CN111783189A - Method for judging reasonable bracket height of layered pouring concrete - Google Patents
Method for judging reasonable bracket height of layered pouring concrete Download PDFInfo
- Publication number
- CN111783189A CN111783189A CN202010469183.7A CN202010469183A CN111783189A CN 111783189 A CN111783189 A CN 111783189A CN 202010469183 A CN202010469183 A CN 202010469183A CN 111783189 A CN111783189 A CN 111783189A
- Authority
- CN
- China
- Prior art keywords
- layer
- concrete
- concrete beam
- support
- height
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 28
- 238000005452 bending Methods 0.000 claims abstract description 19
- 238000004458 analytical method Methods 0.000 claims description 15
- 238000009432 framing Methods 0.000 claims description 15
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims description 10
- 101100234408 Danio rerio kif7 gene Proteins 0.000 claims description 8
- 101100221620 Drosophila melanogaster cos gene Proteins 0.000 claims description 8
- 101100398237 Xenopus tropicalis kif11 gene Proteins 0.000 claims description 8
- 230000009471 action Effects 0.000 claims description 8
- 238000005266 casting Methods 0.000 claims description 8
- 239000000463 material Substances 0.000 claims description 6
- 238000010008 shearing Methods 0.000 claims description 6
- 230000006835 compression Effects 0.000 claims description 5
- 238000007906 compression Methods 0.000 claims description 5
- 239000002184 metal Substances 0.000 claims description 4
- 238000003825 pressing Methods 0.000 claims description 2
- 238000010276 construction Methods 0.000 abstract description 9
- 230000008901 benefit Effects 0.000 abstract description 4
- 238000004519 manufacturing process Methods 0.000 abstract description 2
- 238000004364 calculation method Methods 0.000 description 5
- 229910000831 Steel Inorganic materials 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 238000012360 testing method Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 230000008569 process Effects 0.000 description 3
- 230000005540 biological transmission Effects 0.000 description 2
- 238000010835 comparative analysis Methods 0.000 description 2
- 230000005484 gravity Effects 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 238000012795 verification Methods 0.000 description 2
- 230000004323 axial length Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000001808 coupling effect Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000011159 matrix material Substances 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 230000007935 neutral effect Effects 0.000 description 1
- 230000005476 size effect Effects 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
- G06F30/23—Design optimisation, verification or simulation using finite element methods [FEM] or finite difference methods [FDM]
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2111/00—Details relating to CAD techniques
- G06F2111/10—Numerical modelling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2119/00—Details relating to the type or aim of the analysis or the optimisation
- G06F2119/14—Force analysis or force optimisation, e.g. static or dynamic forces
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Geometry (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Business, Economics & Management (AREA)
- Mathematical Analysis (AREA)
- Human Resources & Organizations (AREA)
- Pure & Applied Mathematics (AREA)
- Computational Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Economics (AREA)
- General Health & Medical Sciences (AREA)
- Mathematical Optimization (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
- Testing Of Devices, Machine Parts, Or Other Structures Thereof (AREA)
Abstract
The invention relates to the field of bridge and culvert engineering in the transportation industry, and particularly discloses a method for judging the height of a reasonable bracket for pouring concrete in a layered mode. However, for the cast-in-place of the support, particularly for the full-hall support supporting and layered pouring of the concrete beam, the height and the rigidity of the support are mutually linked, so that the stress of the first-layer concrete beam is influenced. The early-stage poured concrete is easy to generate tensile stress in a pier top negative bending moment area or a midspan maximum positive bending moment area to form initial tensile strain, so that the early stress of the concrete generates larger creep in the later period, the stress reserve in the bridge forming stage is reduced, and the beam body concrete is cracked when the tensile stress reaches the tensile strength of the concrete. The invention provides a method for judging reasonable bracket height of the layered cast concrete based on the stress safety state of the first beam of the layered cast concrete beam, and during specific construction, an optimal bracket scheme is selected, so that the time and the cost are saved for actual production, and the method has good engineering and economic benefits.
Description
Technical Field
The invention relates to the field of bridge and culvert engineering in the transportation industry, and provides a method for judging the height of a reasonable bracket of layered pouring concrete based on the stress safety state of a first-layer beam of the layered pouring concrete beam.
Background
Concrete bridges are widely used in bridge construction with the advantages of good stress performance, service performance, construction maturity and the like. Most concrete beams are not formed by one-time pouring, and particularly, the concrete beams with higher beam height or complicated detailed structures generally need to be poured in layers for many times. However, for the cast-in-place of the support, particularly for the full-hall support supporting and layered concrete pouring of the beam, the height and the rigidity of the support are mutually linked, so that the stress condition of the first-layer concrete beam is limited. The early-stage poured concrete is easy to generate tensile stress in a pier top negative bending moment area or a midspan maximum positive bending moment area to form initial tensile strain, so that the early stress of the concrete generates larger later-stage creep, the stress reserve in a bridge forming stage is reduced, and the beam body concrete is cracked when the tensile stress reaches the tensile strength of the concrete. And the stress condition of the subsequent cast concrete beam on the first layer is directly determined by different full houses, the first layer concrete beam generates bending moment deformation at the moment, the tensile stress appears at the bottom of the span beam, and if the height of the support is unreasonable, the first layer concrete beam is easy to crack, so that the safety and the durability of the concrete beam are influenced.
Disclosure of Invention
The invention aims to provide a method for judging the reasonable height of a layered casting concrete beam support, which adopts an elastomechanics plane problem analysis method, takes the subsequent casting concrete as load, deduces the stress function of the first layer concrete beam in a system, combines the concrete strength development law, and configures the reasonable full support height under the condition of ensuring the stress of the first layer concrete beam.
In order to achieve the purpose, the invention provides a method for judging the height of a reasonable bracket for layered casting of concrete, which specifically comprises the following steps:
s1, erecting a full-hall support on the foundation, laying a template on the full-hall support, binding a first layer of reinforcing steel bars on the template after pre-pressing the full-hall support, pouring a first layer of concrete beam, binding reinforcing steel bars of a second layer of concrete beam when the first layer of concrete beam is hardened to a certain strength, and pouring the second layer of concrete beam;
s2, acquiring the length of the equal-section concrete beam of the first-layer concrete beam and the uniform load of the second-layer concrete beam on the first-layer concrete beam;
s3, simulating the action of the full framing on the first concrete beam by adopting an analysis model with an elastic support, and constructing a differential equation of the first concrete beam by combining the uniform load of the second concrete beam on the first concrete beam;
s4, solving a differential equation to obtain the tensile stress of the first-layer concrete beam;
s5, obtaining the compressive strength of the first-layer concrete beam, and obtaining the maximum tensile strength of the first-layer concrete beam according to the compressive strength;
s6, solving according to the relation between the tensile stress and the maximum tensile strength of the first-layer concrete beam to obtain the allowable weight of the second-layer concrete beam;
and S7, under the conditions of the allowable maximum tensile strength and the allowable weight of the second-layer concrete beam, solving an implicit function unknown quantity according to the relation between the tensile stress of the first-layer concrete beam and the maximum tensile strength, and solving the allowable height of the full framing according to the implicit function unknown quantity.
Preferably, in the above technical solution, the stiffness coefficient of the analysis model with elastic support is:
formula (1) wherein: em is the modulus of elasticity of the scaffold material; hm is the height of the full support; am is the area of the supporting section of the full support per square meter; i ismyAnd ImzThe inertia moments of the Y axis and the Z axis of the full support are respectively; mu is Poisson's ratio. Because the full framing is mainly resistant to compression, neglecting shearing and bending torsion, the spring stiffness K of the full framing is Em/Hm per linear meter.
Preferably, in the above technical solution, according to a beam deflection differential equation and a coordination condition of the support top settlement S and the deflection deformation of the first-layer beam, S ═ ω, that is:
P=K0S=K0ω (2)
K0the elastic coefficient of the bracket system represents the pressure intensity required by unit deformation; p is the pressure strength of any point on the top of the bracket; s is vertical deformation at the action position of P, and omega is the deflection of the first-layer concrete beam;
according to elasto-mechanical analysis, the beam equation:
formula (3)) -in equation (5): m is the bending moment to which the concrete beam is subjected, FsThe shear force borne by the first-layer concrete beam, E is the elastic modulus of the first-layer concrete beam, omega is the deflection of the first-layer concrete beam, and P (x) is the uniform load on the micro-section of the first-layer concrete beam
Preferably, in the above technical solution, in step S3, in step S4, the equation (3) is applied, and the basic differential equation of the primary beam of the elastic support under the foundation is considered as:
the solution of equation (7) is:
therefore, the temperature of the molten metal is controlled,substituting the formula (8) to obtain:
solving to obtain:
preferably, in the above technical solution, in step S3, the basic differential equation of the elastic support first beam without considering the foundation is as follows:
the solution of equation (8) is:
similarly, the stress function of the elastic support first-layer beam under the foundation is not considered in the solution
Preferably, in the above technical solution, in step S5, the tensile strength f of the first-layer concrete beamt,nTo compressive strength fcu,n0.05 times, i.e. ft,n=0.05fcu,n;
In step S6, the first concrete layer is not formedNow crack, must satisfy sigma<ft,nI.e. by
Considering the foundation as follows:
simplified backstage type (15)
The allowable weight of the second layer of concrete is as follows:
in step S7, f is allowedt,n、p0Then, the unknown quantity β of implicit function is solved by the formula (15)The height allowed for the stent system is then:
formula (17) wherein: h (m) is the allowable height of the support system.
Preferably, in the above technical solution, in step S5, the tensile strength f of the first-layer concrete beamt,nTo compressive strength fcu,n0.05 times, i.e. ft,n=0.05fcu,n;
In step S6, the first concrete layer does not crack and must satisfy the requirement of sigma<ft,nI.e. by
Regardless of the foundation:
simplified backstage formula (19)
The allowable weight of the second layer of concrete is as follows:
in step S7, f is allowedt,n、p0In this way, the implicit function unknowns are solved from equation (18)Then The height allowed for the stent system is then:
formula (21) wherein: h (m) is the allowable height of the support system.
Compared with the prior art, the invention has the beneficial effects that:
the reasonable height configuration method for the layered casting concrete support is based on an elastic mechanics theory, deduces the stress of the first layer concrete beam when the second layer concrete is cast, and determines the reasonable support height of the first layer concrete beam under the stress safety according to the compression strength test value of the same batch of concrete cube test blocks of the first layer concrete beam. This patent can effectively instruct to adopt the layering to pour the reasonable height of support, can guarantee the safety of beam bottom stress, can guarantee the cost again, has good economic benefits.
Drawings
FIG. 1 is a simplified model of the equivalent elastic simply supported beam uniformly loaded without considering the foundation.
FIG. 2 is a simplified model of the invention for the equivalent elastic simply supported beam to be uniformly loaded under the condition of considering the foundation.
FIG. 3 is a schematic view of a stent according to the present invention.
FIG. 4 is a diagram of a finite element model.
FIG. 5 is a first comparison of the analytical solution and finite element calculation results of the present invention.
FIG. 6 is a second comparison of the analytic solution and finite element calculation results of the present invention.
Detailed Description
Specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings, but it should be understood that the scope of the present invention is not limited to the specific embodiments.
In this embodiment, the method for judging the reasonable bracket height in the layered casting of concrete specifically includes:
firstly, the stress mechanism and the state of a first-layer concrete beam are analyzed in the construction process of adopting a support to pour the concrete beam in a layering way. And binding reinforcing steel bars on the template according to a design drawing, pouring the first layer of concrete, binding the reinforcing steel bars of the second layer of concrete beam when the concrete is hardened and reaches a certain strength, and pouring the second layer of concrete. The construction process is analyzed, and the foundation under the first concrete beam provides upward supporting force for balancing the dead weight of the first-layer concrete beam and the steel bars and the concrete gravity of the second-layer beam. The inventor finds out through a large number of engineering actual measurements that when reinforcing steel bars of two-layer beams are bound and concrete is poured, the foundation base is unevenly compressed under the action of the reinforcing steel bars and the concrete of the two-layer beams, so that the first-layer concrete beam is deformed, the midspan deformation is large, the deformation gradually changes to zero at a support, the tensile stress appears near the midspan of the bottom of the first-layer concrete beam, the early initial strain and the later creep increase are generated, and when the tensile stress is greater than the concrete strength at that time, the first-layer concrete beam cracks, and safety and resistance accidents occur.
In summary, in order to ensure that the first-layer concrete beam does not crack, the stress value of the first-layer concrete beam needs to be obtained, and the stress value solving process is as follows:
based on the analysis, the reinforcement binding and concrete pouring construction of the two-layer beam are regarded as loads acting on the first-layer concrete beam and the support, and the following assumptions are made:
(1) simplified analysis is carried out on the first layer of formed concrete beam which is cast by the full-framing in a layered mode, wherein the length of the concrete beam with the equal section is L, the beam end is simply supported, concrete is cast by the full-framing in a layered mode, and uniformly distributed loads P are used0The effect of the steel reinforcement and concrete of the second layer beam on the first layer was simulated, and due to the symmetry of the problem, the origin of coordinates was taken at the midpoint of the beam, as shown in fig. 1 and 2.
(2) The existence of the support of the full support of the actual beam structure can simulate the effect of the support on the concrete beam by adopting an analysis model with an elastic support. The conversion matrix method is adopted, and the middle part is provided with an elastic support. The full-space support is processed according to an elastic foundation, the rigidity coefficient of the full-space support is K, the counter force of the elastic foundation is in direct proportion to the deflection omega of the first-layer beam, the direction of the counter force is opposite to omega, for the full-space support, the elastic support is used for simulating the action on the first-layer beam, the elastic constraint coupling effect is calculated and considered, at the moment, the general elastic support type is shown in the following formula (1), non-zero values except the diagonal line in the formula are the effect of considering the mutual influence and the mutual correlation of certain degrees of freedom, and the horizontal elastic support is not considered.
Formula (1) wherein: em is the modulus of elasticity of the scaffold material; hm is the height of the full support; am is the area of the supporting section of the full support per square meter; i ismyAnd ImzThe inertia moments of the Y axis and the Z axis of the full support are respectively; mu is Poisson's ratio. Because the full framing is mainly resistant to compression, neglecting shearing and bending torsion, the spring stiffness K of the full framing is Em/Hm per linear meter.
(3) The pressure intensity of any point on the top of the bracket is in direct proportion to the vertical deformation S of the point, and P is equal to K0S,K0The foundation bed coefficient represents the pressure intensity required for generating unit deformation; p is the pressure strength of any point on the top of the bracket; s is the vertical deformation at the p-action position. According to the flexural differential equation of the beam and the coordination condition of the support top settlement S and the flexural deformation of the first-layer beam, S is omega, namely:
P=K0S=K0ω (2)
according to the related knowledge of elastic mechanics, the equation of the beam is as follows:
in formulae (3) to (5): m is the bending moment to which the concrete beam is subjected, FsThe shearing force borne by the first-layer concrete beam, E is the elastic modulus of the first-layer concrete beam, omega is the deflection of the first-layer concrete beam, and P (x) is the uniform load on the micro-section of the first-layer concrete beam. Applying equation (3), the basic differential equation of the elastic support first-layer beam under the foundation is considered as follows:
the solution of equation (7) is:
solving to obtain:
the basic differential equation for the spring-loaded first-layer beam without considering the foundation is:
the solution of equation (8) is:
similarly, the stress function of the elastic support first-layer beam under the foundation is not considered in the solution
When the second layer of beam steel bars are bound and concrete is poured, the age of the first layer of concrete is n days, and when the first layer of concrete is cured for n days under the same condition with the same batch of concrete cubic test blocks of the first layer of concrete, the average value of the test compressive strength of the first layer of concrete is fcu,nBased on the relationship between the compressive strength and the tensile strength of the concrete, namely, the tensile strength of the concrete is generally 0.05-0.1 times of the compressive strength, considering the non-uniformity and the size effect of the concrete, the invention safely takes the tensile strength of the concrete as 0.05 times of the compressive strength, namely ft,n= 0.05fcu,n。
The first layer concrete does not crack, so that the safety and the tolerance of the first layer concrete beam can be ensured, and the requirement of sigma must be met<ft,nI.e. by
(1) Considering the foundation as follows:
simplified backstage formula (12)
At the allowable ft,n、p0Then, the implicit function unknown quantity β is solved by the formula (14)The height allowed for the scaffolding system is then:
(2) regardless of the foundation:
simplified backstage type (18)
At the allowable ft,n、p0Next, the implicit function unknowns are solved by equation (17)ThenThe height allowed for the stent system is then:
example 1
For a simple beam bridge, the minimum clearance height under the bridge is 6.0 m, the automobile load grade is highway-I grade, and a support is arranged on a strip foundationSpiral steel pipes are shown in fig. 4 below. The height is poured to the first section 500mm, and when the first floor roof beam belongs to the simply supported beam atress, the height should be taken up in total height 0.3 ~ 0.7 to the first floor height of pouring, and the height is poured to the second section, and the priority considers the construction joint and sets up near neutral axis, divides behind the construction joint, pours the layer equivalence with two layers and is the support system of equipartition load transmission to the first floor. Wherein the full-hall support is simulated by adopting elastic supports with rigidity, one elastic support is distributed every 60cm, 50 elastic supports are distributed in 30m span, and the rigidity of the elastic support is 106According to the actual working conditions of the model, the concrete material is defined as C50 concrete, the height × width of the section size of the first layer of concrete is 0.5m × 1m, the second layer of concrete is loaded on the first layer of concrete in a uniformly distributed load mode, the uniformly distributed load q is 0.5 × 1.0 × 25 is 12.5kN/m, a simple supporting beam in the model should restrict three translational degrees of freedom and two rotational degrees of freedom at the left end of the beam, the negative Z axis is taken as the gravity direction, the X axis is taken as the axial length, and the concrete material is C50 concreteAnd the right end of the beam restrains the translational freedom degrees of Y and Z directions and the rotational freedom degrees of X and Z directions.
The numerical calculation method of the finite element is adopted for verification, as shown in the following table 1 and fig. 3, the calculation is better consistent with the finite element result curve, and the analytic solution is accurate and correct, as shown in fig. 5 and fig. 6.
TABLE 1 comparative analysis of stress results (unit: MPa)
Table 1 Comparative analysis ofstress results(Unit:MPa)
The embodiment discloses a method for judging the reasonable support height of layered casting concrete, wherein a full-hall support is erected on a foundation, a template is laid on the full-hall support, a first layer of reinforcing steel bars are bound on the template after the full-hall support is pre-pressed, a beam end is a simple support, a first layer of concrete beam is cast, when the first layer of concrete beam is hardened to a certain strength, reinforcing steel bars of a second layer of concrete beam are bound, and the second layer of concrete beam is cast; the method for judging the reasonable support height of the layered casting concrete specifically comprises the following steps:
the parameter acquisition module is used for acquiring the length of the equal-section concrete beam of the first layer of concrete beam and the uniform load of the second layer of concrete beam on the first layer of concrete beam;
the differential equation establishing module is used for simulating the action of the full framing on the first-layer concrete beam by adopting an analysis model with an elastic support and establishing a differential equation of the first-layer concrete beam by combining uniform load of the second-layer concrete beam on the first-layer concrete beam;
the differential equation solving module is used for solving a differential equation to obtain the tensile stress of the first-layer concrete beam;
the maximum tensile strength acquisition module is used for acquiring the compressive strength of the first-layer concrete beam and acquiring the maximum tensile strength of the first-layer concrete beam according to the compressive strength;
the allowable weight obtaining module is used for solving according to the relation between the tensile stress and the maximum tensile strength of the first-layer concrete beam to obtain the allowable weight of the second-layer concrete beam;
and the allowable height acquisition module is used for solving an implicit function unknown quantity according to the relation between the tensile stress and the maximum tensile strength of the first layer concrete beam under the allowable maximum tensile strength and the allowable weight of the second layer concrete beam, and solving the allowable height of the full support according to the implicit function unknown quantity.
Further, the rigidity coefficient of the analysis model with the elastic support is as follows:
formula (20) wherein: em is the modulus of elasticity of the scaffold material; hm is the height of the full support; am is the area of the supporting section of the full support per square meter; i ismyAnd ImzThe inertia moments of the Y axis and the Z axis of the full support are respectively; mu is Poisson's ratio. Because the full framing is mainly resistant to compression, neglecting shearing and bending torsion, the spring stiffness K of the full framing is Em/Hm per linear meter.
Further, according to the flexural differential equation of the beam and the coordination condition of the support top settlement S and the flexural deformation of the first-layer beam, S is ω, that is:
P=K0S=K0ω (21)
K0the elastic coefficient of the bracket system represents the pressure intensity required by unit deformation; p is the pressure strength of any point on the top of the bracket; s is vertical deformation at the action position of P, and omega is the deflection of the first-layer concrete beam;
according to elasto-mechanical analysis, the beam equation:
in formulae (22) to (24): m is the bending moment to which the concrete beam is subjected, FsThe shear force borne by the first-layer concrete beam, E is the elastic modulus of the first-layer concrete beam, omega is the deflection of the first-layer concrete beam, and P (x) is the uniform load on the micro-section of the first-layer concrete beam
Further, in step S3, in step S4, equation (22) is applied, and the basic differential equation of the primary beam of the elastic support under the foundation is considered as follows:
the solution of equation (26) is:
therefore, the temperature of the molten metal is controlled,substituting the formula (8) to obtain:
solving to obtain:
further, applying equation (22), the basic differential equation of the elastic support first-layer beam without considering the foundation is:
the solution of equation (27) is:
similarly, the stress function of the elastic support first-layer beam under the foundation is not considered in the solution
Further, the tensile strength f of the first-layer concrete beamt,nTo compressive strength fcu,n0.05 times, i.e. ft,n=0.05fcu,n;
The first layer concrete does not crack and must meet the requirement of sigma<ft,nI.e. by
Considering the foundation as follows:
simplified backstage type (34)
The allowable weight of the second layer of concrete is as follows:
at the allowable ft,n、p0Then, the implicit function unknown β is solved from the formula (34), andthe height allowed for the scaffolding system is then:
formula (36) wherein: h (m) is the allowable height of the support system.
Further, the tensile strength f of the first-layer concrete beamt,nTo compressive strength fcu,n0.05 times, i.e. ft,n=0.05fcu,n;
The first layer concrete does not crack and must meet the requirement of sigma<ft,nI.e. by
Regardless of the foundation:
simplified backstage type (38)
The allowable weight of the second layer of concrete is as follows:
at the allowable ft,n、p0In the following, the implicit function unknowns are solved by equation (39)ThenThe height allowed for the stent system is then:
formula (40) wherein: h (m) is the allowable height of the support system.
In conclusion, the method is based on the elastomechanics plane problem analysis, the subsequent pouring concrete is used as the load, the foundation, the support, the primary concrete beam and the subsequent pouring concrete are really a force transmission system, and the method for judging the reasonable support height of the layered pouring concrete is provided. The method is based on an elastic mechanics plane problem analysis method, a stress function of a first-layer concrete beam is deduced, a judgment method for reasonable support height of the layered poured concrete is provided, during specific construction, an optimal support scheme is selected, and feasibility of the judgment method is demonstrated through mutual verification with finite element calculation, so that time and cost are saved for actual production, and good engineering and economic benefits are achieved.
Claims (7)
1. The method for judging the reasonable support height of the layered pouring concrete is characterized by specifically comprising the following steps of:
s1, erecting a full-hall support on the foundation, laying a template on the full-hall support, binding a first layer of reinforcing steel bars on the template after pre-pressing the full-hall support, pouring a first layer of concrete beam when the beam end is a simple support, binding reinforcing steel bars of a second layer of concrete beam when the first layer of concrete beam is hardened to a certain strength, and pouring the second layer of concrete beam;
s2, acquiring the length of the equal-section concrete beam of the first-layer concrete beam and the uniform load of the second-layer concrete beam on the first-layer concrete beam;
s3, simulating the action of the full framing on the first concrete beam by adopting an analysis model with an elastic support, and constructing a differential equation of the first concrete beam by combining the uniform load of the second concrete beam on the first concrete beam;
s4, solving a differential equation to obtain the tensile stress of the first-layer concrete beam;
s5, obtaining the compressive strength of the first-layer concrete beam, and obtaining the maximum tensile strength of the first-layer concrete beam according to the compressive strength;
s6, solving according to the relation between the tensile stress and the maximum tensile strength of the first-layer concrete beam to obtain the allowable weight of the second-layer concrete beam;
and S7, under the conditions of the allowable maximum tensile strength and the allowable weight of the second-layer concrete beam, solving an implicit function unknown quantity according to the relation between the tensile stress of the first-layer concrete beam and the maximum tensile strength, and solving the allowable height of the full framing according to the implicit function unknown quantity.
2. The method for judging the reasonable height of the layered casting concrete according to claim 1, wherein the rigidity coefficient of the analysis model with the elastic support is as follows:
formula (1) wherein: em is the modulus of elasticity of the scaffold material; hm is the height of the full support; am is the area of the supporting section of the full support per square meter; i ismyAnd ImzThe inertia moments of the Y axis and the Z axis of the full support are respectively; mu is Poisson's ratio. Because the full framing is mainly resistant to compression, neglecting shearing and bending torsion, the spring stiffness K of the full framing is Em/Hm per linear meter.
3. The method for judging the reasonable height of the cast-in-place concrete according to claim 2, wherein according to the flexural differential equation of the beam and the coordination condition of the support top settlement S and the flexural deformation of the first-layer beam, S ═ ω, namely:
P=K0S=K0ω (2)
K0the elastic coefficient of the bracket system represents the pressure intensity required by unit deformation; p is the pressure strength of any point on the top of the bracket; s is vertical deformation at the action position of P, and omega is the deflection of the first-layer concrete beam;
according to elasto-mechanical analysis, the beam equation:
in formulae (3) to (5): m is the bending moment of the concrete beam, Fs is the shearing force of the first layer of concrete beam, E is the elastic modulus of the first layer of concrete beam, omega is the deflection of the first layer of concrete beam, and P (x) is the uniform load on the micro-section of the first layer of concrete beam.
4. The method for determining the reasonable height of the cast-in-place concrete according to claim 3, wherein in step S3 and step S4, the formula (3) is applied, and the basic differential equation of the elastic support first-layer beam under the foundation is as follows:
the solution of equation (7) is:
therefore, the temperature of the molten metal is controlled,substituting the formula (8) to obtain:
solving to obtain:
5. the method for determining the reasonable height of the cast-in-place concrete according to claim 4, wherein in step S3, the basic differential equation without considering the elastic support first-layer beam under the foundation is as follows:
the solution of equation (8) is:
similarly, the stress function of the elastic support first-layer beam under the foundation is not considered in the solution
6. The method for determining the reasonable height of the cast-in-place concrete according to claim 4, wherein in step S5, the tensile strength f of the first-layer concrete beamt,nTo compressive strength fcu,n0.05 times, i.e. ft,n=0.05fcu,n;
In step S6, the first concrete layer does not crack, and sigma < f must be satisfiedt,nI.e. by
Considering the foundation as follows:
simplified backstage type (15)
The allowable weight of the second layer of concrete is as follows:
in step S7, f is allowedt,n、p0Then, the unknown quantity β of implicit function is solved by the formula (15)The height allowed for the stent system is then:
formula (17) wherein: h (m) is the allowable height of the support system.
7. The method for determining the reasonable height of the cast-in-place concrete according to claim 5, wherein in step S5, the tensile strength f of the first-layer concrete beamt,nTo compressive strength fcu,n0.05 times, i.e. ft,n=0.05fcu,n;
In step S6, the first concrete layer does not crack, and sigma < f must be satisfiedt,nI.e. by
Regardless of the foundation:
simplified backstage formula (19)
The allowable weight of the second layer of concrete is as follows:
in step S7, f is allowedt,n、p0In this way, the implicit function unknowns are solved from equation (18)Then The height allowed for the stent system is then:
formula (21) wherein: h (m) is the allowable height of the support system.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010469183.7A CN111783189B (en) | 2020-05-28 | 2020-05-28 | Method for judging reasonable bracket height of layered pouring concrete |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010469183.7A CN111783189B (en) | 2020-05-28 | 2020-05-28 | Method for judging reasonable bracket height of layered pouring concrete |
Publications (2)
Publication Number | Publication Date |
---|---|
CN111783189A true CN111783189A (en) | 2020-10-16 |
CN111783189B CN111783189B (en) | 2022-08-02 |
Family
ID=72754339
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010469183.7A Active CN111783189B (en) | 2020-05-28 | 2020-05-28 | Method for judging reasonable bracket height of layered pouring concrete |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111783189B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112962966A (en) * | 2021-02-09 | 2021-06-15 | 中建三局第一建设工程有限责任公司 | Layered pouring construction method for super-thick reinforced concrete horizontal component |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102121233A (en) * | 2011-04-20 | 2011-07-13 | 天津第三市政公路工程有限公司 | Construction method of bridge cast-in-place box beam |
CN202788877U (en) * | 2012-06-25 | 2013-03-13 | 广州市市政集团有限公司 | Horizontal-vertical loading tunnel combined type full space supporting and propping frame |
CN103437279A (en) * | 2013-08-29 | 2013-12-11 | 中交二公局第一工程有限公司 | Overhead cast-in-place box beam pressure-bearing strut and construction technology thereof |
CN104652280A (en) * | 2014-12-23 | 2015-05-27 | 上海市城市建设设计研究总院 | One-time continuous forming and pouring method for ultralong post-poured fish ridge wall and ultralong fish ridge wall |
CN107905109A (en) * | 2017-11-21 | 2018-04-13 | 重庆建工市政交通工程有限责任公司 | The loads such as the cast-in-place platform simulation of great-leap-forward bridge are segmented precompressed construction method |
CN110761190A (en) * | 2019-10-18 | 2020-02-07 | 中铁八局集团第六工程有限公司 | Construction method of Bailey beam full-space frame combined support |
-
2020
- 2020-05-28 CN CN202010469183.7A patent/CN111783189B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102121233A (en) * | 2011-04-20 | 2011-07-13 | 天津第三市政公路工程有限公司 | Construction method of bridge cast-in-place box beam |
CN202788877U (en) * | 2012-06-25 | 2013-03-13 | 广州市市政集团有限公司 | Horizontal-vertical loading tunnel combined type full space supporting and propping frame |
CN103437279A (en) * | 2013-08-29 | 2013-12-11 | 中交二公局第一工程有限公司 | Overhead cast-in-place box beam pressure-bearing strut and construction technology thereof |
CN104652280A (en) * | 2014-12-23 | 2015-05-27 | 上海市城市建设设计研究总院 | One-time continuous forming and pouring method for ultralong post-poured fish ridge wall and ultralong fish ridge wall |
CN107905109A (en) * | 2017-11-21 | 2018-04-13 | 重庆建工市政交通工程有限责任公司 | The loads such as the cast-in-place platform simulation of great-leap-forward bridge are segmented precompressed construction method |
CN110761190A (en) * | 2019-10-18 | 2020-02-07 | 中铁八局集团第六工程有限公司 | Construction method of Bailey beam full-space frame combined support |
Non-Patent Citations (2)
Title |
---|
Y.Y.Y. CAO 等: "Enhancing flexural performance of ultra-high performance concrete by an optimized layered-structure concept", 《COMPOSITES PART B: ENGINEERING》 * |
吴秋良: "山地城市现浇箱梁满堂支架关键施工技术", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112962966A (en) * | 2021-02-09 | 2021-06-15 | 中建三局第一建设工程有限责任公司 | Layered pouring construction method for super-thick reinforced concrete horizontal component |
CN112962966B (en) * | 2021-02-09 | 2022-06-07 | 中建三局第一建设工程有限责任公司 | Layered pouring construction method for super-thick reinforced concrete horizontal component |
Also Published As
Publication number | Publication date |
---|---|
CN111783189B (en) | 2022-08-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111576231B (en) | Optimization design method for layered pouring concrete beam of upper bracket of soft foundation | |
Vasdravellis et al. | The effects of axial tension on the hogging-moment regions of composite beams | |
Zagon et al. | Shear behaviour of SFR-UHPC I-shaped beams | |
CN111560856B (en) | Construction method for layering pouring concrete beam on soft soil foundation | |
CN111797449B (en) | Method for judging reasonable height of layered pouring concrete beam | |
Griffis | Composite frame construction | |
Arrayago et al. | Experimental investigation on ferritic stainless steel composite slabs | |
CN110795785A (en) | Model building system of concrete continuous box girder bridge | |
CN111625895B (en) | Stress safety judgment method for support uneven settlement concrete beam | |
CN111783189B (en) | Method for judging reasonable bracket height of layered pouring concrete | |
CN111563344B (en) | Method for safely judging stress of first-layer beam of layered casting concrete | |
Gambhir | Fundamentals of reinforced concrete design | |
CN101798856B (en) | Steel-concrete combined beam and construction method thereof | |
Sun et al. | Progressive failure of precast shear wall structure for RC composite column confined uniform hollow panels under cyclic loading | |
Yuan‐Yuan et al. | Mechanical behavior of precast building concrete walls with different connection technologies for seismic areas | |
Lu et al. | Mechanical performance of prefabricated concrete beam-column joints with double-grouted sleeve connectors: A numerical and theoretical study | |
CN111551326B (en) | Displacement monitoring method for settlement foundation layered casting concrete beam | |
Panchal | Advanced design of composite steel-concrete structural element | |
Lárusson et al. | Prefabricated floor panels composed of fiber reinforced concrete and a steel substructure | |
Seo et al. | Evaluation of prism and diagonal tension strength of masonry form-block walls reinforced with steel fibers | |
Pei et al. | Design and key construction technology of steel-concrete-steel sandwich composite pylon for a large span cable-stayed bridge | |
Chira et al. | Load-deformation response of long span prestressed concrete wide beams | |
Frosch et al. | Development and Splice Lengths for High-Strength Reinforcement, Volume I: General Bar Development | |
Tarabia et al. | Behavior of precast reinforced concrete beam-column external connections under cyclic loading | |
Liu et al. | Shear performance of prestressed partially-precast steel reinforced concrete beam: Experiments and analyses |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |