It is a kind of be easily installed, the assembling type steel structure out-hung panel node that is molded and its construction
Technique
Technical field
The invention belongs to the field of manufacturing, more particularly to a kind of plug-in wall of assembling type steel structure for being easily installed, being molded
Plate node.
Background technology
With the fast development of social economy, steel building is increasingly favored by architect and builder, its
Short time limit, is affected by the external environment smaller, in existing firm structural construction, when setting wallboard on Side fascia, by using ADR
Method installs the Side fascia of NALC materials, it is necessary at least three fulcrum, i.e. Side fascia bottom rest(Most important stress point), outside within the walls
Side Xia Di sides drawknot node, inner side of outer wall upper topside drawknot node, by such traditional method, inner side of outer wall upper topside drawknot node
It is arranged between wallboard and girder steel, there is certain difficulty, and floor support plate two-step pouring in operation, second of edge sealing, which is poured, only leans on ox-hide
Paper is as cheek board, and forming effect is poor.
The content of the invention
Goal of the invention:In order to overcome the above not enough, it is an object of the invention to provide a kind of assembled for being easily installed, being molded
Steel construction out-hung panel node, its is simple in construction, reasonable in design, can be good at solving on-site construction operations in ADR engineering methods empty
Between the problem of receive constraint, interdependent node part is tried one's best and uses prefabrication, site operation workload is reduced, it is to avoid traditional side
Flooring edge concrete secondary cast problem in method.
Technical scheme:To achieve these goals, the invention provides a kind of assembling type steel structure for being easily installed, being molded
Out-hung panel node, including:Side fascia and out-hung panel, wherein, Side fascia is divided into upper strata Side fascia and lower floor's Side fascia, described
Supporting plate is provided between upper strata Side fascia and lower floor's Side fascia, one end of the out-hung panel is provided with prefabricated embedded part, and described plug-in
Connected between wallboard and upper strata Side fascia by the first angle steel component, the lower section of the out-hung panel is provided with support frame, the branch
Connected between support and lower floor's Side fascia by connecting plate, and, pass through between the lower section of the connecting plate and lower floor's Side fascia
Two angle steel components are fixedly connected.
A kind of heretofore described assembling type steel structure out-hung panel node for being easily installed, being molded, the angle steel group
Component is fixedly connected by the external wallboard of bolt and out-hung panel, and is formed in the top and bottom of wallboard top respectively and drawn
Node and bottom drawknot node, moreover, the top of wallboard are provided with top angle steel, and lower section is provided with support frame, can greatly carried
The stability that connects between the two of height, is installed during construction using perpendicular dress die panels rock engineering method to it, allows wallboard
Firm connection is formed with Side fascia, so that the security for further improving the stability of its connection and using.
Angle steel and fixture, the angle steel are equipped with heretofore described first angle steel component and the second angle steel component
It is vertical between upper strata Side fascia and out-hung panel or between connecting plate and lower floor's Side fascia, described fixture one end is stuck in
On angle steel, the other end is secured by bolts on Side fascia.
Fixture in heretofore described angle steel sub-assembly is carried out by bolt to upper strata Side fascia and lower floor's Side fascia
Fix, and bottom drawknot node and top drawknot node are formed respectively on the top on the bottom of upper strata Side fascia and lower floor's Side fascia.
Heretofore described out-hung panel uses aerated concrete panel.
Prefabricated embedded part is provided with heretofore described out-hung panel, the prefabricated embedded part is passed through by two U-shaped embedded parts
Dowel is connected and composed.
Heretofore described support frame is in I-shaped, and it is made up of support beam and support column, the support beam and plug-in wall
Plate is fixedly connected, the support column be located at two support beams between, in support frame as described above away from out-hung panel one end support beam with
Connecting plate is connected, and greatly improves its support performance.
Heretofore described supporting plate is L-shaped, and it matches with Side fascia, improves upper strata Side fascia and lower floor's Side fascia connection
Stability, greatly improve the compactness and stickiness of connector and Bolted angle connection.
Heretofore described fixture is S-type, and it is wedge shaped with angle-bar joint, and the fixture and angle steel phase
Match somebody with somebody,.
A kind of heretofore described construction technology of assembling type steel structure out-hung panel node for being easily installed, being molded,
Specific construction technology is as follows:
(1):Agent structure first to building carries out an acceptance inspection, and allows in work progress the materials arrival needed, and the material to marching into the arena
Material is checked;
(2):After after the agent structure acceptance(check) built in previous step, according to the drawing and datum axis and benchmark of construction
Relief is that unwrapping wire is detected according to beginning unwrapping wire, and using theodolite, spirit level and bracing wire measurement;
(3):After unwrapping wire in previous step is by detection, start to set built-in fitting in one end of out-hung panel, then will thereon
Perpendicular dress Side fascia, i.e.,:Weldering is in place by angle steel according to snap the line position by elongated angle cleat, by welding operation requirement and design
It is required that portion's weld seam of first burn-oning, then bottom weld seam is welded, alternately weld;
(4):Treat after the completion of elongated angle cleat welding, by supporting plate on Side fascia lower floor exterior wall plate node, and supporting plate is set
In the back side of angle steel;
(5):After blade position is adjusted, make Side fascia in place, i.e.,:Side fascia is sling with suspender, slowly Side fascia is put
On the supporting plate of lower floor's exterior wall plate node, such as adjustment position is wanted to sling playback, then by again by drawknot node at the top of Side fascia
Fixture and elongated angle steel make preliminary welding, the ㎜ of weld seam length >=30, tighten screw rod;
(6):Then support frame is located to the specified location of out-hung panel, and to be fixed;
(7):After frame to be supported is fixed, by connecting plate by support frame away from out-hung panel one end support beam and lower floor
Side fascia is connected;
(8):Then angle steel is located between connecting plate and lower floor's Side fascia, angle steel and lower floor's Side fascia carried out by fixture
It is fixed, and fixture and lower floor's Side fascia are fixedly connected by bolt, and to two-sided butt weld and fillet weld
Seam;
(9):Then the plate stitch of external wallboard is handled, and PE rods are placed in the outside of Side fascia, and then each plate stitch is carried out
Gluing jointing is handled;
(10):After plate stitch is handled well in previous step, chemise on the inside of Side fascia is installed, it is ensured that be not less than with extraneous thickness
200mm;
(11):Treat step(10)After middle inner side chemise is installed, gluing jointing processing equally is carried out to inner side chemise;
(12):Antirust treatment finally is carried out to whole steel construction.
Side fascia comprising the following steps that in place in the present invention:
A, inspection floor height, check that the plate of Side fascia is long, it is desirable to which plate length is shorter than floor height, otherwise should cut off adjustment;
B, this plate could be in place after plate two ends insertion tube sheet is all installed, twisted again after such as plate is in place tube sheet also can, but must have
Special messenger is responsible for;
C, plate bottom paving one layer of polymeric cement mortar, then it is with specific purpose tool that plate is in place or lift helps in place;
D, the perpendicularity with plumb bob boatswain chair, the flatness of plate is checked with guiding ruler, it is desirable to plate stitch difference of height, flatness error, vertical
Degree error is respectively less than code requirement, is otherwise tapped and special broadside crowbar alignment error with rubber hammer;
Fixed temporarily from top wedging with two pairs of bucketing timber wedges after E, plate face are totally straight.
Above-mentioned technical proposal can be seen that the present invention and have the advantages that:
1st, heretofore described a kind of assembling type steel structure out-hung panel node for being easily installed, being molded, the angle steel combination
Part is fixedly connected by the external wallboard of bolt and wallboard, and forms in the top and bottom in wallboard top drawknot node respectively
With bottom drawknot node, moreover, the top of wallboard is provided with top angle steel, and lower section is provided with support frame, can greatly improve two
The stability connected between person, is installed to it using the perpendicular dress die panels rock engineering method after improving during construction, allowed
Wallboard forms firm connection with Side fascia, so that the security for further improving the stability of its connection and using.
2nd, Side fascia of the present invention uses aerated concrete panel, its can it is prefabricated after arrive site operation, site operation again
The problem of constraint is received in operating space, interdependent node part is tried one's best and uses prefabrication, reduces site operation workload, it is to avoid
Flooring edge concrete secondary cast problem in conventional method.
3rd, prefabricated embedded part is provided with heretofore described wallboard, the prefabricated embedded part is passed through even by two U-shaped embedded parts
Connect muscle to connect and compose, the stability and security used can be greatly improved.
Brief description of the drawings
Fig. 1 is the structural representation of assembling type steel structure out-hung panel node of the present invention for being easily installed, being molded;
In figure:Side fascia -1, upper strata Side fascia -11, lower floor's Side fascia -12, out-hung panel -2, the first angle steel component -31, second
Angle steel component -32, angle steel -33, fixture -34, top drawknot node -4, bottom drawknot node -5, supporting plate -6, support frame -7, support
Beam -71, support column -72, connecting plate -8.
Embodiment
Below in conjunction with the accompanying drawings and specific embodiment, the present invention is furture elucidated.
Embodiment
A kind of assembling type steel structure out-hung panel node for being easily installed, being molded as shown in Figure 1, including:The He of Side fascia 1
Out-hung panel 2, wherein, 1 point of Side fascia is outside upper strata Side fascia 11 and lower floor's Side fascia 12, the upper strata Side fascia 11 and lower floor
Supporting plate 6 is provided between wallboard 12, one end of the out-hung panel 2 is provided with prefabricated embedded part 21, and outside the out-hung panel 2 and upper strata
Connected between wallboard 11 by the first angle steel component 31, the lower section of the out-hung panel 2 is provided with support frame 7, the He of support frame as described above 7
Connected between lower floor's Side fascia 12 by connecting plate 8, and, pass through between the lower section of the connecting plate 8 and lower floor's Side fascia 12
Two angle steel components 32 are fixedly connected.
Angle steel 33 and fixture are equipped with first angle steel component 31 described in the present embodiment and the second angle steel component 32
34, the angle steel 33 be vertical between upper strata Side fascia 11 and out-hung panel 2 or connecting plate 8 and lower floor's Side fascia 12 it
Between, described one end of fixture 34 is stuck on angle steel 33, and the other end is secured by bolts on Side fascia 1.
Fixture 34 in angle steel sub-assembly described in the present embodiment 3 is by bolt to upper strata Side fascia 11 and lower floor's exterior wall
Plate 12 is fixed, and bottom drawknot node 5 is formed respectively on the top on the bottom of upper strata Side fascia 11 and lower floor's Side fascia 12
With top drawknot node 4.
Out-hung panel 2 described in the present embodiment uses aerated concrete panel.
Prefabricated embedded part 21 is provided with out-hung panel 2 described in the present embodiment, the prefabricated embedded part 21 is buried by two U-shaped
Part is connected and composed by dowel.
Support frame 7 described in the present embodiment is in I-shaped, and it is made up of support beam 71 and support column 72, the support beam 71
It is fixedly connected with out-hung panel 2, the support column 72 is located between two support beams 71, away from out-hung panel 2 in support frame as described above 7
The support beam 71 of one end is connected with connecting plate 8.
Supporting plate 6 described in the present embodiment is L-shaped, and it matches with Side fascia 1.
Fixture 34 described in the present embodiment is S-type, and it is wedge shaped with the junction of angle steel 33, and the fixture and angle steel
Match.
Embodiment 2
A kind of assembling type steel structure out-hung panel node for being easily installed, being molded as depicted, including:Side fascia 1 and plug-in
Wallboard 2, wherein, 1 point of Side fascia is upper strata Side fascia 11 and lower floor's Side fascia 12, the upper strata Side fascia 11 and lower floor's Side fascia
Supporting plate 6 is provided between 12, one end of the out-hung panel 2 is provided with prefabricated embedded part 21, and the out-hung panel 2 and upper strata Side fascia
Connected between 11 by the first angle steel component 31, the lower section of the out-hung panel 2 is provided with support frame 7, support frame as described above 7 and lower floor
Connected between Side fascia 12 by connecting plate 8, and, pass through second jiao between the lower section of the connecting plate 8 and lower floor's Side fascia 12
Steel component 32 is fixedly connected.
Angle steel 33 and fixture are equipped with first angle steel component 31 described in the present embodiment and the second angle steel component 32
34, the angle steel 33 be vertical between upper strata Side fascia 11 and out-hung panel 2 or connecting plate 8 and lower floor's Side fascia 12 it
Between, described one end of fixture 34 is stuck on angle steel 33, and the other end is secured by bolts on Side fascia 1.
Fixture 34 in angle steel sub-assembly described in the present embodiment 3 is by bolt to upper strata Side fascia 11 and lower floor's exterior wall
Plate 12 is fixed, and bottom drawknot node 5 is formed respectively on the top on the bottom of upper strata Side fascia 11 and lower floor's Side fascia 12
With top drawknot node 4.
Out-hung panel 2 described in the present embodiment uses aerated concrete panel.
Prefabricated embedded part 21 is provided with out-hung panel 2 described in the present embodiment, the prefabricated embedded part 21 is buried by two U-shaped
Part is connected and composed by dowel.
Support frame 7 described in the present embodiment is in I-shaped, and it is made up of support beam 71 and support column 72, the support beam 71
It is fixedly connected with out-hung panel 2, the support column 72 is located between two support beams 71, away from out-hung panel 2 in support frame as described above 7
The support beam 71 of one end is connected with connecting plate 8.
Supporting plate 6 described in the present embodiment is L-shaped, and it matches with Side fascia 1.
Fixture 34 described in the present embodiment is S-type, and it is wedge shaped with the junction of angle steel 33, and the fixture and angle steel
Match.
A kind of construction work for the assembling type steel structure out-hung panel node that described in the present embodiment be easily installed, is molded
Skill, specific construction technology is as follows:
(1):Agent structure first to building carries out an acceptance inspection, and allows in work progress the materials arrival needed, and the material to marching into the arena
Material is checked;
(2):After after the agent structure acceptance(check) built in previous step, according to the drawing and datum axis and benchmark of construction
Relief is that unwrapping wire is detected according to beginning unwrapping wire, and using theodolite, spirit level and bracing wire measurement;
(3):After unwrapping wire in previous step is by detection, start to set built-in fitting 21 in one end of out-hung panel 2, then by it
Upper perpendicular dress Side fascia 1, i.e.,:Weldering is in place by angle steel 33 according to snap the line position by elongated angle cleat 33, by welding operation requirement
First burn-on with design requirement portion's weld seam, then weld bottom weld seam, alternately welded;
(4):After the completion for the treatment of that elongated angle cleat 33 is welded, by supporting plate 6 on the lower floor's exterior wall plate node of Side fascia 1, and will support
Plate 6 is located at the back side of angle steel 33;
(5):After the position adjustment of supporting plate 6 is good, make Side fascia 1 in place, i.e.,:Side fascia 1 is sling with suspender, slowly by Side fascia
1 rests on the supporting plate 6 of lower floor's exterior wall plate node, such as wants adjustment position to sling playback, then will be again by drawknot at the top of Side fascia
The fixture 34 and elongated angle steel of point 4 make preliminary welding, the ㎜ of weld seam length >=30, tighten screw rod;
(6):Then support frame 7 is located to the specified location of out-hung panel 2, and to be fixed;
(7):After frame 7 to be supported is fixed, by connecting plate 8 by support frame 7 away from out-hung panel 2 one end support beam 71
It is connected with lower floor Side fascia;
(8):Then by angle steel 33 be located between connecting plate 8 and lower floor's Side fascia, by fixture 22 to angle steel 33 and lower floor outside
Wallboard 1 is fixed, and fixture 22 and lower floor's Side fascia 1 are fixedly connected by bolt, and to two-sided docking
Weld seam and corner welding line;
(9):Then the plate stitch of external wallboard 1 is handled, and is carried out gluing jointing processing to each plate stitch, is handled well after plate stitch,
PE rods are placed in the outside of Side fascia 1;
(10):After plate stitch is handled well in previous step, the inner side chemise of Side fascia 1 is installed, it is ensured that be not less than with extraneous thickness
200mm;
(11):After inner side chemise is installed in step 10, gluing jointing processing equally is carried out to inner side chemise;
(12):Antirust treatment finally is carried out to whole steel construction.
Described above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art
For member, under the premise without departing from the principles of the invention, some improvement can also be made, these improvement also should be regarded as the present invention's
Protection domain.