CN113294176B - Grouting amount calculating method for grouting reconstruction engineering of coal seam roof - Google Patents
Grouting amount calculating method for grouting reconstruction engineering of coal seam roof Download PDFInfo
- Publication number
- CN113294176B CN113294176B CN202110653068.XA CN202110653068A CN113294176B CN 113294176 B CN113294176 B CN 113294176B CN 202110653068 A CN202110653068 A CN 202110653068A CN 113294176 B CN113294176 B CN 113294176B
- Authority
- CN
- China
- Prior art keywords
- grouting
- coal seam
- seam roof
- grouting amount
- reconstruction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000003245 coal Substances 0.000 title claims abstract description 41
- 238000000034 method Methods 0.000 title claims abstract description 28
- 238000004364 calculation method Methods 0.000 claims abstract description 24
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 17
- 239000011435 rock Substances 0.000 claims description 14
- 238000005056 compaction Methods 0.000 claims description 3
- 238000005065 mining Methods 0.000 abstract description 4
- 230000008859 change Effects 0.000 abstract description 3
- 230000000694 effects Effects 0.000 abstract description 3
- 230000008569 process Effects 0.000 abstract description 3
- 230000009467 reduction Effects 0.000 abstract description 3
- 238000004519 manufacturing process Methods 0.000 description 6
- 238000009933 burial Methods 0.000 description 3
- 238000010276 construction Methods 0.000 description 3
- 230000002265 prevention Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Theoretical Computer Science (AREA)
- Civil Engineering (AREA)
- Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- General Physics & Mathematics (AREA)
- General Engineering & Computer Science (AREA)
- Geometry (AREA)
- Evolutionary Computation (AREA)
- Remote Sensing (AREA)
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
The invention discloses a grouting amount calculating method for a coal seam roof grouting reconstruction project, which comprises the following steps: s1, lithology thickness statistics of horizontal branch holes; s2, building different lithology grouting amount calculation templates; s3, establishing a crack development section grouting amount calculation template; s4, building a grouting amount calculation template of the branch hole of the grouting reconstruction of the coal seam roof; s5, based on the steps S1-S4, the grouting quantity of the branch holes is obtained through grouting reconstruction of the coal seam roof, the method is suitable for the technical field of coal mining, the data acquisition path is simple, the practicability of the data calculation method is high, the region correction coefficients can be properly adjusted according to the change of geological conditions of different regions, and the method can be directly applied and has high popularization; the method and the program for calculating the grouting quantity are convenient and practical, a foundation is laid for the grouting reconstruction engineering of the coal seam roof, the grouting reconstruction engineering of the coal seam roof has water shutoff and water reduction effects, the method is a novel coal mine water control method, the grouting process can be optimized, and scientific and accurate grouting is realized.
Description
Technical Field
The invention belongs to the technical field of coal mining, and particularly relates to a grouting amount calculating method for a coal seam roof grouting reconstruction project.
Background
Along with the continuous development of the China coal industry, the hydrogeological conditions of the coal mining field are gradually changed from simple type to complex type, and the burial depth conditions of the coal bed are also changed from shallow burial to deep burial. At present, a plurality of coal bases in the middle and west of China represented by Huang Long coal fields are gradually developed along with the construction and production of mines in areas, and in recent years, roof water damage accidents occur in a plurality of mines, so that the mine construction is seriously delayed, mining equipment is flooded and damaged, production is reduced by working face production stopping and the like, and serious economic loss and safety threat are caused to the mines.
Along with the gradual development of mine construction and production, the actual disclosure of production of the mine with simple hydrogeological conditions proves that the mine with complex hydrogeological conditions is seriously inconsistent with the conclusion of prior research, the actual water inflow of the mine is larger than the expected result in advance, and the adoption of mature water prevention and control technical measures can not effectively prevent and control the water damage of the mine roof, so that the mine water prevention and control work and the safety production are brought with larger pressure.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provides a grouting amount calculating method for a grouting reconstruction project of a coal seam roof.
In order to achieve the above purpose, the invention adopts the following technical scheme:
the grouting amount calculating method for the grouting reconstruction engineering of the coal seam roof comprises the following steps:
s1, lithology thickness statistics of horizontal branch holes;
s2, building different lithology grouting amount calculation templates;
s3, establishing a crack development section grouting amount calculation template;
s4, building a grouting amount calculation template of the branch hole of the grouting reconstruction of the coal seam roof;
s5, based on the steps S1-S4, the grouting quantity of the branch holes of the grouting reconstruction of the coal seam roof is obtained.
Preferably, the statistics of lithology thickness of the S1 horizontal branch hole include:
dividing the lithology of the seam roof grouting reconstruction target zone interval into three types, namely mudstone, a permeable layer and a compact layer; counting the accumulated thickness values of the same lithology, and marking the accumulated thickness values of the mudstone, the permeable layer and the compact layer as Hm, hs and Hd in sequence;
and respectively solving density functions of the permeable layer and the compact layer:
fs=Hs/(Hm+Hs+Hd);
fd=Hd/(Hm+Hs+Hd);
wherein, fs: density of the permeation layer, decimal; fd: density of dense layer, decimal.
Preferably, the different lithology grouting amount calculation template comprises:
permeable rock grouting amount: qs=cs (2.83fs+0.45) Hs;
compact rock grouting amount: qd=cd (-2.12fd+1.74) Hd;
wherein, qs: the grouting amount of permeable rock, t; qd is compact rock grouting amount, t; cs is the sandstone cementation coefficient, dimensionless, and has a value of 0.7-1.5; cd: compact layer compaction coefficient, dimensionless, and value between 0.8 and 1.2.
Preferably, the crack development section grouting amount calculating template comprises:
grouting amount of crack development section: qf=cf (-0.9pt+8.05) Hf;
wherein, qf: grouting amount of crack development section, t; pt is the water pressure of the crack section, and MPa; hf, crack development segment length, m; cf is the regional correction coefficient, dimensionless, and takes a value between 0.5 and 2.0.
Preferably, the calculation template for grouting the roof of the coal seam to reconstruct the branch hole grouting amount comprises:
Q total (S) =Qf+Qs+Qd。
In summary, due to the adoption of the technical scheme, the beneficial effects of the invention are as follows:
the data acquisition method is simple, the data calculation method is high in practicability, the regional correction coefficients can be properly adjusted according to the change of geological conditions of different regions, the method can be directly applied, and the method is high in popularization;
the invention can calculate the grouting quantity of the branch holes of the grouting reconstruction of the coal seam roof more accurately, provides a convenient and practical calculation method and a program of the grouting quantity, creates a foundation for the grouting reconstruction engineering of the coal seam roof, ensures that the grouting reconstruction engineering of the coal seam roof has the water shutoff and water reduction effects, becomes a new coal mine water control method, can optimize the grouting process and achieves scientific and accurate grouting.
Drawings
FIG. 1 is a flow chart of a method for calculating grouting amount in a coal seam roof grouting reconstruction project according to the invention;
Detailed Description
The following describes a concrete embodiment of the grouting amount calculating method for the coal seam roof grouting reconstruction project with reference to fig. 1. The grouting amount calculating method for the coal seam roof grouting reconstruction project is not limited to the description of the following embodiments.
Examples:
the embodiment provides a concrete structure of a grouting amount calculating method for a grouting reconstruction project of a coal seam roof, as shown in fig. 1, comprising the following steps:
s1, lithology thickness statistics of horizontal branch holes;
s2, building different lithology grouting amount calculation templates;
s3, establishing a crack development section grouting amount calculation template;
s4, building a grouting amount calculation template of the branch hole of the grouting reconstruction of the coal seam roof;
s5, based on the steps S1-S4, the grouting quantity of the branch holes of the grouting reconstruction of the coal seam roof is obtained.
Specifically, the S1 horizontal branch hole lithology thickness statistics comprise:
dividing the lithology of the seam roof grouting reconstruction target zone interval into three types, namely mudstone, a permeable layer and a compact layer; counting the accumulated thickness values of the same lithology, and marking the accumulated thickness values of the mudstone, the permeable layer and the compact layer as Hm, hs and Hd in sequence;
and respectively solving density functions of the permeable layer and the compact layer:
fs=Hs/(Hm+Hs+Hd);
fd=Hd/(Hm+Hs+Hd);
wherein, fs: density of the permeation layer, decimal; fd: density of dense layer, decimal.
Specifically, the different lithology grouting amount calculation templates comprise:
permeable rock grouting amount: qs=cs (2.83fs+0.45) Hs;
compact rock grouting amount: qd=cd (-2.12fd+1.74) Hd;
wherein, qs: the grouting amount of permeable rock, t; qd is compact rock grouting amount, t; cs is the sandstone cementation coefficient, dimensionless, and has a value of 0.7-1.5; cd: compact layer compaction coefficient, dimensionless, and value between 0.8 and 1.2.
Further, the crack development section grouting amount calculating template comprises:
grouting amount of crack development section: qf=cf (-0.9pt+8.05) Hf;
wherein, qf: grouting amount of crack development section, t; pt is the water pressure of the crack section, and MPa; hf, crack development segment length, m; cf is the regional correction coefficient, dimensionless, and takes a value between 0.5 and 2.0.
Further, the calculation template for grouting the top plate of the coal seam to reconstruct the grouting amount of the branch hole comprises the following components:
Q total (S) =Qf+Qs+Qd。
Working principle:
as shown in fig. 1, firstly, the lithology of a seam roof grouting reconstruction target zone interval is divided into three categories, namely mudstone, a permeable layer and a compact layer; counting the accumulated thickness values of the same lithology, and marking the accumulated thickness values of the mudstone, the permeable layer and the compact layer as Hm, hs and Hd in sequence;
and respectively solving density functions of the permeable layer and the compact layer:
fs=Hs/(Hm+Hs+Hd);
fd=Hd/(Hm+Hs+Hd);
then, the permeable rock grouting amount is calculated respectively: qs=cs (2.83fs+0.45) Hs; and
Compact rock grouting amount: qd=cd (-2.12fd+1.74) Hd;
next, the crack growth stage grouting amount was calculated: qf=cf (-0.9pt+8.05) Hf;
finally, based on Q Total (S) And (3) obtaining grouting quantity of the branch hole for grouting transformation of the coal seam roof by using the method of the combination of Qf, qs and Qd.
The data acquisition method is simple, the data calculation method is high in practicability, the regional correction coefficients can be properly adjusted according to the change of geological conditions of different regions, the method can be directly applied, and the method is high in popularization;
the invention can calculate the grouting amount of the branch hole of the grouting reconstruction of the coal seam roof more accurately, provides a convenient and practical calculation method and program of the grouting amount, lays a foundation for the grouting reconstruction engineering of the coal seam roof, ensures that the grouting reconstruction engineering of the coal seam roof has water shutoff and water reduction effects, becomes a new coal mine water control method, can optimize the grouting process and achieves scientific and accurate grouting.
The foregoing is a further detailed description of the invention in connection with the preferred embodiments, and it is not intended that the invention be limited to the specific embodiments described. It will be apparent to those skilled in the art that several simple deductions or substitutions may be made without departing from the spirit of the invention, and these should be considered to be within the scope of the invention.
Claims (1)
1. The grouting amount calculating method for the grouting reconstruction engineering of the coal seam roof is characterized by comprising the following steps of:
s1, lithology thickness statistics of horizontal branch holes;
s2, building different lithology grouting amount calculation templates;
s3, establishing a crack development section grouting amount calculation template;
s4, building a grouting amount calculation template of the branch hole of the grouting reconstruction of the coal seam roof;
s5, based on the steps S1-S4, obtaining grouting quantity of a branch hole of the grouting reconstruction of the coal seam roof;
the S1 horizontal branch hole lithology thickness statistics comprise:
dividing the lithology of the seam roof grouting reconstruction target zone interval into three types, namely mudstone, a permeable layer and a compact layer; counting the accumulated thickness values of the same lithology, and marking the accumulated thickness values of the mudstone, the permeable layer and the compact layer as Hm, hs and Hd in sequence;
and respectively solving density functions of the permeable layer and the compact layer:
fs=Hs/(Hm+Hs+Hd);
fd=Hd/(Hm+Hs+Hd);
wherein, fs: density of the permeation layer, decimal; fd: density of dense layer, decimal;
the different lithology grouting amount calculation template comprises:
permeable rock grouting amount: qs=cs (2.83fs+0.45) Hs;
compact rock grouting amount: qd=cd (-2.12fd+1.74) Hd;
wherein, qs: the grouting amount of permeable rock, t; qd is compact rock grouting amount, t; cs is the sandstone cementation coefficient, dimensionless, and has a value of 0.7-1.5; cd: compact layer compaction coefficient, dimensionless, value between 0.8 and 1.2;
the crack development section grouting amount calculating template comprises:
grouting amount of crack development section: qf=cf (-0.9pt+8.05) Hf;
wherein, qf: grouting amount of crack development section, t; pt is the water pressure of the crack section, and MPa; hf, crack development segment length, m; cf is an area correction coefficient, the dimensionless value is between 0.5 and 2.0;
the calculation template for grouting calculation of the branch hole of grouting reconstruction of the coal seam roof comprises:
Q total (S) =Qf+Qs+Qd。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110653068.XA CN113294176B (en) | 2021-06-11 | 2021-06-11 | Grouting amount calculating method for grouting reconstruction engineering of coal seam roof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110653068.XA CN113294176B (en) | 2021-06-11 | 2021-06-11 | Grouting amount calculating method for grouting reconstruction engineering of coal seam roof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113294176A CN113294176A (en) | 2021-08-24 |
CN113294176B true CN113294176B (en) | 2023-09-22 |
Family
ID=77327986
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110653068.XA Active CN113294176B (en) | 2021-06-11 | 2021-06-11 | Grouting amount calculating method for grouting reconstruction engineering of coal seam roof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113294176B (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105401971A (en) * | 2015-09-02 | 2016-03-16 | 煤科集团沈阳研究院有限公司 | Surface and underground combined regional grouting method |
CN112127909A (en) * | 2020-09-08 | 2020-12-25 | 河海大学 | Accurate grouting repairing and reinforcing method for broken surrounding rock of tunnel |
CN112377221A (en) * | 2020-10-30 | 2021-02-19 | 中煤科工集团西安研究院有限公司 | Method for inhibiting development of water guide crack belt by grouting before mining and building key layer of structure |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
AUPR576501A0 (en) * | 2001-06-18 | 2001-07-12 | Russell Mineral Equipment Pty Ltd | Rock bolting apparatus and method |
-
2021
- 2021-06-11 CN CN202110653068.XA patent/CN113294176B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105401971A (en) * | 2015-09-02 | 2016-03-16 | 煤科集团沈阳研究院有限公司 | Surface and underground combined regional grouting method |
CN112127909A (en) * | 2020-09-08 | 2020-12-25 | 河海大学 | Accurate grouting repairing and reinforcing method for broken surrounding rock of tunnel |
CN112377221A (en) * | 2020-10-30 | 2021-02-19 | 中煤科工集团西安研究院有限公司 | Method for inhibiting development of water guide crack belt by grouting before mining and building key layer of structure |
Also Published As
Publication number | Publication date |
---|---|
CN113294176A (en) | 2021-08-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103967507B (en) | A kind of curtain-grouting technique being suitable for rich water mine down-hole exploitation water blockoff | |
CN110005389B (en) | Ultra-deep sandstone seam net modification evaluation method based on thermo-fluid-solid coupling effect | |
CN110043312B (en) | Control method for grouting filling ground surface settlement range | |
CN106437824A (en) | Gas-containing-coal multistage permeability increasing method | |
CN108180035B (en) | Gas extraction method for combined operation of drilling and permeability increasing of high-gas low-permeability coal seam | |
CN113177322B (en) | Fracturing single well control reserve calculation method | |
CN109446602B (en) | Numerical test method for extracting gas from ultra-thick coal seam through ground vertical drilling | |
CN109630088A (en) | Method for determining arrangement position of high-position drilling hole | |
CN105484752A (en) | Ground rectification and retracement method for metro operating tunnel | |
CN108614902A (en) | A kind of shale gas well creation data analysis method producing system variation | |
CN111027789B (en) | Calculation method for quantitative optimization of working system of coal-bed gas well | |
CN105297736B (en) | Sequential deepening grouting construction technology and device for soil covering layer on karst cave in karst area | |
CN110017155B (en) | Grouting reinforcement water-proof method for water-rich gravel layer of top plate of coal face | |
CN113294176B (en) | Grouting amount calculating method for grouting reconstruction engineering of coal seam roof | |
CN103628914B (en) | The separate zone production of a kind of low-angle dip coal seam is visited to lower and is oozed the method for low-permeability thick-layer bedrock aquifer | |
CN116108572A (en) | Shale gas condensate well volume fracturing outer zone productivity contribution analysis method | |
CN106499432A (en) | Coal seam with gas mash gas harnessing method based on different preservation regions | |
CN103967506B (en) | A kind of ore body roof Karst Fissures is grown and the curtain-grouting method in strong Fu Shui mineral deposit | |
CN113622907A (en) | Single-hole synchronous monitoring method for movement and fracture distribution in coal seam mining overburden rock | |
CN111119978B (en) | Method for extracting coal seam gas by drilling holes in bedding and hydraulically cutting seams | |
CN110749533B (en) | Water-retention coal mining discrimination method based on equivalent water-resisting layer thickness | |
CN115688396B (en) | Extraction-injection ratio determination method for in-situ leaching uranium mining well site extraction-injection mode | |
CN117627635A (en) | Correction method for abnormal productivity well test data of strong heterogeneous carbonate gas reservoir | |
CN115545283A (en) | Shale oil horizontal well close-cutting fracturing cluster spacing optimization design method | |
CN111335903B (en) | Construction method for penetrating dense building group downwards in stratum of joint zone |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |