CN1129765A - New technology of moving buildings horizontally - Google Patents

New technology of moving buildings horizontally Download PDF

Info

Publication number
CN1129765A
CN1129765A CN 95111898 CN95111898A CN1129765A CN 1129765 A CN1129765 A CN 1129765A CN 95111898 CN95111898 CN 95111898 CN 95111898 A CN95111898 A CN 95111898A CN 1129765 A CN1129765 A CN 1129765A
Authority
CN
China
Prior art keywords
ring beam
pulley
new ring
trailer
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 95111898
Other languages
Chinese (zh)
Inventor
董显枢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 95111898 priority Critical patent/CN1129765A/en
Publication of CN1129765A publication Critical patent/CN1129765A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The translation technique for building includes such steps as disconnecting foundation, reinforcing new ring beam, installing rolling apparatus, tracting and positioning. Big holes are made under original ring beam, in which combined beams and plinthes are set-up. Disconnected foundation is supported by jacks, and track and tracting machine are installed. Using slow-speed which, pulleys and steel cable pulls the building to new positions and all the apparatuses and tools are recovered. It features simplified technology, high efficiency and low cost.

Description

New technology of moving buildings horizontally
The invention belongs to a kind of building translation technology.
In the infrastructure of cities and towns, in order to implement master planning, often to remove the building that some layout is unreasonable or influence is planned, but in these buildings, the service life that has is not long, removes to rebuild and will cause very big waste, and people develop the technology of building translation for this reason, can be with all the building translation, saved a large amount of assets, the extraordinary construction engineering corporation in Shenyang utilized in recent years the building translation technology successfully for the translation of a few family units building, construction quality is also fine, but each operation from construction, also more loaded down with trivial details, difficulty of construction is bigger, and the engineering time is longer, quite a few construction equipment and material can not reclaim, and cause waste.
The purpose of this invention is to provide a kind of new technology of moving buildings horizontally, improve and the simplification construction technology, improve construction quality, shorten the engineering time, construction equipment and material all can be reclaimed, reduce construction cost, increase economic efficiency.
The object of the present invention is achieved like this: it comprises disconnected base, reinforces new ring beam and rolling equipment is installed, drags, four road working procedures in place, it is characterized in that:
A, disconnected basic operation: punch under the original building collar tie beam, install jack in the hole, compound beam is set up in the jack top, and base is built in the below, and adjacent wall will carry out at interval when breaking base, and disconnected basic cut height width will satisfy the requirement of attachment rail and rail car trucks;
B, reinforcing new ring beam and installation rolling equipment operation: reinforcing new ring beam and installation rolling equipment closely cooperate to intersect with the basic segmentation of breaking and carry out, to in time construct down railway roadbed behind the disconnected base, attachment rail and rail car trucks, and build new ring beam by laying bricks or stones, the towing carriage of trailer is connected with the mounting plate that new ring beam is reserved, and adds filler strip between towing carriage and the mounting plate;
C, drag operation: drag steel cable and walk around the assembly pulley that is fixed in the pier stake in a row and the assembly pulley on the new ring beam, adopting at a slow speed, winch drags;
D, operation in place: after building is in place, track and trailer are sealed with the mould utmost point, build concrete then and connect the wall base, reserve the hole that reclaims trailer and track, when solidify reach intensity after, with the filler strip of fire weldering cutting trailer top, trailer and track are reclaimed, at last that all space fillings are tight.
The present invention compares with prior art, has following advantage:
1, according to fabric structure and load condition, rationally determine quantity and the position and the rational deployment jack of hole-opening, a part or whole part holds up building, improve and simplified construction technology, disconnected base highly be 0.6 meter, large space that width is unlimited carries out, use the pneumatic pick operation, easy, the several times of increasing work efficiency.
2, by trailer load is directly delivered on the basis, does not produce shear action, guarantee construction quality.
3, adopt the steel column rolling and the heavy rail of trailer to move building, friction factor is little, and tractive force reduces half, moves steadily, reduces its destroyed possibility.
4, adopt winch, assembly pulley and special steel cable canoe at a slow speed can realize the equilibrium pulling of building, do not produce moment of torsion, move building speed and can improve 10 times, improved construction technology, improve efficiency of construction,
5, trailer, track, compound beam and jack can all reclaim, and reduce construction cost about 20%, increase economic efficiency.
Provide embodiments of the invention below in conjunction with accompanying drawing:
Fig. 1, the 2nd punches, installs jack in the hole under the original building collar tie beam, set up above the jack compound beam and below build the base schematic diagram.
Fig. 3 is the A-A sectional view of Fig. 2.
Fig. 4 is the trailer configuration schematic diagram.
Fig. 5 is the left view of Fig. 4.
Fig. 6 adds the filler strip schematic diagram between towing carriage and the mounting plate.
Fig. 7 is that pulley layout and steel cable twine schematic diagram.
Fig. 8 reinforces new beam circle schematic diagram.
Fig. 9 installs the isolation mode utmost point and pouring concrete schematic diagram before reclaiming trailer and track.
Embodiment is as follows:
One two unit of translation, five floor residential building, carry out four procedures:
(1), at first begins disconnected base from load bearing wall, see Fig. 1,2,3, in 1 time 0-600mm place hole-opening 2 of former wall base collar tie beam, every wall load bearing wall (long 10 meters) is opened four holes, install four jack 5 in each hole 1, compound beam 4 is set up in jack 5 tops, base 3 is built in the below, compound beam 4 is made up of i iron and steel plate, and when confirming that jack load has reached designing requirement, disconnected basic work can begin, adjacent wall mustn't disconnect simultaneously when breaking base, carry out at interval, disconnected base carries out with pneumatic pick, and the cut height of disconnected base will satisfy the requirement of attachment rail and trailer.
(2), see Fig. 4,5,6,8, reinforce new ring beam 15 and attachment rail 9 work and will closely intersect with disconnected basic segmentation and carries out.In time construct down railway roadbed 20 behind the disconnected base, heavy rail road 9 and trailer are installed, and are built by laying bricks or stones new ring beam 15 (see figure 8)s, build before the concrete with template with jack 5 and compound beam 4 isolation, to perform recovery preparation.See Fig. 4,5,6, trailer is made up of towing carriage 7 and steel column 8, the steel column 8 that the below assembling of towing carriage 7 can pack into and roll out, and towing carriage 7 is connected with the pop-up utmost point 6 bolts that building new ring beam 15 is reserved, and adds filler strip 10 between towing carriage 7 and the mounting plate 6.Following railway roadbed 20 concretes are thick to be 150mm, wide 40mm, want the controlling level degree, error does not allow to surpass 2mm, and attachment rail 9 usefulness level gauges are checked track 9 absolute altitudes and direction, eminence polishes with emery wheel, lower is leveled up track 9 with tagger, track 9 horizontal errors are controlled at ± 1mm in, locate with cement nail, install after track section and the trailer, began to build by laying bricks or stones new figure beam 15 in 48 hours.When treating that new ring beam reaches design strength, withdraw from jack 5 and compound beam 4.
(3), see Fig. 7, construction drags anchor block stake 14 well before dragging, and 14 one-tenth one row of several pier stakes are fixed two pulleys 13 in each pier stake 14, at the fixing head pulley 19 of new ring beam 15 upper edge trailer slideways 17, and require fixed joint pulley 18 (traction new ring beam) on new ring beam 15 according to equalising torque.Drag power and adopt winch at a slow speed, the maximum 20t of tractive force, 0.8 meter/minute of rope speed, the winding method of steel cable 16: walk around from the head pulley 19 that is fixed on first assembly pulley on the new ring beam 15, walk around first pulley 13 in first pier stake 14 again, connect down and walk around the head pulley 19 that is fixed on second assembly pulley on the new ring beam 15, successively around the pulley 13 to last pier stake 14, return then and walk around the auxiliary pulley 18 that is fixed on last assembly pulley on the new ring beam 15, connect down and walk around second pulley 13 that is fixed in the stake of penult pier, by same winding way successively around to the auxiliary pulley 18 that is fixed on first assembly pulley on the new ring beam 15, at last steel cable 16 fag ends are fixed in the winch pier stake 12, are connected pressure meter between fag end and the pier stake 12.This winding method comes and goes the tractive force that rough balance reduces because of the pulley friction by steel cable, passes through auxiliary pulley 18 again in new ring beam 15 locational differences, adjusts the arm of force, makes equalising torque at last, reaches the balanced pulling of building, does not produce moment of torsion.Constantly roll out from the car body rear end at trailer steel column 8 in service, need establish the special messenger and the steel column that rolls out is moved on to trailer the place ahead enter in the car body, the steel column throughput time is about 4-5 minute one (each steel column supporting capacity is 18t).When building moves forward, establish in the transverse ends of building and to monitor chi, with the millimeter unit, nonsynchronous length reached building at horizontal wide 1/2000 o'clock, taked corrective action, and measure has two: one, applies in the place ahead of holding of lagging behind with chain hoist to drag; The 2nd, at the hysteresis end rear of building jack applied thrust, make building realize the both sides advanced in unison.
(4), be operation in place at last, see Fig. 7, building is built concrete after moving on to new basic 11 positions immediately, sees Fig. 9, and trailer and track are wrapped with template 21 before building, for recovery creates conditions, trailer and track take out from the hole of reserving, and see Fig. 6, and the method that reclaims trailer is to cut filler strip 10 with the fire weldering, unload trailer, withdraw from track 9 then.Only need recover filler strip 10 get final product again by the time spent for trailer.Trailer and track have reclaimed the back molding utmost point, and be with the concrete spraying machine that all space fillings are tight, and arrangement is on-the-spot, and translation work promptly finishes.

Claims (3)

1, a kind of new technology of moving buildings horizontally comprises disconnected base, reinforces new ring beam and rolling equipment is installed, drags, four road working procedures in place, it is characterized in that:
A, disconnected basic operation: punch under the original building collar tie beam, install jack in the hole, compound beam is set up in the jack top, and base is built in the below, and adjacent wall will carry out at interval when breaking base, and disconnected basic cut height width will satisfy the requirement of attachment rail and rail car trucks;
B, reinforcing new ring beam and installation rolling equipment operation: reinforcing new ring beam and installation rolling equipment closely cooperate to intersect with the basic segmentation of breaking and carry out, to in time construct down railway roadbed behind the disconnected base, attachment rail and rail car trucks, and build new ring beam by laying bricks or stones, the towing carriage of trailer is connected with the pop-up utmost point that new ring beam is reserved, and adds filler strip between towing carriage and the mounting plate;
C, drag operation: drag steel cable and walk around the assembly pulley that is fixed in the pier stake in a row and the assembly pulley on the new ring beam, adopting at a slow speed, winch drags;
D, operation in place: after building is in place, track and trailer are sealed with the mould utmost point, build concrete then and connect the wall base, reserve the hole that reclaims trailer and track, when solidify reach intensity after, with the filler strip of fire weldering cutting trailer top, trailer and track are reclaimed, at last that all space fillings are tight.
2, new technology according to claim 1 is characterized in that: drag in the operation, two pulleys are fixed in each pier stake, at the fixing head pulley of new ring beam upper edge trailer slideway, and require fixed joint pulley on new ring beam according to equalising torque; Steel cable is walked around from the head pulley that is fixed on first assembly pulley on the new ring beam, walk around first pulley in first pier stake again, connect down and walk around the head pulley that is fixed on second assembly pulley on the new ring beam, successively around the pulley to last pier stake, return then and walk around the auxiliary pulley that is fixed on last assembly pulley on the new ring beam, connect down and walk around second pulley that is fixed in the stake of penult pier,, fag end is fixed in the stake of winch pier at last successively around to the auxiliary pulley that is fixed on first assembly pulley on the new ring beam by same winding way.
3, the employed equipment of a kind of new technology of moving buildings horizontally, it is characterized in that: trailer has towing carriage, the steel column that the assembling of towing carriage bottom can pack into and roll out.
CN 95111898 1995-07-27 1995-07-27 New technology of moving buildings horizontally Pending CN1129765A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 95111898 CN1129765A (en) 1995-07-27 1995-07-27 New technology of moving buildings horizontally

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 95111898 CN1129765A (en) 1995-07-27 1995-07-27 New technology of moving buildings horizontally

Publications (1)

Publication Number Publication Date
CN1129765A true CN1129765A (en) 1996-08-28

Family

ID=5079133

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 95111898 Pending CN1129765A (en) 1995-07-27 1995-07-27 New technology of moving buildings horizontally

Country Status (1)

Country Link
CN (1) CN1129765A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100356023C (en) * 2004-12-13 2007-12-19 山东建筑工程学院 Sliding vehicle for moving building
CN101429819B (en) * 2007-11-07 2011-05-18 上海天演建筑物移位工程有限公司 Wall and column underpinning method
CN102425312A (en) * 2011-12-12 2012-04-25 广州市鲁班建筑集团有限公司 Building translational device
CN103061530A (en) * 2013-01-18 2013-04-24 大连久鼎特种建筑工程有限公司 Quantitative deviation correcting method for building translation
CN104265007A (en) * 2014-09-16 2015-01-07 四川大学 Movable building group system and control method thereof
CN106437196A (en) * 2016-12-12 2017-02-22 兰姆(青岛)房屋设备制造有限公司 Hydraulic overall lifting device for house
CN107476598A (en) * 2017-08-24 2017-12-15 叶香雄 The sliding construction structure of raft foundation low layer Wood construction thing
CN111877343A (en) * 2020-08-28 2020-11-03 重庆中环建设有限公司 Two-cutter breaking process for fender post
CN114412166A (en) * 2022-01-06 2022-04-29 上海二十冶建设有限公司 Integrally-moving type cast-in-place concrete roof formwork support and using method thereof

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100356023C (en) * 2004-12-13 2007-12-19 山东建筑工程学院 Sliding vehicle for moving building
CN101429819B (en) * 2007-11-07 2011-05-18 上海天演建筑物移位工程有限公司 Wall and column underpinning method
CN102425312A (en) * 2011-12-12 2012-04-25 广州市鲁班建筑集团有限公司 Building translational device
CN103061530A (en) * 2013-01-18 2013-04-24 大连久鼎特种建筑工程有限公司 Quantitative deviation correcting method for building translation
CN103061530B (en) * 2013-01-18 2015-01-21 大连久鼎特种建筑工程有限公司 Quantitative deviation correcting method for building translation
CN104265007A (en) * 2014-09-16 2015-01-07 四川大学 Movable building group system and control method thereof
CN104265007B (en) * 2014-09-16 2016-08-17 四川大学 A kind of removable groups of building system and control method thereof
CN106437196A (en) * 2016-12-12 2017-02-22 兰姆(青岛)房屋设备制造有限公司 Hydraulic overall lifting device for house
CN107476598A (en) * 2017-08-24 2017-12-15 叶香雄 The sliding construction structure of raft foundation low layer Wood construction thing
CN111877343A (en) * 2020-08-28 2020-11-03 重庆中环建设有限公司 Two-cutter breaking process for fender post
CN114412166A (en) * 2022-01-06 2022-04-29 上海二十冶建设有限公司 Integrally-moving type cast-in-place concrete roof formwork support and using method thereof

Similar Documents

Publication Publication Date Title
CN100587165C (en) Cast-in-situ beam-making construction method of assembled support
CN101537973B (en) Method for continuously hoisting rolling mill housings by hydraulic pushing and lifting
CN108275573B (en) Hoisting construction method of tunnel boring machine and hoisting and translation combined equipment
CN108468430A (en) The not contour bearing steel truss structure hoisting slide construction of large span
US20130081215A1 (en) Bridge beam placement system and apparatus
CN110230261B (en) Mounting construction method for upper frame beam of double-layer synchronous beam
CN211762304U (en) Self-propelled hydraulic integral T-beam template device
CN113123246B (en) Bridge girder erection machine dismantling method
CN1129765A (en) New technology of moving buildings horizontally
CN112575697A (en) Rapid dismantling system and construction method for multi-layer overpass concrete continuous box girder ramp bridge
CN106869948A (en) A kind of construction that technique on shield machine's station-crossing is realized using the delivery vehicle that misses the stop
CN106087768B (en) A kind of method of the assembled mobile formwork in the narrow short transition time section of bridge tunnel
CN111455852A (en) Assembling method of movable formwork for bridge construction
CN108979664A (en) Existing subway tunnel based on mobile casting platform protects steel structure pouring construction method
CN114150593B (en) Simple arch bridge dismantling and reconstructing structure and arch bridge dismantling and reconstructing method
CN110055894B (en) Mobile bridge girder erection machine and large-gradient girder erection construction method thereof
CN214301338U (en) Quick dismantling system for multi-layer overpass concrete continuous box girder ramp bridge
CN212128685U (en) Be suitable for narrow and small space of subway underground line and overhead line track section kludge of striding line
CN218779336U (en) Transverse moving device for T-beam construction
CN103422446B (en) Section assembling bridging bassinet structure
CN111894631A (en) Tunnel disease treatment trolley
CN113898006A (en) Stable and rapid jacking construction method for box culvert under large excavation surface
CN215114447U (en) Detection trolley for inverted arch pouring surface of assembled subway station basement
CN117904977A (en) Method for installing bridge girder erection machine in tunnel
CN217576930U (en) Rail-traveling type conversion parking device for lifting bucket of ultra-deep shaft

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C01 Deemed withdrawal of patent application (patent law 1993)
WD01 Invention patent application deemed withdrawn after publication