CN108468430A - The not contour bearing steel truss structure hoisting slide construction of large span - Google Patents

The not contour bearing steel truss structure hoisting slide construction of large span Download PDF

Info

Publication number
CN108468430A
CN108468430A CN201810201269.4A CN201810201269A CN108468430A CN 108468430 A CN108468430 A CN 108468430A CN 201810201269 A CN201810201269 A CN 201810201269A CN 108468430 A CN108468430 A CN 108468430A
Authority
CN
China
Prior art keywords
steel truss
pin
sliding
large span
truss structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810201269.4A
Other languages
Chinese (zh)
Other versions
CN108468430B (en
Inventor
任峰
李维
王刚
肖红
李果
王晶晶
周钢
蔡珏
张涤非
曾梓义
余弦
刘松涛
高杨
余达峰
饶丹
吴穷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHENGDU CONSTRUCTION ENGINEERING GROUP CORP
Original Assignee
CHENGDU CONSTRUCTION ENGINEERING GROUP CORP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENGDU CONSTRUCTION ENGINEERING GROUP CORP filed Critical CHENGDU CONSTRUCTION ENGINEERING GROUP CORP
Priority to CN201810201269.4A priority Critical patent/CN108468430B/en
Publication of CN108468430A publication Critical patent/CN108468430A/en
Application granted granted Critical
Publication of CN108468430B publication Critical patent/CN108468430B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks

Abstract

The invention discloses a kind of not contour bearing steel truss structure hoisting slide construction of large span, the not contour bearing steel truss structure hoisting slide construction of especially a kind of large span being related to the realm of building construction, including following steps:A, bearing, mounting slip equipment and incremental launching device are set on steel truss;B, Pin is divided, assembly molding, specified altitude assignment is risen to steel truss is hung, it hangs every time and rises a Pin, the Pin for being raised to position is hung afterwards with the Pin for being raised to position has been hung before it to be spliced, using slip device and incremental launching device to Pin before into line slip, after vacating the space in hanging device job area, then hangs and rise the Pin steel truss to designated position;C, after the completion of sliding, bearing is disassembled.The not contour bearing steel truss structure hoisting slide construction of the large span of the application can reduce hoisting machinery grade threshold and energy consumption, reduce preassembling floor space, reduce the deformation of member, improve structure global formation quality.

Description

The not contour bearing steel truss structure hoisting slide construction of large span
Technical field
The present invention relates to a kind of not contour bearing steel truss structure hoisting slide construction of large span, especially one kind relates to And the not contour bearing steel truss structure hoisting slide construction of the large span of the realm of building construction.
Background technology
With the development of architectural construction technology, steel construction has because of it from heavy and light, easily peace are torn open, precision is high, the period is short, residual value High, the features such as anti-seismic performance is good, low in the pollution of the environment, is increasingly favored by market, be widely used in each building structure field. Meanwhile complicated steel structure system can be decomposed by component, realize design, processing, storage and transportation, installation streamlined class production line operation, Proportion is factory produced in increasing, reduces the time cost of situ wet operation and maintenance, and reduction manual operations is brought primary inclined Difference;It is more efficiently controllable " centralized systems with traditional class agricultural Model of " casts in situs " that building trade, which is altered in steps, for a long time Make " progress in industrialization;It is the key breakthrough direction of construction industry transition and upgrade.The developed countries such as America and Europe steel building Accounting, especially based on large span large space public building and large-sized workshop field substantially be more than steel-concrete Structure.
But for the lifting requirements of the not contour bearing steel truss structure of the lifting of large-scale steel structure, especially large span compared with It is high.The common construction method of large span space steel truss has at present:Assembly in pieces at height, slitting piecemeal lift-on/lift-off system, integral hoisting Method, integrated lifting, Integral Lifting, Pantadome methods, folding and expanding Method for Installation etc..When construction hoist lifting is in place tired Difficulty, construction hoist job area is relatively narrow, and assembled floor space is by prescribing a time limit, for the not contour bearing steel truss structure of large span Lifting with regard to extremely difficult, and Lift-on/Lift-off System in the prior art not can solve the problem.
Invention content
It can solve the problems, such as that construction hoist lifting is in place difficult the present invention provides a kind of, reduce hoisting machinery grade Threshold and energy consumption reduce preassembling floor space while can reduce the deformation of member, improve structure global formation quality it is big across The not contour bearing steel truss structure hoisting slide construction of degree.
The present invention in order to solve the above problem used by large span contour bearing steel truss structure hoisting slide is not constructed work Method, including following steps:
A, bearing, mounting slip equipment and incremental launching device are set on steel truss;
B, entire seat steel truss structure is divided into multiple Pin, ready-portioned Pin assembly is molded on ground, is set with lifting Standby hang steel truss rises to specified altitude assignment, hangs rise a Pin every time, after hang the Pin for being raised to position and hung before it and be raised to position Pin spliced, when a certain Pin is when hanging lift from fixed-point installation job area more than hanging device, then set using sliding Standby and incremental launching device vacates the sky in hanging device job area to having hung the Pin for rising to specified altitude assignment before into line slip Between after, then hung with hanging device and rise the Pin steel truss to designated position;
C, after the completion of all slip operations, bearing is disassembled from steel truss.
Further, in construction, first workshop both ends by among steel truss the Pin at position hang and be raised to specified height After degree, both ends is allowed to hang the Pin for being raised to position simultaneously to centre sliding, after vacating the space in hanging device job area, then in cunning It moves structure (13) both ends to hang Pin adjacent thereto and is raised to position and therewith splices, then by spliced steel truss from workshop two Hold to centre and slide, vacate the space in hanging device job area, repeat aforementioned both ends hang liter, splicing, the process of sliding it is straight It is hung to all Pin and is raised to position and is spliced into complete steel truss.
Further, the mechanical simulation for carrying out slipping to steel truss before construction is analyzed, calculate in slipping Structure stress most weak spot and the maximum asynchronous permissible value of sliding, reinforce part not up to standard in analysis result, in cunning Asynchronous amount is controlled during moving is no more than asynchronous permissible value.
Further, to two across mid-span deflection variations of steel truss, rod piece stress variation and each in slipping The synchronism of bearing sliding is monitored.
Further, the pushing tow pressure and stroke to incremental launching device are monitored.
Further, used slip device includes sliding rail and piston shoes, cunning is provided on the sliding rail The lower part of slot, the piston shoes is embedded in sliding slot, and the top of the piston shoes is fixedly connected with slip support abutment, and used pushing tow is set Standby includes sliding pusher and hydraulic pressure output system, and the sliding pusher includes holding device and hydraulic cylinder, described to hold out against dress It sets on sliding rail, described hydraulic cylinder one end is hinged with holding device, and the other end is provided with hingedly to be connect by selection structure Mouthful, the hydraulic pressure output system includes hydraulic pump, fuel tank, fluid pressure line, and the import of the hydraulic pump is connected to fuel tank, described The outlet of hydraulic pump is connected to by fluid pressure line with hydraulic cylinder.
Further, used sliding pusher is multiple, it is parallel between hydraulic pump and hydraulic cylinder and hydraulic pressure The identical hydraulicdirectional control valve of cylinder quantity, a hydraulicdirectional control valve correspond to a hydraulic cylinder, in the outlet of each hydraulicdirectional control valve and its It is provided with holding overflow valve between corresponding hydraulic cylinder.
Further, the piston shoes include structural bearings shear key and the sole in structural bearings shear key lower part are arranged Plate, the tablet that the structural bearings shear key is vertically arranged by three pieces form, and the sole plate is along vertical with three pieces of tablets Direction setting, the sole front edge of board is the arc being upturned, and the both sides of sole plate be provided with arc fall Angle.
Further, being additionally provided with side block blocks on the outside of the sliding rail.
Further, removing column cap both sides channel steel first in step C, then installation unloading bracket and jack will prop up Seat jack up certain altitude, remove pre-embedded steel slab under abutment segment channel steel and channel steel again later, then clear up shearing resistance hole in sandstone and its His sundries, last unloading support seat make it fall into shearing resistance hole.
The beneficial effects of the invention are as follows:Using the sliding construction engineering method of the application, the side for being segmented whole Pin liftings may be used Each component is first assembled into whole Pin on ground, significantly reduces high-altitude installation exercise amount by formula.It is used in slipping The mode of pushing tow keeps sliding steady and controllable, can effectively ensure that stability and the safety of whole installation process.Utilize this The sliding construction engineering method of application, is constructed by hoisting slide, can reduce hoisting machinery grade threshold and energy consumption and integral hoisting It compares, reduce preassembling floor space while the deformation of member can be reduced, improve splicing precision, improve structure global formation matter Amount, and can minimize and be interfered with each other with cross-operation such as civil engineerings, it is conducive to promote concurrent construction, is not necessarily to concrete knot The expense that structure is reinforced increases only slip device and track expenditure, even if in narrow space, the limited feelings of lifting equipment walking The lifting of the not contour bearing steel truss structure of large span can also be completed under condition.
Description of the drawings
Fig. 1 is the structural schematic diagram of the present invention;
Fig. 2 is the schematic diagram of Sliding Structures of the present invention;
Fig. 3 is the structural schematic diagram of piston shoes of the present invention;
Fig. 4 is the structural schematic diagram of pushing tow system of the present invention;
In figure label for:It is sliding rail 1, piston shoes 2, structural bearings shear key 3, sole plate 4, chamfering 5, side block blocks 6, pre- Embedded part 7, holding device 8, hydraulic cylinder 9, connection otic placode 10, steel truss support 11, lifting equipment 12, Sliding Structures 13.
Specific implementation mode
The invention will be further described below in conjunction with the accompanying drawings.
The not contour bearing steel truss structure hoisting slide construction of large span as shown in Figure 1, Figure 2, Figure 3, Figure 4, packet Include following steps:
A, bearing, mounting slip equipment and incremental launching device are set on steel truss;
B, entire seat steel truss structure is divided into multiple Pin, ready-portioned Pin assembly is molded on ground, is set with lifting Standby hang steel truss rises to specified altitude assignment, hangs rise a Pin every time, after hang the Pin for being raised to position and hung before it and be raised to position Pin spliced, when a certain Pin is when hanging lift from fixed-point installation job area more than hanging device, then set using sliding Standby and incremental launching device vacates the sky in hanging device job area to having hung the Pin for rising to specified altitude assignment before into line slip Between after, then hung with hanging device and rise the Pin steel truss to designated position;
C, after the completion of all slip operations, bearing is disassembled from steel truss.
Using the sliding construction engineering method of the application, the mode for being segmented whole Pin liftings may be used, first on ground by each structure Part is assembled into whole Pin, significantly reduces high-altitude installation exercise amount.In slipping by the way of pushing tow, keep sliding flat It is steady and controllable, it can effectively ensure that stability and the safety of whole installation process.Using the sliding construction engineering method of the application, It is constructed by hoisting slide, hoisting machinery grade threshold and energy consumption can be reduced, compared with integral hoisting, reduced preassembling and take up an area Area while the deformation of member can be reduced, improve splicing precision, improve structure global formation quality, and can minimize with The cross-operation such as civil engineering interfere with each other, and are conducive to promote concurrent construction, the expense without concrete structure reinforcement, increase only Slip device and track expenditure, even if large span can also be completed in the case where the walking of narrow space lifting equipment 12 is limited The lifting of not contour bearing steel truss structure.
In construction, first both ends after the Pin at position hangs and is raised to specified altitude assignment among steel truss, will be allowed at workshop both ends It hangs the Pin for being raised to position while being slid to centre, after vacating the space in hanging device job area, then will at Sliding Structures both ends Pin adjacent thereto, which is hung, to be raised to position and splices therewith, is then slid spliced steel truss from workshop both ends to centre, is vacated Space in hanging device job area, repeat aforementioned both ends hang liter, splicing, sliding process be raised to until all Pin are hung Position is simultaneously spliced into complete steel truss.Using the construction method of aforementioned segmentation accumulation slippage, sliding difficulty is not only reduced, also Construction efficiency can be effectively improved, the precision of spicing forming type is improved;Sliding velocity is controllable and efficient, up to 12m/h.By two The lifting equipment 12 of setting is held to organize to lift simultaneously, truss is doubled from both ends to median cumulative sliding velocity, and in work progress Lower part synchronization job is not influenced, shortens the duration, improves working efficiency.
The mechanical simulation that slipping is carried out to steel truss before construction is analyzed, and it is most thin to calculate structure stress in slipping Weakness and the maximum asynchronous permissible value of sliding, reinforce part not up to standard in analysis result, are controlled in slipping Asynchronous amount is no more than asynchronous permissible value.When due to analysis Steel Structural Design based on dead load and design load, do not fill Divide and consider whether the effect of the stress in installation process under different operating modes is more than material mechanical performance limit value, to determine whether to need The tie element that bearing capacity requirement is not achieved in former design is replaced, and can be arranged in slipping not according to analysis result The early warning value of synchronous amount.
To two across mid-span deflection variations, rod piece stress variation and each steel truss support 11 of steel truss in slipping The synchronism of sliding is monitored.Since the slipping of the application is a Pin or more truss structures into line slip, slipping Steel truss stressing conditions are complicated, cause the nonsynchronous factor of steel truss integral slipping also very much, and each steel truss support 11 Designed elevation also differs, and to ensure the quality of steel truss after lifting, steel truss is avoided to be damaged in slipping, this Application is monitored its slipping.Even if but how to monitor simultaneously accurately could find to protect steel truss in slipping There is damaged trend, carry out and take corresponding safeguard measure, is the problem of sliding construction.To this application from mid-span deflection Three aspects of synchronism that variation, rod piece stress variation and each steel truss support 11 slide are simultaneously to the steel in slipping Truss is monitored, and has taken into account displacement output, and whole amount of deflection changes, synchronous with steel truss that part stress variation is reflected Property, it ensure that monitoring ground promptness, reliability, accuracy and comprehensive.The survey of roof truss span centre lower edge is mainly monitored when specific implementation Point position, the height difference variation according to total powerstation in the construction process, calculates the situation of change of measuring point degree of disturbing.Pass through The strain of the main control rod piece of monitoring, then calculates according to stress and strain relationship, and the elasticity modulus of construction material is it is known that logical The measurement of overstrain variation, it is known that the variation of rod piece stress.The change of total powerstation and creep setpoint can be monitored by observing total powerstation Change, weigh the synchronism in slipping, putting down for each measuring point is consistent away from variation, it was demonstrated that synchronism is preferable, otherwise is poor.It is right The abnormal conditions occurred in monitoring, such as significant asynchrony phenomenon, excessive stress, structural deflection, which are more than, to be calculated deformation, goes out The now big sound, support deforms or local vibration etc. occurs in structure, is fed back immediately into row information, takes corresponding emergent Measure is handled.
In slipping, the pushing tow pressure and stroke of incremental launching device are monitored.By to pushing tow pressure and stroke The detection and analysis of variation can quickly learn that some pushing tow point whether occur during pushing tow " clamp rail " occurs or " gnaw Whether the displacement of rail ", each pushing tow point synchronizes, and case above can be fed back to control system, control system control top Equipment adjustment pushing tow parameter is pushed away, is damaged to avoid to steel truss.
Used slip device includes sliding rail 1 and piston shoes 2, and sliding slot, the cunning are provided on the sliding rail 1 In the lower part insertion sliding slot of boots 2, the top of the piston shoes 2 is fixedly connected with slip support abutment, and used incremental launching device includes sliding Pusher and hydraulic pressure output system are moved, the sliding pusher includes holding device 8 and hydraulic cylinder 9, and the holding device 8 is pacified On sliding rail 1,9 one end of the hydraulic cylinder is hinged with holding device 8, and the other end is provided with by selection structure hinged interface, The hydraulic pressure output system includes hydraulic pump, fuel tank, fluid pressure line, and the import of the hydraulic pump is connected to fuel tank, the hydraulic pressure The outlet of pump is connected to by fluid pressure line with hydraulic cylinder 9.The application drives steel truss support 11 to slide using hydraulic cylinder 9, hydraulic pressure It can be coordinated using Sliding Structures and piston shoes 2 by connection otic placode 10 and pin connection between cylinder and steel truss support, constraint sliding Bearing keeps slipping safe, steady, accurate, reliable along 1 accurate movement of sliding rail.
Used sliding pusher is multiple, is parallel between hydraulic pump and hydraulic cylinder 9 identical as 9 quantity of hydraulic cylinder Hydraulicdirectional control valve, hydraulicdirectional control valve corresponds to a hydraulic cylinder 9, corresponding to the outlet of each hydraulicdirectional control valve and its It is provided with holding overflow valve between hydraulic cylinder 9.The application uses the form of multiple hydraulicdirectional control valves parallel connection, each hydraulic pressure commutation Valve all one hydraulic cylinders 9 of independent control, do not interfere between each other, and synchronous push may be implemented, and improve sliding precision.To every The maximum jacking force of platform sliding pusher is set, and when encountering jacking force beyond setting value, sliding pusher is taken automatically Overflow pressurize, can effectively prevent occurring that the distribution of pushing tow point loading is serious uneven is damaged to steel construction.
The piston shoes 2 include the anti-shearing key 3 of structural bearings and the sole plate 4 in anti-shearing 3 lower part of key of structural bearings are arranged, The tablet that the anti-shearing key of the structural bearings 3 is vertically arranged by three pieces forms, and the sole plate 4 hangs down along with three pieces of tablets Straight direction setting, 4 front end of sole plate is the arc being upturned, and the both sides of sole plate 4 are provided with arc Chamfering 5.The piston shoes 2 of the application Sliding Structures are ingenious to utilize the anti-shearing key 3 of structural bearings, increases sole in the lower part of shear key Plate 4, makes being uniformly distributed for compression on piston shoes 2 and sliding rail contact surface, and globality is strong, Path of Force Transfer clear and definite, bearing capacity It is high.In addition, the application is also the arc that front end use is upturned in the direction of 4 front end piston shoes 2 of sole plate movement, and The both sides of sole plate 4 are provided with the chamfering 5 of arc, reduce the contact of piston shoes 2 front end and sliding rail 1, make it in slipping In, it can be effectively prevent the phenomenon that slip support abutment is because of slideway out-of-flatness " clamp rail " and " gnawing rail ", effectively solve steel truss sliding not Synchronous situation.
The outside of the sliding rail 1 is additionally provided with side block blocks 6.The application is also additionally provided in the outside of sliding rail 1 Side block blocks 6 make it play and resist slip support abutment thrust and horizontal force action, make the overall stiffness and bearing capacity of sliding rail 1 All it is greatly improved.
Remove column cap both sides channel steel first in step C, then installation unloads bracket and jack by steel truss support 11 Certain altitude is jacked up, removes pre-embedded steel slab under 11 sections of channel steels of steel truss support and channel steel again later, is then cleared up husky in shearing resistance hole Stone and other sundries, finally unloading steel truss support 11 makes it fall into shearing resistance hole.Shearing resistance is arranged in the application below slip support abutment Embedded board is arranged on shearing resistance hole top in hole, and embedded board covers shearing resistance hole in slipping, and piston shoes 2 can be cheated smoothly from shearing resistance Top passes through, and after the sliding in place of all units, then pre-embedded steel slab is taken out, dismantles slip support abutment, slip support abutment is made smoothly to fall into In shearing resistance hole.Using aforementioned form of construction work, fallen directly into shearing resistance hole after sliding support dismounting, therefore easy to operate, safety Height, since shearing resistance hole is located at ground level hereinafter, therefore saving place, convenient for construction.
The engineering method of the present invention is more suitable for cross-operation work post, truss span 90-120m, Pin number 40-50 Pin, skidding distance 400-500m, sliding weight 5000-6000t, sliding rail 1 are not applied at the scene of the steel truss roof structure of same level absolute altitude Work, especially narrow space, duration anxiety, large lifting equipment 12 can not cover whole working regions or use other construction parties When method construction economy is ineffective, it can be solved the problems, such as using this method.
Embodiment 1
Preparation of construction:
One, the selection of equipment and arrangement.According to the dead weight of steel truss and size, in conjunction with 12 situation of market lifting equipment and conjunction Same cost requirement determines the model and quantity of lifting equipment 12.According to the dead weight of steel truss and size, the steel that need to be slid is calculated The quality and the frictional force in slipping of truss select hydraulic pushing equipment, hydraulic pump source equipment, computer synchronous control And the model of sensing and detecting system, determine the arrangement and slip scheme of pushing tow point.In slipping, what pusher was applied Frictional force F between thrust and all piston shoes 2 and sliding rail reaches balance.By Calculation and Analysis of Force, certainly due to intermediate orbit sliding Weight is larger, so intermediate orbit arranges a pushing tow point every two truss structures.
Two, structural calculation and design
Using finite element analysis software ANSYS or MIDAS, actual loading situation is simulated, establishes three-dimensional simulation model simulation Sliding construction process calculates structure stress most weak spot and the maximum asynchronous permissible value of sliding in slipping.Analyze steel construction When design based on dead load and design load, the work of the mount stress in installation process under different operating modes is not fully considered With whether more than material mechanical performance limit value;To determine the need for replacing the company that bearing capacity requirement is not achieved in former design The early warning value of asynchronous amount in slipping is arranged in tie-rod part.
Three, Ground arrangement and basement process requirement
Assembled moulding bed is set up:Because roof truss needs whole Pin setting-outs, place space should be met the requirements.To meet foundation bearing capacity, palpus Grinding compacting is smooth and pours 10cm bed courses, and I-steel of arranging thereon puts truss loose mail above moulding bed, mats formation as moulding bed Girder steel etc., as sample placement platform.
The requirement of crawler crane walking passageway:Straight section walking width 8m, and both sides are cheated without big hole side;Turn width 12m;Ground Base bearing capacity >=0.2Mpa, road grade≤3 ‰.
Crawler crane walking, hoisting passage bearing pressure of foundation it is necessary >=0.2Mpa;Basement process must be carried out if it cannot meet.
Four, mounting slip interim measures
3 groups of elongated sliding rails 1 are arranged in structure sliding construction altogether, are respectively arranged at two ends and the center of structure.It is sliding 1 center line of track is moved to overlap with bearing center line.Track is made of 16b channel steels and side block blocks 6.16b channel steels are welded with built-in fitting 7 Fixation is connect, load-bearing and guiding role are played in slipping.6 specification of side block blocks is 20 × 40 × 150mm, material Q235B, weldering 16b channel steels edge of a wing both sides are connected on, plays and resists slip support abutment thrust and horizontal force action.6 weld seam of side block blocks uses dihedral angle Weld seam, by welding seam calculating, foot welding height is not less than 10mm.
To ensure the levelness of slideway inner surface, reduces the obstruction in slipping, reduces the coefficient of sliding friction, slideway exists When laying, it should accomplish:Improve mass intensity, rigidity and the flatness of slide rail section, the stringent height for controlling track section joint Difference is within the scope of tolerance 1mm, it is ensured that levelling pad and reach can after necessary intensity requirement for back-grouting below track Implement sliding;1 center line of sliding rail should be controlled with sliding disalignment within ± 3mm;Steel slide block and sliding rail 1 Upper surface should answer coating butter to lubricate before sliding;Slideway side block blocks 6 are played directly against pushing reaction and sliding precision control The effect of system, therefore during the installation process it should be noted that the following aspects:To ensure between slideway side block blocks 6 and pushing tow bearing There are enough contact surfaces, the setting form of slideway side shield that should be installed in strict accordance with layout design pattern;Slideway side block blocks 6 with The weld bead height of sliding rail 1 should meet design requirement, to meet the requirement for resisting pushing reaction;On all sliding rails 1 The starting installation site of side block blocks 6 should be at same axial location, and resets starting point at every axial location, with Reduce installation accumulated error, meets the requirement of sliding synchronization;6 installation error of side block blocks of same sliding beam both sides should be less than The interval error of 1mm, adjacent slideway side block blocks 6 should be less than 3mm;6 front sliding direction of advance of side block blocks is forbidden to weld.
Five, component assembly
H steel is put above 50 ㎜ bed courses of assembled place channel both sides as truss preassembling moulding bed.It is adopted on H steel moulding beds With lower edge on the high-strength bolt assembly truss of M24 × 100, and unwrapping wire positions on upper lower edge, while marking web member Position position line.On truss after lower edge positioning, vertical web rod is assembled.After assembled vertical web rod is completed, diagonal web member is assembled.One is whole After truss structure rod piece assembly is completed, horizontal, vertical, diagonal line checks the geometric dimension of truss comprehensively, and is welded on moulding bed Baffle prevents displacement, then starts to be symmetrically welded.All welding is completed for all downhand welds in the first face of truss and all cross joints After, the downhand weld of the lower one side of turn-over welding.Entire all weld seams of truss are after all welding is completed, check again it is horizontal, Perpendicular, diagonal line checks the geometric dimension of truss comprehensively, meets design and code requirement, is fixed, as the assembly of truss below Mold, the first truss structure is motionless after being fully completed, behind truss it is assembled on the first truss structure respectively, repeat front 7 A step.The second assembled truss structure is completed above the same moulding bed be divided into five sections to disassemble, carry out benefit priming, spraying Fireproof coating.Fireproof coating application is divided into five sections after completing, and is transported to end lifting region using flat car.It is divided into five sections It is transported to the lifting region of end using flat car, uses high-strength bolt the whole purlins Pin as assembling jig frame using H steel Frame assembles, and crawler crane is waited for lift to roofing.
Six, lifting component:
Steel Truss Beam lifting before reply steel wire rope construction and type, the position of suspension centre, foundation bearing capacity, lifting radius into Row review checking computations.
Steel roof truss lifts the condition that should have:No-sundries, center line are answered to finish on roof truss installation buttress, size has been checked and accepted It finishes.Tool, rigging needed for lifting transport scene to, for use after passed examination.There is a batch experienced, there is steel construction peace The operating personnel of dress experience.The bad weathers such as non-sleet mist, wind-force is below level Four.On ground, assembling should meet company to steel roof truss Continuous lifting condition.
Hoisting Program:
This Steel Truss Beam lifting construction disposes a work surface respectively in two ends.It is sketched by taking wherein one end as an example:
The first step:First Pin steel truss should be hung to the position away from one axis in end, it is contemplated that the bearing capacity of lifting machine Problem can not achieve whole Pin liftings, so being divided into three sections, by 200t crawler crane complete independentlies;
Second step:After the lifting of first truss structure is in place, installation cable wind rope is fixed;
Third walks:Crawler crane is walked respectively arrives double-machine lifting crane position;
4th step:The 2nd Pin entirety truss of double-machine lifting crane, 200t crawler cranes move back 6m to designated position, with 150t crawler belts It hangs one and at first completes integral assembling, then double-machine lifting crane;
5th step:After the lifting of second truss structure is in place, installation cable wind rope is fixed;
6th step:It lifts and the primary-secondary beam and girder between the first and second truss structure is installed;
7th step:The whole length for sliding a wheelbase forward of unit, reserves the installation site of the 3rd Pin Steel Truss Beams;It is assorted In the case of advanced line slip, then lift;
8th step:The 3rd Pin is lifted, lifts primary-secondary beam and girder after the completion;
9th step:Follow-up beam installation is same as above, until installing last Pin.
It is segmented accumulation slippage:
Each pushing tow spot speed is set to remain a constant speed, synchronize in hydraulic synchronization thrusting slip operation process as possible.It divides a structure into Two sliding subregions, it is assembled to carry out accumulation by cross, utilize " hydraulic synchronization thrusting slip " system by structure accumulation slippage in place.
Steps are as follows for sliding:
The first step:First and second truss structure and between the structures installation such as linking beam it is in place after;
Second step:To assembled one vehicle wheel base length of the first and second truss structure completed of intermediate direction sliding, after sliding in place Pause;
Third walks:Track flatness is checked and adjusted, is ready for the sliding of next truss structure;
4th step:Lifting next truss structure in place, on assembled moulding bed respectively the lower truss structure of assembled axis and between link Girder construction;
5th step:As soon as to the first, second and third truss structure vehicle wheel base length of intermediate direction sliding assembled completion, sliding Suspend behind position;
6th step:Track flatness is checked and adjusted, is ready for the sliding of next truss structure;
7th step:It repeats the above steps and completes the assembly and sliding of all truss;
Slide points for attention:
The synchronism monitoring for reinforcing slipping, should be arranged the asynchronous early warning value of sliding, ensure in slipping as possible not Synchronization value is no more than 30cm.
When meeting with clamp rail in slipping or gnawing the obstacles such as rail, the interim card that should stop checks reason, avoids sliding by force as possible It moves, is further continued for sliding after the completion of correction to be adjusted.
When accumulation slippage Pin numbers are few, since the rigidity of structure is smaller, inside is more prone to different step displacements, therefore early period is slided It moves and emphasis is answered to reinforce the monitoring connected to the component purlin of longitudinal direction, linking beam, support and its roof truss.It should make each axis of an orbit The end reaction jacking force of line is as consistent as possible, is convenient for Construction control.
Seven, it drops in place
After whole complete sliding in place of unit, truss drops that in place steps are as follows:
The first step:After being slid onto design position, column cap both sides 5000mm and 4000mm channel steel is removed first.
Second step:Bearing is jacked up 10mm by installation unloading bracket and jack;
Third walks:Pre-embedded steel slab under abutment segment 600mm channel steels and channel steel is removed, it can be by steel plate and slot for convenience of steel plate is taken out Steel spot welding;
4th step:Clear up sandstone and other sundries in shearing resistance hole;
5th step:It executes unloading scheme and bearing is fallen into shearing resistance hole.
Eight, monitoring analysis
In order to grasp the stress and deformation state of structural elements in slipping, it is ensured that construction safety understands sliding in time Emergency situations and reduce its influence in the process, it is proposed that monitored over time or the monitoring of partial slip section are carried out in slipping.Monitoring Content includes mainly:The synchronism monitorings of each piston shoes 2, the stress monitoring of truss portion rod piece, part linking beam or purlin are answered Power monitoring, the stress monitoring of crucial connecting portion and truss across interior deflection monitoring etc..For the exception occurred in monitoring Situation, such as significant asynchrony phenomenon, excessive stress, structural deflection, which are more than, to be calculated deformation, the big sound, support hair occurs There is local vibration etc. in the shape that changes or structure, are fed back immediately into row information, corresponding emergency measure is taken to be handled.
Monitoring and warning index see the table below shown:
Monitoring and warning index

Claims (10)

1. the not contour bearing steel truss structure hoisting slide construction of large span, it is characterised in that:Including following steps:
A, bearing, mounting slip equipment and incremental launching device are set on steel truss;
B, entire seat steel truss structure is divided into multiple Pin, is molded ready-portioned Pin assembly on ground, it will with hanging device Steel truss, which is hung, rises to specified altitude assignment, hang every time rise a Pin, after hang be raised to position Pin and hung the Pin for being raised to position before it Spliced, when a certain Pin is when hanging lift from fixed-point installation job area more than hanging device, then utilize slip device and Incremental launching device to having hung the Pin for rising to specified altitude assignment into line slip before, after vacating the space in hanging device job area, It is hung again with hanging device and rises the Pin steel truss to designated position;
C, after the completion of all slip operations, bearing is disassembled from steel truss.
2. the not contour bearing steel truss structure hoisting slide construction of large span as described in claim 1, it is characterised in that: In construction, first allows both ends to hang after the Pin at position hangs and is raised to specified altitude assignment among steel truss at workshop both ends and be raised to position Pin slid simultaneously to centre, after vacating the space in hanging device job area, then will therewith at Sliding Structures (13) both ends Adjacent Pin, which is hung, to be raised to position and splices therewith, is then slid spliced steel truss from workshop both ends to centre, is vacated lifting Space within the scope of equipment operation, repeat aforementioned both ends hang liter, splicing, sliding process be raised to position until all Pin are hung and spell It is connected into complete steel truss.
3. the not contour bearing steel truss structure hoisting slide construction of large span as described in claim 1, it is characterised in that: The mechanical simulation that slipping is carried out to steel truss before construction is analyzed, and structure stress most weak spot and cunning in slipping are calculated Maximum asynchronous permissible value is moved, part not up to standard in analysis result is reinforced, asynchronous amount is controlled in slipping No more than asynchronous permissible value.
4. the not contour bearing steel truss structure hoisting slide construction of large span as described in claim 1, it is characterised in that: The synchronism of two across mid-span deflection variations of steel truss, rod piece stress variation and each bearing sliding is carried out in slipping Monitoring.
5. the not contour bearing steel truss structure hoisting slide construction of large span as described in claim 1, it is characterised in that: In slipping, the pushing tow pressure and stroke of incremental launching device are monitored, the pushing tow pressure and stroke to incremental launching device into Row monitoring.
6. the not contour bearing steel truss structure hoisting slide construction of large span as described in claim 1, it is characterised in that: Used slip device includes sliding rail (1) and piston shoes (2), and sliding slot, the piston shoes are provided on the sliding rail (1) (2) in lower part insertion sliding slot, the top of the piston shoes (2) is fixedly connected with slip support abutment, and used incremental launching device includes Slide pusher and hydraulic pressure output system, the sliding pusher includes holding device (8) and hydraulic cylinder (9), described to hold out against dress (8) are set on sliding rail (1), described hydraulic cylinder (9) one end is hinged with holding device (8), and the other end is provided with and is pushed away Structure hinged interface, the hydraulic pressure output system include hydraulic pump, fuel tank, fluid pressure line, the import of the hydraulic pump and fuel tank Connection, the outlet of the hydraulic pump is connected to by fluid pressure line with hydraulic cylinder (9).
7. the not contour bearing steel truss structure hoisting slide construction of large span as claimed in claim 6, it is characterised in that: Used sliding pusher is multiple, and liquid identical with hydraulic cylinder (9) quantity is parallel between hydraulic pump and hydraulic cylinder (9) Reversal valve, a hydraulicdirectional control valve is pressed to correspond to a hydraulic cylinder (9), in the outlet of each hydraulicdirectional control valve and the hydraulic pressure corresponding to it Cylinder is provided with holding overflow valve between (9).
8. the not contour bearing steel truss structure hoisting slide construction of large span as claimed in claim 6, it is characterised in that: The piston shoes (2) include the sole plate (4) of the anti-shearing key of structural bearings (3) and setting in the anti-shearing key of structural bearings (3) lower part, The tablet that the anti-shearing key of structural bearings (3) is vertically arranged by three pieces forms, and the sole plate (4) is along equal with three pieces of tablets Vertical direction setting, sole plate (4) front end is the arc being upturned, and is provided in the both sides of sole plate (4) The chamfering (5) of arc.
9. the not contour bearing steel truss structure hoisting slide construction of large span as claimed in claim 6, it is characterised in that: It is additionally provided with side block blocks (6) on the outside of the sliding rail (1).
10. the not contour bearing steel truss structure hoisting slide construction of large span as described in claim 1, feature exist In:Remove column cap both sides channel steel first in step C, then bearing is jacked up certain altitude by installation unloading bracket and jack, It removes pre-embedded steel slab under abutment segment channel steel and channel steel again later, then clears up sandstone and other sundries in shearing resistance hole, finally unload Bearing makes it fall into shearing resistance hole.
CN201810201269.4A 2018-03-12 2018-03-12 Hoisting and sliding construction method for large-span unequal-height support steel truss structure Active CN108468430B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810201269.4A CN108468430B (en) 2018-03-12 2018-03-12 Hoisting and sliding construction method for large-span unequal-height support steel truss structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810201269.4A CN108468430B (en) 2018-03-12 2018-03-12 Hoisting and sliding construction method for large-span unequal-height support steel truss structure

Publications (2)

Publication Number Publication Date
CN108468430A true CN108468430A (en) 2018-08-31
CN108468430B CN108468430B (en) 2021-02-05

Family

ID=63264274

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810201269.4A Active CN108468430B (en) 2018-03-12 2018-03-12 Hoisting and sliding construction method for large-span unequal-height support steel truss structure

Country Status (1)

Country Link
CN (1) CN108468430B (en)

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842638A (en) * 2018-09-03 2018-11-20 江苏省建筑工程集团有限公司 Steel pipe truss beam orbit formula moulding bed limit assembly, cluster lifting jack unloading engineering method
CN109138425A (en) * 2018-09-27 2019-01-04 浙江精工钢结构集团有限公司 A kind of anti-certainly sliding construction equipment and its method tilted in sliding construction from top to bottom
CN109281479A (en) * 2018-09-12 2019-01-29 北京市机械施工有限公司 A kind of gliding construction method of large span Stretching chord arch shape steel structure truss
CN109487912A (en) * 2018-11-30 2019-03-19 北京市建筑工程研究院有限责任公司 A kind of construction method of super-span truss-string-structure
CN109537914A (en) * 2018-11-30 2019-03-29 上海宝冶集团有限公司 Multiple groups self-traveling module transportation vehicle runs simultaneously control method
CN109764844A (en) * 2019-02-14 2019-05-17 中国建筑科学研究院有限公司 Building track slippage monitoring method
CN109779269A (en) * 2019-03-21 2019-05-21 中冶建工集团有限公司 Large-span truss segmental hoisting high-altitude closes up measure device and construction method
CN109812024A (en) * 2019-02-16 2019-05-28 中建一局集团第一建筑有限公司 A kind of high-altitude inclination angle across truss greatly is from anchor accumulation slippage construction method
CN109812023A (en) * 2019-02-16 2019-05-28 中建一局集团第一建筑有限公司 A kind of truss sections accumulation lifting construction method of ladder work surface
CN110439297A (en) * 2019-08-13 2019-11-12 上海宝冶集团南京建筑有限公司 One kind is for monolithic large span steel truss overturning lifting device and its construction method
CN111779274A (en) * 2020-07-10 2020-10-16 广州协安建设工程有限公司 Construction method for integrally lifting temporary hoisting point of large-span unequal-height steel structure net rack
CN111980420A (en) * 2020-08-11 2020-11-24 上海隧道工程有限公司 Steel truss pushing equipment and pushing method thereof
CN112049433A (en) * 2020-08-11 2020-12-08 上海隧道工程有限公司 Steel truss pushing attitude control equipment and attitude control method thereof
CN112267690A (en) * 2020-09-24 2021-01-26 中建四局第六建设有限公司 Large-span box-type steel beam sliding installation construction process and device
CN112878696A (en) * 2019-11-29 2021-06-01 中冶(上海)钢结构科技有限公司 Early warning system of out-of-plane instability in sliding construction of inverted-triangle truss type roof
CN113323405A (en) * 2021-06-10 2021-08-31 中国建筑第八工程局有限公司 Sliding construction method applied to large-span steel structure
WO2021174481A1 (en) * 2020-03-05 2021-09-10 广州建筑股份有限公司 Construction method for accumulative sliding of single-side subsection orbital transfer of unequal-span structure
CN113565332A (en) * 2021-09-08 2021-10-29 中建八局第二建设有限公司 Roof steel structure and air pipe synchronous sliding construction method
CN114687565A (en) * 2022-04-26 2022-07-01 中国建筑第七工程局有限公司 Construction method for splicing, sliding and lifting large-span steel beam at high altitude
CN114737808A (en) * 2022-03-24 2022-07-12 山东电力工程咨询院有限公司 Construction method of super-large-span dry coal shed grid structure
CN115046660A (en) * 2022-05-06 2022-09-13 中铁广州工程局集团有限公司 System and method for monitoring stress of suspension platform in real time based on BIM (building information modeling)
CN115324363A (en) * 2022-08-16 2022-11-11 北京首钢建设集团有限公司 N-point supporting and sliding method for multiple slideways of super-large span prestressed pipe truss
CN115478699A (en) * 2022-10-31 2022-12-16 中国建筑一局(集团)有限公司 Roof truss steel structure sliding installation method
CN116905817A (en) * 2023-09-12 2023-10-20 北京城建集团有限责任公司 Large-scale steel roof efficient accumulation sliding construction method with limited construction field

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202969960U (en) * 2012-10-29 2013-06-05 五冶集团上海有限公司 Sliding shoe for steel structure with anti-shear key arranged at bottom of steel column
CN103806658A (en) * 2012-11-14 2014-05-21 五冶集团上海有限公司 Whole high-cleanliness electronic plant steel structure slippage and detachment method
CN204728720U (en) * 2015-06-08 2015-10-28 浙江精工钢结构集团有限公司 A kind of single Pin sliding assembly of inverted triangle truss
CN105113693A (en) * 2015-07-07 2015-12-02 江苏沪宁钢机股份有限公司 Slope roof truss slide composition and construction method thereof
CN105421771A (en) * 2015-09-30 2016-03-23 浙江精工钢结构集团有限公司 Accumulated slip construction method for unequal-elevation string truss with columns

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202969960U (en) * 2012-10-29 2013-06-05 五冶集团上海有限公司 Sliding shoe for steel structure with anti-shear key arranged at bottom of steel column
CN103806658A (en) * 2012-11-14 2014-05-21 五冶集团上海有限公司 Whole high-cleanliness electronic plant steel structure slippage and detachment method
CN204728720U (en) * 2015-06-08 2015-10-28 浙江精工钢结构集团有限公司 A kind of single Pin sliding assembly of inverted triangle truss
CN105113693A (en) * 2015-07-07 2015-12-02 江苏沪宁钢机股份有限公司 Slope roof truss slide composition and construction method thereof
CN105421771A (en) * 2015-09-30 2016-03-23 浙江精工钢结构集团有限公司 Accumulated slip construction method for unequal-elevation string truss with columns

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨向阳: "不等高张弦三角管桁架带柱累积滑移施工技术", 《施工技术》 *

Cited By (31)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108842638A (en) * 2018-09-03 2018-11-20 江苏省建筑工程集团有限公司 Steel pipe truss beam orbit formula moulding bed limit assembly, cluster lifting jack unloading engineering method
CN109281479A (en) * 2018-09-12 2019-01-29 北京市机械施工有限公司 A kind of gliding construction method of large span Stretching chord arch shape steel structure truss
CN109281479B (en) * 2018-09-12 2021-04-23 北京市机械施工有限公司 Slippage construction method of large-span chord-span arched steel structure truss
CN109138425A (en) * 2018-09-27 2019-01-04 浙江精工钢结构集团有限公司 A kind of anti-certainly sliding construction equipment and its method tilted in sliding construction from top to bottom
CN109487912A (en) * 2018-11-30 2019-03-19 北京市建筑工程研究院有限责任公司 A kind of construction method of super-span truss-string-structure
CN109537914A (en) * 2018-11-30 2019-03-29 上海宝冶集团有限公司 Multiple groups self-traveling module transportation vehicle runs simultaneously control method
CN109764844A (en) * 2019-02-14 2019-05-17 中国建筑科学研究院有限公司 Building track slippage monitoring method
CN109812024A (en) * 2019-02-16 2019-05-28 中建一局集团第一建筑有限公司 A kind of high-altitude inclination angle across truss greatly is from anchor accumulation slippage construction method
CN109812023A (en) * 2019-02-16 2019-05-28 中建一局集团第一建筑有限公司 A kind of truss sections accumulation lifting construction method of ladder work surface
CN109779269B (en) * 2019-03-21 2024-02-09 中冶建工集团有限公司 Large-span truss sectional hoisting high-altitude folding measure device and construction method
CN109779269A (en) * 2019-03-21 2019-05-21 中冶建工集团有限公司 Large-span truss segmental hoisting high-altitude closes up measure device and construction method
CN110439297A (en) * 2019-08-13 2019-11-12 上海宝冶集团南京建筑有限公司 One kind is for monolithic large span steel truss overturning lifting device and its construction method
CN110439297B (en) * 2019-08-13 2024-03-26 上海宝冶集团南京建筑有限公司 Turnover lifting device for single-piece large-span steel truss and construction method thereof
CN112878696A (en) * 2019-11-29 2021-06-01 中冶(上海)钢结构科技有限公司 Early warning system of out-of-plane instability in sliding construction of inverted-triangle truss type roof
WO2021174481A1 (en) * 2020-03-05 2021-09-10 广州建筑股份有限公司 Construction method for accumulative sliding of single-side subsection orbital transfer of unequal-span structure
CN111779274A (en) * 2020-07-10 2020-10-16 广州协安建设工程有限公司 Construction method for integrally lifting temporary hoisting point of large-span unequal-height steel structure net rack
CN111980420A (en) * 2020-08-11 2020-11-24 上海隧道工程有限公司 Steel truss pushing equipment and pushing method thereof
CN112049433A (en) * 2020-08-11 2020-12-08 上海隧道工程有限公司 Steel truss pushing attitude control equipment and attitude control method thereof
CN112267690A (en) * 2020-09-24 2021-01-26 中建四局第六建设有限公司 Large-span box-type steel beam sliding installation construction process and device
CN113323405A (en) * 2021-06-10 2021-08-31 中国建筑第八工程局有限公司 Sliding construction method applied to large-span steel structure
CN113565332A (en) * 2021-09-08 2021-10-29 中建八局第二建设有限公司 Roof steel structure and air pipe synchronous sliding construction method
CN114737808A (en) * 2022-03-24 2022-07-12 山东电力工程咨询院有限公司 Construction method of super-large-span dry coal shed grid structure
CN114687565A (en) * 2022-04-26 2022-07-01 中国建筑第七工程局有限公司 Construction method for splicing, sliding and lifting large-span steel beam at high altitude
CN115046660A (en) * 2022-05-06 2022-09-13 中铁广州工程局集团有限公司 System and method for monitoring stress of suspension platform in real time based on BIM (building information modeling)
CN115046660B (en) * 2022-05-06 2024-03-12 中铁广州工程局集团有限公司 Real-time monitoring system and method for stress of suspension platform based on BIM model
CN115324363A (en) * 2022-08-16 2022-11-11 北京首钢建设集团有限公司 N-point supporting and sliding method for multiple slideways of super-large span prestressed pipe truss
CN115324363B (en) * 2022-08-16 2023-08-15 北京首钢建设集团有限公司 N-point supporting and sliding method for multiple slide ways of extra-large-span prestressed pipe truss
CN115478699A (en) * 2022-10-31 2022-12-16 中国建筑一局(集团)有限公司 Roof truss steel structure sliding installation method
CN115478699B (en) * 2022-10-31 2024-04-12 中国建筑一局(集团)有限公司 Sliding installation method for steel structure of roof truss
CN116905817A (en) * 2023-09-12 2023-10-20 北京城建集团有限责任公司 Large-scale steel roof efficient accumulation sliding construction method with limited construction field
CN116905817B (en) * 2023-09-12 2023-11-21 北京城建集团有限责任公司 Large-scale steel roof efficient accumulation sliding construction method with limited construction field

Also Published As

Publication number Publication date
CN108468430B (en) 2021-02-05

Similar Documents

Publication Publication Date Title
CN108468430A (en) The not contour bearing steel truss structure hoisting slide construction of large span
CN103967050B (en) Construction system of subway station
CN107338963B (en) A kind of over-the-counter construction method for hanging of super-span truss string structure
CN103806658B (en) High-cleanness, high electronic workshop steel work integral slipping and discharging method
CN106978784B (en) A kind of Long span highway suspension bridge Demolition Construction method
CN106638325B (en) Suitable for the construction method of steel member liding assembling under narrow space
CN103161126A (en) Road bridge variable section hollow high pier slip-form construction method
CN107245951B (en) Mid-span and double-side simultaneous closure construction method for cable-stayed bridge
CN106522096A (en) Curved incremental launching construction technology for 48m-long-span railway simply-supported box girders and high piers
CN107542268A (en) The reverse construction method of installation of stage steel construction in a kind of grand theater room
CN107013038A (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN109610834A (en) The high-altitude construction method of Long-span Multi-storey Frame heavy duty concrete structure
CN113047447B (en) Split-level steel structure building semi-reverse construction method
CN107060070A (en) Load transfer device and the construction method that steel vestibule is lifted with the device
CN103774856A (en) Method for glidingly constructing large-span special-shaped heavy steel girder on super high-rise roof
CN106087768B (en) A kind of method of the assembled mobile formwork in the narrow short transition time section of bridge tunnel
CN107806019A (en) Large-span suspension bridge gate Sarasota construction method
CN112663516A (en) Construction method of bridge thin-wall hollow pier column
CN115162182B (en) Cantilever type steel box girder high-precision cable hoisting construction method
CN111455852A (en) Assembling method of movable formwork for bridge construction
CN202064281U (en) Slip form frame
CN105155418B (en) A kind of construction method of bridge translation
CN102286932A (en) Construction method for off-site assembling and automatic mounting on bridge of mobile mould bridge abutment
CN202401753U (en) Sliding die device
CN102877412A (en) Method of pre-assembly in integral erecting way of steel tower

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant