CN112962966A - Layered pouring construction method for super-thick reinforced concrete horizontal component - Google Patents

Layered pouring construction method for super-thick reinforced concrete horizontal component Download PDF

Info

Publication number
CN112962966A
CN112962966A CN202110179001.7A CN202110179001A CN112962966A CN 112962966 A CN112962966 A CN 112962966A CN 202110179001 A CN202110179001 A CN 202110179001A CN 112962966 A CN112962966 A CN 112962966A
Authority
CN
China
Prior art keywords
component layer
reinforced concrete
thickness
layer
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110179001.7A
Other languages
Chinese (zh)
Other versions
CN112962966B (en
Inventor
王文斌
吴亮亮
杜君子
方品
严豪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Third Engineering Division
Original Assignee
First Construction Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Third Engineering Division filed Critical First Construction Co Ltd of China Construction Third Engineering Division
Priority to CN202110179001.7A priority Critical patent/CN112962966B/en
Publication of CN112962966A publication Critical patent/CN112962966A/en
Application granted granted Critical
Publication of CN112962966B publication Critical patent/CN112962966B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/16Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2119/00Details relating to the type or aim of the analysis or the optimisation
    • G06F2119/14Force analysis or force optimisation, e.g. static or dynamic forces

Abstract

The invention discloses a construction method for layered pouring of an ultra-thick reinforced concrete horizontal component, which comprises the following steps: calculating the effective layering thickness h of the first-poured component layer according to the total load S of the later-poured component layer and the maximum bending moment M which can be borne by the first-poured component layer0(ii) a Calculating the effective layering thickness h of the pre-cast component layer according to a reinforcement ratio formula1And h2(ii) a Comparison h0、h1And h2Selecting the sum of the maximum value and the thickness H of the protective layer of the pre-cast component layer as the layering thickness H of the pre-cast component layer; determining the final layering thickness through deflection checking calculation; designing the arrangement of the frame bodies; carrying out formwork construction and pouring construction of a first-poured component layer; pouring a post-pouring component layer,and forming the ultra-thick reinforced concrete horizontal member. The invention has the beneficial effects that: the using amount of the frame body erection is saved, the construction cost is reduced, the construction period is shortened, and the workload of labor service is reduced.

Description

Layered pouring construction method for super-thick reinforced concrete horizontal component
Technical Field
The invention relates to the field of buildings, in particular to a layered pouring construction method for an ultra-thick reinforced concrete horizontal component.
Background
The application of large-volume concrete is more and more extensive in the current building industry, and the construction method of layered pouring has great progress significance for the pouring of large-volume super-thick reinforced concrete horizontal members. Before the horizontal component of present super thick reinforced concrete pours, need set up the support body in the component bottom, the load design that the density of setting up of support body corresponds according to super thick reinforced concrete horizontal component's gross thickness leads to the quantity of support body very big, and the setting up of support body with demolish waste time and energy, be unfavorable for shortening construction cycle and reduction construction cost.
Disclosure of Invention
The invention aims to solve the problems of high construction cost, long construction period and high construction cost of a large-size super-thick reinforced concrete horizontal component pouring construction method in the prior art due to large erection amount of a frame body, and provides a super-thick reinforced concrete horizontal component layered pouring construction method which comprises the following steps:
the method comprises the following steps: calculating a design value [ M ] meeting the bending moment according to the total load S of the post-cast component layer and the maximum bending moment M which can be borne by the pre-cast component layer]Effective layer thickness h of the pre-cast component layer0(ii) a Calculating the reinforcement ratio rho reaching the maximum limit according to a reinforcement ratio formulamaxAnd the relative compressed zone height xi of the boundarybThe effective layering thickness h of the pre-cast component layer1And h2
Step two: comparing h in the step one0、h1And h2Selecting the sum of the maximum value and the protective layer thickness H of the pre-cast component layer as the layering thickness H of the pre-cast component layer;
step three: and (3) deflection checking calculation: checking and calculating the maximum deflection value delta of the pre-cast component layer based on the layered thickness HmaxWhether or not it exceeds the deflection limit for its normal useδb
If deltamax≤δbTaking the layering thickness H as the final layering thickness of the cast-in-place component layer;
if deltamax>δbPasses said deflection limit δbThe minimum thickness of the pre-cast component layer which can be calculated through deflection checking is calculated in a reverse mode and is used as the final layering thickness of the pre-cast component layer;
step four: designing the arrangement of the frame bodies according to the final layering thickness in the third step;
step five: carrying out formwork construction and pouring construction of a first-poured component layer;
step six: after the early-poured component layer poured in the fifth step is solidified and hardened to the required strength; and pouring the post-cast component layer to form the super-thick reinforced concrete horizontal component.
Further, in the first step,
the calculation formula of the total load S of the post-cast component layer is as follows:
S=0.0344H0+1.4Qk
the effective delamination thickness h0The calculation formula of (2) is as follows:
Figure BDA0002941598750000021
the effective delamination thickness h1The calculation formula of (2) is as follows:
Figure BDA0002941598750000022
the effective delamination thickness h2The calculation formula of (2) is as follows:
Figure BDA0002941598750000023
in the formula: f. ofyIs the yield strength of the steel bar, AsIs the cross-sectional area of the steel bar, l is the span of the horizontal member, and b isWidth of the band or beam of the super-thick horizontal member of reinforced concrete, fcIs the axial compressive strength of concrete, H0Is the total thickness of the super-thick reinforced concrete horizontal member, QkFor construction live loads, pmaxReinforcement ratio, xi, of maximum limitbThe relative compression zone height is bounded.
Further, the maximum deflection value delta of the pre-cast component layer in the third stepmaxThe calculation formula of (2) is as follows:
Figure BDA0002941598750000024
in the formula: h0Is the total thickness of the super-thick reinforced concrete horizontal member, QkFor construction of live loads, l is the span of the horizontal member, EcAnd B is the elastic modulus of the concrete, b is the bandwidth or beam width of the super-thick reinforced concrete horizontal component, and H is the layering thickness of the pre-cast component layer in the second step.
Further, the frame body in the fourth step is a coil buckle type steel pipe frame or a fastener type steel pipe frame.
Furthermore, the post-cast component layer in the sixth step is provided with a plurality of layers, and the layers are respectively cast layer by layer from bottom to top.
Further, horizontal construction joint treatment is carried out between the first casting component layer and the later casting component layer and between the later casting component layers of adjacent layers: removing floating slurry, loose stones and a soft concrete layer on the surface of the hardened concrete; the clear water washes away the dirt on the concrete surface and fully wets the dirt.
Further, before the post-cast component layer is poured in the sixth step, the frame body in contact with the lower portion of the pre-cast component layer is detached or loosened. So as to avoid the damage of the upper load to the frame body when the post-cast component layer is poured.
Further, the super-thick reinforced concrete horizontal component is a reinforced concrete slab or a reinforced concrete beam.
The invention has the beneficial effects that: the super-thick reinforced concrete horizontal component is subjected to layered calculation and consists of a first casting component layer and a second casting component layer; therefore, the density of the erected frame body is calculated only according to the load of the member layer poured in advance, the usage amount of the erected frame body is saved, the construction cost is reduced, the construction period is shortened, the workload of labor is reduced, the safety is improved, and the method has obvious social benefits and economic benefits.
Drawings
FIG. 1 is a schematic structural view of an ultra-thick reinforced concrete horizontal member after casting construction of a cast-in-place member layer is completed.
Fig. 2 is a schematic top view of the structure of fig. 1.
In the figure: 1-casting a component layer firstly; 2-a frame body; 3-U-shaped jacking; 4-longitudinally distributing reinforcing steel bars; 5-short direction stress steel bar; 6-the bandwidth or beam width of the super-thick reinforced concrete horizontal component; 7-span of the super-thick reinforced concrete horizontal member.
Detailed Description
The invention is described in further detail below with reference to the figures and specific embodiments.
Before the pouring construction of the ultra-thick reinforced concrete horizontal component (hereinafter, also referred to as a horizontal component for short) shown in fig. 1 and 2, the ultra-thick reinforced concrete horizontal component is divided into a first-pouring component layer 1 and a second-pouring component layer by calculation; wherein, the post-cast component layer can be divided into a plurality of layers. Before the pouring construction of the first-poured component layer 1 is carried out, a frame body 2 is erected below the first-poured component layer 1 to be constructed, the frame body 2 comprises a disc-buckle type steel pipe frame or a fastener type steel pipe frame, and a U-shaped jacking 3 used for being abutted against the lower end of the first-poured component layer 1 is arranged at the upper end of the disc-buckle type steel pipe frame or the fastener type steel pipe frame; after the pouring construction of the first-poured component layer 1 is completed and before the pouring construction of the later-poured component layer is performed, the U-shaped jacking support 3 is loosened, so that the upper end of the U-shaped jacking support keeps a distance from the first-poured component layer 1, and the distance is larger than the maximum deflection value of the super-thick reinforced concrete horizontal component. It should be noted that the super-thick reinforced concrete horizontal member of the present embodiment may be a reinforced concrete slab or a reinforced concrete beam.
The layered pouring construction method of the ultra-thick reinforced concrete horizontal component comprises the following steps:
the method comprises the following steps: according to the total load S of the post-cast component layerAnd the maximum bending moment M which can be borne by the first-cast component layer 1, and calculating a design value [ M ] meeting the bending moment]Effective layer thickness h of the pre-cast component layer 10(ii) a Calculating the reinforcement ratio rho reaching the maximum limit according to a reinforcement ratio formulamaxAnd the relative compressed zone height xi of the boundarybIn the meantime, the effective layer thickness h of the component layer 1 is poured first1And h2(ii) a In the embodiment, the calculation of the load and the selection of each subentry coefficient are all based on the most unfavorable principle of the unified safety technology standard GB-51210-2016 for the scaffold for building construction, and the calculation of the bending resistance bearing capacity of the normal section is based on a simply supported beam model. The reinforcement ratio of the embodiment is calculated by only considering the total cross-sectional area of the short stressed steel bars 5 of the pre-cast component layer 1 and not considering the total cross-sectional area of the long distributed steel bars 4.
The method specifically comprises the following steps:
the calculation formula of the total load S of the post-cast component layer is as follows:
S=γGSGQγLψcSQ=γG(bH0Gk)+γQγLψc(bQk)
wherein b is the thick plate width or the thick beam width, in this embodiment, it is assumed that b is 1000 mm, and the permanent load γ is taken as the fractional coefficient of the permanent load and the variable load according to the worst principleG1.35 and variable load γQ1.40, the adjusting coefficient of the design service life is gammaL=1.0。SGTaking 25.5kN/m3, Q for the dead weight of the reinforced concretekIs a construction live load. The above equation can be simplified as:
S=1.35×[1000×H0×25.5×10-6]+1.4×1.0×1.0×[Qk×10-$×1000]
it can further be deduced that:
S=0.0344H0+1.4Qk
substituting the total load S of the post-cast component layer into the midspan maximum bending moment calculation formula of the simply supported beam to obtain the maximum bending moment M which can be borne by the pre-cast component layer 1:
Figure BDA0002941598750000051
and then calculating a bending moment design value [ M ] of the normal section bending of the single-rib rectangular section bending component:
Figure BDA0002941598750000052
according to the relation that M is less than or equal to [ M ], calculating the minimum effective layered thickness h0 of the post-cast component layer meeting the bending moment design value:
Figure BDA0002941598750000053
further, it can be deduced that the effective layering thickness h0The calculation formula of (2) is as follows:
Figure BDA0002941598750000054
calculating the reinforcement ratio rho reaching the maximum limit according to a reinforcement ratio formulamaxIn the meantime, the effective layer thickness h of the component layer 1 is poured first1The size of (2):
Figure BDA0002941598750000055
similarly, the height xi of the relative compression zone reaching the boundary is calculatedbEffective layer thickness h0The size of (2):
Figure BDA0002941598750000056
in the above formulas: f. ofyIs the yield strength of the steel bar, AsIs the section area of the steel bar, x is the height of the compression zone of the equivalent rectangular stress pattern, b is the bandwidth or beam width 6 of the super-thick reinforced concrete horizontal component, l is the span 7 of the super-thick reinforced concrete horizontal component of the embodiment, fcCompressive strength of concrete axle center,α1Alpha is the equivalent rectangular stress diagram coefficient of the concrete in the compression zone, and the concrete strength is C50 or below1Take 1.0, H0Is the total thickness of the super-thick reinforced concrete horizontal member, QkFor construction live loads, pmaxReinforcement ratio, xi, of maximum limitbThe relative compression zone height is bounded.
Step two: h in the comparison step I0、h1And h2Selecting the sum of the maximum value and the protective layer thickness H of the pre-cast component layer 1 as the layering thickness H of the pre-cast component layer 1;
namely, the calculation formula of the layered thickness H of the pre-cast component layer 1 is as follows:
H=max(h0,h1,h2)+h
in combination with the above formula, this can be converted into:
Figure BDA0002941598750000061
wherein h is the protective layer thickness of the pre-cast component layer 1.
Step three: after the layering thickness H of the first-poured component layer 1 is preliminarily determined, the deflection of the first-poured component layer 1 based on the layering thickness H is also checked:
calculating the line load q under the normal use state:
q=[1000×H0×25.5×10-6]+[Qk×10-$×1000]=0.0255H0+Qk
calculating the maximum deflection value delta of the early-poured component layer 1 based on the layered thickness H of the early-poured component layer 1 and the deflection formula of the simply supported beammax
Figure BDA0002941598750000062
Will maximize the deflection value deltamaxDeflection limit delta from pre-cast component layer 1bComparing;
if deltamax≤δbThen, thenThe layering thickness H of the first-poured component layer 1 meets the requirements of bearing capacity and deflection in normal use at the same time, and can be used as the final layering thickness of the first-poured component layer 1;
if deltamax>δbThen the deflection limit delta of the pre-cast component layer 1 is setbThe formula of the deflection of the simply supported beam is substituted, and the first cast component layer 1 is reversely calculated to reach the maximum deflection value deltamaxThe layer thickness H' of the component layer 1 is poured firstly:
Figure BDA0002941598750000071
the layered thickness H' of the pre-cast component layer 1 can be taken as the final layered thickness of the pre-cast component layer 1.
In the above formula: h0Is the total thickness of the super-thick reinforced concrete horizontal member, QkFor construction of live loads, l is the span of the horizontal member, EcAnd B is the elastic modulus of the concrete, b is the bandwidth or beam width 6 of the super-thick reinforced concrete horizontal component, and H is the layered thickness of the first cast component layer 1 in the second step.
Deflection limit value deltabThe maximum deflection allowable value of the flexural member with different spans in the basic principle of concrete structure is determined; referring to fig. 2, the spans of the ultra-thick reinforced concrete horizontal members analyzed in the construction method are all default to short-side spans, namely, spans along the direction of the short-direction stressed steel bars 5; maximum deflection value deltamaxIs based on a simply supported beam model.
Step four: designing the arrangement of the frame bodies 2 according to the final layering thickness of the step three (including the span and the step pitch of the vertical rods of the frame bodies 2); the design of the step pitch of the vertical rods of the frame body 2 preferentially considers the pulling-through of the vertical rods of the frame body 2 with the surrounding frame body 2.
If the coil buckling type steel pipe frame is used as the support body 2 for supporting, the coil buckling frames need to be arranged from the beam edge bearing the short span of the super-thick reinforced concrete horizontal component or the wall, column and beam structures at two ends of the super-thick reinforced concrete horizontal component according to the modulus of the space between the support bodies 2.
If the frame body 2 for supporting the seat of the fastener type steel pipe frame is used, the bearing capacity, the rigidity and the overall stability are directly checked, and the heat insulation structure design is carried out according to the maintenance method adopted by the existing large-volume concrete.
Step five: carrying out formwork construction and pouring construction of the first pouring component layer 1; adopting related safety and stability measures in the process of installing the die carrier of the first casting component layer 1; before pouring construction of the member layer 1, specially designing bottom ribs of the super-thick reinforced concrete horizontal member in the stress direction according to anchoring requirements in corresponding drawing sets and specifications so as to meet design assumptions of layered pouring; the concrete pouring construction method of the first pouring component layer 1 adopts the conventional large-volume concrete pouring method.
Step six: after the cast member layer 1 poured in the step five is solidified and hardened to the required strength; and pouring a post-pouring component layer, wherein the post-pouring component layer has multiple layers, and is poured layer by layer from bottom to top, and finally, the component layer 1 and the multiple layers of post-pouring component layers are poured firstly to form the super-thick reinforced concrete horizontal component.
It should be noted that horizontal construction joint treatment is carried out between the first casting component layer 1 and the post-casting component layer and between the post-casting component layers of adjacent layers: removing floating slurry, loose stones and a soft concrete layer on the surface of the hardened concrete; rinsing dirt on the surface of the concrete with clear water, fully wetting the dirt, and not accumulating water; when the waterproof requirement exists, treatment measures such as a steel plate waterstop and the like are adopted. Of course, the horizontal construction joint processing process may be other existing methods, and this embodiment is not limited.
The above is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above-mentioned embodiments, and all technical solutions belonging to the idea of the present invention belong to the protection scope of the present invention. It should be noted that modifications and embellishments within the scope of the invention may be made by those skilled in the art without departing from the principle of the invention.

Claims (8)

1. A layered pouring construction method for an ultra-thick reinforced concrete horizontal component is characterized by comprising the following steps: the method comprises the following steps:
the method comprises the following steps: according to the total load S of the post-cast component layer and the pre-cast structureCalculating the maximum bending moment M which can be borne by the part layer to meet the bending moment design value [ M]Effective layer thickness h of the pre-cast component layer0(ii) a Calculating the reinforcement ratio rho reaching the maximum limit according to a reinforcement ratio formulamaxAnd the relative compressed zone height xi of the boundarybThe effective layering thickness h of the pre-cast component layer1And h2
Step two: comparing h in the step one0、h1And h2Selecting the sum of the maximum value and the protective layer thickness H of the pre-cast component layer as the layering thickness H of the pre-cast component layer;
step three: and (3) deflection checking calculation: checking and calculating the maximum deflection value delta of the pre-cast component layer based on the layered thickness HmaxWhether or not the deflection limit delta for normal use thereof is exceededb
If deltamax≤δbTaking the layering thickness H as the final layering thickness of the cast-in-place component layer;
if deltamax>δbPasses said deflection limit δbThe minimum thickness of the pre-cast component layer which can be calculated through deflection checking is calculated in a reverse mode and is used as the final layering thickness of the pre-cast component layer;
step four: designing the arrangement of the frame bodies according to the final layering thickness in the third step;
step five: carrying out formwork construction and pouring construction of a first-poured component layer;
step six: after the early-poured component layer poured in the fifth step is solidified and hardened to the required strength; and pouring the post-cast component layer to form the super-thick reinforced concrete horizontal component.
2. The layered pouring construction method for the ultra-thick reinforced concrete horizontal component according to claim 1 is characterized in that: in the first step, the first step is carried out,
the calculation formula of the total load S of the post-cast component layer is as follows:
S=0.0344H0+1.4Qk
the effective delamination thickness h0The calculation formula of (2) is as follows:
Figure FDA0002941598740000011
the effective delamination thickness h1The calculation formula of (2) is as follows:
Figure FDA0002941598740000021
the effective delamination thickness h2The calculation formula of (2) is as follows:
Figure FDA0002941598740000022
in the formula: f. ofyIs the yield strength of the steel bar, AsIs the section area of the steel bar, l is the span of the horizontal member, b is the bandwidth or beam width of the super-thick reinforced concrete horizontal member, fcIs the axial compressive strength of concrete, H0Is the total thickness of the super-thick reinforced concrete horizontal member, QkFor construction live loads, pmaxReinforcement ratio, xi, of maximum limitbThe relative compression zone height is bounded.
3. The layered pouring construction method for the ultra-thick reinforced concrete horizontal component according to claim 1 is characterized in that: the maximum deflection value delta of the pre-cast component layer in the third stepmaxThe calculation formula of (2) is as follows:
Figure FDA0002941598740000023
in the formula: h0Is the total thickness of the super-thick reinforced concrete horizontal member, QkFor construction of live loads, l is the span of the horizontal member, EcB is the bandwidth or the beam width of the super-thick reinforced concrete horizontal component, and H is the layering thickness of the pre-cast component layer in the second stepAnd (4) degree.
4. The layered pouring construction method for the ultra-thick reinforced concrete horizontal component according to claim 1 is characterized in that: and in the fourth step, the frame body is a coil buckle type steel pipe frame or a fastener type steel pipe frame.
5. The layered pouring construction method for the ultra-thick reinforced concrete horizontal component according to claim 1 is characterized in that: and sixthly, pouring the post-cast component layer from bottom to top layer by layer respectively, wherein the post-cast component layer in the step six has multiple layers.
6. The layered pouring construction method for the ultra-thick reinforced concrete horizontal component according to claim 5, is characterized in that: horizontal construction joint treatment is carried out between the first casting component layer and the later casting component layer and between the later casting component layers of adjacent layers: removing floating slurry, loose stones and a soft concrete layer on the surface of the hardened concrete; the clear water washes away the dirt on the concrete surface and fully wets the dirt.
7. The layered pouring construction method for the ultra-thick reinforced concrete horizontal component according to claim 1 is characterized in that: before the post-cast component layer is poured in the sixth step, the frame body in contact with the lower part of the pre-cast component layer is detached or loosened.
8. The layered pouring construction method for the ultra-thick reinforced concrete horizontal component according to claim 1 is characterized in that: the super-thick reinforced concrete horizontal component is a reinforced concrete slab or a reinforced concrete beam.
CN202110179001.7A 2021-02-09 2021-02-09 Layered pouring construction method for super-thick reinforced concrete horizontal component Active CN112962966B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110179001.7A CN112962966B (en) 2021-02-09 2021-02-09 Layered pouring construction method for super-thick reinforced concrete horizontal component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110179001.7A CN112962966B (en) 2021-02-09 2021-02-09 Layered pouring construction method for super-thick reinforced concrete horizontal component

Publications (2)

Publication Number Publication Date
CN112962966A true CN112962966A (en) 2021-06-15
CN112962966B CN112962966B (en) 2022-06-07

Family

ID=76284560

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110179001.7A Active CN112962966B (en) 2021-02-09 2021-02-09 Layered pouring construction method for super-thick reinforced concrete horizontal component

Country Status (1)

Country Link
CN (1) CN112962966B (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4343482A1 (en) * 1993-12-21 1995-06-22 Heitkamp Gmbh Bau Concrete construction to contain water contaminating materials
CN105297630A (en) * 2015-10-10 2016-02-03 正平路桥建设股份有限公司 Construction method for double-component steel tubes of main arch arcs
CN106759354A (en) * 2016-11-22 2017-05-31 西安建筑科技大学 A kind of stratified continuous pouring mode of ultra-long and ultra-thick volume of concrete foundation
CN110387806A (en) * 2019-07-31 2019-10-29 中交路桥北方工程有限公司 A kind of restressed beam slab deflection deformation control method
CN111255239A (en) * 2018-11-30 2020-06-09 中国建筑第八工程局有限公司 Mass radiation-proof concrete homogeneous pouring method
CN111563344A (en) * 2020-05-28 2020-08-21 广西交科集团有限公司 Method for safely judging stress of first-layer beam of layered casting concrete
CN111560856A (en) * 2020-05-28 2020-08-21 广西交科集团有限公司 Construction method for layering pouring concrete beam on soft soil foundation
CN111783189A (en) * 2020-05-28 2020-10-16 广西交科集团有限公司 Method for judging reasonable bracket height of layered pouring concrete
CN111797449A (en) * 2020-05-28 2020-10-20 广西交科集团有限公司 Method for judging reasonable height of layered pouring concrete beam
CN112031423A (en) * 2020-08-12 2020-12-04 河南高建工程管理有限公司 Construction quality control method for ultra-large-volume concrete

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4343482A1 (en) * 1993-12-21 1995-06-22 Heitkamp Gmbh Bau Concrete construction to contain water contaminating materials
CN105297630A (en) * 2015-10-10 2016-02-03 正平路桥建设股份有限公司 Construction method for double-component steel tubes of main arch arcs
CN106759354A (en) * 2016-11-22 2017-05-31 西安建筑科技大学 A kind of stratified continuous pouring mode of ultra-long and ultra-thick volume of concrete foundation
CN111255239A (en) * 2018-11-30 2020-06-09 中国建筑第八工程局有限公司 Mass radiation-proof concrete homogeneous pouring method
CN110387806A (en) * 2019-07-31 2019-10-29 中交路桥北方工程有限公司 A kind of restressed beam slab deflection deformation control method
CN111563344A (en) * 2020-05-28 2020-08-21 广西交科集团有限公司 Method for safely judging stress of first-layer beam of layered casting concrete
CN111560856A (en) * 2020-05-28 2020-08-21 广西交科集团有限公司 Construction method for layering pouring concrete beam on soft soil foundation
CN111783189A (en) * 2020-05-28 2020-10-16 广西交科集团有限公司 Method for judging reasonable bracket height of layered pouring concrete
CN111797449A (en) * 2020-05-28 2020-10-20 广西交科集团有限公司 Method for judging reasonable height of layered pouring concrete beam
CN112031423A (en) * 2020-08-12 2020-12-04 河南高建工程管理有限公司 Construction quality control method for ultra-large-volume concrete

Also Published As

Publication number Publication date
CN112962966B (en) 2022-06-07

Similar Documents

Publication Publication Date Title
US8549805B2 (en) Grid-type drop-panel structure, and a construction method therefor
JP5184836B2 (en) Construction method of synthetic steel slab girder bridge
CN207812307U (en) The construction system of Cable stayed Bridge Main Tower and steel anchor beam
KR101133420B1 (en) Precast concrete connection block and the continuity method of composite bridges using it
CN112962966B (en) Layered pouring construction method for super-thick reinforced concrete horizontal component
CN216076559U (en) Assembled self-adaptation vertical deformation's concrete structure system
CN115262811A (en) Construction method of transverse section steel concrete combined shear wall
KR100989153B1 (en) Psc girder connection structure with strength connector detail for substitution of rebar placement in deck and bridge construction method using the same
CN210947410U (en) Prestressed recycled concrete hollow composite beam
CN103498530A (en) Prestressed tooth hole-shaped web T-shaped steel reinforced concrete composite beam
CN113174862A (en) Construction method of diaphragm plate in high pier and diaphragm plate structure system in high pier
JP2812178B2 (en) Bridge pier construction method by self-elevating formwork method
JP6886811B2 (en) Foundation structure and method of constructing foundation structure
CN216428794U (en) Assembled multi-cavity composite concrete frame column
CN206071085U (en) A kind of high ductility space constraint reinforced masonry wall system of industrialization
JP2004176344A (en) Box girder bridge
CN217897380U (en) Box type steel pipe reinforced concrete frame beam
CN218028302U (en) Archaize building blue brick and wall connection system
CN216865651U (en) Prestressed composite floor slab with upper reverse ribs
CN219753487U (en) Supporting beam structure in large-span floor slab
CN213198076U (en) Concrete anchor pier aluminum template and system of anchor cable frame structure
CN212358903U (en) Prefabricated stair node structure of assembled antidetonation
KR20110006225U (en) Combination reinforcement
CN213952487U (en) Beam column node of support-free horizontal prefabricated floor system
CN220704781U (en) Reinforced concrete column rigidity overlap joint conversion node

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant