CN113322819A - First-span T-beam erection method at tunnel outlet - Google Patents

First-span T-beam erection method at tunnel outlet Download PDF

Info

Publication number
CN113322819A
CN113322819A CN202110610602.9A CN202110610602A CN113322819A CN 113322819 A CN113322819 A CN 113322819A CN 202110610602 A CN202110610602 A CN 202110610602A CN 113322819 A CN113322819 A CN 113322819A
Authority
CN
China
Prior art keywords
crown block
crane
bridge
tunnel
abutment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110610602.9A
Other languages
Chinese (zh)
Other versions
CN113322819B (en
Inventor
宋超
刘永松
董俭召
刘波
章儒愿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge East China Engineering Co Ltd
Original Assignee
Road and Bridge East China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge East China Engineering Co Ltd filed Critical Road and Bridge East China Engineering Co Ltd
Priority to CN202110610602.9A priority Critical patent/CN113322819B/en
Publication of CN113322819A publication Critical patent/CN113322819A/en
Application granted granted Critical
Publication of CN113322819B publication Critical patent/CN113322819B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention belongs to the technical field of bridge engineering construction, and discloses a first-span T-beam erecting method at a tunnel outlet, wherein a bridge crane is installed at the tunnel outlet, and a front hoisting crown block and a rear hoisting crown block are positioned at the initial positions of the tunnel outlet; the beam transporting trolley transports the T beam to the exit of the tunnel; the rear hoisting crown block hoists the front end hoisting point of the T beam, and the front hoisting crown block and the rear hoisting crown block synchronously move forwards; the rear hoisting crown block hoists the T beam to the middle supporting leg, and the front hoisting crown block and the rear hoisting crown block move back to the initial positions; the front and rear hoisting crown blocks hoist the T-shaped beam and move the T-shaped beam above the bridge abutment and the bridge pier; the bridge girder erection machine integrally drives the T-shaped girder to transversely move to a designated position, and the T-shaped girder is temporarily placed on the abutment and the bridge pier; moving the T-shaped beam on the adjusting bridge abutment and the bridge pier so as to enable the T-shaped beam to be installed on the permanent support; and the bridge girder erection machine returns to the right position, and the front and rear hoisting crown blocks return to the initial positions. The method is adopted to build the T-shaped beam at the tunnel outlet, all the T-shaped beam erection can be completed by utilizing the conventional-size bridge girder erection machine, the construction cost is low, the process is simple, and the operation is convenient.

Description

First-span T-beam erection method at tunnel outlet
Technical Field
The invention relates to the technical field of bridge engineering construction, in particular to a first-span T-beam erection method at a tunnel outlet.
Background
In bridge engineering, the assembled prefabricated T-beam bridge is widely applied to the field of highway construction in China due to the advantages of simple structure, mature technology, economic manufacturing cost, convenience in maintenance and the like. When the number of the prefabricated T-shaped beams is large, a bridge girder erection machine is generally adopted for installation; due to the particularity of use, the bridge girder erection machine is large in size.
When the mountain highway is constructed, under the influence of mountain terrain conditions, the number of the bridges and the tunnels accounts for a larger proportion, the number of the roadbed is small and short, and the condition that the space between the bridges and the tunnels is extremely short or the bridges and the tunnels are directly connected easily occurs. When the bridge girder erection machine is adopted to complete the first span girder at the tunnel outlet, the bridge girder erection machine hoisting overhead traveling crane can only be placed outside the tunnel under the influence of the tunnel building limit and the size of the bridge girder erection machine, and when the girder transporting trolley transports the girder in a conventional mode, the hoisting point at the front end of the girder body cannot be aligned with the front hoisting overhead traveling crane; meanwhile, as the widths of the tunnel and the road width of the bridge are different, part of the T-shaped beam bodies cannot be transversely moved to be in place by directly using the bridge girder erection machine.
Among the prior art, to the first T roof beam of striding of tunnel exit erect, the utility model patent that application number is 201621247674.2 discloses a tunnel import and export closely frame roof beam highway bridging machine, and this application is through adopting small-size jack-up overhead traveling crane hoist engine, riding wheel crossbeam and sideslip wheelbox in the transformation in order to reduce the bridging machine height, has realized carrying out the lifting beam in the jack-up overhead traveling crane entering tunnel. But the above solution does not really solve the problem of positioning the T-beam. By adopting the scheme, a bridge girder erection machine needs to be newly purchased or the existing bridge girder erection machine is greatly improved, equipment such as a small winch is newly purchased, the construction investment is high, and the construction period is long.
Therefore, a first-step T-beam installation method at the exit of the tunnel is needed to solve the above problems.
Disclosure of Invention
The invention aims to provide a first-span T-beam erection method at a tunnel outlet, which can finish the erection of all T-beams by utilizing a conventional-size bridge girder erection machine without modifying the conventional bridge girder erection machine, and has the advantages of low construction cost, simple process, convenience in operation, small safety risk and short construction period.
In order to achieve the purpose, the invention adopts the following technical scheme:
a first-span T-beam erection method at a tunnel exit comprises the following steps:
step S1, installing a bridge girder erection machine at the tunnel outlet, wherein the front crane crown block and the rear crane crown block are positioned at the initial positions of the tunnel outlet;
s2, transporting the T beam to the tunnel outlet by the beam transporting trolley, wherein the front end lifting point of the T beam is positioned right below the rear lifting crown block lifting point;
step S3, the rear hoisting crane hoists the front end hoisting point of the T beam, and the front hoisting crane and the rear hoisting crane move forwards synchronously until the front end hoisting point of the T beam is positioned right below the initial position hoisting point of the front hoisting crane;
step S4, the rear hoisting crown block hoists the T beam to the middle supporting leg, and the front hoisting crown block and the rear hoisting crown block move back to the initial positions;
step S5, the front crane hoists the front end hoisting point of the T-shaped beam, the rear crane hoists the rear end hoisting point of the T-shaped beam, and the T-shaped beam is moved to the upper part of the bridge abutment and the bridge pier;
step S6, the whole bridge girder erection machine drives the T girder to move transversely to a specified position, and the T girder is temporarily placed on the bridge abutment and the bridge pier;
step S7, movably adjusting the T-shaped beam on the bridge abutment and the bridge pier so as to enable the T-shaped beam to be installed on a permanent support;
step S8, the bridge girder erection machine returns to the right state, and the front crane crown block and the rear crane crown block move back to the initial positions;
and S9, repeating the steps S2-S8 until all the T-shaped beams between the bridge abutment and the bridge pier are built.
As a preferred technical solution of the present invention, in step S5, the front crane block and the rear crane block are hoisted by a hoist and a first wire rope together with a front end hoisting point of the T-beam and a rear end hoisting point of the T-beam, and the first wire rope binds the T-beam in a bottom-in-pocket manner.
In a preferred embodiment of the present invention, in step S6, the bridge girder erection machine temporarily places the T-beam on a sand cylinder above the abutment and the pier.
As a preferable embodiment of the present invention, in step S7, the method further includes disconnecting the first wire rope from the spreader, moving the spreader to a position right above the position where the T-beam is to be installed, and hanging a second wire rope on the spreader.
As a preferred technical solution of the present invention, in the step S7, the method further includes installing a first pulling assembly on a side of the T-beam away from the location to be installed.
In a preferred embodiment of the present invention, in step S7, the method further includes removing the sand cylinder, and controlling and adjusting the first pulling assembly such that the T-beam is placed on the permanent support.
As a preferable embodiment of the present invention, the step S1 further includes installing a traveling unit on the abutment and the pier.
As a preferable aspect of the present invention, in step S6, the hanger places the T-beam on the traveling unit on the abutment and the pier through the first wire rope.
As a preferred technical solution of the present invention, in the step S7, a second traction assembly and a third traction assembly are respectively installed on both sides of the T-beam, and the second traction assembly and the third traction assembly are controlled and adjusted to make the T-beam traverse on the walking assembly until the T-beam traverses to a position to be installed.
As a preferable embodiment of the present invention, in step S7, after the T-beam is traversed to the position to be installed by the traveling assembly, a jack is installed on the abutment or the pier, the jack is made to jack up the T-beam, the traveling assembly, the second traction assembly, and the third traction assembly are removed, and the T-beam is placed on the permanent support.
The invention has the beneficial effects that: the first-span T-beam erecting method at the tunnel outlet is applied to T-beam erection at the tunnel outlet, when the method is used for erecting the T-beam at the tunnel outlet, the existing bridge girder erection machine is not required to be modified, all T-beam erection can be completed by using the conventional-size bridge girder erection machine, the construction cost is low, the process is simple, the operation is convenient, the safety risk is small, and the construction period is short.
Drawings
FIG. 1 is a side view of a bridge girder erection machine via according to a first embodiment of the invention;
FIG. 2 is a side view of the girder transporting trolley according to the first embodiment of the present invention for transporting a T-beam;
FIG. 3 is a side view of a T-beam transported to the exit of a tunnel according to a first embodiment of the present invention;
fig. 4 is a side view of a rear lifting crown block lifting T-beam moving forward according to a first embodiment of the present invention;
FIG. 5 is an elevation view of the front end of a T-beam placed on a center leg according to one embodiment of the present invention;
FIG. 6 is a side view of the bridge girder erection machine according to the first embodiment of the present invention after the T-beam is fed into position according to a conventional operation;
FIG. 7 is an elevational view of the bridge girder erection machine according to the first embodiment of the present invention, with the T-beam in place, in normal operation;
FIG. 8 is a front view of a bridge erecting machine carried T-beam after being traversed according to a first embodiment of the present invention;
FIG. 9 is a front elevational view of a first alternative embodiment of the present invention showing a T-beam swing;
FIG. 10 is a rear elevational view of the T-beam being swung into position in accordance with one embodiment of the present invention;
FIG. 11 is a front view of a walking assembly according to a second embodiment of the present invention;
FIG. 12 is a side view of a walking assembly according to a second embodiment of the present invention;
fig. 13 is a front view of the bridging machine carried T-beam according to the second embodiment of the present invention after being traversed;
FIG. 14 is a front view of the leftmost T-beam of the second embodiment of the present invention before it is slid;
FIG. 15 is an elevation view of the leftmost T-beam of embodiment two of the present invention after it has been slid into place;
FIG. 16 is a side view of the leftmost T-beam after being jacked by jacks according to the second embodiment of the present invention;
FIG. 17 is a front view of the left-most T-beam after jack-up according to embodiment two of the present invention;
figure 18 is a side view of the leftmost T-beam of embodiment two of the present invention lowered into position.
In the figure:
1. a bridge girder erection machine; 11. a front crane; 12. a rear hoisting crown block; 13. a middle support leg; 14. a spreader; 141. hanging wires; 15. a first wire rope; 16. a second wire rope; 17. a first pulling assembly; 171. a first chain block; 172. a first connecting member; 18. a walking assembly; 181. a steel rail; 182. walking a stick; 19. a second traction assembly; 191. a second hand-pulled gourd; 20. a third traction assembly; 201. a third chain block; 202. a third connecting member; 21. a permanent support; 22. a beam transporting trolley; 221. a main vehicle; 222. a secondary vehicle; 23. a front leg; 24. a rear riding wheel; 25. an upper chord; 26. a lower chord; 27. a jack;
100. a tunnel; 101. an abutment; 1011. a roadbed behind the platform; 102. a bridge pier; 103. a sand cylinder; 104. a stopper; 200. and a T-beam.
Detailed Description
Reference will now be made in detail to the embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like or similar reference numerals refer to the same or similar parts throughout or parts having the same or similar functions. The embodiments described below with reference to the drawings are illustrative and intended to be illustrative of the invention and are not to be construed as limiting the invention.
In the description of the present invention, unless otherwise expressly specified or limited, the terms "connected," "connected," and "fixed" are to be construed broadly, e.g., as meaning a fixed connection, a removable connection, a mechanical connection, an electrical connection, a direct connection, an indirect connection via an intermediary, a connection between two elements, or an interaction between two elements. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
In the description of the present invention, unless otherwise expressly specified or limited, the first feature "on" or "under" the second feature may include the first feature and the second feature being in direct contact, or may include the first feature and the second feature being in contact not directly but with another feature therebetween. Also, the first feature being "on," "above" and "over" the second feature includes the first feature being directly on and obliquely above the second feature, or merely indicating that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature includes the first feature being directly under and obliquely below the second feature, or simply meaning that the first feature is at a lesser elevation than the second feature.
The technical scheme of the invention is further explained by the specific implementation mode in combination with the attached drawings.
Example one
In this embodiment, the length of the T-beam 200 is 40m, the height of the bridge girder erection machine 1 is 8.76m, and the width is about 5.5m, while the size of the tunnel 100 is 7.5m net height and 10.5m net width, and the front hoisting crown block 11 and the rear hoisting crown block 12 of the bridge girder erection machine 1 cannot directly enter the tunnel 100. The abutment 101 is spaced from the tunnel 100 by only 4m, and the front end lifting point of the T-beam 200 cannot be aligned with the front crane 11. The bridge of the present embodiment has five T-beams 200 arranged in parallel between the abutment 101 and the pier 102. Wherein, the two side T-beams 200 far away from the central axis of the tunnel 100 can not be directly transversely moved to be in place by the bridge girder erection machine 1 due to the size limitation of the tunnel 100 and the bridge girder erection machine 1.
In order to solve the above technical problem, the present embodiment provides a first-span T-beam installation method at a tunnel exit, as shown in fig. 1 to 10, including the following steps:
step S1, installing a bridge girder erection machine 1 at the exit of the tunnel 100, wherein the front hoisting crown block 11 and the rear hoisting crown block 12 are positioned at the initial positions of the exit of the tunnel 100; as shown in fig. 1, this step is a preparation operation, before the T-beam 200 is installed, the hole passing operation of the bridge girder erection machine 1 is completed, such that the front leg 23 of the bridge girder erection machine 1 is supported on the pier 102, the middle leg 13 is supported on the abutment 101 and the abutment roadbed 1011, the rear riding wheel 24 is disposed next to the middle leg 13, is supported on the abutment roadbed 1011 and the tunnel 100, the rear crown block 12 is disposed next to the exit of the tunnel 100, the front crown block 11 is disposed next to the rear crown block 12, and the front crown block 11 and the rear crown block 12 are located at the initial positions at the exit of the tunnel 100.
Step S2, the beam transporting trolley 22 transports the T beam 200 to the exit of the tunnel 100, and the front end lifting point of the T beam 200 is positioned right below the lifting point of the rear lifting crown block 12; as shown in fig. 2, the girder trolley 22 includes a powered primary car 221 and a non-powered secondary car 222. In the precast yard, when the T-beam 200 is placed on the girder transporting trolley 22, the front end suspension point of the T-beam 200 is spaced apart from the foremost edge of the sub-trolley 222 by a designated distance D, which is preferably 0.45m in this embodiment. The beam transporting trolley 22 transports the T-beam 200 to the exit of the tunnel 100 until the front end hoisting point of the T-beam 200 is located right below the hoisting point of the rear hoisting crown block 12, as shown in fig. 3.
Step S3, the rear hoisting crane 12 hoists the front end hoisting point of the T beam 200, and the front hoisting crane 11 and the rear hoisting crane 12 move forwards synchronously until the front end hoisting point of the T beam 200 is positioned right below the initial position hoisting point of the front hoisting crane 11; as shown in fig. 4, in this step, the rear crane 12 lifts the front end lifting point of the T-beam 200 to disengage the front end of the T-beam 200 from the sub-vehicle 222 and slowly moves forward, while the main vehicle 221 transports the T-beam 200 forward in coordination with the synchronous same speed, the sub-vehicle 222 is stationary in place, the front crane 11 and the rear crane 12 move forward in synchronization, and stops when the front end lifting point of the T-beam 200 is located right below the initial position lifting point of the front crane 11.
Step S4, the rear crane crown block 12 lifts the T beam 200 onto the middle leg 13, and the front crane crown block 11 and the rear crane crown block 12 move back to the initial positions; as shown in fig. 5, in this step, the rear crane crown 12 slowly hangs the T-beam 200 on the U-shaped reinforcement assembly on the middle leg 13, a crosstie is supported between the bottom of the front end of the T-beam 200 and the top of the U-shaped reinforcement assembly, and the front crane crown 11 and the rear crane crown 12 are moved back to the initial positions.
Step S5, the front crane 11 lifts the front end lifting point of the T-beam 200, the rear crane 12 lifts the rear end lifting point of the T-beam 200, and the T-beam 200 is moved above the abutment 101 and the pier 102; in this step, as shown in fig. 6 and 7, the front crane 11 lifts the front end lifting point of the T-beam 200, the rear crane 12 lifts the rear end lifting point of the T-beam 200, and the bridge girder erection machine 1 completes the girder lifting and conveying operation in a normal operation. Preferably, in step S5, the front hoisting crown block 11 and the rear hoisting crown block 12 are hoisted by the hoist 14 and the first wire rope 15, the front end hoisting point of the T-beam 200 and the rear end hoisting point of the T-beam 200, in this embodiment, the hoist 14 and the first wire rope 15 are respectively installed at the bottom of the front hoisting crown block 11 and the bottom of the rear hoisting crown block 12, the first wire rope 15 is wound between the hoist 14 and the T-beam 200, and the first wire rope 15 binds the T-beam 200 in a bottom-in-pocket manner.
Step S6, the bridge girder erection machine 1 integrally drives the T-shaped girder 200 to move transversely to a specified position, and the T-shaped girder 200 is temporarily placed on the abutment 101 and the pier 102; as shown in fig. 8, in this step, the front crane crown 11 and the rear crane crown 12 synchronously traverse the T-beam 200 in the installation position direction until the suspension wire 141 of the spreader 14 is stopped at about 1cm from the lower chord 26. After the fixing of the rear riding wheels 24 and the ground is released, the whole bridge girder erection machine 1 with the T-shaped girder 200 moves transversely to the installation position until the upper chord 25 is about 1cm away from the tunnel 100, and the T-shaped girder 200 is temporarily placed on the abutment 101 and the pier 102. Preferably, the bridge girder erection machine 1 temporarily places the T-beam 200 on the sand drum 103 above the abutment 101 and the pier 102, with the bottom elevation of the T-beam 200 being about 5cm higher than the design elevation.
Step S7, moving the T-shaped beam 200 on the adjusting bridge abutment 101 and the bridge pier 102 so as to enable the T-shaped beam 200 to be installed on the permanent support 21; specifically, in this step, the first wire rope 15 is disconnected from the spreader 14, the spreader 14 is lifted to the bottom of the upper boom 25, and the front crane 11 and the rear crane 12 traverse right above the installation position of the T-beam 200. And a second steel wire rope 16 is arranged on the lifting appliance 14, and the bottom end of the second steel wire rope 16 is connected with the first steel wire rope 15 through a shackle. Specifically, a first traction assembly 17 is installed on one side of the T-beam 200 far away from the position to be installed, so as to control the swinging speed of the T-beam 200 and ensure the stability of the T-beam 200, in this embodiment, two sets of first traction assemblies 17 are installed, one set is installed at the abutment 101 and one set is installed at the pier 102, the first traction assembly 17 comprises a first chain hoist 171 and a first connecting member 172 which are connected, one end of the first chain hoist 171 is connected with the bottom side surface of the T-beam 200, one end of the first connecting member 172 is fixedly connected with a cover beam on the abutment 101 or the pier 102, the front hoisting crown block 11 and the rear hoisting crown block 12 slightly lift the T-beam 200, so that the bottom of the T-beam 200 is separated from the sand cylinder 103, after the sand cylinder 103 is removed, the first chain hoists 171 of the two sets of first traction assemblies 17 on the abutment 101 and the pier 102 are controlled to synchronously and slowly release at the same speed, so that the T-beam 200 lifts the T-beam under the combined action of the first traction assemblies 17, the front hoisting crown block 11 and the rear hoisting block 12, and gradually moving towards the installation position until the T-shaped beam 200 moves right above the installation position, so that the T-shaped beam 200 swings and moves in position at a small distance. The front crane 11 and the rear crane 12 slowly drop the beam, so that the T beam 200 is stably placed on the permanent support 21, and the erection work of the T beam 200 is completed. In this embodiment, embedded parts are arranged on the T-beam 200, the abutment 101 and the pier 102 to connect the first traction assembly 17.
Step S8, the bridge girder erection machine 1 returns to the right, and the front crane crown block 11 and the rear crane crown block 12 return to the initial positions; in this step, the bridge girder erection machine 1, the front crane crown block 11, and the rear crane crown block 12 return to their original positions, and the next T-beam 200 is prepared for construction work. Preferably, also includes the recovery disassembly of the first pulling assembly 17 for the next use.
And S9, repeating the steps S2-S8 until all the T-shaped beams 200 between the abutment 101 and the pier 102 are built. In this embodiment, the five T-beams 200 are constructed in sequence in the above manner, the T-beams 200 far away from both sides of the central axis of the tunnel 100 are constructed first, and then the T-beams near the central axis of the tunnel 100 are constructed.
The first-span T-beam erection method at the tunnel outlet is suitable for the erection of the T beam 200 at the tunnel outlet, and a small hoisting crane winch does not need to be purchased additionally, and a middle riding wheel cross beam and a transverse moving wheel box of the conventional bridge girder erection machine 1 do not need to be modified, so that the overall height of the bridge girder erection machine 1 is reduced. The first-span T-beam erection method at the tunnel outlet is suitable for various conventional-size bridge cranes 1, and solves the problem that the front end hoisting point of the T beam 200 is difficult to align with the front hoisting crown block 11, and the problem that the outermost T beam 200 is in place when the T beam 200 cannot be directly carried by the bridge cranes 1 to transversely move in place. According to the first-span T-beam erection method at the tunnel outlet, all T-beam erection can be completed by utilizing the conventional-size bridge girder erection machine 1, the construction cost is low, the process is simple, the operation is convenient, the safety risk is small, and the construction period is short.
However, in practical operation, due to the limitation of factors such as terrain, the median lines of the tunnel 100 and the abutment 101 are not necessarily completely coincident, as shown in fig. 10 in this embodiment, the tunnel 100 and the abutment 101 are offset, that is, the abutment 101 is offset to the left with respect to the tunnel 100 (the present embodiment is illustrated by the offset to the left, and the practical working condition may also be offset to the right, which is not limited by this embodiment), the right end of the abutment 101 is closer to the exit of the tunnel 100, when the T-beam 200 at the rightmost end of the abutment 101 is installed, the bridge erecting machine 1 integrally drives the T-beam 200 to integrally traverse, and when the T-beam 200 is installed in place by a small distance swing-in-and-out manner, that is, the first-span T-beam erecting method in this embodiment is more suitable for the case that the distance between the outer side wall of the abutment 101 and the inner wall of the tunnel 100 is not much different, when the distance between the outer side wall of the abutment 101 and the inner wall of the tunnel 100 is much different (as in the case that the distance between the left end of the abutment 101 and the exit of the tunnel 100 is far from the exit in fig. 10 in this embodiment), the first-span T-beam erecting method in this embodiment may also be used to assist in installing the leftmost T-beam 200 by small-distance swing-out-and-place, but it is preferable to erect the leftmost T-beam 200 by the first-span T-beam erecting method in the second embodiment described below.
Example two
In this embodiment, as shown in fig. 11 to 18, a first-span T-beam erection method at a tunnel exit is provided, where the first-span T-beam erection method at the tunnel exit provided in the second embodiment is more suitable for a case that a distance between a side wall of a bridge 101 and an outer wall of a tunnel 100 is large, and it is difficult to assist in installing the T-beam 200 by using the first embodiment, the construction of the leftmost T-beam 200 is completed by the walking assembly 18, and the first-span T-beam erection method at the tunnel exit in the second embodiment includes the following steps:
step SS0, according to the first-span T beam erection method at the tunnel exit in the first embodiment, the rightmost T beam 200 is completed; in this step, according to the first T-beam spanning method at the exit of the tunnel in the first embodiment, that is, according to steps S1 to S8 in the first embodiment, the right-most T-beam 200 closer to the abutment 101 and the exit of the tunnel 100 is completely erected, and the bridge girder erection machine 1, the front crane crown block 11, and the rear crane crown block 12 are all returned to their original positions, thereby preparing the erection operation of the left-most T-beam 200.
Step SS1, mounting the walking assembly 18 on the abutment 101 and the pier 102; in this step, a group of walking assemblies 18 are respectively installed on the bridge abutment 101 and the bridge pier 102, the structure of the walking assemblies 18 is shown in fig. 11 and 12, each walking assembly 18 comprises two P90-shaped steel rails 181 which are arranged in parallel and transversely at an interval of 25cm, the bottoms of the steel rails 181 are installed on a bent cap on the bridge abutment 101 or the bridge pier 102 in a bolster sleeper mode, a plurality of walking sticks 182 perpendicular to the length direction of the steel rails are arranged at the tops of the steel rails 181, the walking sticks 182 are connected with the steel rails 181 in a rolling mode, the interval between the walking sticks 182 is 5cm, the walking sticks 182 are made of round steel bars, and the length of each walking stick 182 is 40 cm. The length of the walking assembly 18 should be ensured to be 50cm from the center of the leftmost T-beam 200 to the end of the walking assembly 18, so as to prevent the leftmost T-beam 200 from slipping out of the walking assembly 18 and overturning due to misoperation, and the length of the walking assembly 18 is 3.75m in this embodiment.
And step SS2, executing steps S2-S5 in sequence according to the first embodiment, and enabling the bridge girder erection machine 1 to complete the beam lifting, beam conveying and beam moving operations according to the first embodiment, so that the leftmost T beam 200 is moved above the abutment 101 and the pier 102. In this step, after the installation of the traveling assemblies 18 on the abutment 101 and the pier 102 is completed, the beam lifting, beam feeding, and beam moving operations for the leftmost T-beam 200 are completed according to steps S2 to S5 in the first embodiment, specifically: the beam transporting trolley 22 transports the leftmost T beam 200 to the exit of the tunnel 100, and the front end lifting point of the leftmost T beam 200 is positioned right below the lifting point of the rear lifting crown block 12; the rear hoisting crown block 12 hoists the front end hoisting point of the leftmost T beam 200, and the front hoisting crown block 11 and the rear hoisting crown block 12 synchronously move forwards until the front end hoisting point of the leftmost T beam 200 is positioned right below the initial position hoisting point of the front hoisting crown block 11; the rear hoisting crown block 12 hoists the leftmost T-beam 200 onto the middle support leg 13, and the front hoisting crown block 11 and the rear hoisting crown block 12 move back to the initial positions; the front crane 11 lifts the front end lifting point of the leftmost T-beam 200, and the rear crane 12 lifts the rear end lifting point of the leftmost T-beam 200, and moves the leftmost T-beam 200 over the abutment 101 and the pier 102.
And step SS3, the bridge girder erection machine 1 integrally drives the leftmost T-beam 200 to move transversely to a specified position, and the leftmost T-beam 200 is temporarily placed on the traveling assemblies 18 on the abutment 101 and the pier 102. As shown in fig. 13, in this step, according to step S6 in the first embodiment, the leftmost T-beam 200 is placed on the walking stick 182 of the walking assembly 18, specifically: the front hoisting crown block 11 and the rear hoisting crown block 12 synchronously move the leftmost T beam 200 transversely leftwards, after moving to a proper position, the fixing of the rear riding wheel 24 and the ground is removed, the bridge girder erection machine 1 carries the leftmost T beam 200 to move transversely leftwards, the hanger 14 places the leftmost T beam 200 on the walking stick 182 through the first steel wire rope 15, but the first steel wire rope 15 is not removed temporarily, and at the moment, the bottom elevation of the leftmost T beam 200 is consistent with the designed elevation.
Step SS4, moving adjustment abutment 101 and leftmost T-beam 200 on pier 102 so that leftmost T-beam 200 is mounted on permanent support 21. In this step, as shown in fig. 14 and 15, a second traction assembly 19 and a third traction assembly 20 are respectively installed on both sides of the leftmost T-beam 200, the second traction assembly 19 is disposed at the bottom of the leftmost T-beam 200 near the installation position side to provide traction for the movement of the leftmost T-beam 200 on the traveling assembly 18, the second traction assembly 19 includes a second pulling block 191 connected, one end of the second pulling block 191 is connected to the bottom side of the leftmost T-beam 200, and the other end is connected to the stopper 104. The third traction assembly 20 is arranged on the top of the leftmost T-beam 200 far away from the installation position side and used for ensuring the stability of the leftmost T-beam 200 in the moving process on the walking assembly 18, the third traction assembly 20 comprises a third chain block 201 and a third connecting piece 202 which are connected, one end of the third chain block 201 is connected with the reserved steel bars of the top flange plate of the leftmost T-beam 200, and one end of the third connecting piece 202 is connected with the reserved steel bars of the top flange plate of the T-beam 200 which is well built in the first embodiment. After the second traction assembly 19 and the third traction assembly 20 are installed, the second chain block 191 and the third chain block 201 are properly tightened to enable the leftmost T-beam 200 to be in a stable state, and the first steel wire rope 15 is removed. The second chain block 191 at the abutment 101 and the pier 102 is synchronously tightened slowly at the same speed, so that the leftmost T-beam 200 slides towards the installation position gradually on the walking stick 182, meanwhile, the third chain block 201 is matched with the synchronous and loosened at the same speed, in the sliding process of the leftmost T-beam 200, the walking stick 182 away from the installation position side is continuously transferred to the side close to the installation position, and the placement is uniform, so that the leftmost T-beam 200 can continuously slide until the leftmost T-beam 200 slides to the position right above the installation position. The second traction assembly 19 and the third traction assembly 20 are controlled and adjusted to enable the leftmost T-beam 200 to traverse on the walking assembly 18 until the leftmost T-beam 200 traverses above the position to be installed.
And step SS5, after the leftmost T-shaped beam 200 transversely moves to the position above the position to be installed, installing the jack 27 on the abutment 101 or the pier 102. As shown in fig. 16-18, in this step, the jack 27 in this embodiment is a 50t thin jack, and the bottom of the jack 27 is supported on the bridge abutment 101 or the cap beam of the bridge pier 102 by means of a bolster type steel, which is a type of the tribe I20 a. After the installation is finished, the jack 27 is enabled to synchronously and slowly jack the leftmost T beam 200 for about 2cm at the same speed, the walking assembly 18, the second traction assembly 19 and the third traction assembly 20 are removed, and the permanent support 21 is installed; after the permanent support 21 is installed, the jack 27 synchronously and slowly places the leftmost T-beam 200 at the same speed, so that the leftmost T-beam 200 is stably placed on the permanent support 21, and the erection work of the leftmost T-beam 200 is completed.
The first-span T-beam installation method at the tunnel outlet in the second embodiment is more suitable for the working condition that the distance between the outer side wall of the abutment 101 and the inner wall of the tunnel 100 is large, and the T-beam 200 cannot be installed in an auxiliary manner of small-distance swing and in-place. In actual operation, a suitable first-span T beam erection method at the tunnel outlet can be selected according to field operation conditions, that is, in the first-span T beam erection method at the tunnel outlet in the first embodiment and the second embodiment, only one of the first-span T beam erection methods can be selected to construct a plurality of T beams 200, or two methods can be simultaneously selected to construct a plurality of T beams 200, all the T beams 200 between the abutment 101 and the pier 102 are constructed by mixing and matching the methods according to the actual operation conditions, and in the embodiment, no one example is given, so that accurate positioning and rapid construction of the T beams 200 at the outermost positions on the left side and the right side of the abutment 101 and the pier 102 are ensured.
It should be understood that the above-described embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. Any modification, equivalent replacement, and improvement made within the spirit and principle of the present invention should be included in the protection scope of the claims of the present invention.

Claims (10)

1. A first-span T-beam erection method at a tunnel exit is characterized by comprising the following steps:
step S1, installing a bridge girder erection machine (1) at the exit of the tunnel (100), and enabling a front crane crown block (11) and a rear crane crown block (12) to be located at the initial positions of the exit of the tunnel (100);
s2, the beam conveying trolley (22) conveys the T beam (200) to the exit of the tunnel (100), and the front end lifting point of the T beam (200) is positioned right below the lifting point of the rear hoisting overhead crane (12);
step S3, the rear crane crown block (12) lifts the front end lifting point of the T-shaped beam (200), and the front crane crown block (11) and the rear crane crown block (12) move forwards synchronously until the front end lifting point of the T-shaped beam (200) is positioned right below the lifting point of the initial position of the front crane crown block (11);
step S4, the rear crane overhead crane (12) lifts the T-beam (200) to the middle support leg (13), and the front crane overhead crane (11) and the rear crane overhead crane (12) move back to initial positions;
step S5, the front crane crown block (11) lifts the front end lifting point of the T-shaped beam (200), the rear crane crown block (12) lifts the rear end lifting point of the T-shaped beam (200), and the T-shaped beam (200) is moved to the position above the abutment (101) and the pier (102);
s6, the bridge girder erection machine (1) integrally drives the T beam (200) to move transversely to a specified position, and the T beam (200) is temporarily placed on the abutment (101) and the pier (102);
step S7, movably adjusting the T beam (200) on the bridge abutment (101) and the bridge pier (102) so as to enable the T beam (200) to be installed on a permanent support (21);
step S8, the bridge girder erection machine (1) returns to the right, and the front crane overhead crane (11) and the rear crane overhead crane (12) return to the initial positions;
and S9, repeating the steps S2-S8 until the T-shaped beams (200) between the bridge abutment (101) and the bridge pier (102) are built.
2. The first-span T-beam erection method at the tunnel exit according to claim 1, wherein in the step S5, the front crane crown block (11) and the rear crane crown block (12) are hoisted with the front end hoisting point of the T-beam (200) and the rear end hoisting point of the T-beam (200) through a hoist (14) and a first wire rope (15), and the first wire rope (15) binds the T-beam (200) in a bottom-in-pocket manner.
3. The first-pass T-beam erecting method at the tunnel exit according to claim 2, wherein in the step S6, the bridge girder erection machine (1) temporarily places the T-beam (200) on the sand cylinder (103) above the abutment (101) and the pier (102).
4. The method for first-span T-beam erection at the tunnel exit according to claim 3, wherein in the step S7, the method further comprises disconnecting the first wire rope (15) from the hanger (14), moving the hanger (14) to a position right above the position where the T-beam (200) is to be installed, and hanging a second wire rope (16) on the hanger (14).
5. The method for installing the first-span T-beam at the tunnel exit according to claim 4, wherein in the step S7, the method further comprises installing a first traction assembly (17) on the side of the T-beam (200) far away from the position to be installed.
6. The method for T-beam first-pass installation at tunnel exit of claim 5, wherein in step S7, further comprising removing the sand drum (103), controlling and adjusting the first pulling assembly (17) so that the T-beam (200) is placed on the permanent seat (21).
7. The first-pass T-beam erection method at the tunnel exit according to claim 2, further comprising installing walking assemblies (18) on said abutment (101) and said pier (102) in said step S1.
8. The method for first-span T-beam erection at a tunnel exit according to claim 7, wherein said hanger (14) places said T-beam (200) on said traveling assemblies (18) on said abutment (101) and said pier (102) through said first wire rope (15) in said step S6.
9. The head-on T-beam installation method at the tunnel exit according to claim 8, wherein in the step S7, a second traction assembly (19) and a third traction assembly (20) are respectively installed on two sides of the T-beam (200), and the second traction assembly (19) and the third traction assembly (20) are controlled and adjusted to enable the T-beam (200) to traverse on the walking assembly (18) until the T-beam (200) traverses to a position to be installed.
10. The head-on T-beam installation method at the tunnel exit according to claim 9, wherein in the step S7, after the T-beam (200) is traversed to the position to be installed by the walking assembly (18), a jack (27) is installed on the abutment (101) or the pier (102), the jack (27) jacks up the T-beam (200), the walking assembly (18), the second traction assembly (19) and the third traction assembly (20) are removed, and the T-beam (200) is placed on the permanent support (21).
CN202110610602.9A 2021-06-01 2021-06-01 Method for erecting first-span T beam at tunnel outlet Active CN113322819B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110610602.9A CN113322819B (en) 2021-06-01 2021-06-01 Method for erecting first-span T beam at tunnel outlet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110610602.9A CN113322819B (en) 2021-06-01 2021-06-01 Method for erecting first-span T beam at tunnel outlet

Publications (2)

Publication Number Publication Date
CN113322819A true CN113322819A (en) 2021-08-31
CN113322819B CN113322819B (en) 2023-02-10

Family

ID=77423145

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110610602.9A Active CN113322819B (en) 2021-06-01 2021-06-01 Method for erecting first-span T beam at tunnel outlet

Country Status (1)

Country Link
CN (1) CN113322819B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113957806A (en) * 2021-12-02 2022-01-21 中交路桥华东工程有限公司 Construction method of T-shaped beam at bridge-tunnel joint

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0579018A (en) * 1991-09-18 1993-03-30 P S Co Ltd Bridge girder laying device
JPH1088991A (en) * 1996-09-11 1998-04-07 Ishikawajima Harima Heavy Ind Co Ltd Method and device for supplying segment
CN1880582A (en) * 2006-01-18 2006-12-20 秦皇岛市北戴河通联路桥机械有限公司 Bridging method of bridge girder erection machine at tunnel exit
CN101851898A (en) * 2010-06-09 2010-10-06 中铁科工集团有限公司 Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof
CN101864736A (en) * 2010-04-29 2010-10-20 郑州市华中建机有限公司 Full-span bridge erection machine for box girder passing through tunnels on passenger dedicated line
CN201801818U (en) * 2010-09-01 2011-04-20 秦皇岛天业通联重工股份有限公司 Bridge erecting machine capable of erecting double-track twin beams at tunnel entrance by zero distance
CN201943004U (en) * 2010-12-02 2011-08-24 秦皇岛天业通联重工股份有限公司 Double-girder transporting and erecting integrated bridge girder erecting machine capable of realizing girder erecting at zero distance from tunnel portal
WO2011143923A1 (en) * 2010-05-19 2011-11-24 北京万桥兴业机械有限公司 Transportation and erection integrated machine with displacement platforms and method for erecting bridge using the same
CN102979040A (en) * 2012-12-13 2013-03-20 中铁二局股份有限公司 Assembly method of bridge-building machine at exit of tunnel connected with bridge
CN107905122A (en) * 2017-11-10 2018-04-13 秦皇岛优益重工科技有限公司 A kind of T-shaped beam twin beams traversing erecting process in parallel
KR101933965B1 (en) * 2018-07-16 2018-12-31 에스오씨기술지주 주식회사 Girder launching system
CN110130229A (en) * 2019-06-24 2019-08-16 中交一公局第六工程有限公司 It a kind of several juxtaposed double cantilever erections machines and its sets a roof beam in place and passing method
CN209508837U (en) * 2019-01-16 2019-10-18 中交一公局海威工程建设有限公司 A kind of precast beam traverse displacement unit and precast beam crossing system
CN110886233A (en) * 2019-12-17 2020-03-17 中交路桥建设有限公司 Construction method for connecting T-shaped beam with bridge
CN212247900U (en) * 2020-04-08 2020-12-29 中铁六局集团有限公司 A artifical beam device that traverses that is used for bridge and tunnel zero distance to erect T roof beam
CN112575694A (en) * 2020-12-10 2021-03-30 江苏捷达交通工程集团有限公司 Mounting construction method for long-span T beam

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0579018A (en) * 1991-09-18 1993-03-30 P S Co Ltd Bridge girder laying device
JPH1088991A (en) * 1996-09-11 1998-04-07 Ishikawajima Harima Heavy Ind Co Ltd Method and device for supplying segment
CN1880582A (en) * 2006-01-18 2006-12-20 秦皇岛市北戴河通联路桥机械有限公司 Bridging method of bridge girder erection machine at tunnel exit
CN101864736A (en) * 2010-04-29 2010-10-20 郑州市华中建机有限公司 Full-span bridge erection machine for box girder passing through tunnels on passenger dedicated line
WO2011143923A1 (en) * 2010-05-19 2011-11-24 北京万桥兴业机械有限公司 Transportation and erection integrated machine with displacement platforms and method for erecting bridge using the same
CN101851898A (en) * 2010-06-09 2010-10-06 中铁科工集团有限公司 Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof
CN201801818U (en) * 2010-09-01 2011-04-20 秦皇岛天业通联重工股份有限公司 Bridge erecting machine capable of erecting double-track twin beams at tunnel entrance by zero distance
CN201943004U (en) * 2010-12-02 2011-08-24 秦皇岛天业通联重工股份有限公司 Double-girder transporting and erecting integrated bridge girder erecting machine capable of realizing girder erecting at zero distance from tunnel portal
CN102979040A (en) * 2012-12-13 2013-03-20 中铁二局股份有限公司 Assembly method of bridge-building machine at exit of tunnel connected with bridge
CN107905122A (en) * 2017-11-10 2018-04-13 秦皇岛优益重工科技有限公司 A kind of T-shaped beam twin beams traversing erecting process in parallel
KR101933965B1 (en) * 2018-07-16 2018-12-31 에스오씨기술지주 주식회사 Girder launching system
CN209508837U (en) * 2019-01-16 2019-10-18 中交一公局海威工程建设有限公司 A kind of precast beam traverse displacement unit and precast beam crossing system
CN110130229A (en) * 2019-06-24 2019-08-16 中交一公局第六工程有限公司 It a kind of several juxtaposed double cantilever erections machines and its sets a roof beam in place and passing method
CN110886233A (en) * 2019-12-17 2020-03-17 中交路桥建设有限公司 Construction method for connecting T-shaped beam with bridge
CN212247900U (en) * 2020-04-08 2020-12-29 中铁六局集团有限公司 A artifical beam device that traverses that is used for bridge and tunnel zero distance to erect T roof beam
CN112575694A (en) * 2020-12-10 2021-03-30 江苏捷达交通工程集团有限公司 Mounting construction method for long-span T beam

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
于乐鹏: "TTYJ900运架一体机在350km/h高铁隧道口负距离架设中小桥施工技术", 《施工技术》 *
崔明等: "超短距离隧接桥T梁架设施工技术", 《四川水力发电》 *
张兴佳等: "桥隧相连处隧道洞口T梁安装施工技术", 《交通世界》 *
张耀辉等: "大型架桥机设备在高铁施工中的应用", 《筑路机械与施工机械化》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113957806A (en) * 2021-12-02 2022-01-21 中交路桥华东工程有限公司 Construction method of T-shaped beam at bridge-tunnel joint
CN113957806B (en) * 2021-12-02 2023-10-20 中交路桥华东工程有限公司 Construction method of T-beam at bridge-tunnel junction

Also Published As

Publication number Publication date
CN113322819B (en) 2023-02-10

Similar Documents

Publication Publication Date Title
CN108330842B (en) Bridge girder erection machine for erection construction of large-span reinforced concrete composite girder and construction method
CN100547225C (en) A kind of tunnel overhead arch mould plate trolley with floating type traffic under carriage
CN101787678B (en) Large-span section assembling bridge manufacturing machine and assembling construction process thereof
CN111852521B (en) Mouth-shaped piece assembling trolley for construction of internal structure of large-section shield tunnel and synchronous construction method
CN207932932U (en) A kind of twin beams slope Bridge Erector
CN108677742A (en) The moving cantilever type Bridge Erector of full precast pier, cushion cap and beam body prefabricated construction
CN207498754U (en) A kind of novel track-laying machine of city track traffic engineering
CN103485282A (en) Method for gantry machine to go into and out of tunnels to erect box girders
CN217378620U (en) Intelligent bridge erecting system
CN110093863A (en) A kind of double face integration Bridge Erector being not provided with front leg strut
CN210561749U (en) Multi-frame juxtaposed double-cantilever bridge girder erection machine
CN2921280Y (en) Tunnel invert form trolley with floating running chassis
CN202482776U (en) Web type bridge fabrication machine for bridge constructions under conditions of heavy winds and high altitudes
CN110158486B (en) Bridge girder erection machine for erecting spliced wide beams and construction method
CN201943004U (en) Double-girder transporting and erecting integrated bridge girder erecting machine capable of realizing girder erecting at zero distance from tunnel portal
CN113322819B (en) Method for erecting first-span T beam at tunnel outlet
CN208533370U (en) A kind of Bridge Erector of large span steel reinforced concrete combination beam erection construction
CN112144401B (en) Bridge girder erection machine over-span method based on curve track and large longitudinal slope environment
CN105735142A (en) Bridge girder erection machine for prestressed concrete bridge precast section span-by-span splicing construction
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
CN106192761B (en) A kind of method for disassembling mobile formwork in the narrow short transition time section of bridge tunnel
CN209338005U (en) A kind of mobile height leg gantry crane of erecting beam construction
CN208430437U (en) A kind of mobile formwork bridge fabrication machine
CN102535351B (en) Web plate type bridge fabrication machine for constructing bridge under strong wind and high altitude conditions and construction process
CN211973152U (en) Large-tonnage box girder erection construction system capable of realizing height control

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant