CN113026728A - Rock-socketed pile construction method of XG360 rotary drilling rig for deep-buried hard rock stratum - Google Patents

Rock-socketed pile construction method of XG360 rotary drilling rig for deep-buried hard rock stratum Download PDF

Info

Publication number
CN113026728A
CN113026728A CN202110276800.6A CN202110276800A CN113026728A CN 113026728 A CN113026728 A CN 113026728A CN 202110276800 A CN202110276800 A CN 202110276800A CN 113026728 A CN113026728 A CN 113026728A
Authority
CN
China
Prior art keywords
rock
construction
pile
rock stratum
drilling rig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110276800.6A
Other languages
Chinese (zh)
Inventor
滕非
郑欣家
张伟
徐鑫
徐勇
冯雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Urban Construction Group Co Ltd
Third Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Original Assignee
China Railway Urban Construction Group Co Ltd
Third Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Urban Construction Group Co Ltd, Third Engineering Co Ltd of China Railway Urban Construction Group Co Ltd filed Critical China Railway Urban Construction Group Co Ltd
Priority to CN202110276800.6A priority Critical patent/CN113026728A/en
Publication of CN113026728A publication Critical patent/CN113026728A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B3/00Rotary drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0037Clays
    • E02D2300/004Bentonite or bentonite-like
    • E02D2300/0043Bentonite or bentonite-like with other ingredients
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Earth Drilling (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a rock-socketed pile construction method of a XG360 rotary drilling rig for deeply burying a hard rock stratum, which comprises the following steps: the method comprises the following steps: designing and intersecting bottoms by a design unit before engineering construction, and when the construction unit finds that a construction drawing has errors, providing a design change requirement to the design unit in time; step two: technical responsible personnel should lead the engineering technical personnel to compile deeply buried hard rock stratum rock-socketed pile special construction scheme according to the design drawing, and carry out the technology to technical personnel and team leaders, study the engineering geology and hydrology condition before the construction, carefully analyze the geological survey report provided by the design, carry out the comprehensive analysis to the engineering geology; step three: the construction site is reasonably arranged according to the designed pile position, and the four-way pipe is flat. The rock-socketed pile construction method of the XG360 rotary drilling rig for the deep-buried hard rock stratum saves resources, reduces cost of construction from head exploration, is simple to operate, can accurately position, can shorten construction time, and has obvious economic benefit.

Description

Rock-socketed pile construction method of XG360 rotary drilling rig for deep-buried hard rock stratum
Technical Field
The invention belongs to the technical field of civil engineering, and particularly relates to a construction method of a rock-socketed pile of a XG360 rotary drilling rig for deeply burying a hard rock stratum.
Background
With the development of urban construction, especially the acceleration of old city transformation, pipeline burying projects of various pipe diameters are continuously increased, and a deep foundation (see a figure) consisting of piles and pile bearing platforms (bearing platforms for short) connected with pile tops or a single-pile foundation (pile foundation for short) connected with pile foundations through piles is provided. If the pile body is completely buried in the soil and the bottom surface of the bearing platform is contacted with the soil body, the pile body is called a low bearing platform pile foundation; when the upper part of the pile body is exposed out of the ground and the bottom of the pile cap is positioned above the ground, the pile body is called a high pile cap pile foundation. The building pile foundation is generally a low-bearing platform pile foundation, and the pile foundation is widely applied in high-rise buildings. The rock-socketed pile construction method of the existing XG360 rotary drilling rig for the deep-buried hard rock stratum has the advantages of complex operation, inaccurate positioning, unobvious economic benefit, and incapability of reducing construction cost and environmental pollution.
Disclosure of Invention
The invention aims to provide a rock-socketed pile construction method of a XG360 rotary drilling rig for a deep-buried hard rock stratum, and aims to solve the problems that the existing rock-socketed pile construction method of the XG360 rotary drilling rig for the deep-buried hard rock stratum, which is proposed in the background art, is complex to operate, cannot accurately position, cannot shorten the construction time, is not obvious in economic benefit, cannot reduce the construction cost and reduce the environmental pollution.
In order to achieve the purpose, the invention provides the following technical scheme: the construction method of the rock-socketed pile of the XG360 rotary drilling rig for deeply burying the hard rock stratum comprises the following specific steps:
the method comprises the following steps: designing and intersecting bottoms by a design unit before engineering construction, and when the construction unit finds that a construction drawing has errors, providing a design change requirement to the design unit in time;
step two: technical responsible personnel should lead the engineering technical personnel to compile deeply buried hard rock stratum rock-socketed pile special construction scheme according to the design drawing, and carry out the technology to technical personnel and team leaders, study the engineering geology and hydrology condition before the construction, carefully analyze the geological survey report provided by the design, carry out the comprehensive analysis to the engineering geology;
step three: reasonably arranging a construction site according to the designed pile position, leveling a compaction cross joint, arranging a pile machine chassis on a solid foundation, and for a soft foundation, replacing soft soil and ramming to be compact;
step four: the pile foundation steel casing adopts a pit digging method, the steel casing is embedded and lofted through a positioned control pile, so that the center of the steel casing is coincided with the center of a drilled hole, meanwhile, a horizontal ruler or a vertical ball is used for checking, so that the plane position and the verticality of the steel casing are accurate, and the height of the steel casing is 1.5m-2.0 m;
step five: preparing a slurry pool, installing a slurry pump, and preparing slurry by adopting water, bentonite, CNC (sodium cellulose) and lignin family decomposer alkali (Na2CO 3);
step six: before pore-forming, drilling by adopting a small-diameter rock-embedded cylinder drill, loosening the circumference of a rock core in a pore, and increasing the free surface of a rock stratum so as to reduce the stress level of the rock stratum, thereby being beneficial to the one-step drilling of the large-diameter cylinder drill and improving the working efficiency of the large-diameter cylinder drill;
step seven: then, a short spiral drill bit is used for crushing a rock core to create a crushing free surface, a 1.5m non-coring rock embedding cylinder type is used for drilling a one-step loose rock surface, and finally a 2.0m rock embedding rotary drill bit is used for drilling and slag removal to achieve the purpose of efficient rock entering;
step eight: when the final hole depth is reached, cleaning sediment at the bottom of the hole by using a bottom cleaning drill bit, stopping for 20-30min to precipitate suspended matters in the slurry, fishing out by using the drill bit to finish the first hole cleaning, and measuring the hole forming depth by using a measuring rope;
step nine: after having gone down the steel reinforcement cage, carry out the clear hole of secondary, the concrete under water of pouring, pile foundation concrete placement accomplishes the back, in time clears up pile bolsters, and whether inspection pile foundation sounding pipe is unobstructed, treats that pile foundation concrete reaches the health preserving period after, carries out ultrasonic detection.
Furthermore, in the second step, for engineering geology with geological hardness less than 5Mpa, soil indexes such as hydrogeological structure parameters and the like can be known during analysis; for lithology, the cause and type of rock, the size and shape of rock particles, rock structure and fracture development, the nature of cementation and the form of cementation are known.
Further, in the fifth step, the mixture ratio of water, bentonite, CNC (sodium cellulose) and lignin group decomposer alkali (Na2CO3) is as follows: 100:6:0.8:3.
And furthermore, the bucket teeth of the seventh medium-short spiral drill bit adopt bullet heads with tungsten-cobalt hard alloy inlaid at the heads, and the bucket teeth adopt tooth teeth to drill and take slag.
Furthermore, the underwater concrete pouring in the ninth step adopts a vertical lift conduit method, the conduit is pre-spliced and subjected to a water filling test before use, and the pressure during the water filling test is not less than 1.5 times of the maximum pressure possibly borne by the conduit wall during the concrete pouring.
Furthermore, the steel reinforcement cage is lengthened by adopting a straight thread sleeve to connect, the steel reinforcement cage is sunk after being lengthened section by section, and the steel reinforcement cage is fixed by welding steel lugs on the inner wall of the steel casing after being sunk to the designed elevation, so that the steel reinforcement cage is prevented from deviating or floating in the concrete pouring process.
Compared with the prior art, the invention has the beneficial effects that:
(1) compared with the traditional percussion drilling hole forming and high-power rotary drilling machine hole forming, the technology greatly shortens the construction time, has obvious economic benefit, and has very high verticality precision of a hole forming part, thereby greatly reducing the construction allowance reserved for ensuring the net size in a pile hole, reducing the waste, ensuring the integrity of the pile by adopting long pile casing construction, reducing the over-irrigation amount and having good quality benefit.
(2) The technology replaces the water medium pore-forming and soil-taking technology in the process, and the requirement and the discharge of slurry are greatly reduced. The soil is taken out and transported along with the soil, so that the field is saved, other operation and construction are facilitated, meanwhile, the transportation cost, the water cost and the electricity cost are saved, the construction cost is reduced, and the environmental pollution is reduced; the most important advantages are low noise, small vibration and little influence on surrounding residents.
(3) The rock-socketed pile construction method of the XG360 rotary drilling rig for the deep-buried hard rock stratum has the advantages that resources are saved, the cost of construction from the beginning is reduced, the operation is simple, the positioning can be accurately carried out, the construction time can be shortened, the economic benefit is obvious, the construction cost can be reduced, the environmental pollution is reduced, and the social benefit is also obvious.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1
The construction method of the rock-socketed pile of the XG360 rotary drilling rig for deeply burying the hard rock stratum comprises the following specific steps:
the method comprises the following steps: designing and intersecting bottoms by a design unit before engineering construction, and when the construction unit finds that a construction drawing has errors, providing a design change requirement to the design unit in time;
step two: technical responsible personnel should lead the engineering technical personnel to compile deeply buried hard rock stratum rock-socketed pile special construction scheme according to the design drawing, and carry out the technology to technical personnel and team leaders, study the engineering geology and hydrology condition before the construction, carefully analyze the geological survey report provided by the design, carry out the comprehensive analysis to the engineering geology;
step three: reasonably arranging a construction site according to the designed pile position, leveling a compaction cross joint, arranging a pile machine chassis on a solid foundation, and for a soft foundation, replacing soft soil and ramming to be compact;
step four: the pile foundation steel casing adopts a pit digging method, the steel casing is embedded and lofted through a positioned control pile, so that the center of the steel casing is coincided with the center of a drilled hole, meanwhile, a horizontal ruler or a vertical ball is used for checking, so that the plane position and the verticality of the steel casing are accurate, and the height of the steel casing is 1.5m-2.0 m;
step five: preparing a slurry pool, installing a slurry pump, and preparing slurry by adopting water, bentonite, CNC (sodium cellulose) and lignin family decomposer alkali (Na2CO 3);
step six: before pore-forming, drilling by adopting a small-diameter rock-embedded cylinder drill, loosening the circumference of a rock core in a pore, and increasing the free surface of a rock stratum so as to reduce the stress level of the rock stratum, thereby being beneficial to the one-step drilling of the large-diameter cylinder drill and improving the working efficiency of the large-diameter cylinder drill;
step seven: then, a short spiral drill bit is used for crushing a rock core to create a crushing free surface, a 1.5m non-coring rock embedding cylinder type is used for drilling a one-step loose rock surface, and finally a 2.0m rock embedding rotary drill bit is used for drilling and slag removal to achieve the purpose of efficient rock entering;
step eight: when the final hole depth is reached, cleaning sediment at the bottom of the hole by using a bottom cleaning drill bit, stopping for 20-30min to precipitate suspended matters in the slurry, fishing out by using the drill bit to finish the first hole cleaning, and measuring the hole forming depth by using a measuring rope;
step nine: after having gone down the steel reinforcement cage, carry out the clear hole of secondary, the concrete under water of pouring, pile foundation concrete placement accomplishes the back, in time clears up pile bolsters, and whether inspection pile foundation sounding pipe is unobstructed, treats that pile foundation concrete reaches the health preserving period after, carries out ultrasonic detection.
Wherein, in the second step, for engineering geology with geological hardness less than 5Mpa, the soil indexes such as hydrogeological structure parameters and the like can be known during analysis; for lithology, the cause and type of rock, the size and shape of rock particles, rock structure and fracture development, the nature of cementation and the form of cementation are known.
In the fifth step, the mixture ratio of water, bentonite, CNC (sodium cellulose) and lignin decomposer alkali (Na2CO3) is as follows: 100:6:0.8:3.
And seventhly, adopting a bullet head with a tungsten-cobalt hard alloy embedded at the head part of a bucket tooth of the middle-short spiral drill bit, and adopting tooth teeth to drill and take slag.
And C, pouring the underwater concrete in the step nine by adopting a vertical lifting guide pipe method, pre-splicing and water filling tests are carried out on the guide pipe before the guide pipe is used, and the pressure during the water filling test is not less than 1.5 times of the maximum pressure possibly borne by the guide pipe wall during pouring the concrete.
And C, in the ninth step, the steel reinforcement cage is lengthened by adopting a straight thread sleeve to be connected, the steel reinforcement cage sinks after being lengthened section by section, and the steel reinforcement cage is fixed by welding steel oxcles on the inner wall of the steel casing after being sunk to the designed elevation, so that the steel reinforcement cage is prevented from deviating or floating in the concrete pouring process.
Example 2
The construction method of the rock-socketed pile of the XG360 rotary drilling rig for deeply burying the hard rock stratum comprises the following specific steps:
the method comprises the following steps: designing and intersecting bottoms by a design unit before engineering construction, and when the construction unit finds that a construction drawing has errors, providing a design change requirement to the design unit in time;
step two: technical responsible personnel should lead the engineering technical personnel to compile deeply buried hard rock stratum rock-socketed pile special construction scheme according to the design drawing, and carry out the technology to technical personnel and team leaders, study the engineering geology and hydrology condition before the construction, carefully analyze the geological survey report provided by the design, carry out the comprehensive analysis to the engineering geology;
step three: reasonably arranging a construction site according to the designed pile position, leveling a compaction cross joint, arranging a pile machine chassis on a solid foundation, and for a soft foundation, replacing soft soil and ramming to be compact;
step four: the pile foundation steel casing adopts a pit digging method, the steel casing is embedded and lofted through a positioned control pile, so that the center of the steel casing is coincided with the center of a drilled hole, meanwhile, a horizontal ruler or a vertical ball is used for checking, so that the plane position and the verticality of the steel casing are accurate, and the height of the steel casing is 1.5m-2.0 m;
step five: preparing a slurry pool, installing a slurry pump, and preparing slurry by adopting water, bentonite, CNC (sodium cellulose) and lignin family decomposer alkali (Na2CO 3);
step six: before pore-forming, drilling by adopting a small-diameter rock-embedded cylinder drill, loosening the circumference of a rock core in a pore, and increasing the free surface of a rock stratum so as to reduce the stress level of the rock stratum, thereby being beneficial to the one-step drilling of the large-diameter cylinder drill and improving the working efficiency of the large-diameter cylinder drill;
step seven: then, a short spiral drill bit is used for crushing a rock core to create a crushing free surface, a 1.5m non-coring rock embedding cylinder type is used for drilling a one-step loose rock surface, and finally a 2.0m rock embedding rotary drill bit is used for drilling and slag removal to achieve the purpose of efficient rock entering;
step eight: when the final hole depth is reached, cleaning sediment at the bottom of the hole by using a bottom cleaning drill bit, stopping for 20-30min to precipitate suspended matters in the slurry, fishing out by using the drill bit to finish the first hole cleaning, and measuring the hole forming depth by using a measuring rope;
step nine: after having gone down the steel reinforcement cage, carry out the clear hole of secondary, the concrete under water of pouring, pile foundation concrete placement accomplishes the back, in time clears up pile bolsters, and whether inspection pile foundation sounding pipe is unobstructed, treats that pile foundation concrete reaches the health preserving period after, carries out ultrasonic detection.
Wherein, in the second step, for engineering geology with geological hardness less than 5Mpa, the soil indexes such as hydrogeological structure parameters and the like can be known during analysis; for lithology, the cause and type of rock, the size and shape of rock particles, rock structure and fracture development, the nature of cementation and the form of cementation are known.
In the fifth step, the mixture ratio of water, bentonite, CNC (sodium cellulose) and lignin decomposer alkali (Na2CO3) is as follows: 100:15:0.8:3.
And seventhly, adopting a bullet head with a tungsten-cobalt hard alloy embedded at the head part of a bucket tooth of the middle-short spiral drill bit, and adopting tooth teeth to drill and take slag.
And C, pouring the underwater concrete in the step nine by adopting a vertical lifting guide pipe method, pre-splicing and water filling tests are carried out on the guide pipe before the guide pipe is used, and the pressure during the water filling test is not less than 1.5 times of the maximum pressure possibly borne by the guide pipe wall during pouring the concrete.
And C, in the ninth step, the steel reinforcement cage is lengthened by adopting a straight thread sleeve to be connected, the steel reinforcement cage sinks after being lengthened section by section, and the steel reinforcement cage is fixed by welding steel oxcles on the inner wall of the steel casing after being sunk to the designed elevation, so that the steel reinforcement cage is prevented from deviating or floating in the concrete pouring process.
When the invention works: compared with the traditional percussion drilling hole forming and high-power rotary drilling machine hole forming, the technology greatly shortens the construction time, has obvious economic benefit, and has very high verticality precision of a hole forming part, thereby greatly reducing the construction allowance reserved for ensuring the net size in a pile hole, reducing the waste, ensuring the integrity of the pile by adopting long pile casing construction, reducing the over-irrigation amount and having good quality benefit. The technology replaces the water medium pore-forming and soil-taking technology in the process, and the requirement and the discharge of slurry are greatly reduced. The soil is taken out and transported along with the soil, so that the field is saved, other operation and construction are facilitated, meanwhile, the transportation cost, the water cost and the electricity cost are saved, the construction cost is reduced, and the environmental pollution is reduced; the most important advantages are low noise, small vibration and little influence on surrounding residents. The rock-socketed pile construction method of the XG360 rotary drilling rig for the deep-buried hard rock stratum has the advantages that resources are saved, the cost of construction from the beginning is reduced, the operation is simple, the positioning can be accurately carried out, the construction time can be shortened, the economic benefit is obvious, the construction cost can be reduced, the environmental pollution is reduced, and the social benefit is also obvious.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The construction method of the rock-socketed pile of the XG360 rotary drilling rig for deeply burying the hard rock stratum is characterized by comprising the following steps:
the method comprises the following steps: designing and intersecting bottoms by a design unit before engineering construction, and when the construction unit finds that a construction drawing has errors, providing a design change requirement to the design unit in time;
step two: technical responsible personnel should lead the engineering technical personnel to compile deeply buried hard rock stratum rock-socketed pile special construction scheme according to the design drawing, and carry out the technology to technical personnel and team leaders, study the engineering geology and hydrology condition before the construction, carefully analyze the geological survey report provided by the design, carry out the comprehensive analysis to the engineering geology;
step three: reasonably arranging a construction site according to the designed pile position, leveling a compaction cross joint, arranging a pile machine chassis on a solid foundation, and for a soft foundation, replacing soft soil and ramming to be compact;
step four: the pile foundation steel casing adopts a pit digging method, the steel casing is embedded and lofted through a positioned control pile, so that the center of the steel casing is coincided with the center of a drilled hole, meanwhile, a horizontal ruler or a vertical ball is used for checking, so that the plane position and the verticality of the steel casing are accurate, and the height of the steel casing is 1.5m-2.0 m;
step five: preparing a slurry pool, installing a slurry pump, and preparing slurry by adopting water, bentonite, CNC (sodium cellulose) and lignin family decomposer alkali (Na2CO 3);
step six: before pore-forming, drilling by adopting a small-diameter rock-embedded cylinder drill, loosening the circumference of a rock core in a pore, and increasing the free surface of a rock stratum so as to reduce the stress level of the rock stratum, thereby being beneficial to the one-step drilling of the large-diameter cylinder drill and improving the working efficiency of the large-diameter cylinder drill;
step seven: then, a short spiral drill bit is used for crushing a rock core to create a crushing free surface, a 1.5m non-coring rock embedding cylinder type is used for drilling a one-step loose rock surface, and finally a 2.0m rock embedding rotary drill bit is used for drilling and slag removal to achieve the purpose of efficient rock entering;
step eight: when the final hole depth is reached, cleaning sediment at the bottom of the hole by using a bottom cleaning drill bit, stopping for 20-30min to precipitate suspended matters in the slurry, fishing out by using the drill bit to finish the first hole cleaning, and measuring the hole forming depth by using a measuring rope;
step nine: after having gone down the steel reinforcement cage, carry out the clear hole of secondary, the concrete under water of pouring, pile foundation concrete placement accomplishes the back, in time clears up pile bolsters, and whether inspection pile foundation sounding pipe is unobstructed, treats that pile foundation concrete reaches the health preserving period after, carries out ultrasonic detection.
2. The rock-socketed pile construction method of the deep-buried hard rock stratum XG360 rotary drilling rig according to claim 1, characterized in that: in the second step, for engineering geology with geological hardness less than 5Mpa, soil indexes such as hydrogeological structure parameters and the like are acquired during analysis; for lithology, the cause and type of rock, the size and shape of rock particles, rock structure and fracture development, the nature of cementation and the form of cementation are known.
3. The rock-socketed pile construction method of the deep-buried hard rock stratum XG360 rotary drilling rig according to claim 1, characterized in that: in the fifth step, the mixture ratio of water, bentonite, CNC (sodium cellulose) and lignin group decomposer alkali (Na2CO3) is as follows: 100:6:0.8:3.
4. The rock-socketed pile construction method of the deep-buried hard rock stratum XG360 rotary drilling rig according to claim 1, characterized in that: and the bucket teeth of the seven-medium-short spiral drill bit in the step adopt bullet heads with tungsten-cobalt hard alloy inlaid at the heads, and the bucket teeth adopt tooth teeth to drill and take slag.
5. The rock-socketed pile construction method of the deep-buried hard rock stratum XG360 rotary drilling rig according to claim 1, characterized in that: and step nine, pouring the underwater concrete by adopting a vertical lifting guide pipe method, performing pre-assembly and water filling tests on the guide pipe before the guide pipe is used, wherein the pressure during the water filling test is not less than 1.5 times of the maximum pressure possibly borne by the guide pipe wall during pouring the concrete.
6. The rock-socketed pile construction method of the deep-buried hard rock stratum XG360 rotary drilling rig according to claim 1, characterized in that: and step nine, the steel reinforcement cage is lengthened by adopting a straight thread sleeve to be connected, the steel reinforcement cage sinks after being lengthened section by section, and the steel reinforcement cage is fixed by welding steel oxcles on the inner wall of the steel casing after being sunk to the designed elevation, so that the steel reinforcement cage is prevented from deviating or floating in the concrete pouring process.
CN202110276800.6A 2021-03-15 2021-03-15 Rock-socketed pile construction method of XG360 rotary drilling rig for deep-buried hard rock stratum Pending CN113026728A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110276800.6A CN113026728A (en) 2021-03-15 2021-03-15 Rock-socketed pile construction method of XG360 rotary drilling rig for deep-buried hard rock stratum

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110276800.6A CN113026728A (en) 2021-03-15 2021-03-15 Rock-socketed pile construction method of XG360 rotary drilling rig for deep-buried hard rock stratum

Publications (1)

Publication Number Publication Date
CN113026728A true CN113026728A (en) 2021-06-25

Family

ID=76470513

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110276800.6A Pending CN113026728A (en) 2021-03-15 2021-03-15 Rock-socketed pile construction method of XG360 rotary drilling rig for deep-buried hard rock stratum

Country Status (1)

Country Link
CN (1) CN113026728A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106245626A (en) * 2016-08-15 2016-12-21 中建三局基础设施工程有限公司 A kind of hard formation churning driven enters method
CN106988302A (en) * 2017-04-21 2017-07-28 江苏地基工程有限公司 A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN111058767A (en) * 2019-12-06 2020-04-24 广东省基础工程集团有限公司 Construction method of rock-socketed cast-in-situ bored pile

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106245626A (en) * 2016-08-15 2016-12-21 中建三局基础设施工程有限公司 A kind of hard formation churning driven enters method
CN106988302A (en) * 2017-04-21 2017-07-28 江苏地基工程有限公司 A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN111058767A (en) * 2019-12-06 2020-04-24 广东省基础工程集团有限公司 Construction method of rock-socketed cast-in-situ bored pile

Similar Documents

Publication Publication Date Title
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN106245626A (en) A kind of hard formation churning driven enters method
CN108797587A (en) A kind of novel sinking construction technology of static pressed pile
CN101818505B (en) Soil pressure testing method for a cutting edge of caisson
CN109555116A (en) A kind of high density karst intense development area fully-sleeved filled pile construction method
CN104929146B (en) A kind of multilayer karst growth zone pile foundation engineering method
CN111593728A (en) Embedded rock-socketed pile 'pile-first method' interpolation type jacket foundation construction system
CN110700248A (en) Miniature steel pipe pile for grouting small and medium-sized span bridge, pile foundation and construction method
CN112031017A (en) Construction method suitable for deep water pile foundation steel casing under bare rock geological condition
CN110705095A (en) Karst ground collapse analysis method
CN112482364A (en) Construction process of rotary digging cast-in-place pile under strong corrosive soft geological conditions in coastal region
CN112030956A (en) Karst stratum bored pile construction method
CN112878375A (en) Vertical jacking implementation method and structure in underwater tunnel suitable for hard stratum
CN111254933B (en) Karst grouting construction method for sleeve valve pipe
CN107246007A (en) A kind of construction method CFG
CN114319388A (en) Construction method of foundation pit enclosure structure in existing building in karst area
CN104314071A (en) Construction method of underground diaphragm wall by employing rotary drilling rig
CN112576265A (en) Sedimentation control method for old villages penetrated by shield
CN115369860A (en) Construction method of super-long isolation pile close to subway
CN112252332A (en) Grooving construction method for underground diaphragm wall of ultra-deep shaft
CN104141300A (en) Foundation pile hole drilling construction process
CN117107749A (en) Construction method of large-diameter punched bored pile under influence of sea water seepage in sea-filling land-building area
CN117364553A (en) Karst cave piling method under complex geological conditions
CN103806444A (en) Soft soil layer rotary excavating pile construction method
CN113026728A (en) Rock-socketed pile construction method of XG360 rotary drilling rig for deep-buried hard rock stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210625