CN113153322A - Shield horizontal freezing starting construction method under existing operation subway - Google Patents
Shield horizontal freezing starting construction method under existing operation subway Download PDFInfo
- Publication number
- CN113153322A CN113153322A CN202110356066.4A CN202110356066A CN113153322A CN 113153322 A CN113153322 A CN 113153322A CN 202110356066 A CN202110356066 A CN 202110356066A CN 113153322 A CN113153322 A CN 113153322A
- Authority
- CN
- China
- Prior art keywords
- shield
- freezing
- grouting
- hole
- starting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000008014 freezing Effects 0.000 title claims abstract description 117
- 238000007710 freezing Methods 0.000 title claims abstract description 117
- 238000010276 construction Methods 0.000 title claims abstract description 71
- 238000007789 sealing Methods 0.000 claims abstract description 36
- 238000000034 method Methods 0.000 claims abstract description 33
- 239000002689 soil Substances 0.000 claims abstract description 25
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 22
- 239000004744 fabric Substances 0.000 claims abstract description 14
- 238000012544 monitoring process Methods 0.000 claims abstract description 8
- 230000005641 tunneling Effects 0.000 claims abstract description 8
- 238000004519 manufacturing process Methods 0.000 claims abstract description 7
- 238000005553 drilling Methods 0.000 claims description 53
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 46
- 238000010079 rubber tapping Methods 0.000 claims description 31
- 230000001681 protective effect Effects 0.000 claims description 18
- 230000002787 reinforcement Effects 0.000 claims description 12
- 229910003460 diamond Inorganic materials 0.000 claims description 10
- 239000010432 diamond Substances 0.000 claims description 10
- 239000004568 cement Substances 0.000 claims description 8
- 230000000694 effects Effects 0.000 claims description 7
- 229920001971 elastomer Polymers 0.000 claims description 6
- 238000003466 welding Methods 0.000 claims description 6
- 230000000149 penetrating effect Effects 0.000 claims description 5
- 230000001360 synchronised effect Effects 0.000 claims description 5
- RNFJDJUURJAICM-UHFFFAOYSA-N 2,2,4,4,6,6-hexaphenoxy-1,3,5-triaza-2$l^{5},4$l^{5},6$l^{5}-triphosphacyclohexa-1,3,5-triene Chemical compound N=1P(OC=2C=CC=CC=2)(OC=2C=CC=CC=2)=NP(OC=2C=CC=CC=2)(OC=2C=CC=CC=2)=NP=1(OC=1C=CC=CC=1)OC1=CC=CC=C1 RNFJDJUURJAICM-UHFFFAOYSA-N 0.000 claims description 4
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 238000010521 absorption reaction Methods 0.000 claims description 4
- 238000006243 chemical reaction Methods 0.000 claims description 4
- 239000003063 flame retardant Substances 0.000 claims description 4
- 229920002457 flexible plastic Polymers 0.000 claims description 4
- 238000009434 installation Methods 0.000 claims description 4
- 239000002984 plastic foam Substances 0.000 claims description 4
- 238000003825 pressing Methods 0.000 claims description 4
- 239000002002 slurry Substances 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 238000003860 storage Methods 0.000 claims description 4
- 238000010257 thawing Methods 0.000 claims description 4
- 238000004804 winding Methods 0.000 claims description 4
- 241000251468 Actinopterygii Species 0.000 claims description 3
- 239000011083 cement mortar Substances 0.000 claims description 3
- 238000002347 injection Methods 0.000 claims description 3
- 239000007924 injection Substances 0.000 claims description 3
- 238000011900 installation process Methods 0.000 claims description 3
- 239000004033 plastic Substances 0.000 claims description 3
- 229920003023 plastic Polymers 0.000 claims description 3
- 238000001556 precipitation Methods 0.000 description 14
- 239000004576 sand Substances 0.000 description 8
- 239000012267 brine Substances 0.000 description 6
- 238000013461 design Methods 0.000 description 6
- 239000000463 material Substances 0.000 description 6
- HPALAKNZSZLMCH-UHFFFAOYSA-M sodium;chloride;hydrate Chemical compound O.[Na+].[Cl-] HPALAKNZSZLMCH-UHFFFAOYSA-M 0.000 description 6
- 229920000742 Cotton Polymers 0.000 description 4
- FAPWRFPIFSIZLT-UHFFFAOYSA-M Sodium chloride Chemical compound [Na+].[Cl-] FAPWRFPIFSIZLT-UHFFFAOYSA-M 0.000 description 4
- 238000009413 insulation Methods 0.000 description 4
- 238000002360 preparation method Methods 0.000 description 4
- 239000011780 sodium chloride Substances 0.000 description 4
- 239000011440 grout Substances 0.000 description 3
- 235000019353 potassium silicate Nutrition 0.000 description 3
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 description 3
- 239000000243 solution Substances 0.000 description 3
- 238000009529 body temperature measurement Methods 0.000 description 2
- 239000003673 groundwater Substances 0.000 description 2
- 230000000977 initiatory effect Effects 0.000 description 2
- 238000005259 measurement Methods 0.000 description 2
- 238000012360 testing method Methods 0.000 description 2
- 244000267222 Brasenia schreberi Species 0.000 description 1
- 235000006506 Brasenia schreberi Nutrition 0.000 description 1
- 244000025254 Cannabis sativa Species 0.000 description 1
- 235000012766 Cannabis sativa ssp. sativa var. sativa Nutrition 0.000 description 1
- 235000012765 Cannabis sativa ssp. sativa var. spontanea Nutrition 0.000 description 1
- 238000009825 accumulation Methods 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 235000009120 camo Nutrition 0.000 description 1
- 235000005607 chanvre indien Nutrition 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000002349 favourable effect Effects 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 238000011010 flushing procedure Methods 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 239000011487 hemp Substances 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000011835 investigation Methods 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000002156 mixing Methods 0.000 description 1
- 229920002635 polyurethane Polymers 0.000 description 1
- 239000004814 polyurethane Substances 0.000 description 1
- 238000004321 preservation Methods 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/06—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/105—Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/18—Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/001—Improving soil or rock, e.g. by freezing; Injections
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
The invention discloses a shield horizontal freezing originating construction method under an existing operation subway, which specifically comprises the following steps: freezing and reinforcing the stratum by using a horizontal freezing hole, and meanwhile, laying a monitoring net and manufacturing an originating guide platform; completing configuration; the starting condition is checked and accepted, the tunnel portal is broken, and then the tunnel face is leveled; then, pulling out the freezing pipe in the shield propelling range to enable the shield to initially enter the tunnel portal to form a perfect tunnel portal sealing system; then, synchronously grouting the shield tail through the portal curtain cloth, and normally tunneling the shield to finish the starting of the shield; secondary grouting in the hole after starting; the invention adopts a horizontal freezing method to carry out shield starting construction under the existing operation subway, and can freeze and reinforce the stratum by using the horizontal freezing holes, so that the soil body in the range of the tunnel mouth of the shield machine is frozen into a water-tight plate with high strength, thereby providing conditions for breaking the tunnel door.
Description
Technical Field
The invention relates to the technical field of water shield construction, in particular to a shield horizontal freezing starting construction method under an existing operation subway.
Background
The shield tunneling method has become a common method for rail transit in cities.
According to the 3.1.2 regulation in the technical Specification for the safety protection of urban railway traffic structures (CJJ/T202-2013): a control protection area is arranged in 50m of the outer side line of the underground station and the tunnel structure, and the construction of the tunnel portal ring beam influences the existing operation subway station. In order to ensure the safety of the existing operation subway station, the influence of the shield construction on the existing operation subway station can be completely eliminated only when the shield tunneling length reaches 100 meters and the tunnel portal ring beam construction is completed.
Therefore, the shield initiation becomes a major key link in the shield construction technology and also serves as one of the main construction risks in the shield construction tunnel.
In order to ensure the smooth operation of shield horizontal freezing starting construction under the existing operation subway, technical preparation works such as drawing consultation, design bottom-meeting, measurement, test, construction scheme and technical bottom-meeting, safety bottom-meeting and the like are required to be carried out before construction. Meanwhile, construction site and construction preparation such as working, material and machine must be made in advance. In order to ensure safe, stable and smooth completion of shield tunnel portal horizontal freezing reinforcement construction under the existing operation subway, a special construction method is urgently needed to reduce stratum deformation and water and soil loss caused in the horizontal freezing construction process.
Disclosure of Invention
The invention aims to provide a shield horizontal freezing starting construction method under the existing operation subway aiming at the defects of the prior art; the method can effectively control the water and soil loss, the frost heaving and thawing sinking control and the freezing curtain reinforcement effect in the drilling and pipe drawing construction process, thereby reducing the stratum deformation and the water and soil loss caused in the horizontal freezing construction process.
The technical scheme of the invention is as follows: a shield horizontal freezing starting construction method under an existing operation subway specifically comprises the following steps:
the method comprises the following steps: horizontal freezing reinforcement for shield starting tunnel portal of shield starting front shield
Freezing and reinforcing the stratum by using the horizontal freezing holes;
step two: shield originating under existing operation subway
Horizontally freezing and reinforcing the starting tunnel portal, and meanwhile, laying a monitoring network and manufacturing a starting guide platform; the method comprises the following steps of carrying out matching and laying of a storage battery car track behind a station bottom plate, and then assembling and matching with a trailer; installing a portal curtain cloth pressing plate, and additionally welding a shield tail brush in a portal ring; then assembling the host machine of the shield machine, and simultaneously completing the matching connection with the host machine; debugging the shield and installing a reaction frame and a support; assembling negative ring pipe sheets, and performing air pushing on the shield until the distance between the shield and the tunnel portal is 1.5 m; the starting condition is checked and accepted, the tunnel portal is broken, and then the tunnel face is leveled; then, pulling out the freezing pipe in the shield propelling range to enable the shield to initially enter the tunnel portal to form a perfect tunnel portal sealing system; then, synchronously grouting the shield tail through the portal curtain cloth, and normally tunneling the shield to finish the starting of the shield;
step three: secondary grouting in hole after starting
After the shield tail enters the portal ring for sealing, synchronous grouting is started; after thawing, appropriate follow-up secondary grouting is performed in the tunnel.
Further, step one, the horizontal freezing hole needs to implement protective measures in the drilling hole; the protective measures specifically comprise protective measures before drilling, protective measures in drilling and guarantee measures for the reinforcing effect of the frozen curtain.
Further, the protection measure before drilling is specifically to set up precipitation well: supplementary precipitation is carried out before drilling construction, gushes water and gushes husky construction risk when reducing drilling construction, and can in time carry out precipitation treatment if the emergence accident in the construction.
Further, the protective measures in the drilling hole are specifically as follows:
1) before drilling, accurately measuring and positioning the drilling position, arranging freezing holes according to a freezing hole construction drawing by positioning the holes and installing the orifice pipe according to a construction datum point, and positioning the holes on the tunnel portal according to hole positions of all the holes;
2) fixing a tapping machine according to the position of the hole site of the lofting frozen hole, tapping by a tapping device, adjusting the angle of the frozen hole during drilling by a drilling machine, and then tapping the diaphragm wall once, wherein the freezing tapping depth of the outer ring is 1300-1800 mm; after primary tapping is finished, timely installing an orifice pipe sealing and blowout preventing device, reinforcing the orifice pipe sealing and blowout preventing device by using a high-strength expansion wire, then installing a ball valve, then adopting a diamond drill bit to perform secondary tapping, tapping through a station enclosure structure, and stopping the ball valve in time after the tapping machine is withdrawn; and after the secondary opening, carefully checking the sealing of the orifice pipe and the existence of water leakage points of the ball valve, and if water leakage exists, adopting grouting plugging in time.
Furthermore, the installation method of the blowout preventer comprises the following steps: installing four expansion screws, winding a sealing object on a fish scale buckle of the orifice pipe, smashing the orifice pipe into the sealing object, connecting the sealing object with the expansion screws, installing a ball valve, forming a hole in the valve by using a diamond drill bit, penetrating the hole through the hole all the time, and closing the valve in time; can effectively ensure that the phenomena of water burst and sand burst can not occur, and can play the role of a blowout preventer.
Further, the measures for ensuring the reinforcement effect of the frozen curtain specifically include: laying a heat-insulating layer of 60-80 mm on the inner wall of the station bottom plate near the freezing wall; the heat-insulating layer is made of flame-retardant flexible plastic foam soft boards, the heat conductivity coefficient is less than or equal to 0.04W/MH, the water absorption rate is less than or equal to 02%, and the laying range is more than 0.5m outside the boundary of the frozen soil curtain; because concrete dispels the heat relative to the soil layer easily, can influence the freezing speed of soil layer to influence the overall stability and the water sealing nature of freezing the curtain, consequently carry out the setting of heat preservation and can avoid this problem effectively.
Further, the specific installation process of the hole door sealing system in the second step is as follows: the tunnel portal is sealed by adopting rubber curtain cloth and a circular ring plate with a turning plate, wherein the circular ring plate is fixed on an embedded tunnel portal steel ring through bolts, and the tunnel portal is sealed by the shield under the combined action of the rear turning plate and the rubber curtain cloth.
Further, the grouting in the tunnel in the third step is performed in the sequence of tunnel bottom plate → two sides of the tunnel → tunnel top plate.
Further, the concrete grouting process in the third step comprises the following steps: selecting a proper grouting hole position before grouting, drilling concrete at the hole position by using a hammer after wearing a grouting one-way check valve, and connecting a tee joint and a cement pipe; during grouting, directly injecting pure cement slurry, opening the grouting head after waiting for 5-10 minutes after grouting in one hole is finished, dredging and checking the injection effect, if the water amount is large, injecting again until less water flows out, finishing the hole, finally removing the grouting head, plugging the grouting hole with quick cement mortar, and carrying out the next grouting hole after a plastic cover is arranged; the secondary grouting is performed to fill the cavity on the back of the duct piece and the settlement amount of the frozen soil when the frozen soil is melted in time, so that the stratum has no space for deformation and water accumulation, and the coagulation of the grouting is synchronized, so that the ground subsidence can be effectively controlled, and the existing operation subway station is protected; meanwhile, the secondary grouting can reduce the influence of unset grout behind the tunnel on the tunneling and shield tail brush.
Compared with the prior art, the invention has the beneficial effects that:
1. the invention adopts a horizontal freezing method to carry out shield starting construction under the existing operation subway, and can freeze and reinforce the stratum by using the horizontal freezing holes, so that the soil body in the range of the tunnel mouth of the shield machine is frozen into a water-tight plate with high strength, thereby providing conditions for breaking the tunnel door;
2. the method can reduce stratum deformation and water and soil loss caused in the horizontal freezing construction process; the method can effectively control the loss of water and soil, the control of frost heaving and thawing sinking and the guarantee of the reinforcing effect of the freezing curtain in the drilling and pipe drawing construction process, thereby providing an effective means for protecting the existing operation subway in the horizontal freezing and reinforcing stage;
3. by utilizing various protective measures, safe, stable and smooth completion of the horizontal freezing reinforcement construction of the shield tunnel portal under the existing operation subway can be effectively ensured; is suitable for mass popularization.
Detailed Description
Example 1: a shield horizontal freezing starting construction method under an existing operation subway specifically comprises the following steps:
the method comprises the following steps: horizontal freezing reinforcement for shield starting tunnel portal of shield starting front shield
Freezing and reinforcing the stratum by using the horizontal freezing holes; wherein the horizontal freeze hole requires protective measures to be implemented in the borehole; the protective measures specifically comprise protective measures before drilling, protective measures in drilling and guarantee measures for the reinforcing effect of the frozen curtain; the protective measures before drilling are specifically to set a precipitation well: auxiliary precipitation is carried out before drilling construction, so that the construction risk of water burst and sand burst during drilling construction is reduced, and precipitation treatment can be carried out in time if an accident occurs during construction;
step two: shield originating under existing operation subway
Horizontally freezing and reinforcing the starting tunnel portal, and meanwhile, laying a monitoring network and manufacturing a starting guide platform; the method comprises the following steps of carrying out matching and laying of a storage battery car track behind a station bottom plate, and then assembling and matching with a trailer; installing a portal curtain cloth pressing plate, and additionally welding a shield tail brush in a portal ring; then assembling the host machine of the shield machine, and simultaneously completing the matching connection with the host machine; debugging the shield and installing a reaction frame and a support; assembling negative ring pipe sheets, and performing air pushing on the shield until the distance between the shield and the tunnel portal is 1.5 m; the starting condition is checked and accepted, the tunnel portal is broken, and then the tunnel face is leveled; then, pulling out the freezing pipe in the shield propelling range to enable the shield to initially enter the tunnel portal to form a perfect tunnel portal sealing system; then, synchronously grouting the shield tail through the portal curtain cloth, and normally tunneling the shield to finish the starting of the shield; the specific installation process of the tunnel door sealing system comprises the following steps: the tunnel portal is sealed by adopting rubber curtain cloth and a circular ring plate with a turning plate, wherein the circular ring plate is fixed on an embedded tunnel portal steel ring by a bolt;
step three: secondary grouting in hole after starting
After the shield tail enters the portal ring for sealing, synchronous grouting is started; after unfreezing, performing appropriate tracking secondary grouting in the tunnel; wherein, the sequence of grouting in the tunnel is tunnel bottom plate → two sides of the tunnel → tunnel top plate; the concrete grouting process comprises the following steps: selecting a proper grouting hole position before grouting, drilling concrete at the hole position by using a hammer after wearing a grouting one-way check valve, and connecting a tee joint and a cement pipe; during grouting, pure cement slurry is directly injected, the grouting head is opened to dredge and check the injection effect after the completion of grouting in one hole is waited for 8 minutes, if the water amount is large, the grouting head is injected again until less water flows out, the hole can be finished, finally the grouting head is dismantled, the grouting hole is plugged by using quick cement mortar, a plastic cover is arranged, and the next grouting hole is formed.
Example 2: the difference from example 1 is: the protection measures in the drilling are specifically as follows:
1) before drilling, accurately measuring and positioning the drilling position, arranging freezing holes according to a freezing hole construction drawing by positioning the holes and installing the orifice pipe according to a construction datum point, and positioning the holes on the tunnel portal according to hole positions of all the holes;
2) fixing a tapping machine according to the position of the hole site of the lofting frozen hole, tapping by a tapping device, adjusting the angle of the frozen hole during drilling by a drilling machine, and then tapping the diaphragm wall once, wherein the freezing tapping depth of the outer ring is 1500 mm; after primary tapping is finished, timely installing an orifice pipe sealing and blowout preventing device, reinforcing the orifice pipe sealing and blowout preventing device by using a high-strength expansion wire, then installing a ball valve, then adopting a diamond drill bit to perform secondary tapping, tapping through a station enclosure structure, and stopping the ball valve in time after the tapping machine is withdrawn; and after the secondary opening, carefully checking the sealing of the orifice pipe and the existence of water leakage points of the ball valve, and if water leakage exists, adopting grouting plugging in time.
The installation method of the blowout preventer comprises the following steps: installing four expansion screws, winding a sealing object on a fish scale buckle of the orifice pipe, smashing the orifice pipe into the sealing object, connecting the sealing object with the expansion screws, installing a ball valve, forming a hole in the valve by using a diamond drill bit, penetrating the hole door all the time, and closing the valve in time.
Example 3: the difference from example 2 is: the guarantee measures for the reinforcing effect of the frozen curtain specifically comprise the following steps: laying a 60mm heat insulation layer on the inner wall of the station bottom plate near the freezing wall; the heat insulating layer is made of flame-retardant flexible plastic foam board, the heat conductivity coefficient is less than or equal to 0.04W/MH, the water absorption rate is less than or equal to 02%, and the laying range is more than 0.5m outside the boundary of the frozen soil curtain.
Application example: constructing the shield horizontal freezing initiation under No. 2 line of a certain city operation subway by using the implementation 3 method; before construction, technical preparation works such as drawing consultation, design bottom-meeting, measurement, test, construction scheme, technical bottom-meeting, safety bottom-meeting and the like must be carried out. Meanwhile, construction site and construction preparation such as working, material and machine must be made in advance.
The method comprises the following steps: specially designing the horizontal freezing reinforcement of the starting tunnel portal:
(1) the starting tunnel portal freezing reinforcement design adopts a cup-shaped freezing wall to carry out soil body reinforcement, the thickness of the cup wall is more than or equal to 1.5m, the thickness of the cup bottom is 3.0-3.562 m, and the cup length is 12 m. The average temperature of the freezing wall is not higher than-10 ℃; the reinforced soil body has no lateral compressive strength of 3.6MPa, tensile strength of not less than 2MPa, bending strength of not less than 1.8MPa and shearing strength of not less than 1.5 MPa.
(2) Arrangement of freeze holes: the horizontal freezing holes of the shield starting tunnel portal are annularly arranged in three layers, a central hole is positioned in the center of the freezing curtain, the distance between the layers of the central ring is 1.35m, and the distance between the layers of the outermost ring is 1.2 m. The central holes are N8, the inner layer is N1-N7, the middle layer is Z1-Z15, the outer layer is W1-W34, and the positions of frozen soil needing to be chiseled are supplemented with b1 frozen holes, and the total number is 58. The specific parameters are shown in the following table:
section left line starting tunnel portal freeze hole characteristic list
Section right line starting tunnel portal freeze hole characteristic list
(3) Arrangement of temperature measuring holes: 7 temperature measuring holes are arranged in the freezing curtain of the starting tunnel door of the interval shield (1 temperature measuring hole is additionally arranged at the position W31). The temperature measuring pipes are seamless steel pipes with the diameter of 89 multiplied by 8mm, and the front ends of the pipes are welded and sealed to ensure that water cannot seep in the pipes.
The temperature tubes are shown in the following table:
section left line starting tunnel portal temperature measurement hole characteristic list
Numbering | Quantity (root) | Length of single hole (m) | Deflection angle (°) | Specification of | Remarks for note |
C1 | 1 | 15.100 | 0 | Φ89*8 | |
C2 | 1 | 15.100 | 0 | Φ89*8 | |
C3 | 1 | 15.100 | 0 | Φ89*8 | |
C4 | 1 | 15.100 | 0 | Φ89*8 | |
C5 | 1 | 5.000 | 0 | Φ89*8 | The shield is required to be pulled out when starting |
C6 | 1 | 5.000 | 0 | Φ89*8 | The shield is required to be pulled out when starting |
C7 | 1 | 5.000 | 0 | Φ89*8 | The shield is required to be pulled out when starting |
Total up to | 7 | 75.4 |
Section right line starting tunnel portal temperature measurement hole characteristic list
Numbering | Quantity (root) | Length of single hole (m) | Deflection angle (°) | Specification of | Remarks for note |
C1 | 1 | 15.300 | 0 | Φ89*8 | |
C2 | 1 | 15.300 | 0 | Φ89*8 | |
C3 | 1 | 15.300 | 0 | Φ89*8 | |
C4 | 1 | 15.300 | 0 | Φ89*8 | |
C5 | 1 | 5.200 | 0 | Φ89*8 | The shield is required to be pulled out when starting |
C6 | 1 | 5.200 | 0 | Φ89*8 | The shield is required to be pulled out when starting |
C7 | 1 | 5.200 | 0 | Φ89*8 | The shield is required to be pulled out when starting |
Total up to | 7 | 76.8 |
(4) Design of a freezing wall: the main parameters are as follows:
main technical parameter table for starting tunnel portal frozen wall freezing
Carrying out specific construction:
the method comprises the following steps: horizontal freezing reinforcement for shield starting tunnel portal of shield starting front shield
Freezing and reinforcing the stratum by using the horizontal freezing holes;
the protective measures before drilling are specifically to set a precipitation well: supplementary precipitation is carried out before drilling construction, gushes water and gushes husky construction risk when reducing drilling construction, and can in time carry out precipitation treatment if the emergence accident in the construction.
The following protective measures are taken in the horizontal freeze hole drilling:
(1) before drilling, the drilling position is accurately measured and positioned, the positioning hole opening and the installation of the orifice pipe are arranged according to the construction datum point and the freezing holes are arranged according to the freezing hole construction drawing. The holes are positioned on the portal according to the hole positions, so that water gushing and sand gushing caused by hole position deviation hole patching are avoided.
(2) Secondary hole opening: a J-200 type diamond drilling machine is selected for primary drilling, and a diamond core bit with the diameter of 140mm is used for drilling. Fixing a tapping machine according to the position of the hole site of the lofting frozen hole, carefully correcting the angle of the frozen hole during tapping of the tapper and adjusting drilling of the drilling machine, and then tapping the diaphragm wall once, wherein the frozen tapping depth of the outer ring is 1500mm (the side wall of the main structure of the station needs to be punched through by 900mm first, and then the outer ring needs to be drilled into the surrounding structure of the station by 600 mm); after primary opening is finished, installing an orifice pipe seal and a blowout preventer in time, reinforcing the orifice pipe seal and the blowout preventer by using a high-strength expansion wire, then installing a phi 125mm ball valve, and before installing the ball valve, checking the integrity of the ball valve, including the opening and closing, sealing, appearance damage and the like of the ball valve; and then, adopting a diamond drill bit with the diameter of 110mm to carry out secondary hole opening, penetrating the station enclosure structure, and closing the ball valve in time after exiting the hole opening machine. And after the secondary opening, carefully checking the sealing of the orifice pipe and the existence of water leakage points of the ball valve, and if water leakage exists, adopting grouting plugging in time.
(3) The specific method for installing the blowout preventer comprises the following steps: installing four expansion screws, winding hemp or cotton and other sealing objects on the scale buttons of the orifice pipe, smashing the orifice pipe into the expansion screws, connecting the orifice pipe with the expansion screws, installing a DN125 ball valve, opening a hole in the valve by using a phi 98mm diamond drill bit, and always penetrating the orifice, wherein if the water and sand flow in the stratum is large, the valve can be closed in time, so that the phenomena of water burst and sand burst are avoided, and the function of a blowout preventer can be realized.
(4) The freezing pipe is arranged before being put into the drill hole, the concentric axes of the freezing pipe are overlapped, during welding, a welding line is full, the freezing pipe is guaranteed to have enough strength, the freezing pipe is prevented from being drilled and broken during drilling, and water burst and sand burst caused by hole repairing are avoided.
(5) When the drill bit is normally drilled, the one-way valve processed on site is adopted for inlaying the drill bit, and the waterless drilling is preferentially adopted, so that the loss of water and soil can be reduced, and the control method is very favorable for controlling the settlement of the ground and the tunnel. If the drilling is difficult, the water drilling is adopted. And flushing the one-way valve after the freezing pipe reaches the designed depth, and sealing the end part of the freezing pipe.
(6) In the drilling process, if water and soil loss occurs, soil can be timely subjected to grouting by a bypass valve arranged at the position of a hole pipe according to the daily monitoring conditions of the ground and an existing No. 2 line station, single-fluid grouting is mainly used (grouting treatment is carried out on an outer ring hole, conditions are created for cutting out a later-stage outer side freezing hole), and the influence of a drilling hole on the surrounding environment is controlled.
(7) Ground monitoring is enhanced, and once single settlement is larger than 3mm, grouting is carried out from the ground immediately.
(8) Emergency materials such as wood plugs, cotton yarns and polyurethane are prepared, plugging is carried out at any time, and a large amount of water and sand gushes are avoided.
(9) Three dewatering wells are additionally arranged at the middle positions of the left and right lines and avoid the underground pipeline. Supplementary precipitation is carried out before drilling construction, gushes water and gushes husky construction risk when reducing drilling construction, and can in time carry out precipitation treatment if the emergence accident in the construction.
The guarantee measures for the reinforcing effect of the freezing curtain specifically comprise the following steps:
(1) freezing hole sites are reasonably arranged, the best freezing effect is realized, and the freezing speed is accelerated. And (4) confirming that the thickness and the average temperature of the frozen wall meet the design requirements through detection, and then performing tunnel portal breaking and shield starting construction.
(2) During the formation of the frozen wall, no precipitation measures must be taken in the permeable sand layer in the region 200m outside the frozen wall and no concentrated water flows must be present in the soil layer in the frozen region. And in the positive freezing process, the auxiliary ground inspection personnel are additionally arranged to mainly check whether precipitation operation exists or not. Even if the area is outside the range, different construction sites can cause corresponding groundwater flow if precipitation operation is carried out simultaneously, and if the groundwater loss in the freezing range exceeds 5m/d, countermeasures need to be considered. Relevant investigations should be done before active freezing.
At present, 3 dewatering wells are arranged in a south end well of a station and are all near a north shield hoisting well of the station, the unit is in strengthened contact with related units, and dewatering is stopped when freezing is carried out.
(3) Because concrete is easy to radiate heat relative to the soil layer, the freezing speed of the soil layer can be influenced, and therefore the overall stability and the water sealing performance of the freezing curtain are influenced. An insulating layer is laid on the inner wall of the station bottom plate near the frozen wall, the insulating layer is made of a flame-retardant flexible plastic foam board, the thickness of the insulating layer is 60mm, the heat conductivity coefficient is not more than 0.04W/MH, and the water absorption rate is not more than 2%. The laying range is not less than 0.5m outside the boundary of the frozen soil curtain, when the heat insulation plates are adopted, the heat insulation plates are closely attached to the inner wall by adopting special glue, and no gap is formed between the plates. And the evaporator and the low-temperature pipeline of the refrigerating unit are insulated by cotton wool, and the brine tank and the brine main pipe are insulated by an insulation board or cotton wool with the thickness of 40 mm.
(4) The flow rate of the single-hole brine in the freezing hole is determined according to the series length of the freezing holes and is not less than 5m3Preferably,/h; the active freezing time is designed to be 30 days, the temperature of the saline water is reduced to be below 18 ℃ below zero after 7 days of active freezing, the temperature of the saline water is reduced to be below 24 ℃ below zero after 15 days of active freezing, the temperature of the saline water is reduced to be below 28 ℃ below zero before the freezing pipe is pulled out, and the temperature difference of the saline water in the return circuit is not more than 2 ℃. If the brine temperature and the brine flow rate do not meet the design requirements, the active freezing time is prolonged to ensure that the designed thickness and temperature of the freezing wall are achieved. The liquid collecting and distributing ring is connected with the freezing pipes through high-pressure rubber pipes, and valves are respectively arranged at the inlet and the outlet of each group of freezing pipes so as to control the flow of brine.
(5) Monitoring should be strengthened in the tunnel door construction process, when the average temperature at the interface of the soil layer and the diaphragm wall is not higher than-5 ℃. When the average temperature of the frozen wall is designed to be-10 ℃ at other parts, the frozen wall meets the requirement of reinforcing effect.
(6) And (4) measuring the temperature, judging that the freezing curtain is crossed and coiled, reaching the designed thickness, and entering a maintenance freezing stage after the freezing curtain is completely cemented with the diaphragm wall. And maintaining the temperature in the freezing period below-28 ℃, wherein the freezing time runs through the shield machine and is started to manufacture the tunnel portal ring beam. The freezing and reinforcing effect during the period from the starting of the shield to the manufacture of the tunnel portal ring beam is ensured.
Step two: shield originating under existing operation subway
Horizontally freezing and reinforcing the starting tunnel portal, and meanwhile, laying a monitoring network and manufacturing a starting guide platform; the method comprises the following steps of carrying out matching and laying of a storage battery car track behind a station bottom plate, and then assembling and matching with a trailer; installing a portal curtain cloth pressing plate, and additionally welding a shield tail brush in a portal ring; then assembling the host machine of the shield machine, and simultaneously completing the matching connection with the host machine; debugging the shield and installing a reaction frame and a support; assembling negative ring pipe sheets, and performing air pushing on the shield until the distance between the shield and the tunnel portal is 1.5 m; the starting condition is checked and accepted, the tunnel portal is broken, and then the tunnel face is leveled; then, pulling out the freezing pipe in the shield propelling range to enable the shield to initially enter the tunnel portal to form a perfect tunnel portal sealing system; then, synchronously grouting the shield tail through the portal curtain cloth, and normally tunneling the shield to finish the starting of the shield;
step three: secondary grouting in hole after starting
After the shield tail enters the portal ring for sealing, synchronous grouting is started; after unfreezing, performing appropriate tracking secondary grouting in the tunnel; wherein, the grouting material mainly uses single grout as main grouting material and uses double grout as auxiliary grouting material. The cement-water glass solution is prepared by mixing cement slurry and water glass solution in a volume ratio of 1:1, wherein the water cement ratio is 1:1, and the water glass solution is diluted by adding 2 times of water glass in the volume of B35-B40.
Claims (10)
1. A shield horizontal freezing starting construction method under an existing operation subway is characterized by specifically comprising the following steps:
the method comprises the following steps: horizontal freezing reinforcement for shield starting tunnel portal of shield starting front shield
Freezing and reinforcing the stratum by using the horizontal freezing holes;
step two: shield originating under existing operation subway
Horizontally freezing and reinforcing the starting tunnel portal, and meanwhile, laying a monitoring network and manufacturing a starting guide platform; the method comprises the following steps of carrying out matching and laying of a storage battery car track behind a station bottom plate, and then assembling and matching with a trailer; installing a portal curtain cloth pressing plate, and additionally welding a shield tail brush in a portal ring; then assembling the host machine of the shield machine, and simultaneously completing the matching connection with the host machine; debugging the shield and installing a reaction frame and a support; assembling negative ring pipe sheets, and performing air pushing on the shield until the distance between the shield and the tunnel portal is 1.5 m; the starting condition is checked and accepted, the tunnel portal is broken, and then the tunnel face is leveled; then, pulling out the freezing pipe in the shield propelling range to enable the shield to initially enter the tunnel portal to form a perfect tunnel portal sealing system; then, synchronously grouting the shield tail through the portal curtain cloth, and normally tunneling the shield to finish the starting of the shield;
step three: secondary grouting in hole after starting
After the shield tail enters the portal ring for sealing, synchronous grouting is started; after thawing, appropriate follow-up secondary grouting is performed in the tunnel.
2. The shield horizontal freezing starting construction method under the existing operation subway is characterized in that in the step one, protective measures are required to be implemented in a drilled hole by the horizontal freezing hole; the protective measures specifically comprise protective measures before drilling, protective measures in drilling and guarantee measures for the reinforcing effect of the frozen curtain.
3. The shield horizontal freezing starting construction method under the existing operation subway is characterized in that a protective measure before drilling is specifically to arrange a dewatering well.
4. The shield horizontal freezing starting construction method under the existing operation subway as claimed in claim 2, wherein the protection measures in the drilling are specifically:
1) before drilling, accurately measuring and positioning the drilling position, arranging freezing holes according to a freezing hole construction drawing by positioning the holes and installing the orifice pipe according to a construction datum point, and positioning the holes on the tunnel portal according to hole positions of all the holes;
2) fixing a tapping machine according to the position of the hole site of the lofting frozen hole, tapping by a tapping device, adjusting the angle of the frozen hole during drilling by a drilling machine, and then tapping the diaphragm wall once, wherein the freezing tapping depth of the outer ring is 1300-1800 mm; after primary tapping is finished, timely installing an orifice pipe sealing and blowout preventing device, reinforcing the orifice pipe sealing and blowout preventing device by using a high-strength expansion wire, then installing a ball valve, then adopting a diamond drill bit to perform secondary tapping, tapping through a station enclosure structure, and stopping the ball valve in time after the tapping machine is withdrawn; and after the secondary opening, carefully checking the sealing of the orifice pipe and the existence of water leakage points of the ball valve, and if water leakage exists, adopting grouting plugging in time.
5. The shield horizontal freezing starting construction method under the existing operation subway is characterized in that the installation method of the blowout preventer comprises the following steps: installing four expansion screws, winding a sealing object on a fish scale buckle of the orifice pipe, smashing the orifice pipe into the sealing object, connecting the sealing object with the expansion screws, installing a ball valve, forming a hole in the valve by using a diamond drill bit, penetrating the hole door all the time, and closing the valve in time.
6. The shield horizontal freezing starting construction method under the existing operation subway is characterized in that the guarantee measure of the freezing curtain reinforcement effect specifically comprises the following steps: laying a heat-insulating layer of 60-80 mm on the inner wall of the station bottom plate near the freezing wall; the heat insulating layer is made of flame-retardant flexible plastic foam board, the heat conductivity coefficient is less than or equal to 0.04W/MH, the water absorption rate is less than or equal to 02%, and the laying range is more than 0.5m outside the boundary of the frozen soil curtain.
7. The shield horizontal freezing starting construction method under the existing operation subway is characterized in that the concrete installation process of the tunnel portal sealing system in the step two is as follows: the tunnel portal is sealed by adopting rubber curtain cloth and a circular ring plate with a turning plate, wherein the circular ring plate is fixed on an embedded tunnel portal steel ring through bolts, and the tunnel portal is sealed by the shield under the combined action of the rear turning plate and the rubber curtain cloth.
8. The shield horizontal freezing starting construction method under the existing operation subway is characterized in that the grouting in the third step is performed in the sequence of tunnel bottom plate → two sides of tunnel → tunnel top plate.
9. The shield horizontal freezing starting construction method under the existing operation subway is characterized in that the concrete process of grouting in the third step is as follows: selecting a proper grouting hole position before grouting, drilling concrete at the hole position by using a hammer after wearing a grouting one-way check valve, and connecting a tee joint and a cement pipe; during grouting, pure cement slurry is directly injected, after the completion of grouting in one hole, the grouting head is opened for dredging and checking the injection effect after waiting for 5-10 minutes, if the water amount is large, the grouting head is injected again, the hole can be finished when less water flows out, finally the grouting head is dismantled, the grouting hole is plugged by using quick cement mortar, a plastic cover is arranged, and the next grouting hole is formed.
10. The shield horizontal freezing starting construction method under the existing operation subway is characterized in that the stratum in the step one is reinforced by freezing of horizontal freezing holes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110356066.4A CN113153322B (en) | 2021-04-01 | 2021-04-01 | Shield horizontal freezing originating construction method under existing operation subway |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110356066.4A CN113153322B (en) | 2021-04-01 | 2021-04-01 | Shield horizontal freezing originating construction method under existing operation subway |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113153322A true CN113153322A (en) | 2021-07-23 |
CN113153322B CN113153322B (en) | 2024-02-23 |
Family
ID=76886052
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110356066.4A Active CN113153322B (en) | 2021-04-01 | 2021-04-01 | Shield horizontal freezing originating construction method under existing operation subway |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113153322B (en) |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103527214A (en) * | 2013-11-04 | 2014-01-22 | 南京林业大学 | Horizontal freezing and pipe shed combined subway shield tunnel reinforcing tip and method |
CN104405400A (en) * | 2014-10-08 | 2015-03-11 | 海南大学 | Method for arranging cup-shaped horizontal freezing holes in end of large-diameter shield tunnel |
CN104695964A (en) * | 2013-12-04 | 2015-06-10 | 宏润建设集团股份有限公司 | Subway shield tunnel freeze entering method |
CN106761782A (en) * | 2016-12-30 | 2017-05-31 | 中铁二局集团有限公司 | A kind of tunneling construction method for wearing operation tunnel under shield in rich water powder land floor |
CN108374664A (en) * | 2018-02-07 | 2018-08-07 | 中铁十二局集团有限公司 | The closed station-crossing construction method of ventilating shaft steel bushing among rich water soft soil layer |
CN109403987A (en) * | 2018-12-11 | 2019-03-01 | 南京林业大学 | Shield end horizontal frozen combines reception device and construction method with short steel case |
CN110017142A (en) * | 2019-04-25 | 2019-07-16 | 中铁十二局集团有限公司 | The emergency management method of tunnel safety based on frozen construction |
CN110821504A (en) * | 2019-12-04 | 2020-02-21 | 中铁十二局集团有限公司 | Water-rich stratum shield starting end rotary spraying and freezing combined reinforcing structure and construction method |
CN110924961A (en) * | 2019-12-06 | 2020-03-27 | 中交第三航务工程局有限公司 | Construction method for starting shield tunneling machine to pass through existing station |
CN210530847U (en) * | 2019-07-04 | 2020-05-15 | 中铁十一局集团城市轨道工程有限公司 | Shield starting tunnel portal water stop device close to existing line |
CN111550251A (en) * | 2020-06-29 | 2020-08-18 | 中交二公局第三工程有限公司 | Structure for realizing freezing of contact channel of shield tunnel of water-rich sand layer and construction process |
-
2021
- 2021-04-01 CN CN202110356066.4A patent/CN113153322B/en active Active
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103527214A (en) * | 2013-11-04 | 2014-01-22 | 南京林业大学 | Horizontal freezing and pipe shed combined subway shield tunnel reinforcing tip and method |
CN104695964A (en) * | 2013-12-04 | 2015-06-10 | 宏润建设集团股份有限公司 | Subway shield tunnel freeze entering method |
CN104405400A (en) * | 2014-10-08 | 2015-03-11 | 海南大学 | Method for arranging cup-shaped horizontal freezing holes in end of large-diameter shield tunnel |
CN106761782A (en) * | 2016-12-30 | 2017-05-31 | 中铁二局集团有限公司 | A kind of tunneling construction method for wearing operation tunnel under shield in rich water powder land floor |
CN108374664A (en) * | 2018-02-07 | 2018-08-07 | 中铁十二局集团有限公司 | The closed station-crossing construction method of ventilating shaft steel bushing among rich water soft soil layer |
CN109403987A (en) * | 2018-12-11 | 2019-03-01 | 南京林业大学 | Shield end horizontal frozen combines reception device and construction method with short steel case |
CN110017142A (en) * | 2019-04-25 | 2019-07-16 | 中铁十二局集团有限公司 | The emergency management method of tunnel safety based on frozen construction |
CN210530847U (en) * | 2019-07-04 | 2020-05-15 | 中铁十一局集团城市轨道工程有限公司 | Shield starting tunnel portal water stop device close to existing line |
CN110821504A (en) * | 2019-12-04 | 2020-02-21 | 中铁十二局集团有限公司 | Water-rich stratum shield starting end rotary spraying and freezing combined reinforcing structure and construction method |
CN110924961A (en) * | 2019-12-06 | 2020-03-27 | 中交第三航务工程局有限公司 | Construction method for starting shield tunneling machine to pass through existing station |
CN111550251A (en) * | 2020-06-29 | 2020-08-18 | 中交二公局第三工程有限公司 | Structure for realizing freezing of contact channel of shield tunnel of water-rich sand layer and construction process |
Non-Patent Citations (19)
Title |
---|
HU, J等: "Finite-Element Analysis of Heat Transfer of Horizontal Ground-Freezing Method in Shield-Driven Tunneling", INTERNATIONAL JOURNAL OF GEOMECHANICS, vol. 17, no. 10 * |
侯建军;肖铭钊;: "高水压粉砂地层泥水盾构水下到达施工技术", 土工基础, no. 06 * |
吴全立;王梦恕;朱磊;董新平;孙正阳;: "盾构近始发端头下穿既有地铁线路的综合施工技术研究", 现代隧道技术, no. 04 * |
孙延盼;万凯;王涛;刘跃雄;彭俊锋;何知;董晓龙;: "无锡地铁盾构组合工法接收施工技术", 市政技术, no. 06 * |
安宏斌;怀平生;白晓岭;漆伟强;景晨钟;: "特拉维夫富水砂层盾构短套筒始发技术研究", 现代城市轨道交通, no. 12 * |
岳红波;梁聪;刘媛莹;燕晓;梅源;: "杯形水平冻结法端头加固联合钢套筒盾构接收技术研究", 施工技术, no. 04 * |
底龙飞;: "基于昆明轨道五号线盾构下穿既有隧道施工技术研究", 四川建筑, no. 02 * |
李广军;邓旭;李颖;张稳军;郑刚;: "冻结加固地层中盾构进出端头井施工风险研究", 建筑科学, vol. 28, no. 1, pages 267 - 272 * |
杨涛;: "软土地层中地铁既有站内盾构暗接收暗始发技术", 建筑安全, no. 05 * |
王振勇;董震永;江玉生;管晓明;王旭春;: "砂卵石地层盾构穿越人工湖安全风险控制技术", 施工技术, no. 4 * |
祝和意;马晓华;: "水平冻结法在苏州地铁盾构进出洞中的应用", 铁道建筑, no. 08 * |
程林飞: "冷冻法端头加固盾构始发技术", 四川水泥, no. 2017, pages 182 - 184 * |
艾零件: "不良地质条件下盾构机整体下沉处理技术――基于冻结帷幕加固技术", 福建建筑, no. 2019, pages 80 - 85 * |
苑锁霞;: "一种新型盾构始发洞门密封的设计和应用", 建筑机械化, no. 03 * |
郑世兴;: "盾构机水平冻结法进洞技术", 建筑施工, no. 11 * |
郭剑虹;袁忠银;沈楠;张丽娟;李文婷;: "长江隧道江中段连接通道施工技术", 低温建筑技术, vol. 1, no. 09, pages 230 - 231 * |
郭士峰;梁真;刘凤华;: "深覆土隧道施工中盾构出洞施工技术", 建筑施工, no. 09 * |
马俊;杨平;刘增光;陈亮;: "浅埋富含水砂层盾构下穿敏感性建筑水平冻结+短钢箱接收技术", 防灾减灾工程学报, no. 02 * |
龚成明;王永义;: "高原高寒地区隧道内渗漏水整治与环境保护", 铁道工程学报, no. 03 * |
Also Published As
Publication number | Publication date |
---|---|
CN113153322B (en) | 2024-02-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111594181B (en) | Construction method for communicating and connecting newly-added underground excavation channel and existing station hall layer | |
CN105804758B (en) | Across constructing metro tunnel method on the rectangular top pipe of the shallow small spacing of earthing big cross section | |
CN110685697A (en) | Freezing construction method and freezing system for connection channel | |
CN105908765B (en) | For protecting the open trench tunnel water sealing structure and construction method of groundwater environment | |
CN106050266A (en) | Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel | |
CN109139052B (en) | Grouting hole device based on high-pressure deep hole grouting and construction method | |
CN101418567A (en) | Protective cutting construction method for tunnel segment | |
CN106121686B (en) | Underground excavation tunnel water stop structure for protecting groundwater environment and construction method thereof | |
CN111119900A (en) | Earth pressure balance shield liquid nitrogen vertical freezing and underwater receiving comprehensive construction method | |
CN109162298A (en) | A kind of construction method of hydrous fluids pipe gallery | |
CN110878697A (en) | Shield underwater receiving method next to urban main road in high-water-rich sandy gravel stratum | |
CN109296371A (en) | MJS method and horizontal freezing joint reinforcement pressure-bearing rich water arenaceous stratum overlap the system and its construction method that section is worn under station | |
CN114233385A (en) | Treatment method for mud burst and water burst of inclined shaft | |
CN107034874A (en) | Double-screw type slip casting type freezing plant and construction method | |
CN113266373A (en) | Freezing wall and cement reinforcement combined enclosure system in large-section tunnel construction and excavation method thereof | |
CN113756825A (en) | Mechanical method connecting channel construction method utilizing pipe jacking technology | |
CN114109442A (en) | Tunnel karst broken zone collapse half-section curtain forward grouting reinforcement treatment method | |
Chen et al. | Construction technology of large diameter underwater shield tunnel | |
CN108915702A (en) | It is a kind of circle narrow-bore tunnel in shield method of reseptance | |
CN210714701U (en) | Freezing system for freezing construction of communication channel | |
CN113153322B (en) | Shield horizontal freezing originating construction method under existing operation subway | |
CN111075455A (en) | Freezing method channel construction process | |
CN215169989U (en) | Freezing system for reinforcing 60-meter-grade ultra-long distance communication channel by freezing method | |
CN115306407A (en) | Method for shield launching by adopting vertical liquid nitrogen freezing reinforcement and steel sleeve | |
CN115030731A (en) | Pilot tunnel construction method in cross tunnel engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |