CN113236309A - Shallow tunnel arch-up open-construction arch-down underground excavation construction method - Google Patents

Shallow tunnel arch-up open-construction arch-down underground excavation construction method Download PDF

Info

Publication number
CN113236309A
CN113236309A CN202110466910.9A CN202110466910A CN113236309A CN 113236309 A CN113236309 A CN 113236309A CN 202110466910 A CN202110466910 A CN 202110466910A CN 113236309 A CN113236309 A CN 113236309A
Authority
CN
China
Prior art keywords
arch
construction
underground excavation
concrete
open
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110466910.9A
Other languages
Chinese (zh)
Inventor
戚小磊
王英森
熊永川
曹镇范
龙蛟
黄明琦
庞万福
赵俊猛
李鹏翔
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 22nd Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd
Original Assignee
China Railway 22nd Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 22nd Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway 22nd Bureau Group Co Ltd filed Critical China Railway 22nd Bureau Group Co Ltd
Priority to CN202110466910.9A priority Critical patent/CN113236309A/en
Publication of CN113236309A publication Critical patent/CN113236309A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a shallow tunnel arch up-arch open-arch and down-arch underground excavation construction method, and relates to the technical field of tunnel construction. The method comprises the following steps: s1, leveling a gutter and excavating a side slope; s2, excavating an arch part by an open cut method; s3, arch support is performed; s4, backfilling the surface on the arch; s5, excavating the three steps and the temporary inverted arch; s6, secondary lining; and S7, paving a waterproof layer. The construction method for the shallow tunnel under-arch underground excavation with the top-exposed arch structure effectively controls the surface subsidence, protects the ground buildings, prevents the ground buildings from being influenced by the tunnel construction, avoids the result of dismantling the ground buildings, greatly saves the construction time, thereby saving the cost, has reasonable design of the tunnel secondary lining structure, simple construction method and easy control of the construction quality, thereby greatly reducing the construction cost, saving the construction period, ensuring the construction safety and having good social benefit.

Description

Shallow tunnel arch-up open-construction arch-down underground excavation construction method
Technical Field
The invention relates to the technical field of tunnel construction, in particular to a construction method for underground excavation of a shallow tunnel with an upper open arch and a lower open arch.
Background
In recent years, with the rapid development of tunnel construction technology, tunnel sections are increasingly large, and geological conditions are increasingly poor, especially in ultra-shallow buried sections, large-section tunnel construction is difficult, slow in progress and high in danger, and large excavation construction is not allowed by adopting an open cut method for the ultra-shallow buried sections of tunnels, which are often penetrated by buildings (structures) on the ground surface or have poor geological conditions.
The tunnel section is large in the construction process, the vertical height of open cut to be excavated is large in the shallow tunnel construction process, further excavation slope enlargement is large, disturbance and damage are inevitably generated to surrounding soil bodies in the excavation process, open cut tunnel concrete construction is difficult, backfill amount is large and other problems exist, and meanwhile, the shallow tunnel is easy to collapse due to the safety risk when improper support is generated, and further the surrounding environments such as the earth surface are affected.
Disclosure of Invention
Aiming at the defects of the prior art, the invention provides a shallow tunnel arch top open arch bottom underground excavation construction method, which aims to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: a shallow tunnel top open arch and bottom underground excavation construction method comprises the following steps:
s1, leveling the gutter and digging a side slope: after the gutter is smoothly applied, permanent side slopes on two sides of the line begin to be excavated, and spray-seeding grass planting protection is applied;
s2, arch part excavation by an open cut method: excavating an arch part by adopting an open cut method, constructing a temporary slope support, carrying out anchor net guniting operation on the temporary slope support, and arranging a mortar anchor rod;
s3, arch support: constructing arch support, erecting steel frames, arranging 2 42 locking anchor pipes on the left arch foot and the right arch foot respectively, and pouring a molded concrete arch protection;
s4, arch backfilling: after the arch protection strength in the step S3 reaches the design, tamping and filling soil and stones to the temporary backfill surface;
s5, excavating three steps and a temporary inverted arch: when the backfill soil in the step S4 recovers the surface building (structure), the construction is changed from arch top open construction to arch bottom underground excavation construction, and the normal excavation of the hole body is carried out under the arch by adopting a three-step and temporary inverted arch method;
s6, secondary lining: when the excavation under the arch in the step S5 is finished by adopting the three steps and the temporary inverted arch, constructing a side wall and a temporary support, and constructing second lining concrete;
s7, paving a waterproof layer: and (5) after the second-lining concrete in the step S6 reaches the design strength, timely backfilling the earth stones to the design elevation, and paving a clay waterproof layer to finish the construction.
Further optimizing the technical scheme, in the step S2, the thickness of the sprayed concrete after the anchor nets are sprayed with the slurry is 12-18cm, 8 steel bar nets are adopted, and the space between the grids is 20cm x 20 cm.
Further optimizing the technical scheme, in the step S2, the diameter of the mortar anchor rod is 20-22cm, the length of the anchor rod is 3.5-4.0m, and the distance between two adjacent anchor rods of the pre-embedded anchor rod is 1.0 x 1.0 m.
Further optimizing the technical scheme, the steel frames in the step S3 are I20b type steel frames, the spacing between erected steel frames is 0.6 m/truss, the length of the 42-pin anchor pipe in the step S3 is 6.0m, and the longitudinal spacing is 0.6 m.
Further optimizing the technical scheme, the concrete poured in the step S3 is C25 concrete, and the thickness of the concrete is 100-110 cm.
Further optimizing the technical scheme, in the step S3, when the steel frame is erected, a protective arch I20b steel frame joint is reserved so as to be connected with an arch wall steel frame during underground excavation under the arch.
Further optimizing the technical scheme, the height of the arch top in the step S4 is 3-4m, and the thickness of the clay waterproof layer in the step S7 is 40-60 cm.
Further optimizing the technical scheme, in the step S2, the anchor rods are arranged in the poured concrete, then the reinforcing mesh is laid along the excavated slope, and then the concrete is sprayed along the surface of the reinforcing mesh.
Compared with the prior art, the invention provides a shallow tunnel arch top open arch bottom underground excavation construction method, which has the following beneficial effects:
1. the invention relates to a method for constructing a shallow tunnel by adopting an arch top open construction and an arch bottom underground excavation construction, which is characterized in that the arch top open construction is converted into the arch bottom underground excavation construction, the arch bottom is normally excavated by adopting a three-step and temporary inverted arch method, so that the construction safety is ensured, and the influence on the surrounding environment is reduced.
2. The construction method for the shallow tunnel under-arch underground excavation with the top-exposed arch structure effectively controls the surface subsidence, protects the ground buildings, prevents the ground buildings from being influenced by the tunnel construction, avoids the result of dismantling the ground buildings, greatly saves the construction time, thereby saving the cost, has reasonable design of the tunnel secondary lining structure, simple construction method and easy control of the construction quality, thereby greatly reducing the construction cost, saving the construction period, ensuring the construction safety and having good social benefit.
Drawings
FIG. 1 is a schematic flow chart of a shallow tunnel arch top open arch bottom underground excavation construction method provided by the invention;
FIG. 2 is a schematic structural diagram of a flat gutter and an excavated slope of the shallow tunnel under-arch underground excavation construction method with an arch-up and an arch-down structure;
FIG. 3 is a schematic view of an arch portion excavated by an open cut method of the shallow tunnel arch-up open arch-down underground excavation construction method provided by the invention;
FIG. 4 is a schematic diagram of a construction arch support structure of the construction method of the shallow tunnel arch with an upper open arch and a lower underground excavation;
FIG. 5 is a schematic structural view of an arch backfill surface of the shallow tunnel arch top open arch bottom underground excavation construction method provided by the invention;
fig. 6 is a schematic diagram of a three-step + temporary inverted arch excavation structure of the shallow tunnel arch top-open arch bottom-arch underground excavation construction method provided by the invention;
fig. 7 is a schematic structural diagram of a secondary lining and a waterproof layer laying structure of the shallow tunnel arch top open arch bottom underground excavation construction method provided by the invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The first embodiment is as follows: referring to fig. 1 to 7, the present invention discloses a shallow tunnel arch top-open arch bottom-underground excavation construction method, which includes the following steps:
s1, leveling the gutter and digging a side slope: after the gutter is smoothly applied, permanent side slopes on two sides of the line begin to be excavated, and spray-seeding grass planting protection is applied;
s2, arch part excavation by an open cut method: excavating an arch part by adopting an open cut method, constructing a temporary slope support, wherein the temporary slope support is operated by adopting anchor net guniting, and is provided with a mortar anchor rod, the thickness of concrete sprayed after the anchor net guniting is 12cm, 8 steel bar nets are adopted, the space between grids is 20 cm-20 cm, the diameter of the mortar anchor rod is 20cm, the length of the anchor rod is 3.5m, the space between two adjacent anchor rods of the anchor rod is 1.0-1.0 m, the anchor rod is arranged on an excavation slope, then the steel bar net is laid on the surface of the excavated slope, and then the concrete is sprayed along the surface of the steel bar net;
s3, arch support: constructing arch support, erecting steel frames, arranging 2 42 locking anchor pipes on left and right arch legs respectively, pouring a molded concrete arch protector, wherein the steel frames are I20b steel frame, the distance between erected steel frames is 0.6 m/pin, the length of the 42 locking anchor pipe is 6.0m, the longitudinal distance is 0.6, the poured concrete is C25 concrete, the thickness of the concrete is 100cm, and an arch protector I20b steel frame joint is reserved when erecting the steel frames so as to be connected with an arch wall during underground excavation under the arch;
s4, arch backfill surface: after the arch protection strength in the step S3 reaches the design, tamping and filling soil and stones to the temporary backfill surface;
s5, excavating three steps and a temporary inverted arch: when the surface construction (structure) of the backfill soil in the step S4 is recovered, the arch top open construction is changed into the arch bottom underground excavation construction, and the normal excavation of the hole body is carried out under the arch by adopting a three-step and temporary inverted arch method;
s6, secondary lining: when the excavation under the arch in the step S5 is finished by adopting the three steps and the temporary inverted arch, constructing a side wall and a temporary support, and constructing second lining concrete;
s7, paving a waterproof layer: and (5) after the second-lining concrete in the step S6 reaches the design strength, timely backfilling the earth stones to the design elevation, and paving a clay waterproof layer with the thickness of 40cm to finish the construction.
Example two: referring to fig. 1 to 7, the present invention discloses a shallow tunnel arch top-open arch bottom-underground excavation construction method, which includes the following steps:
s1, leveling the gutter and digging a side slope: after the gutter is smoothly applied, permanent side slopes on two sides of the line begin to be excavated, and spray-seeding grass planting protection is applied;
s2, arch part excavation by an open cut method: excavating an arch part by adopting an open cut method, constructing a temporary slope support, wherein the temporary slope support is operated by adopting anchor mesh guniting, and is provided with a mortar anchor rod, the thickness of concrete sprayed after the anchor mesh guniting is 15cm, 8 steel bar meshes are adopted, the space between grids is 20cm to 20cm, the diameter of the mortar anchor rod is 22cm, the length of the anchor rod is 4.0m, the space between two adjacent anchor rods with the embedded anchor rods is 1.0 to 1.0m, the anchor rod is arranged on the surface of the excavated slope, then the steel bar meshes are laid on the surface of the excavated slope, and then the concrete is sprayed along the surface of the steel bar meshes;
s3, arch support: constructing arch support, erecting steel frames, arranging 2 42 locking anchor pipes on left and right arch legs respectively, pouring a molded concrete arch protector, wherein the steel frames are I20b steel frame, the distance between erected steel frames is 0.6 m/pin, the length of the 42 locking anchor pipe is 6.0m, the longitudinal distance is 0.6, the poured concrete is C25 concrete, the thickness of the concrete is 100cm, and an arch protector I20b steel frame joint is reserved when erecting the steel frames so as to be connected with an arch wall during underground excavation under the arch;
s4, arch backfill surface: after the arch protection strength in the step S3 reaches the design, tamping and filling soil and stones to the temporary backfill surface;
s5, excavating three steps and a temporary inverted arch: when the backfill soil in the step S4 recovers the surface building (structure), the construction is changed from arch top open construction to arch bottom underground excavation construction, and the normal excavation of the hole body is carried out under the arch by adopting a three-step and temporary inverted arch method;
s6, secondary lining: when the excavation under the arch in the step S5 is finished by adopting the three steps and the temporary inverted arch, constructing a side wall and a temporary support, and constructing second lining concrete;
s7, paving a waterproof layer: and (5) after the second-lining concrete in the step S6 reaches the design strength, timely backfilling the earth stones to the design elevation, and paving a clay waterproof layer with the thickness of 50cm, thereby completing construction.
Example three: referring to fig. 1 to 7, the present invention discloses a shallow tunnel arch top-open arch bottom-underground excavation construction method, which includes the following steps:
s1, leveling the gutter and digging a side slope: after the gutter is smoothly applied, permanent side slopes on two sides of the line begin to be excavated, and spray-seeding grass planting protection is applied;
s2, arch part excavation by an open cut method: excavating an arch part by adopting an open cut method, constructing a temporary slope support, wherein the temporary slope support is operated by adopting anchor net guniting, and is provided with a mortar anchor rod, the thickness of concrete sprayed after the anchor net guniting is 16cm, 8 steel bar nets are adopted, the space between grids is 20cm to 20cm, the diameter of the mortar anchor rod is 22cm, the length of the anchor rod is 3.8m, the space between two adjacent anchor rods with pre-embedded anchor rods is 1.0 to 1.0m, the mortar anchor rod is arranged on the excavated slope, then the steel bar nets are laid on the surface of the excavated slope, and then the concrete is sprayed along the surface of the steel bar nets;
s3, arch support: constructing arch support, erecting steel frames, arranging 2 42 locking anchor pipes on left and right arch legs respectively, pouring a molded concrete arch protector, wherein the steel frames are I20b steel frame, the distance between erected steel frames is 0.6 m/pin, the length of the 42 locking anchor pipe is 6.0m, the longitudinal distance is 0.6, the poured concrete is C25 concrete, the thickness of the concrete is 100cm, and an arch protector I20b steel frame joint is reserved when erecting the steel frames so as to be connected with an arch wall during underground excavation under the arch;
s4, arch backfill surface: after the arch protection strength in the step S3 reaches the design, tamping and filling soil and stones to the temporary backfill surface;
s5, excavating three steps and a temporary inverted arch: when the backfill soil in the step S4 recovers the surface building (structure), the construction is changed from arch top open construction to arch bottom underground excavation construction, and the normal excavation of the hole body is carried out under the arch by adopting a three-step and temporary inverted arch method;
s6, secondary lining: when the excavation under the arch in the step S5 is finished by adopting the three steps and the temporary inverted arch, constructing a side wall and a temporary support, and constructing second lining concrete;
s7, paving a waterproof layer: and (5) after the second-lining concrete in the step S6 reaches the design strength, timely backfilling the earth stones to the design elevation, and paving a clay waterproof layer with the thickness of 60cm to finish the construction.
And (4) judging the standard: through comparison of the three embodiments, the best effect is the second embodiment, so that the second embodiment is selected as the best embodiment, and the specific change of the amount also belongs to the protection scope of the technical scheme.
The invention has the beneficial effects that: the invention relates to a method for constructing a shallow tunnel under an arch with an open top and an open bottom, which is characterized in that the construction is converted from the construction of the open top to the construction of the underground bottom, the normal excavation of a tunnel body is carried out under the arch by adopting a three-step and temporary inverted arch method, the construction safety is ensured, and the influence on the surrounding environment is reduced; in the construction of the shallow-buried underpass tunnel, the invention effectively controls the ground surface settlement, protects the ground buildings, prevents the ground buildings from being influenced by the tunnel construction, avoids the result of dismantling the ground buildings, greatly saves the construction time, thereby saving the cost, has reasonable design of the tunnel secondary lining structure, simple construction method and easy control of the construction quality, thereby greatly reducing the construction cost, saving the construction period, ensuring the construction safety and having good social benefit.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. A shallow tunnel arch top open arch bottom underground excavation construction method is characterized by comprising the following steps:
s1, leveling the gutter and digging a side slope: after the gutter is smoothly applied, permanent side slopes on two sides of the line begin to be excavated, and spray-seeding grass planting protection is applied;
s2, arch part excavation by an open cut method: excavating an arch part by adopting an open cut method, constructing a temporary slope support, carrying out anchor net guniting operation on the temporary slope support, and arranging a mortar anchor rod;
s3, arch support: constructing arch support, erecting steel frames, arranging 2 42 locking anchor pipes on the left arch foot and the right arch foot respectively, and pouring a molded concrete arch protection;
s4, arch backfill surface: after the arch protection strength in the step S3 reaches the design, tamping and filling soil and stones to the temporary backfill surface;
s5, excavating three steps and a temporary inverted arch: when the backfill soil in the step S4 recovers the surface building (structure), the construction is changed from arch top open construction to arch bottom underground excavation construction, and the normal excavation of the hole body is carried out under the arch by adopting a three-step and temporary inverted arch method;
s6, secondary lining: when the excavation under the arch in the step S5 is finished by adopting the three steps and the temporary inverted arch, constructing a side wall and a temporary support, and constructing second lining concrete;
s7, paving a waterproof layer: and (5) after the second-lining concrete in the step S6 reaches the design strength, timely backfilling the earth stones to the design elevation, and paving a clay waterproof layer to finish the construction.
2. The underground excavation construction method for the upper open arch and the lower arch of the shallow tunnel according to claim 1, wherein the thickness of the concrete sprayed after the anchor nets are sprayed with the slurry in the step S2 is 12-18cm, 8 steel bar nets are adopted, and the space between the grids is 20cm by 20 cm.
3. The underground excavation construction method for the upper open arch and the lower arch of the shallow tunnel according to claim 1, wherein the diameter of the mortar anchor rod in the step S2 is 20-22cm, the length of the anchor rod is 3.5-4.0m, and the distance between two adjacent anchor rods of the embedded anchor rod is 1.0 x 1.0 m.
4. The underground excavation construction method for the upper arch and the lower arch of the shallow tunnel arch according to claim 1, wherein the steel frames in the step S3 are I20b type steel frames, the spacing between the erected steel frames is 0.6 m/truss, the length of the 42-pin anchor pipe in the step S3 is 6.0m, and the longitudinal spacing is 0.6 m.
5. The underground excavation construction method for the upper arch and the lower arch of the shallow tunnel according to claim 1, wherein the concrete poured in the step S3 is C25 concrete, and the thickness of the concrete is 100-110 cm.
6. The underground excavation construction method for the upper open arch and the lower arch of the shallow tunnel according to claim 1, wherein in the step S3, a steel frame joint of a protective arch I20b steel frame is reserved during steel frame erection operation, so as to be connected with an arch wall steel frame during underground excavation.
7. The underground excavation construction method for the shallow tunnel arch with the open arch and the closed arch according to claim 1, wherein the height of the arch top in the step S4 is in the range of 3-4m, and the thickness of the clay waterproof layer in the step S7 is in the range of 40-60 cm.
8. The underground excavation method for the shallow tunnel according to claim 1, wherein the anchor rods are installed in the excavated slopes, the reinforcing mesh is laid on the surfaces of the excavated slopes, and the concrete is sprayed along the surfaces of the reinforcing mesh in step S2.
CN202110466910.9A 2021-04-28 2021-04-28 Shallow tunnel arch-up open-construction arch-down underground excavation construction method Pending CN113236309A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110466910.9A CN113236309A (en) 2021-04-28 2021-04-28 Shallow tunnel arch-up open-construction arch-down underground excavation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110466910.9A CN113236309A (en) 2021-04-28 2021-04-28 Shallow tunnel arch-up open-construction arch-down underground excavation construction method

Publications (1)

Publication Number Publication Date
CN113236309A true CN113236309A (en) 2021-08-10

Family

ID=77129774

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110466910.9A Pending CN113236309A (en) 2021-04-28 2021-04-28 Shallow tunnel arch-up open-construction arch-down underground excavation construction method

Country Status (1)

Country Link
CN (1) CN113236309A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114233297A (en) * 2021-12-09 2022-03-25 中建八局南方建设有限公司 Excavation construction method for large-span small-clear-distance shallow-buried tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114233297A (en) * 2021-12-09 2022-03-25 中建八局南方建设有限公司 Excavation construction method for large-span small-clear-distance shallow-buried tunnel

Similar Documents

Publication Publication Date Title
CN107762535B (en) Cut-and-cover tunnel secretly does construction technology under complicated geological environment
CN105464686B (en) Multi-layer underground space curtain posture excavating construction method and supporting construction under existing facility
CN111411993A (en) Large-section tunnel supporting system penetrating through huge karst cave hall and construction method
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN202969392U (en) Combined support for complex geological deep foundation pit
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN207003499U (en) A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN209924998U (en) Shallow earthing shield tunnel is worn road reinforcement protection architecture down
CN110159294B (en) Construction method for lengthening open cut tunnel at tunnel junction section of high and steep terrain bridge
CN104989425A (en) Underground excavation hole entering supporting structure and method
JP2024007536A (en) Projection type air duct structure perpendicular to vertical direction at large depth subway station, and construction method
CN111734425A (en) Construction method of underground excavation tunnel for downwards passing through airport terminal building
CN113236259A (en) Special construction process for excavation and supporting of combined tunnel
CN101838957B (en) Integral type T-shaped outer cantilever roads and construction method thereof
CN109853399A (en) Big section for arch bridge tilts tunnel type skewback structure and its construction method
CN104653195A (en) Gully landform tunnel portal structure and construction method thereof
CN107143149B (en) A kind of existing masonry structure building adds the construction method of basement
CN109898556A (en) A kind of underground pipe gallery structure and sunk type construction method
CN113236309A (en) Shallow tunnel arch-up open-construction arch-down underground excavation construction method
CN107165640A (en) Tunnels and underground engineering surely builds method certainly
CN114622574B (en) Water-rich throwing filling deep foundation pit water interception excavation supporting method and supporting device
CN109973122A (en) A kind of tunnel reinforcement control method of wall rock loosening or soft rock large deformation
CN215406119U (en) Tall and big side slope plain noodles supporting construction
CN102691307B (en) Construction method for caisson at tunnel portal section
CN209704560U (en) Build the scaffolding structure that an ultra shallow buries Large Underground space

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination