure is easy to crack under the long-term action of water pressure load so as to cause seepage water diseases; (3) the control type waterproof system combining prevention and drainage usually adopts a half-pack waterproof mode, allows partial drainage of underground water, can ensure the structural safety and reduce the water pressure at the back of a lining, but the method is difficult to realize the relation between dynamic balance water pressure and drainage, so that the ideal state is difficult to achieve. Above 3 kinds of urban tunnel prevent drainage mode all have certain drawback, prevent that the displacement is difficult to control, consequently need an intelligent urban tunnel prevent drainage system.
In the existing urban tunnel water-proof and drainage system, 3 water-proof and drainage modes can not be switched as required. In addition, in the operation maintenance process in the urban tunnel later stage, drainage system's inspection shaft is located urban tunnel road surface's town central point usually and puts, and at the maintenance in-process, maintainer's personal safety is difficult to ensure, and the passage of vehicle in the tunnel also can receive the influence. Therefore, a maintenance-type intelligent urban tunnel water-proof and drainage system is needed to be constructed, the switching of the urban tunnel water-proof and drainage system according to needs can be realized, and the maintenance requirements can be met.
Disclosure of Invention
The invention aims to solve the defects in the prior art, and provides a maintainable urban tunnel intelligent waterproof and drainage system, which can switch 3 waterproof and drainage modes of full-drainage waterproof, full-package waterproof and half-package waterproof according to the waterproof and drainage requirements of urban tunnels, and can be used for later operation and maintenance workers to conveniently and safely perform waterproof and drainage maintenance so as to ensure the health state of urban tunnels in the operation stage.
In order to achieve the purpose, the invention is implemented according to the following technical scheme:
a maintainable tunnel intelligent water-proof and drainage system comprises a longitudinal drainage blind pipe, an annular drainage blind pipe, a vertical inspection well, a side drainage pipe, a drainage side ditch and a central drainage ditch; the longitudinal drainage blind pipes are arranged between a primary tunnel supporting structure and a secondary lining structure of the tunnel supporting structure along the depth direction of the tunnel, the circumferential drainage blind pipes are arranged between the primary tunnel supporting structure and the secondary lining structure of the tunnel supporting structure along the vault of the tunnel, and the longitudinal drainage blind pipes are communicated with the circumferential drainage blind pipes; the vertical inspection well is arranged at the bottoms of two arch feet of the tunnel supporting structure at intervals along the depth direction of the tunnel, and comprises a vertical shaft and an access door arranged on the vertical shaft; the lateral drainage pipes are arranged at two arch feet of the tunnel supporting structure along the depth direction of the tunnel, and two ends of the annular drainage blind pipe are communicated with the two lateral drainage pipes and are distributed in the vertical inspection well; the central drainage ditch is arranged in the center of the bottom of the inverted arch structure of the tunnel, and two sides of the central drainage ditch are communicated with side drainage pipes through drainage blind pipes of the central drainage ditch; the drainage side ditches are arranged on two sides of a road in the tunnel and communicated with the side drainage pipes through side ditch drainage blind pipes.
Furthermore, an electronic valve is installed at the connecting part of the annular drainage blind pipe and the side drainage pipe, and the electronic valve is integrated with a water pressure sensor capable of collecting and recording water pressure data of the urban tunnel in real time; the electronic valve is connected with a computer terminal in a wired or wireless mode, and the computer terminal is used for receiving and analyzing urban tunnel water pressure load data transmitted by the electronic valve, sending an instruction to the electronic valve and controlling the opening and closing of the electronic valve so as to achieve the balance of tunnel engineering water pressure-water discharge.
Furthermore, a ladder stand is arranged on the inner wall of the vertical shaft.
Preferably, the vertical inspection wells are arranged at intervals of 12m at the bottoms of two arch feet of the tunnel supporting structure along the depth direction of the tunnel.
In addition, the invention also provides an intelligent waterproof and drainage method of the maintainable urban tunnel intelligent waterproof and drainage system, which comprises the following steps:
s1, after the urban tunnel is built, the electronic valve is related, the whole tunnel is in a fully-wrapped waterproof state, underground water cannot enter the tunnel, and the supporting structure bears surrounding rock pressure and underground water pressure load;
s2, along with the operation of the tunnel, collecting the underground water infiltrated into the urban tunnel by the longitudinal drainage blind pipe, the circumferential drainage blind pipe, the central drainage ditch and the drainage side ditch, and collecting and recording the water pressure data of the urban tunnel in real time by the water pressure sensor integrated by the electronic valve and transmitting the data to the computer terminal;
s3, based on S2, along with the operation of the tunnel, the computer terminal receives tunnel water pressure data transmitted by the water pressure sensor integrated with the electronic valve, sends an opening instruction to the electronic valve according to the water prevention and drainage requirements of the tunnel, and opens the electronic valve to enable the tunnel to be in a drainage state;
s4, based on S3, the tunnel underground water collected by the circumferential drainage blind pipes and the longitudinal drainage blind pipes enters the side drainage pipes through the opened electronic valves, the central drainage ditch passes through the central drainage blind pipe, and the drainage side ditches pass through the side drainage blind pipes to enable the collected underground water to enter the side drainage pipes through the opened electronic valves;
s5, based on S4, the side drain pipes discharge the collected underground water out of the urban tunnel, and the water pressure sensor integrated with the electronic valve collects and records the water pressure data of the urban tunnel in the current full-discharge state in real time and transmits the data to the computer terminal;
s6, based on S5, the computer terminal receives tunnel water pressure data transmitted by the water pressure sensor integrated with the electronic valve, and managers send closing instructions to the electronic valve through the computer terminal according to actual tunnel water prevention and drainage requirements to close part or all of the electronic valve so as to realize the conversion between a half-pack water prevention and drainage state and a full-pack water prevention and drainage state;
s7, when the electronic valve is damaged in the tunnel operation process, the electronic valve feeds fault information back to the computer terminal, and maintenance personnel can enter the vertical inspection well through the crawling ladder to maintain or manually open the electronic valve according to actual conditions.
Compared with the prior art, the invention has the following beneficial effects:
1) different from traditional self drainage type system, wrap waterproof system and control type waterproof system entirely, this kind of novel intelligent drainage system of preventing in tunnel can be according to the actual demand of preventing and discharging water in tunnel, accomplishes the switching of 3 kinds of urban tunnel drainage modes of preventing, has realized that the tunnel prevents that the drainage is electronic, information-based management.
2) The novel maintainable tunnel water-proof and drainage system can meet the water-proof and drainage requirements during the operation of a tunnel structure, and also has the maintainable function, and when the drainage function is obstructed, the drainage system can enter a vertical inspection well to be operated and maintained on the premise of not influencing urban tunnel traffic.
Drawings
FIG. 1 is a schematic view of the construction of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail with reference to the following embodiments. The specific embodiments described herein are merely illustrative of the invention and do not limit the invention.
The embodiment shown in fig. 1 provides an intelligent maintainable tunnel water-proof and drainage system, which is characterized by comprising a longitudinal drainage blind pipe 2, a circumferential drainage blind pipe 3, a vertical inspection well 4, a side drainage pipe 402, a drainage side ditch 6 and a central drainage ditch 5; the longitudinal drainage blind pipes 2 are arranged between a primary tunnel supporting structure and a secondary lining structure of the tunnel supporting structure 1 along the depth direction of the tunnel, the circumferential drainage blind pipes 3 are arranged between the primary tunnel supporting structure and the secondary lining structure of the tunnel supporting structure along the vault of the tunnel, and the longitudinal drainage blind pipes 2 are communicated with the circumferential drainage blind pipes 3; the vertical inspection well 4 is arranged at the bottom of two arch feet of a tunnel supporting structure at intervals of 12m along the depth direction of a tunnel, the vertical inspection well 4 comprises a vertical shaft 405 and an access door 404 arranged on the vertical shaft 405, a ladder 403 is arranged on the inner wall of the vertical shaft 405, the size of the vertical inspection well 4 can be set according to geological conditions and design information, the side drain pipe 402 is ensured to be positioned at the lowest position of the urban tunnel elevation, and the vertical inspection well 4 can be longitudinally set to be more than 3m in length for facilitating the entry and exit of later-stage operation and maintenance personnel; maintenance personnel enter the vertical inspection well 4 through the access door 404, enter the vertical shaft 405 through the ladder 403 to perform equipment maintenance and perform related operations on post-drainage prevention and drainage of urban tunnels; the side drain pipes 402 are arranged at two arch feet of the tunnel supporting structure along the depth direction of the tunnel and are positioned at the lowest point of the whole urban tunnel; two ends of the annular drainage blind pipe 3 are communicated with the two side drainage pipes 402 and distributed in the vertical inspection well 4, and the annular drainage blind pipe 3 is used for collecting the underground water discharged by the central drainage ditch drainage blind pipe 501 and the side ditch drainage blind pipe 601 and discharging the underground water out of the urban tunnel; the central drainage ditch 5 is arranged at the center of the bottom of the inverted arch structure of the tunnel, and two sides of the central drainage ditch 5 are communicated with the side drainage pipes 402 through a central drainage ditch drainage blind pipe 501; the drainage side ditches 6 are arranged at two sides of a road in the tunnel, and the drainage side ditches 6 are communicated with the side drainage pipe 402 through side ditch drainage blind pipes 601; the above pipes are connected to form a whole drainage system, and the underground water is collected in the side drainage pipe 402.
An electronic valve 401 is installed at the connecting part of the annular drainage blind pipe 2 and the side drainage pipe 402, a water pressure sensor capable of collecting and recording water pressure data of the urban tunnel in real time is integrated on the electronic valve 401, and of course, a manual device is also arranged on the electronic valve 401, so that maintenance personnel can manually control the opening and closing of the electronic valve system 401 when the electronic valve system 401 cannot normally work or the electronic valve system is lack of electric power support; the electronic valve 401 is connected with a computer terminal (not shown in the figure) in a wired or wireless mode, and the computer terminal is used for receiving and analyzing urban tunnel water pressure load data transmitted by the electronic valve 401, sending an instruction to the electronic valve 401, and controlling the opening and closing of the electronic valve 401 so as to achieve the balance of tunnel engineering water pressure-water discharge.
It should be noted that: the tunnel supporting structure 1, the longitudinal drainage blind pipe 2, the circumferential drainage blind pipe 3, the central drainage ditch 5, the drainage side ditch 6, the central drainage blind pipe 501 and the side ditch drainage blind pipe 601 in the embodiment of the invention are all basic components in tunnel engineering, and for a person skilled in the art, the specific meanings of the above terms in the application can be understood in specific situations.
Utilize above-mentioned maintainable urban tunnel intelligence to prevent drainage system can realize intelligence and prevent drainage, its concrete implementation process as follows:
s1, after the urban tunnel is built, the electronic valve 401 is related, the whole tunnel is in a fully-wrapped waterproof state, underground water cannot enter the tunnel, and the supporting structure 1 bears surrounding rock pressure and underground water pressure loads;
s2, along with the operation of the tunnel, collecting the underground water infiltrated by the urban tunnel by the longitudinal drainage blind pipe 1, the circumferential drainage blind pipe 2, the central drainage ditch 5 and the drainage side ditch 6, and collecting and recording the water pressure data of the urban tunnel in real time by the water pressure sensor integrated by the electronic valve 401 and transmitting the data to the computer terminal;
s3, based on S2, along with the operation of the tunnel, the computer terminal receives tunnel water pressure data transmitted by the water pressure sensor integrated with the electronic valve 401, sends an opening instruction to the electronic valve 401 according to the water-proof and drainage requirements of the tunnel, and opens the electronic valve 401 to enable the tunnel to be in a drainage state;
s4, based on S3, the tunnel underground water collected by the circumferential drainage blind pipes and 3 the longitudinal drainage blind pipe 2 enters the side drainage pipe 402 through the opened electronic valve 401, the central drainage ditch 5 passes through the central drainage blind pipe 501, and the drainage side ditch 6 enters the collected underground water into the side drainage pipe 402 through the opened electronic valve 401 through the side ditch drainage blind pipe 601;
s5, based on S4, the side drain pipes drain the collected underground water out of the urban tunnel, and the water pressure sensor integrated by the electronic valve 401 collects and records the water pressure data of the urban tunnel in the current full-discharge state in real time and transmits the data to the computer terminal;
s6, based on S5, the computer terminal receives tunnel water pressure data transmitted by a water pressure sensor integrated with the electronic valve system 401, and managers send closing instructions to the electronic valve system 401 through the computer terminal according to actual tunnel water-proof and drainage requirements to close part or all of the electronic valve system 401, so that the conversion between a half-pack water-proof and drainage state and a full-pack water-proof and drainage state is realized;
s7, when the electronic valve 401 is damaged in the tunnel operation process, the electronic valve system 401 feeds fault information back to the computer terminal, and maintenance personnel can enter the vertical inspection well 4 through the ladder 403 to maintain or manually open the electronic valve 401 according to actual conditions.
Through the implementation of the scheme, the switching of 3 urban tunnel water prevention and drainage modes can be completed according to the actual tunnel water prevention and drainage requirements, and the electronic and information management of tunnel water prevention and drainage is realized; can satisfy the waterproof and drainage demand during the operation of tunnel structure, but still possess the maintenance function, when the drainage function is obstructed, can get into vertical inspection shaft and operate the maintenance under the prerequisite that does not influence urban tunnel traffic.
The technical solution of the present invention is not limited to the limitations of the above specific embodiments, and all technical modifications made according to the technical solution of the present invention fall within the protection scope of the present invention.

Claims (5)

1. A maintainable tunnel intelligent water-proof and drainage system is characterized by comprising a longitudinal drainage blind pipe, an annular drainage blind pipe, a vertical inspection well, a side drainage pipe, a drainage side ditch and a central drainage ditch; the longitudinal drainage blind pipes are arranged between a primary tunnel supporting structure and a secondary lining structure of the tunnel supporting structure along the depth direction of the tunnel, the circumferential drainage blind pipes are arranged between the primary tunnel supporting structure and the secondary lining structure of the tunnel supporting structure along the vault of the tunnel, and the longitudinal drainage blind pipes are communicated with the circumferential drainage blind pipes; the vertical inspection well is arranged at the bottoms of two arch feet of the tunnel supporting structure at intervals along the depth direction of the tunnel, and comprises a vertical shaft and an access door arranged on the vertical shaft; the lateral drainage pipes are arranged at two arch feet of the tunnel supporting structure along the depth direction of the tunnel, and two ends of the annular drainage blind pipe are communicated with the two lateral drainage pipes and are distributed in the vertical inspection well; the central drainage ditch is arranged in the center of the bottom of the inverted arch structure of the tunnel, and two sides of the central drainage ditch are communicated with side drainage pipes through drainage blind pipes of the central drainage ditch; the drainage side ditches are arranged on two sides of a road in the tunnel and communicated with the side drainage pipes through side ditch drainage blind pipes.
2. The maintainable intelligent tunnel waterproofing and drainage system of claim 1, wherein: an electronic valve is installed at the connecting part of the annular drainage blind pipe and the side drainage pipe, and the electronic valve is integrated with a water pressure sensor capable of collecting and recording water pressure data of the urban tunnel in real time; the electronic valve is connected with a computer terminal in a wired or wireless mode, and the computer terminal is used for receiving and analyzing urban tunnel water pressure load data transmitted by the electronic valve, sending an instruction to the electronic valve and controlling the opening and closing of the electronic valve so as to achieve the balance of tunnel engineering water pressure-water discharge.
3. The maintainable intelligent tunnel waterproofing and drainage system of claim 1, wherein: and a ladder stand is arranged on the inner wall of the vertical shaft.
4. The maintainable intelligent tunnel waterproofing and drainage system of claim 1, wherein: the vertical inspection wells are arranged at the bottoms of the two arch feet of the tunnel supporting structure every 12m along the depth direction of the tunnel.
5. An intelligent water-proof and drainage method of a maintainable urban tunnel intelligent water-proof and drainage system is characterized by comprising the following steps:
s1, after the urban tunnel is built, the electronic valve is related, the whole tunnel is in a fully-wrapped waterproof state, underground water cannot enter the tunnel, and the supporting structure bears surrounding rock pressure and underground water pressure load;
s2, along with the operation of the tunnel, collecting the underground water infiltrated into the urban tunnel by the longitudinal drainage blind pipe, the circumferential drainage blind pipe, the central drainage ditch and the drainage side ditch, and collecting and recording the water pressure data of the urban tunnel in real time by the water pressure sensor integrated by the electronic valve and transmitting the data to the computer terminal;
s3, based on S2, along with the operation of the tunnel, the computer terminal receives tunnel water pressure data transmitted by the water pressure sensor integrated with the electronic valve, sends an opening instruction to the electronic valve 401 according to the water prevention and drainage requirements of the tunnel, and opens the electronic valve to enable the tunnel to be in a drainage state;
s4, based on S3, the tunnel underground water collected by the circumferential drainage blind pipes and the longitudinal drainage blind pipes enters the side drainage pipes through the opened electronic valves, the central drainage ditch passes through the central drainage blind pipe, and the drainage side ditches pass through the side drainage blind pipes to enable the collected underground water to enter the side drainage pipes through the opened electronic valves;
s5, based on S4, the side drain pipes discharge the collected underground water out of the urban tunnel, and the water pressure sensor integrated with the electronic valve collects and records the water pressure data of the urban tunnel in the current full-discharge state in real time and transmits the data to the computer terminal;
s6, based on S5, the computer terminal receives tunnel water pressure data transmitted by the water pressure sensor integrated with the electronic valve, and managers send closing instructions to the electronic valve through the computer terminal according to actual tunnel water prevention and drainage requirements to close part or all of the electronic valve so as to realize the conversion between a half-pack water prevention and drainage state and a full-pack water prevention and drainage state;
s7, when the electronic valve is damaged in the tunnel operation process, the electronic valve feeds fault information back to the computer terminal, and maintenance personnel can enter the vertical inspection well through the crawling ladder to maintain or manually open the electronic valve according to actual conditions.
CN202110375440.5A 2021-04-08 2021-04-08 Maintainable tunnel intelligent water-proof and drainage system and method Pending CN113339059A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110375440.5A CN113339059A (en) 2021-04-08 2021-04-08 Maintainable tunnel intelligent water-proof and drainage system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110375440.5A CN113339059A (en) 2021-04-08 2021-04-08 Maintainable tunnel intelligent water-proof and drainage system and method

Publications (1)

Publication Number Publication Date
CN113339059A true CN113339059A (en) 2021-09-03

Family

ID=77467986

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110375440.5A Pending CN113339059A (en) 2021-04-08 2021-04-08 Maintainable tunnel intelligent water-proof and drainage system and method

Country Status (1)

Country Link
CN (1) CN113339059A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114483082A (en) * 2022-01-26 2022-05-13 华设设计集团股份有限公司 Tunnel sewage interception and drainage prevention structure for downward-penetrating refuse landfill and construction method thereof
CN114934808A (en) * 2022-06-29 2022-08-23 招商局重庆交通科研设计院有限公司 Automatic control discharge system and method for water-rich tunnel based on structural safety

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06221100A (en) * 1993-01-26 1994-08-09 Kajima Corp Drainage system in gallery
CH686040A5 (en) * 1993-02-17 1995-12-15 Nalco Chemie Gmbh Deutsche Preventing formation of deposits in drainage system
CN201496072U (en) * 2009-08-31 2010-06-02 中铁第四勘察设计院集团有限公司 Fully-closed water-proof composite lining structure capable of adjusting water pressure
CN103397908A (en) * 2013-07-30 2013-11-20 西南交通大学 Buffering system for solving scarce drainage capability of central drainage ditch of tunnel and control method of buffering system
CN203669886U (en) * 2014-01-23 2014-06-25 招商局重庆交通科研设计院有限公司 Maintainable-type tunnel drainage system
KR20170089262A (en) * 2016-01-26 2017-08-03 호서대학교 산학협력단 Multiple tunnel drainage system
CN208073551U (en) * 2018-04-19 2018-11-09 四川省交通运输厅公路规划勘察设计研究院 Tunnel drainage system
CN109505653A (en) * 2018-12-20 2019-03-22 中国电建集团华东勘测设计研究院有限公司 A kind of stifled arrange of convertible type of rich water tunnel combines supporting construction
CN111119995A (en) * 2020-02-24 2020-05-08 山东省交通规划设计院有限公司 Dynamic monitoring and dredging drainage method for water pressure and flow velocity at back of tunnel lining
CN214464266U (en) * 2021-04-08 2021-10-22 重庆城投基础设施建设有限公司 Maintainable tunnel intelligent water-proof and drainage system

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06221100A (en) * 1993-01-26 1994-08-09 Kajima Corp Drainage system in gallery
CH686040A5 (en) * 1993-02-17 1995-12-15 Nalco Chemie Gmbh Deutsche Preventing formation of deposits in drainage system
CN201496072U (en) * 2009-08-31 2010-06-02 中铁第四勘察设计院集团有限公司 Fully-closed water-proof composite lining structure capable of adjusting water pressure
CN103397908A (en) * 2013-07-30 2013-11-20 西南交通大学 Buffering system for solving scarce drainage capability of central drainage ditch of tunnel and control method of buffering system
CN203669886U (en) * 2014-01-23 2014-06-25 招商局重庆交通科研设计院有限公司 Maintainable-type tunnel drainage system
KR20170089262A (en) * 2016-01-26 2017-08-03 호서대학교 산학협력단 Multiple tunnel drainage system
CN208073551U (en) * 2018-04-19 2018-11-09 四川省交通运输厅公路规划勘察设计研究院 Tunnel drainage system
CN109505653A (en) * 2018-12-20 2019-03-22 中国电建集团华东勘测设计研究院有限公司 A kind of stifled arrange of convertible type of rich water tunnel combines supporting construction
CN111119995A (en) * 2020-02-24 2020-05-08 山东省交通规划设计院有限公司 Dynamic monitoring and dredging drainage method for water pressure and flow velocity at back of tunnel lining
CN214464266U (en) * 2021-04-08 2021-10-22 重庆城投基础设施建设有限公司 Maintainable tunnel intelligent water-proof and drainage system

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘清文;杨其新;: "地铁可维护性防水新理念", 都市快轨交通, no. 06, pages 65 - 68 *
王元清;: "富水隧道分区减压防排水技术研究", 施工技术, no. 10, 25 May 2015 (2015-05-25), pages 122 - 126 *
高洁;郑东;卢腾泽;: "高水压条件下隧道水压力智能控制技术研究", 施工技术, no. 20, pages 74 - 77 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114483082A (en) * 2022-01-26 2022-05-13 华设设计集团股份有限公司 Tunnel sewage interception and drainage prevention structure for downward-penetrating refuse landfill and construction method thereof
CN114934808A (en) * 2022-06-29 2022-08-23 招商局重庆交通科研设计院有限公司 Automatic control discharge system and method for water-rich tunnel based on structural safety

Similar Documents

Publication Publication Date Title
CN214464266U (en) Maintainable tunnel intelligent water-proof and drainage system
CN108316354A (en) With waterproof, the underground pipe gallery structure of drain function and its construction method
CN109854253B (en) Extension method for existing underground excavation and island-stacking transfer station of subway
CN208088344U (en) With waterproof, the underground pipe gallery structure of drain function
CN113339059A (en) Maintainable tunnel intelligent water-proof and drainage system and method
CN206386150U (en) A kind of Underground Subway Station draining and examination and repair system
CN106351254A (en) Multilayer urban underground comprehensive pipe gallery
CN111173563A (en) Merging structure in tunnel drainage system and construction method
CN111750172A (en) Pipe jacking construction process
CN215329049U (en) Track structure with drainage pump station in integral ballast bed
CN111878162B (en) Dredging and pollution discharging method for underground mine leakage filling mortar storage facility
CN110820803B (en) Open excavation construction method for transverse connection channel of shield tunnel
CN106545343B (en) Construction method for underground pipe gallery and storage well
CN109853621B (en) Underground station entrance and exit structure and construction method thereof
CN116145729A (en) Subway layered station structure in sea-land connection area and construction method thereof
CN211819509U (en) Merging structure in tunnel drainage system
CN109339097A (en) It is a kind of with waterproof, the underground pipe gallery structure of drain function
CN214118206U (en) Submarine subway tunnel in hard rock stratum
CN114737586A (en) Multi-well-point linkage precipitation construction method for large basement in water-rich sandy soil area
CN114635748A (en) Shaft sinking water damage prevention method
CN109736274A (en) A kind of semi-underground well shaft type workshop of hydroelectric project
CN111550180A (en) Construction method and construction equipment for hard rock stratum pile foundation in low-clearance narrow space
CN211200451U (en) Extensible utility tunnel
CN113279429B (en) Underground diversion operation plugging structure and plugging method
CN219240617U (en) Inspection shaft suitable for ground storehouse roof heating power pipeline lays

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination