CN113216487A - Laminated slab overhanging joist steel construction method based on BIM technology - Google Patents

Laminated slab overhanging joist steel construction method based on BIM technology Download PDF

Info

Publication number
CN113216487A
CN113216487A CN202110464864.9A CN202110464864A CN113216487A CN 113216487 A CN113216487 A CN 113216487A CN 202110464864 A CN202110464864 A CN 202110464864A CN 113216487 A CN113216487 A CN 113216487A
Authority
CN
China
Prior art keywords
model
laminated
anchor ring
concrete
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110464864.9A
Other languages
Chinese (zh)
Inventor
廖盈
赵胤铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC5 Group Corp Ltd
Original Assignee
China MCC5 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC5 Group Corp Ltd filed Critical China MCC5 Group Corp Ltd
Priority to CN202110464864.9A priority Critical patent/CN113216487A/en
Publication of CN113216487A publication Critical patent/CN113216487A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00—Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/18—Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by cantilevers or other provisions mounted in openings in the building, e.g. window openings
    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00—Component parts or accessories for scaffolds
    • E04G5/04—Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • G—PHYSICS
    • G06—COMPUTING OR CALCULATING; COUNTING
    • G06F—ELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00—Computer-aided design [CAD]
    • G06F30/10—Geometric CAD
    • G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Geometry (AREA)
  • Theoretical Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Computer Hardware Design (AREA)
  • General Physics & Mathematics (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Mathematical Analysis (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to the technical field of building engineering; specifically discloses a laminated slab overhanging joist steel construction method based on BIM technology, which specifically comprises the following steps: establishing a model; combining the models; performing collision analysis; according to the design scheme of the cantilever crane, calculating the stress of the anchor ring, and accurately placing the position of the anchor ring to be used as a reference object of the laminated slab model; building a laminated slab support frame and a cast-in-place strip formwork model, optimizing the positions of the vertical rods and the support beams, and carrying out encryption setting on the vertical rods of the support frame at the anchor ring position to play a role in back jacking of the floor slab; data analysis and collision optimization; step S5, processing, positioning, manufacturing and molding; mounting a laminated slab; binding gluten, pouring concrete and maintaining; and erecting an overhanging frame. The invention can effectively avoid collision with the steel bar, the embedded pipeline and the slab bottom keel, improve the construction efficiency and avoid the waste of manpower, financial resources and time.

Description

Laminated slab overhanging joist steel construction method based on BIM technology
Technical Field
The invention relates to the technical field of erection of cantilever frames, in particular to a construction method of laminated slab cantilever I-shaped steel based on a BIM (building information modeling) technology.
Background
In assembled superimposed sheet work progress, the reinforcing bar system is complicated, the spool is in large quantity, the frame I-steel anchor ring of encorbelmenting generally adopts back trompil construction technology, do not carry out deepening consideration in the design stage, there is certain structural safety hidden danger, the back trompil degree of difficulty is big in addition, the trompil position probably conflicts with the reinforcing bar, pre-buried pipeline, board bottom keel position, lead to the unable normal installation of anchor ring, the efficiency of construction is low, probably lead to repeated trompil, influence the appearance quality of continuous beam concrete, the trompil expense is higher simultaneously, the input of cost and resource has been increased, there are a great deal of problems.
Disclosure of Invention
The invention aims to solve the technical problem of providing a construction method of laminated slab overhanging I-shaped steel based on the BIM technology, effectively avoiding collision with steel bars, embedded pipelines and slab bottom keels, improving the construction efficiency and avoiding waste of manpower, financial resources and time.
The technical problem to be solved by the invention is as follows:
a laminated slab overhanging joist steel construction method based on a BIM technology specifically comprises the following steps:
step S1, establishing a model; sequentially creating a laminated plate part model, a cast-in-place part model and a pipeline model to obtain a complete model;
step S2, combining the models;
step S3, collision analysis;
according to the design scheme of the cantilever crane, calculating the stress of the anchor ring, and accurately placing the position of the anchor ring to be used as a reference object of the laminated slab model;
building a laminated slab support frame and a cast-in-place strip formwork model, optimizing the positions of the vertical rods and the support beams, and carrying out encryption setting on the vertical rods of the support frame at the anchor ring position to play a role in back jacking of the floor slab;
step S4, analyzing data and optimizing collision;
step S5, processing, positioning, manufacturing and molding;
step S6, mounting the laminated plate;
step S7: gluten binding, concrete pouring and maintenance
Step S8: and erecting an overhanging frame.
In some possible embodiments, the anchor rod is in a U-shaped structure in step S3, and includes two screw rods, and a connecting rod connected with the two screw rods; the distance between the two screws is D, the section width of the overhanging I-shaped steel is D, and D-D is 20 mm; by extracting the data, a DWG file is exported, and an accurate collision position is identified.
In some possible embodiments, the step S4 specifically refers to:
after the data of the collision analysis is exported, carrying out optimization adjustment in the collision analysis data according to the collision depth of each pore channel and the components such as pipelines, steel bars and the like;
inputting the stress of an anchor ring of the cantilever frame, optimizing the reinforcement at the position of the anchor ring according to the mechanical calculation of structural design software, analyzing according to the relevant mechanical calculation after optimization, performing secondary positioning, optimizing and reinforcing the reinforcement, and adding anchor ring positioning reinforcement;
outputting optimized anchor ring and laminated slab steel bar drawings and statistics of blanking length and specification.
In some possible embodiments, the step S1 specifically refers to:
according to the received and checked design drawing, building a model for the superposed plate concrete outline, the superposed plate truss, the bottom plate steel bar system, the embedded pipeline, the cast-in-place partial concrete outline and the steel bar system, the superposed plate support frame and the cantilever frame according to a 1:1 ratio by using a BIM technology, determining the size of the model, and controlling the precision error to be in millimeter level;
wherein, the establishing sequence of the model is as follows: coordinate positioning, building of a laminated slab model, building of a cast-in-place part model, building of a pipeline model, building of a laminated slab support frame and a cantilever frame model, and building of a complete construction model.
In some possible embodiments, the laminated plate concrete profile laminated plate comprises an outer contour, a pre-embedded wire box, a reserved wire pipe hole, a reserved wire releasing hole, a rough surface and an edge chamfer;
the laminated slab steel bar system comprises a truss lower chord steel bar, a truss upper chord steel bar, a truss web steel bar, an additional steel bar and a slab bottom steel bar;
the embedded pipeline comprises a laminated slab embedded line box and a cast-in-place part embedded pipeline;
the cast-in-place partial concrete profile and steel bar system comprises concrete cast-in-place belt concrete, reinforcing plate belt concrete and plate gluten;
the laminated slab support frame comprises upright posts, cross rods, main beams and secondary beams;
the cantilever frame model comprises an anchor ring, I-shaped steel, a steel pipe, a safety net and a pocket net protection.
In some possible embodiments, the step S2 specifically refers to: and integrating according to the primary design drawing of the laminated slab according to the serial number sequence, and integrating the established concrete outline model, the steel bar system and the pre-buried pipeline model into a whole.
In some possible embodiments, the step S5 specifically refers to: and (3) processing and welding reinforcing steel bars of the anchor ring and the laminated slab according to the optimized drawing and the optimized blanking list, reliably connecting the anchor ring and the reinforcing steel bars of the laminated slab through positioning reinforcing steel bars, accurately checking by adopting a measuring instrument, putting the reinforcement cage into a sizing template after ensuring accurate positioning, and pouring the concrete of the laminated slab.
In some possible embodiments, the step S6 specifically refers to: arranging upright posts and primary and secondary beams according to the laminated slab support frame model; and installing a cast-in-place strip position template and a support, and accurately installing and correcting the laminated slab by adopting a hoisting machine and a hoisting tool.
In some possible embodiments, the step S7 specifically refers to: binding the cast-in-place part of reinforcing steel bars and the reinforcing steel bars at the positions of the anchor rings, pouring concrete after acceptance, paying attention to the fact that the reinforcing steel bars do not collide with the anchor rings during vibration, and maintaining in time after collection.
In some possible embodiments, the step S8 specifically refers to: after the strength of the concrete meets the corresponding requirement, installing I-shaped steel, and wedging a gap by using wood chips; and after the concrete strength meets the corresponding requirements, erecting a cantilever frame on the I-shaped steel.
Compared with the prior art, the invention has the beneficial effects that:
according to the invention, the arrangement drawing of the anchor ring can be effectively realized, the anchor ring is pre-embedded in advance as a construction reference, and the post-tapping operation is cancelled by pre-embedding the anchor ring in advance, so that the potential safety hazard of the structure is reduced; collision is avoided during construction, a large amount of unnecessary reworking is reduced, and the construction efficiency and the forming quality are improved;
the invention can avoid repeated hole opening, thereby avoiding the influence of repeated hole opening on the appearance quality of concrete, reducing the cost of hole opening and the cost of plugging, and only cutting off and cleaning the anchor ring at the later stage;
the invention reduces the rework rate and greatly reduces the safety quality risk.
Drawings
FIG. 1 is a flow chart of the present invention;
FIG. 2 is a schematic view showing the structural relationship among anchor rings, I-beams and superimposed plates according to the present invention;
wherein 1, anchor ring; 11. a screw; 12. a connecting rod; 2. i-shaped steel; 3. a laminated plate.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention more apparent, the embodiments of the present invention will be described in detail and completely with reference to the accompanying drawings. All other embodiments, which can be obtained by a person skilled in the art without any inventive step based on the embodiments of the present invention, are within the scope of the present invention. Thus, the detailed description of the embodiments of the present invention provided below is not intended to limit the scope of the invention as claimed, but is merely representative of selected embodiments of the invention.
In the description of the present invention, it is to be understood that the terms indicating an orientation or positional relationship are based on the orientation or positional relationship shown in the drawings only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
In the drawings of the present invention, it should be understood that different technical features which are not mutually substituted are shown in the same drawing only for the convenience of simplifying the drawing description and reducing the number of drawings, and the embodiment described with reference to the drawings does not indicate or imply that all the technical features in the drawings are included, and thus the present invention is not to be construed as being limited thereto.
The present invention will be described in detail below.
As shown in fig. 1 and 2;
a laminated slab overhanging joist steel construction method based on a BIM technology specifically comprises the following steps:
step S1, establishing a model; sequentially creating a laminated plate part model, a cast-in-place part model and a pipeline model to obtain a complete model;
according to the received and checked design drawing, building models for the concrete outline of the laminated slab 3, the truss and bottom plate steel bar system of the laminated slab 3, the embedded pipeline, the concrete outline and steel bar system of the cast-in-place part, the supporting frame of the laminated slab 3 and the cantilever frame according to a ratio of 1:1 by using a BIM technology, determining the size of the models, and controlling the precision error to be in millimeter level;
wherein, the establishing sequence of the model is as follows: coordinate positioning, building of a laminated slab 3 model, building of a cast-in-place part model, building of a pipeline model, building of a laminated slab 3 support frame and a cantilever frame model, and building of a complete construction model.
The concrete profile of the laminated slab 3 is characterized by comprising the outer profile of the laminated slab 3, a pre-buried wire box, a reserved wire tube hole, a reserved wire releasing hole, a rough surface and an edge chamfer;
the laminated slab 3 steel bar system comprises a truss lower chord steel bar, a truss upper chord steel bar, a truss web steel bar, an additional steel bar and a slab bottom steel bar;
the embedded pipeline comprises an embedded wire box of the laminated slab 3 and a cast-in-place part embedded pipeline;
the cast-in-place partial concrete profile and steel bar system comprises concrete cast-in-place belt concrete, reinforcing plate belt concrete and plate gluten;
the support frame of the laminated slab 3 comprises upright rods, cross rods, main beams and secondary beams;
the cantilever frame model comprises an anchor ring 1, I-shaped steel 2, a steel pipe, a safety net and a pocket net protection.
Step S2, combining the models; and integrating according to the preliminary design drawing of the laminated slab 3 according to the serial number sequence, and integrating the established concrete outline model, the steel bar system and the pre-buried pipeline model into a whole.
Step S3, collision analysis;
according to the design scheme of the cantilever frame, calculating the stress of the anchor ring 1, and accurately placing the position of the anchor ring 1 to be used as a reference object of the laminated slab 3 model;
building a support frame of a laminated slab 3 and a cast-in-place strip formwork model, optimizing the positions of the vertical rods and the support beams, and carrying out encryption setting on the vertical rods of the support frame at the position of the anchor ring 1 to play a role in back jacking of the floor slab;
the anchor rod is of a U-shaped structure and comprises two screw rods 11 and a connecting rod 12 connected with the two screw rods 11; the distance between the two screw rods 11 is D, the section width of the overhanging I-shaped steel 2 is D, and D-D is 20 mm; by extracting the data, a DWG file is exported, and an accurate collision position is identified.
Step S4, carrying out data analysis and crash optimization drawing deepening; after the data of the collision analysis is exported, carrying out optimization adjustment in the collision analysis data according to the collision depth of each pore channel and the components such as pipelines, steel bars and the like;
inputting stress of an anchor ring 1 of the cantilever frame, optimizing reinforcement at the position of the anchor ring 1 according to mechanical calculation of structural design software, analyzing according to relevant mechanical calculation after optimization, performing secondary positioning, optimizing and reinforcing the reinforcement, and adding positioning reinforcement of the anchor ring 1;
outputting optimized reinforcing steel bar drawings of the anchor ring 1 and the laminated slab 3, and counting blanking length and specification;
after the position of the anchor ring 1 is optimized by combining comprehensive consideration of reinforcing steel bars, pipelines and the like, reinforcing steel bar drawings of the anchor ring 1 and the laminated slab 3 are drawn, DWG files are exported, and accurate collision positions are identified to be capable of being used as references for follow-up work.
Step S5, processing, positioning, manufacturing and molding; and (3) processing and welding reinforcing steel bars of the anchor ring 1 and the laminated slab 3 according to the optimized drawing and the optimized blanking list, reliably connecting the anchor ring 1 with the reinforcing steel bars of the laminated slab 3 through positioning reinforcing steel bars, accurately checking by adopting a measuring instrument, placing a reinforcing steel bar framework into a shaping template after ensuring that the positioning is accurate, and pouring concrete of the laminated slab 3.
Step S6, mounting the laminated slab 3; arranging vertical rods and primary and secondary beams according to the support frame model of the laminated slab 3; and installing a cast-in-place strip position template and a support, and accurately installing and correcting the laminated slab 3 by adopting a hoisting machine and a hoisting tool.
Step S7: binding gluten, pouring concrete and maintaining; binding the cast-in-place part of reinforcing steel bars and reinforcing steel bars at the position of the anchor ring 1, pouring concrete after acceptance, paying attention to the fact that the concrete does not collide with the anchor ring 1 during vibration, and maintaining in time after collection.
Step S8: erecting an overhanging frame; after the strength of the concrete meets the corresponding requirement, installing I-shaped steel 2 and wedging a gap by using wood chips; and after the concrete strength meets the corresponding requirements, erecting a cantilever frame on the I-shaped steel 2.
Such as: after the strength of the concrete reaches C10, installing I-steel 2 and wedging a gap with wood chips; and after the concrete strength reaches C15, erecting a cantilever on the I-shaped steel 2.
According to the invention, the anchor ring 1 is reserved in advance in the laminated slab 3, and the rear opening after concrete pouring is omitted, so that the potential safety hazard of the structure is avoided, and the safe operation of a construction site is ensured; the cost of back trompil and shutoff expense have been reduced, practice thrift time limit for a project and cost.
According to the invention, a complete construction model is established and completed, the collision relation is analyzed in advance, and an optimization scheme is made, so that collision is avoided in construction, a large amount of unnecessary reworking is reduced, and the construction efficiency is improved.
The invention is not limited to the foregoing embodiments. The invention extends to any novel feature or any novel combination of features disclosed in this specification and any novel method or process steps or any novel combination of features disclosed.

Claims (10)

1.一种基于BIM技术的叠合板悬挑工字钢施工方法,其特征在于,具体包括以下步骤:1. a superimposed plate cantilever I-beam construction method based on BIM technology, is characterized in that, specifically comprises the following steps: 步骤S1:建立模型;依次创建叠合板部分模型、现浇部分模型、管线模型,获得完整的模型;Step S1: establish a model; successively create a partial model of a laminated plate, a cast-in-place partial model, and a pipeline model to obtain a complete model; 步骤S2:组合模型;Step S2: combination model; 步骤S3:碰撞分析;Step S3: collision analysis; 根据悬挑架设计方案,计算锚环受力,并将锚环位置进行精确放置,作为叠合板模型的参考对象;According to the design scheme of the cantilever frame, calculate the force of the anchor ring, and place the anchor ring position accurately, as the reference object of the laminated plate model; 建立叠合板支撑架和现浇带模板模型,优化立杆及支撑梁位置,对锚环位置支撑架立杆进行加密设置,起到对楼板的回顶作用;Establish the model of the superimposed plate support frame and the cast-in-place belt template, optimize the position of the pole and the support beam, and perform the encryption setting of the support frame pole at the anchor ring position, which plays the role of returning the floor to the top; 步骤S4:数据分析和碰撞优化;Step S4: data analysis and collision optimization; 步骤S5:加工、定位及制作成型;Step S5: processing, positioning and making molding; 步骤S6:叠合板安装;Step S6: laminated board installation; 步骤S7:面筋绑扎、混凝土浇筑、养护Step S7: Gluten binding, concrete pouring, curing 步骤S8:悬挑架搭设。Step S8: erecting the cantilever frame. 2.根据权利要求1所述的一种基于BIM技术的叠合板悬挑工字钢施工方法,其特征在于,在步骤S3中锚杆呈U型结构,包括两根螺杆、与两根螺杆连接的连接杆;其中,两根螺杆间距为D,悬挑工字钢截面宽度为d,D-d=20mm;通过提取数据,导出DWG文件,标识出准确碰撞位置。2. A kind of construction method based on BIM technology for cantilevering I-beam of laminated plate according to claim 1, it is characterized in that, in step S3, the anchor rod is in U-shaped structure, comprising two screws, connected with two screws Among them, the distance between the two screws is D, the width of the cantilevered I-beam section is d, and D-d=20mm; by extracting data, export the DWG file to identify the exact collision position. 3.根据权利要求2所述的一种基于BIM技术的叠合板悬挑工字钢施工方法,其特征在于,所述步骤S4具体是指:3. a kind of construction method based on BIM technology of laminated plate cantilever I-beam according to claim 2, is characterized in that, described step S4 specifically refers to: 将碰撞分析的数据导出后,在碰撞分析数据里根据各孔道与管线、钢筋等构件的碰撞深度进行优化调整;After exporting the collision analysis data, optimize and adjust the collision analysis data according to the collision depth of each tunnel and pipeline, steel bars and other components; 输入悬挑架锚环受力,根据结构设计软件力学计算对锚环位置配筋进行优化,优化后根据相关力学计算进行分析,进行二次定位,进行配筋优化、加强,并增加锚环定位钢筋;Input the stress of the anchor ring of the cantilever frame, optimize the anchor ring position reinforcement according to the mechanical calculation of the structural design software, analyze the relevant mechanical calculation after optimization, carry out secondary positioning, optimize and strengthen the reinforcement, and increase the anchor ring positioning rebar; 输出优化后的锚环及叠合板钢筋图纸及下料长度、规格统计。Output the optimized anchor ring and laminated steel reinforcement drawings, cutting length and specification statistics. 4.根据权利要求3所述的一种基于BIM技术的叠合板悬挑工字钢施工方法,其特征在于,所述步骤S1具体是指:4. a kind of construction method based on BIM technology of laminated plate cantilever I-beam according to claim 3, is characterized in that, described step S1 specifically refers to: 根据接收并检查后的设计图纸,应用BIM技术对叠合板混凝土轮廓、叠合板桁架及底板钢筋体系、预埋管线、现浇部分混凝土轮廓及钢筋体系、叠合板支撑架、悬挑架按照1:1比例建立模型,确定模型尺寸,精度误差控制在毫米级;According to the design drawings received and inspected, the BIM technology is applied to the composite slab concrete profile, composite slab truss and bottom reinforcement system, pre-buried pipelines, cast-in-place partial concrete profile and reinforcement system, composite slab support frame, and cantilever frame according to 1: 1. Build the model in scale, determine the size of the model, and control the accuracy error at the millimeter level; 其中,模型的建立顺序为:坐标定位、创建叠合板模型、创建现浇部分模型、创建管线模型、叠合板支撑架及悬挑架模型,建立完成完整的施工模型。Among them, the building sequence of the model is: coordinate positioning, creating a laminated plate model, creating a cast-in-place part model, creating a pipeline model, a laminated plate support frame and a cantilever frame model, and establishing a complete construction model. 5.根据权利要求4所述的一种基于BIM技术的叠合板悬挑工字钢施工方法,其特征在于,所述叠合板混凝土轮廓叠合板外轮廓、预埋线盒、预留线管洞、预留放线孔、粗糙面、边缘倒角;5. A BIM technology-based construction method for cantilevered I-beams of laminated slabs, characterized in that, the external contour of the laminated slabs, the concrete contours of the laminated slabs, the pre-embedded wire boxes, and the reserved conduit holes , Reserve pay-off holes, rough surfaces, and edge chamfers; 所述叠合板钢筋体系包括桁架下弦筋、桁架上弦筋、桁架腹筋、附加钢筋、以及板底筋;The superimposed slab reinforcement system includes truss lower chord bars, truss upper chord bars, truss web bars, additional reinforcement bars, and slab bottom bars; 所述预埋管线包括叠合板预埋线盒及现浇部分预埋管线;The pre-embedded pipeline includes a laminated board pre-embedded wire box and a cast-in-place part of the pre-embedded pipeline; 所述现浇部分混凝土轮廓及钢筋体系包括混凝土现浇带混凝土、加强板带混凝土、以及板面筋;The cast-in-situ partial concrete profile and reinforcement system include concrete cast-in-situ strip concrete, reinforced slab concrete, and slab gluten; 所述叠合板支撑架包括立杆、横杆、主梁、以及次梁;The laminated plate support frame includes a vertical rod, a cross rod, a main beam, and a secondary beam; 所述悬挑架模型包括锚环、工字钢、钢管、安全网以及兜网防护。The cantilever frame model includes anchor rings, I-beams, steel pipes, safety nets and pocket net protection. 6.根据权利要求1-5任一项所述的一种基于BIM技术的叠合板悬挑工字钢施工方法,其特征在于,所述步骤S2具体是指:依据叠合板初步设计图纸按照编号顺序进行集成,将建立好的混凝土轮廓模型、钢筋体系、预埋管线模型集成形成整体。6. a kind of construction method of cantilevered I-beam for laminated board based on BIM technology according to any one of claims 1-5, it is characterized in that, described step S2 specifically refers to: according to the preliminary design drawings of laminated board according to the serial number Integrate in sequence, and integrate the established concrete contour model, steel reinforcement system, and embedded pipeline model to form a whole. 7.根据权利要求6所述的一种基于BIM技术的叠合板悬挑工字钢施工方法,其特征在于,所述步骤S5具体是指:根据优化后的图纸及下料单进行锚环及叠合板的钢筋加工、焊接,通过定位钢筋将锚环与叠合板钢筋进行可靠连接,并采用测量仪器准确校核,保证定位准确无误后,将钢筋骨架放入定型模板中,浇筑叠合板混凝土。7. A kind of construction method based on BIM technology for cantilevering I-beam of laminated plate according to claim 6, is characterized in that, described step S5 specifically refers to: carry out anchor ring and blanking list according to the optimized drawing and blanking list. The steel bars of the laminated plate are processed and welded, and the anchor ring and the laminated steel bars are connected reliably through the positioning steel bars, and the measuring instruments are used for accurate verification to ensure that the positioning is accurate. 8.根据权利要求7所述的一种基于BIM技术的叠合板悬挑工字钢施工方法,其特征在于,所述步骤S6具体是指:按照叠合板支撑架模型进行立杆及主次梁布置;安装现浇带位置模板及支撑,采用吊装机械及吊具准确安装、校正叠合板。8. A BIM technology-based construction method for cantilevered I-beams of laminated plates according to claim 7, characterized in that, the step S6 specifically refers to: carrying out vertical poles and primary and secondary beams according to the laminated plate support frame model Layout; install the cast-in-place belt position template and support, and use hoisting machinery and spreaders to accurately install and correct the laminated board. 9.根据权利要求8所述的一种基于BIM技术的叠合板悬挑工字钢施工方法,其特征在于:所述步骤S7具体是指:绑扎现浇部分钢筋及锚环位置加强钢筋,验收合格后浇筑混凝土,注意振捣时不要碰撞锚环,收面后及时养护。9. A kind of construction method based on BIM technology for cantilevering I-beam of laminated plate according to claim 8, it is characterized in that: described step S7 specifically refers to: binding cast-in-place part steel bar and anchor ring position reinforcing steel bar, checking and accepting Concrete is poured after passing the test, pay attention not to collide with the anchor ring when vibrating, and maintain it in time after closing the surface. 10.根据权利要求9所述的一种基于BIM技术的叠合板悬挑工字钢施工方法,其特征在于:所述步骤S8具体是指:待混凝土强度符合相应的要求后,安装工字钢,并用木屑楔紧空隙;混凝土强度达到符合相应的要求后在工字钢上搭设悬挑架。10. A BIM technology-based construction method for cantilevered I-beams for laminated plates according to claim 9, wherein the step S8 specifically refers to: after the strength of the concrete meets the corresponding requirements, install the I-beams , and wedge the gap with wood chips; after the concrete strength meets the corresponding requirements, a cantilever frame is erected on the I-beam.
CN202110464864.9A 2021-04-28 2021-04-28 Laminated slab overhanging joist steel construction method based on BIM technology Pending CN113216487A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110464864.9A CN113216487A (en) 2021-04-28 2021-04-28 Laminated slab overhanging joist steel construction method based on BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110464864.9A CN113216487A (en) 2021-04-28 2021-04-28 Laminated slab overhanging joist steel construction method based on BIM technology

Publications (1)

Publication Number Publication Date
CN113216487A true CN113216487A (en) 2021-08-06

Family

ID=77089508

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110464864.9A Pending CN113216487A (en) 2021-04-28 2021-04-28 Laminated slab overhanging joist steel construction method based on BIM technology

Country Status (1)

Country Link
CN (1) CN113216487A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113971310A (en) * 2021-12-02 2022-01-25 三一筑工科技股份有限公司 Modeling method and device
CN114809300A (en) * 2022-05-20 2022-07-29 中建八局第二建设有限公司 Construction method of high-altitude multilayer large-cantilever steel reinforced concrete composite structure
CN116738527A (en) * 2023-04-06 2023-09-12 中铁六局集团有限公司 Automatic optimization method and system for continuous beam reinforcement collision

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107100358A (en) * 2017-05-23 2017-08-29 北京六建集团有限责任公司 Cantilever bracket, frame body and construction method for non-unloading industrialized safety protection
CN109684662A (en) * 2018-11-20 2019-04-26 唐炳贵 A kind of construction method of intellectual assembled architecture
CN110468968A (en) * 2019-07-26 2019-11-19 上海建工五建集团有限公司 A kind of the fixation device and fixing means of laminated floor slab overhanging type steel
CN111809856A (en) * 2020-07-22 2020-10-23 上海泾东建筑发展有限公司 Anchoring device for cantilevered scaffolding of composite superposed floor and construction method thereof
CN112144859A (en) * 2020-10-22 2020-12-29 中联建设集团股份有限公司 Prefabricated laminated slab cantilever frame pre-embedding device, building component finished product and cantilever frame structure
CN215055132U (en) * 2021-06-01 2021-12-07 成都建工第三建筑工程有限公司 A pull rod hangs scaffold frame for assembled shear wall structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107100358A (en) * 2017-05-23 2017-08-29 北京六建集团有限责任公司 Cantilever bracket, frame body and construction method for non-unloading industrialized safety protection
CN109684662A (en) * 2018-11-20 2019-04-26 唐炳贵 A kind of construction method of intellectual assembled architecture
CN110468968A (en) * 2019-07-26 2019-11-19 上海建工五建集团有限公司 A kind of the fixation device and fixing means of laminated floor slab overhanging type steel
CN111809856A (en) * 2020-07-22 2020-10-23 上海泾东建筑发展有限公司 Anchoring device for cantilevered scaffolding of composite superposed floor and construction method thereof
CN112144859A (en) * 2020-10-22 2020-12-29 中联建设集团股份有限公司 Prefabricated laminated slab cantilever frame pre-embedding device, building component finished product and cantilever frame structure
CN215055132U (en) * 2021-06-01 2021-12-07 成都建工第三建筑工程有限公司 A pull rod hangs scaffold frame for assembled shear wall structure

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
刘寰宇: "基于BIM的装配式叠合板施工", 《住宅与房地产》 *
彭友元等: "全预制装配整体式框架结构建筑技术研发与应用", 《施工技术》 *
田东等: "基于BIM的装配式混凝土建筑构件系统设计分析与研究", 《建筑结构》 *
贾琦: "bim技术在装配式建筑中的应用与研究", 《四川水泥》 *
黄亚江等: "基于BIM技术的装配式建筑结构深化设计研究", 《施工技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113971310A (en) * 2021-12-02 2022-01-25 三一筑工科技股份有限公司 Modeling method and device
CN113971310B (en) * 2021-12-02 2024-10-11 三一筑工科技股份有限公司 Modeling method and device
CN114809300A (en) * 2022-05-20 2022-07-29 中建八局第二建设有限公司 Construction method of high-altitude multilayer large-cantilever steel reinforced concrete composite structure
CN116738527A (en) * 2023-04-06 2023-09-12 中铁六局集团有限公司 Automatic optimization method and system for continuous beam reinforcement collision

Similar Documents

Publication Publication Date Title
CN107905109B (en) Equal-load simulation segmented preloading construction method for crossing type bridge cast-in-place platform
CN201339250Y (en) Stiffness structure framework beam preformed steel reinforcement framework structure
CN113158295A (en) Construction method applied to formwork support frame based on BIM formwork self-assembly technology
CN112049146A (en) Steel structure foundation embedded part and technological process thereof
CN105332510A (en) Construction method of complicated beam column joint core area
CN107083804A (en) A kind of wall structure post joint bar construction method
CN118308966A (en) A method for installing and positioning inward-inclined arch ribs of steel structures based on BIM and point cloud
CN116910854A (en) Large-span arch concrete structure construction method based on digital construction
CN106592867A (en) Construction method of reinforced concrete beam
CN114086467A (en) Prefabricated installation construction method for steel-concrete composite beam bridge deck
CN112458905A (en) Splicing adjustment method for prefabricated capping beam and prefabricated stand column
CN116905805B (en) Construction method of arc beam based on BIM technology
CN110096828A (en) The modeling and construction method of the elongated muscle in floor Vierendeel girder top or bearing rod based on BIM technology
CN115319911B (en) Digital production process of concrete prefabricated part with complex shape
CN111535482A (en) Aluminum mould construction concrete structure and tool and electromechanical reservation pre-embedding construction method
CN115408756A (en) Railway continuous beam construction method based on BIM
KR102808849B1 (en) Apparatus and method for automating building design and site management
CN114790793A (en) A prefabricated building prefabricated PC board line and pipe integrated construction method
CN116480161B (en) Method, device and system for correcting the position of dowel bars in precast concrete wall panels
CN118498715A (en) Construction method of stainless steel-concrete structure module of reactor CIS water tank
CN114382196B (en) A method for constructing steel bars in cast-in-place areas of integrally assembled shear wall structures
CN215858605U (en) Measuring tool applied to inclined cylinder construction method
CN118278092A (en) Method for measuring and calculating early disassembly of girder plate formwork based on finite element analysis
CN116591477A (en) A construction method for binding steel bars in the core area of beams and columns
CN117845767A (en) Precast concrete board UHPC wet joint structure, construction method and design method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210806

RJ01 Rejection of invention patent application after publication