CN112897339A - Method for turning large-diameter single pile of full-rotation crane ship - Google Patents

Method for turning large-diameter single pile of full-rotation crane ship Download PDF

Info

Publication number
CN112897339A
CN112897339A CN202110042303.XA CN202110042303A CN112897339A CN 112897339 A CN112897339 A CN 112897339A CN 202110042303 A CN202110042303 A CN 202110042303A CN 112897339 A CN112897339 A CN 112897339A
Authority
CN
China
Prior art keywords
single pile
hook
auxiliary
main
ship
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110042303.XA
Other languages
Chinese (zh)
Inventor
李宏权
陈永青
彭小亮
张宝刚
陈文兵
刘永平
韩天星
周文
罗国兵
梁其旻
袁春进
叶剑振
刘红志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Poly Changda Engineering Co Ltd
Original Assignee
Poly Changda Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Poly Changda Engineering Co Ltd filed Critical Poly Changda Engineering Co Ltd
Priority to CN202110042303.XA priority Critical patent/CN112897339A/en
Publication of CN112897339A publication Critical patent/CN112897339A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/36Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
    • B66C23/52Floating cranes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Abstract

The invention discloses a method for turning a large-diameter single pile of a full-circle slewing crane ship, which comprises the following steps of: s1: positioning a ship, namely anchoring and positioning a crane ship and a transport ship when the crane ship and the transport ship run to the wind field machine position, and keeping the positions relatively stable; s2: selecting proper sling, main sling and auxiliary sling, welding a pad beam and a limiter on the transport ship in advance, and facilitating the fixed placement of the single pile; s3: the main lifting rope parallelly hangs the lifting rope tool on the main hook, the auxiliary hook is hung on the auxiliary hook, one end of the auxiliary lifting rope is hung on the main hook, the main lifting rope is connected with lifting lugs on two sides of the single pile, and the other end of the auxiliary lifting rope is provided with a tail sliding hook fixed at the other end of the single pile; s4: and the main hook lifts the single pile, after the single pile leaves the transport ship, the transport ship drives away from the crane ship, the single pile is lifted until the tail hook is unhooked, and then the single pile is continuously lifted to be vertical, so that pile turning is completed. The main and auxiliary lifting ropes on the crane ship enable the single pile to be more stable under the matching of the lifting piles, the operation safety is improved, the whole construction process is simple and reliable, and the construction efficiency is high.

Description

Method for turning large-diameter single pile of full-rotation crane ship
[ technical field ] A method for producing a semiconductor device
The invention belongs to the technical field of offshore wind power engineering, and particularly relates to a method for turning a large-diameter single pile of a full-rotation crane ship.
[ background of the invention ]
The offshore wind power generation method has the advantages that offshore wind power is rapid, the power generation is realized by fully utilizing offshore wind power resources, a part of electric energy sources can be provided for cities, the power supply pressure of the cities is relieved, the construction of offshore wind power engineering is complex and difficult to achieve, the single-pile foundation is one of the most common structures of offshore wind turbine foundations, the structure is simple, the technology is mature, after the single-pile foundation is constructed and transported to a construction site by a transport ship, a crane ship is used for turning over and erecting piles, the single pile is large in size and large in mass, the existing technology is used for hanging and turning over piles on the sea, and the working efficiency is low.
[ summary of the invention ]
In order to solve the existing problems in the background art, the invention provides a method for turning a large-diameter single pile by a full-rotation crane ship.
The invention adopts the following technical scheme:
a method for turning over a large-diameter single pile of a full-rotation crane ship comprises the following steps:
s1: positioning a ship, namely anchoring and positioning a crane ship and a transport ship when the crane ship and the transport ship run to the wind field machine position, and keeping the positions relatively stable;
s2: selecting proper sling, main sling and auxiliary sling, welding a pad beam and a limiter on the transport ship in advance, and facilitating the fixed placement of the single pile;
s3: the main lifting rope parallelly hangs the lifting rope tool on the main hook, the auxiliary hook is hung on the auxiliary hook, one end of the auxiliary lifting rope is hung on the main hook, the main lifting rope is connected with lifting lugs on two sides of the single pile, and the other end of the auxiliary lifting rope is provided with a tail sliding hook fixed at the other end of the single pile;
s4: and the main hook lifts the single pile, after the single pile leaves the transport ship, the transport ship drives away from the crane ship, the single pile is lifted until the tail hook is unhooked, and then the single pile is continuously lifted to be vertical, so that pile turning is completed.
Further, step S1 includes:
s11: calculating coordinates of five anchor points in advance according to the wind field machine position;
s12: the crane ship is anchored and positioned on the coordinates of the five anchor points, and the crane ship is accurately positioned on the wind field machine position 150m away from the pile stabilizing platform by anchor winches;
s13: the transport ship runs to the transport ship and is positioned under the main hook and is parallel to the crane ship.
Further, step S2 includes:
s21: after selecting a proper sling, connecting a main lifting rope to two ends of the sling;
s22: one end of the auxiliary lifting rope is connected with the tail sliding hook.
Further, step S3 includes:
s31: the main lifting rope and the auxiliary lifting rope are hung on the main hook together, meanwhile, the auxiliary rope is tied on the auxiliary hook, after the main hook is placed right above the single pile, the main lifting rope and lifting lugs on two sides of the single pile are connected, the tail sliding hook on the auxiliary lifting rope clamps the other end of the single pile, the guy rope is tied at the lifting lugs to prevent the rope from falling off, and the main lifting rope, the auxiliary lifting rope and the single pile are connected in a tightening mode through dragging the guy rope.
Further, step S4 includes:
s41: lifting the main hook, gradually lifting the single pile, obliquely lifting the single pile until the single pile is completely separated from the transport ship, and then driving the transport ship away from the crane ship;
s42: and (3) the single pile begins to sink to the mud surface, the main hook is observed to bear the tonnage, after the tonnage is detected to be reduced, the auxiliary hook tightens the auxiliary rope to drive the auxiliary lifting rope to be separated from the main hook, the auxiliary hook is pulled again to enable the tail sliding hook to be separated from the single pile, then the main hook is lifted to the single pile to be erected, the guy rope is tightened, and pile overturning is completed.
The invention has the following beneficial effects:
the construction is carried out by adopting the full-circle-turning crane ship, the traditional double ships are replaced to participate in lifting, and the investment cost of equipment is reduced.
The boom on the crane ship is provided with a main hook and an auxiliary hook for matching, lifting ropes are hung on the main hook and connected with lifting lugs on two sides of a single pile, one end of an auxiliary lifting rope is hung on the main hook and connected on the auxiliary hook through an auxiliary rope, the other end of the auxiliary lifting rope is connected with a tail hook in a clamping mode and connected with the tail end of the single pile, the single pile is lifted and sunk to a mud surface gradually by lifting of the main hook, the auxiliary lifting rope is tightened by the auxiliary hook and gradually separated from the main hook and the tail hook separated from the single pile, finally the single pile is lifted to be erected by the main hook to complete pile overturning, the single pile can be more stable by the main lifting rope and the auxiliary lifting rope under the matching of the lifting piles, the operation safety is improved, the whole construction process is simple and reliable.
[ description of the drawings ]
FIG. 1 is a schematic view of the positioning structure of a fully slewing crane vessel and a transport vessel according to the present invention;
FIG. 2 is a schematic structural view of the crane of the present invention with the main lifting rope, the auxiliary lifting rope and the mono-pile connected;
FIG. 3 is a schematic view of the construction of the present invention in lifting a single pile;
fig. 4 is a schematic view of the construction of the present invention for lifting a mono pile.
[ detailed description ] embodiments
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not limiting of the invention.
The invention relates to a method for turning a large-diameter single pile of a full-rotation crane ship, which specifically comprises the following steps:
s1: positioning a ship, namely driving a crane ship 1 and a transport ship 2 to a wind field machine position for anchoring and positioning as shown in figure 1, and keeping the positions relatively stable; specifically, five anchor point coordinates are obtained through pre-calculation according to the wind field machine position, the crane ship 1 is anchored and positioned on the five anchor point coordinates, the crane ship 1 is accurately positioned on the wind field machine position 150m away from the pile stabilizing platform through anchor mooring, then the transport ship 2 runs to a position right below a main hook 3 on the transport ship 2 and is anchored, the position parallel to the crane ship 1 is convenient for the follow-up main hook 3 to be lowered to directly lift a single pile 4, and the steps of arm support adjustment are reduced.
S2: as shown in fig. 2, selecting proper lifting rigging 5, main lifting rope 6 and auxiliary lifting rope 7, and welding pad beams and a stopper before the transport ship 2 is lifted, so as to facilitate the fixed placement of the single pile 4; specifically, the main lifting rope 6 is connected to two ends of the lifting rigging 5, in the installation process, the lifting rigging 5 must be adjusted to be horizontal, the stress of the lifting pile can be evenly applied to two sides of the single pile 4, one end of the auxiliary lifting rope 7 is tied with the tail sliding hook 8, and the main lifting rope 7 and the auxiliary lifting rope 7 participate in the safety of the lifting construction together.
S3: as shown in fig. 2, the main lifting rope 6 hangs the lifting rope tool 5 on the main hook 3 in parallel, the auxiliary lifting rope 9 hangs the auxiliary rope 10 on the auxiliary hook 9 to hang one end of the auxiliary lifting rope 7 on the main hook 3, the main lifting rope 6 is connected with the lifting lugs on two sides of the single pile 4, and the other end of the auxiliary lifting rope 7 is provided with the tail sliding hook 8 fixed at the other end of the single pile 4; specifically, main lifting rope 6 and vice lifting rope 7 are together hung and are established on main hook 3, supplementary rope 10 system simultaneously on vice hook 9, main hook 3 transfers to single pile 4 directly over the back, the lug of both sides is connected on main lifting rope 6 and the single pile 4, smooth tail hook 8 on the vice lifting rope 7 blocks on the other end of single pile 4, the rope is prevented from taking off in lug department tie up the guy rope, pull guy rope and step up main lifting rope 6, vice lifting rope 7 and single pile 4 and connect, the further dangerous emergence that the main and vice lifting rope breaks away from single pile 4 in the work progress of ensureing, the stake of single pile 4 is more firm simultaneously.
S4: as shown in fig. 3, the single pile 4 is lifted by the main hook 3, after the single pile 4 leaves the transport ship 2, the transport ship 2 drives away from the crane ship 1, the single pile 4 is lifted to the unhooking position of the tail slipping hook 8, and then the single pile 4 is continuously lifted to be vertical, specifically, in the lifting process of the main hook 3, the single pile 4 is gradually lifted, because the lifting lug is designed at one end of the middle part of the single pile 4, after the main hook 3 is lifted, the gravity center is positioned at one section of the lifting lug and the low end, and when the auxiliary lifting rope 7 is clamped at the tail end of the single pile 4 through the tail slipping hook 8, the auxiliary lifting rope 7 is not in a tight state, but in a relatively loose state, and after the single pile 4 is continuously lifted to be completely separated from the transport ship 2, the transport ship 2 drives away from the crane ship 1; the main hook 3 is lowered, the single pile 4 is slowly sunk into a mud surface, the pile bottom firstly contacts the seabed, the stress point of the single pile 4 is on a lifting lug and the seabed at the moment, the stability of pile turning is facilitated, the difficulty is reduced, then the observation that the main hook 3 bears the tonnage is carried out, after the tonnage is detected to be reduced, the auxiliary hook 9 tightens the auxiliary rope 10 to drive the auxiliary lifting rope 7 to be separated from the main hook 3, the auxiliary hook 9 is pulled again to enable the tail sliding hook 8 to be separated from the single pile 4, then the main hook 3 is lifted until the single pile 4 is erected, and the guy rope is tightened to finish pile turning in the state shown in the figure 4; it can be seen that under main lifting rope 6 and vice lifting rope 7 participate in jointly for the pile process is more firm, improves the construction security, and holistic work progress is efficient, reliable practical.
The invention has the advantages that:
the construction is carried out by adopting the full-circle-turning crane ship, the traditional double ships are replaced to participate in lifting, and the investment cost of equipment is reduced.
The boom on the crane ship is provided with a main hook and an auxiliary hook for matching, lifting ropes are hung on the main hook and connected with lifting lugs on two sides of a single pile, one end of an auxiliary lifting rope is hung on the main hook and connected on the auxiliary hook through an auxiliary rope, the other end of the auxiliary lifting rope is connected with a tail hook in a clamping mode and connected with the tail end of the single pile, the single pile is lifted and sunk to a mud surface gradually by lifting of the main hook, the auxiliary lifting rope is tightened by the auxiliary hook and gradually separated from the main hook and the tail hook separated from the single pile, finally the single pile is lifted to be erected by the main hook to complete pile overturning, the single pile can be more stable by the main lifting rope and the auxiliary lifting rope under the matching of the lifting piles, the operation safety is improved, the whole construction process is simple and reliable.
It will be appreciated by those skilled in the art that the invention may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. The embodiments disclosed above are therefore to be considered in all respects as illustrative and not restrictive. All changes which come within the scope of or equivalence to the invention are intended to be embraced therein.

Claims (5)

1. A method for turning over a large-diameter single pile of a full-rotation crane ship is characterized by comprising the following steps:
s1: positioning a ship, namely anchoring and positioning a crane ship and a transport ship when the crane ship and the transport ship run to the wind field machine position, and keeping the positions relatively stable;
s2: selecting proper sling, main sling and auxiliary sling, welding a pad beam and a limiter on the transport ship in advance, and facilitating the fixed placement of the single pile;
s3: the main lifting rope parallelly hangs the lifting rope tool on the main hook, the auxiliary hook is hung on the auxiliary hook, one end of the auxiliary lifting rope is hung on the main hook, the main lifting rope is connected with lifting lugs on two sides of the single pile, and the other end of the auxiliary lifting rope is provided with a tail sliding hook fixed at the other end of the single pile;
s4: and the main hook lifts the single pile, after the single pile leaves the transport ship, the transport ship drives away from the crane ship, the single pile is lifted until the tail hook is unhooked, and then the single pile is continuously lifted to be vertical, so that pile turning is completed.
2. The method for upending a large-diameter single pile by a full slewing crane vessel as claimed in claim 1, wherein the step S1 comprises:
s11: calculating coordinates of five anchor points in advance according to the wind field machine position;
s12: the crane ship is anchored and positioned on the coordinates of the five anchor points, and the crane ship is accurately positioned on the wind field machine position 150m away from the pile stabilizing platform by anchor winches;
s13: the transport ship runs to the transport ship and is positioned under the main hook and is parallel to the crane ship.
3. The method for upending a large-diameter single pile by a full slewing crane vessel as claimed in claim 1, wherein the step S2 comprises:
s21: after selecting a proper sling, connecting a main lifting rope to two ends of the sling;
s22: one end of the auxiliary lifting rope is connected with the tail sliding hook.
4. The method for upending a large-diameter single pile by a full slewing crane vessel as claimed in claim 1, wherein the step S3 comprises:
s31: the main lifting rope and the auxiliary lifting rope are hung on the main hook together, meanwhile, the auxiliary rope is tied on the auxiliary hook, after the main hook is placed right above the single pile, the main lifting rope and lifting lugs on two sides of the single pile are connected, the tail sliding hook on the auxiliary lifting rope clamps the other end of the single pile, the guy rope is tied at the lifting lugs to prevent the rope from falling off, and the main lifting rope, the auxiliary lifting rope and the single pile are connected in a tightening mode through dragging the guy rope.
5. The method for upending a large-diameter single pile by a full slewing crane vessel as claimed in claim 1, wherein the step S4 comprises:
s41: lifting the main hook, gradually lifting the single pile, obliquely lifting the single pile until the single pile is completely separated from the transport ship, and then driving the transport ship away from the crane ship;
s42: and (3) the single pile begins to sink to the mud surface, the main hook is observed to bear the tonnage, after the tonnage is detected to be reduced, the auxiliary hook tightens the auxiliary rope to drive the auxiliary lifting rope to be separated from the main hook, the auxiliary hook is pulled again to enable the tail sliding hook to be separated from the single pile, then the main hook is lifted to the single pile to be erected, the guy rope is tightened, and pile overturning is completed.
CN202110042303.XA 2021-01-13 2021-01-13 Method for turning large-diameter single pile of full-rotation crane ship Pending CN112897339A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110042303.XA CN112897339A (en) 2021-01-13 2021-01-13 Method for turning large-diameter single pile of full-rotation crane ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110042303.XA CN112897339A (en) 2021-01-13 2021-01-13 Method for turning large-diameter single pile of full-rotation crane ship

Publications (1)

Publication Number Publication Date
CN112897339A true CN112897339A (en) 2021-06-04

Family

ID=76112709

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110042303.XA Pending CN112897339A (en) 2021-01-13 2021-01-13 Method for turning large-diameter single pile of full-rotation crane ship

Country Status (1)

Country Link
CN (1) CN112897339A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113896088A (en) * 2021-09-01 2022-01-07 中国化学工程第三建设有限公司 Device and method for single-machine hoisting of climbing-free hook unloading of spherical shell plate with column legs
CN116924208A (en) * 2023-09-18 2023-10-24 中交第一航务工程局有限公司 Single-ship double-main-hook large-diameter single pile turning method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425167A (en) * 2011-11-25 2012-04-25 天津港航工程有限公司 Pile sinking method for driving large-diameter steel pipe pile in intertidal zone
JP2015168485A (en) * 2014-03-04 2015-09-28 ジャパンマリンユナイテッド株式会社 Crane device, work ship, and work method of ocean wind power generation facility
CN109775565A (en) * 2019-02-25 2019-05-21 中交第三航务工程局有限公司 A kind of large-diameter pile single hook turns over piling method under water
CN110453709A (en) * 2019-06-24 2019-11-15 中交第三航务工程局有限公司 A kind of offshore wind farm large-diameter pile process for sinking

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425167A (en) * 2011-11-25 2012-04-25 天津港航工程有限公司 Pile sinking method for driving large-diameter steel pipe pile in intertidal zone
JP2015168485A (en) * 2014-03-04 2015-09-28 ジャパンマリンユナイテッド株式会社 Crane device, work ship, and work method of ocean wind power generation facility
CN109775565A (en) * 2019-02-25 2019-05-21 中交第三航务工程局有限公司 A kind of large-diameter pile single hook turns over piling method under water
CN110453709A (en) * 2019-06-24 2019-11-15 中交第三航务工程局有限公司 A kind of offshore wind farm large-diameter pile process for sinking

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113896088A (en) * 2021-09-01 2022-01-07 中国化学工程第三建设有限公司 Device and method for single-machine hoisting of climbing-free hook unloading of spherical shell plate with column legs
CN113896088B (en) * 2021-09-01 2023-08-04 中国化学工程第三建设有限公司 Device and method for lifting spherical shell plate with column legs by single machine without ascending and unhooking
CN116924208A (en) * 2023-09-18 2023-10-24 中交第一航务工程局有限公司 Single-ship double-main-hook large-diameter single pile turning method
CN116924208B (en) * 2023-09-18 2023-12-01 中交第一航务工程局有限公司 Single-ship double-main-hook large-diameter single pile turning method

Similar Documents

Publication Publication Date Title
CN109853567B (en) Pile sinking method for offshore wind power rock-socketed steel pipe pile
CN101798869B (en) Method for automatically centering and inversely installing vertical shaft pipelines
CN102328732A (en) Offshore pile driving, pile pressing and installing united engineering ship
CN112897339A (en) Method for turning large-diameter single pile of full-rotation crane ship
CN111648362A (en) Large-diameter overweight and overlong single-pile single-hook hoisting and turning-over process
CN112482388A (en) Pile hoisting method of full-rotation crane ship
CN105417403A (en) Method for installing ultrahigh ultra-large type floating crane in dock
CN108396754B (en) Construction method of suspended floating splicing steel cofferdam
CN115788782A (en) Floating type fan offshore installation process
CN108396762A (en) A kind of steady stake platform of monoblock type
CN204702437U (en) A kind of build-up type power pontoon combination mast crane device
CN107487724B (en) Non-crane-assisted large floating crane arm support mounting device and mounting method
CN112726622A (en) Method for overturning large-diameter single pile of fixed-boom crane ship
CN113044717A (en) Pile turning construction method for steel pipe pile
CN111155520A (en) Offshore large-diameter steel pipe pile erecting method and pile erecting device thereof
CN203452013U (en) Integrated unloading device for cantilever casting cradle template
CN102926329B (en) Device dedicated for lifting steel box beam of small and medium-sized long-span suspension bridge and lifting method
CN112412154B (en) Ultra-high voltage transmission line construction process with floating type overwater platform as operation surface
CN114348852A (en) H-shaped steel beam erection hoisting device
CN112373652A (en) High strutting arrangement of platform is dismantled in semi-submerged formula jack-up
CN112850488B (en) Method for overturning steel pipe pile by fixed arm frame crane ship
CN219862799U (en) Device for assisting pile inserting and positioning of steel pipe pile
CN219906751U (en) Offshore pile turning device
CN111017117A (en) Mooring chain underwater connection method and underwater connection platform
CN115009433B (en) Pile-driving shore protection emergency rescue ship-based integrated equipment platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination