CN112854290A - Construction method for reinforcing transformer substation equipment foundation - Google Patents

Construction method for reinforcing transformer substation equipment foundation Download PDF

Info

Publication number
CN112854290A
CN112854290A CN202110056920.5A CN202110056920A CN112854290A CN 112854290 A CN112854290 A CN 112854290A CN 202110056920 A CN202110056920 A CN 202110056920A CN 112854290 A CN112854290 A CN 112854290A
Authority
CN
China
Prior art keywords
foundation
reinforcing
original
channel steel
anchor rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110056920.5A
Other languages
Chinese (zh)
Inventor
李翠凤
舒恺
郭高鹏
任建炜
俞嘉辉
郑学渊
王朴炎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Electric Power Design Institute Co ltd
Original Assignee
Ningbo Electric Power Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Electric Power Design Institute Co ltd filed Critical Ningbo Electric Power Design Institute Co ltd
Priority to CN202110056920.5A priority Critical patent/CN112854290A/en
Publication of CN112854290A publication Critical patent/CN112854290A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a construction method for reinforcing a substation equipment foundation, which comprises the following construction steps: a. excavating the ground until the original foundation is exposed, cleaning the surface of the ground, and leveling the ground within the reinforcing range of the periphery of the foundation; punching the side face of the original foundation which needs to be amplified and reinforced, fixing the anchor rod on the original foundation, and then injecting an inorganic injection material into the hole to ensure that the hole is dense; mounting channel steel on the anchor rod, fixing the channel steel on the original foundation through the anchor rod by using a nut, and then injecting an inorganic injection material between the channel steel and the original foundation to ensure compactness; arranging a reinforcing mesh for reinforcing the foundation part on the leveled ground, wherein the reinforcing mesh is fixed on the original foundation through welding with a channel steel flange; and pouring concrete to a specified elevation for reinforcement, and backfilling the foundation soil after the maintenance reaches a specified age. The advantages are that: the invention is connected with the original foundation to form an integral stress, and the bearing capacity of the foundation is increased.

Description

Construction method for reinforcing transformer substation equipment foundation
Technical Field
The invention relates to a construction method for reinforcing a substation equipment foundation, which is suitable for integrally reinforcing the equipment foundation after the substation equipment is subjected to capacity expansion and load increase and belongs to the field of civil and architectural engineering.
Background
With the rapid development of domestic economy, the loads of industrial electricity and domestic electricity of residents are rapidly increased, and the construction and capacity allocation of the transformer substation cannot meet the electricity demand of the residents. There are two general ways to solve the above contradiction, one is to increase the speed and force of the new substation, and the other is to expand the capacity based on the original substation. Partial transformer substations in cities in China are built in core positions of commercial centers, financial centers and the like, if a mode of increasing new transformer substations needs to occupy more land resources, a mode of expanding capacity on the basis of original transformer substations is a more reasonable mode.
The expansion on the basis of the original transformer substation causes that the foundation of the original equipment needs to be reinforced due to the reasons that the bearing capacity of the foundation is not met or the settlement is too large and the like. Meanwhile, the foundation reinforcement of the transformer substation equipment has the following restrictions that firstly, the equipment operates in an electric field area of a transformer substation, the safety requirement is extremely high, and the construction operation height is limited; secondly, various existing construction machines cannot enter the site for construction due to the limitation of safe construction distance; thirdly, the original foundation and foundation cannot be disturbed; fourthly, the basic distribution quantity is large and wide, and the dispersion is independent.
Disclosure of Invention
The invention aims to overcome the defects in the prior art, and provides a construction method for reinforcing a substation equipment foundation.
In order to achieve the purpose, the invention adopts the technical scheme that: a construction method for reinforcing a substation equipment foundation comprises the following construction steps:
a. excavating foundation soil: excavating the ground until the original foundation is exposed, cleaning the surface of the ground, and leveling the ground within the reinforcing range of the periphery of the foundation;
b. installing an anchor rod: punching the side face of the original foundation which needs to be amplified and reinforced, fixing the anchor rod on the original foundation, and then injecting an inorganic injection material into the hole to ensure that the hole is dense;
c. installing channel steel: mounting channel steel on the anchor rod, fixing the channel steel on the original foundation through the anchor rod by using a nut, and then injecting an inorganic injection material between the channel steel and the original foundation to ensure compactness;
d. welding a reinforcing mesh: arranging a reinforcing mesh for reinforcing the foundation part on the leveled ground, wherein the reinforcing mesh is fixed on the original foundation through welding with a channel steel flange;
e. pouring concrete: and pouring concrete to a specified elevation for reinforcement, and backfilling the foundation soil after the maintenance reaches a specified age.
The anchor rod is made of fiber composite reinforced materials.
And e, adopting basalt fiber reinforced concrete as the concrete in the step e.
Compared with the prior art, the invention has the advantages that:
1. according to the invention, the original stress form of the foundation is not changed, the channel steel and the anchor rod are tightly connected with the foundation, the transmission of force is ensured through the bolt and bolt action of the anchor rod, meanwhile, the fiber reinforced composite material anchor rod has higher rigidity, and basalt fiber reinforced concrete with better mechanical property is adopted, so that the integrity of a foundation reinforcing part and the original part is ensured, and the effective transmission of load is ensured;
2. the anchor rods are adopted to connect the side surfaces of the foundation, so that the foundation does not need to be excavated to a position below the elevation of the foundation, and the disturbance to foundation soil and peripheral facilities is small;
3. the non-conductive fiber composite reinforced material is adopted, so that the construction safety of a live plant area is ensured, the construction is convenient and simple, large-scale equipment is not needed, and the construction period is short.
Drawings
FIG. 1 is a schematic structural view of a masonry structure building foundation reinforced by the present invention
Detailed Description
The following description is only a preferred embodiment of the present invention, and does not limit the scope of the present invention.
Example, see figure 1: a construction method for reinforcing a substation equipment foundation comprises the following construction steps:
a. excavating foundation soil: detecting and evaluating the current situation of the original equipment foundation, and determining the foundation size of the foundation reinforcement part by referring to corresponding specifications according to the conditions of the settlement degree and the stress condition of the foundation 1, the current situation of the original foundation 2 and the like; and excavating the ground until the original foundation 2 is exposed, cleaning the surface of the ground, and leveling the ground within the reinforcing range of the periphery of the foundation.
b. Installing an anchor rod: calculating and determining the installation positions and the number of the anchor rods 3 according to the conditions such as the foundation condition, the stress condition, the material size, the construction requirement and the like; punching holes on the side faces of the original foundation 2 which needs to be amplified and reinforced, fixing an anchor rod 3 made of fiber composite reinforced materials on the original foundation 2, and then injecting inorganic injection materials into the holes to ensure that the holes are compact; in order to reduce the disturbance to the foundation, the holes are preferably arranged in a staggered manner.
c. Installing channel steel: processing channel steel 4 according to the length of the original foundation 2 and the position of the hole, wherein the channel steel 4 is provided with a reserved hole for allowing the anchor rod 3 to penetrate through the installation position and the number; then pass through the nut with channel-section steel 4 and fix on original basis 2 through stock 3, inject into inorganic material 9 of irritating again between channel-section steel 4 and original basis 2 to guarantee closely knit, with the transmission of assurance power.
d. Welding a reinforcing mesh: and arranging a reinforcing mesh 5 for reinforcing the foundation part on the leveled ground, wherein the reinforcing mesh 5 is fixed on the original foundation 2 by welding with the flange of the channel steel 4.
e. Pouring concrete: and (3) pouring concrete 6 to a specified elevation, reinforcing, namely adopting basalt fiber reinforced concrete for the concrete 6, and backfilling the foundation soil 7 to the ground to the specified elevation after leveling maintenance to a specified age.

Claims (3)

1. A construction method for reinforcing a substation equipment foundation is characterized by comprising the following steps: the construction steps are as follows:
a. excavating foundation soil: excavating the ground until the original foundation is exposed, cleaning the surface of the ground, and leveling the ground within the reinforcing range of the periphery of the foundation;
b. installing an anchor rod: punching the side face of the original foundation which needs to be amplified and reinforced, fixing the anchor rod on the original foundation, and then injecting an inorganic injection material into the hole to ensure that the hole is dense;
c. installing channel steel: mounting channel steel on the anchor rod, fixing the channel steel on the original foundation through the anchor rod by using a nut, and then injecting an inorganic injection material between the channel steel and the original foundation to ensure compactness;
d. welding a reinforcing mesh: arranging a reinforcing mesh for reinforcing the foundation part on the leveled ground, wherein the reinforcing mesh is fixed on the original foundation through welding with a channel steel flange;
e. pouring concrete: and pouring concrete to a specified elevation for reinforcement, and backfilling the foundation soil after the maintenance reaches a specified age.
2. The method of consolidating a substation equipment foundation of claim 1, wherein: the anchor rod is made of fiber composite reinforced materials.
3. The construction method for reinforcing the substation equipment foundation according to claim 1, wherein: and e, adopting basalt fiber reinforced concrete as the concrete in the step e.
CN202110056920.5A 2021-01-15 2021-01-15 Construction method for reinforcing transformer substation equipment foundation Pending CN112854290A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110056920.5A CN112854290A (en) 2021-01-15 2021-01-15 Construction method for reinforcing transformer substation equipment foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110056920.5A CN112854290A (en) 2021-01-15 2021-01-15 Construction method for reinforcing transformer substation equipment foundation

Publications (1)

Publication Number Publication Date
CN112854290A true CN112854290A (en) 2021-05-28

Family

ID=76007006

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110056920.5A Pending CN112854290A (en) 2021-01-15 2021-01-15 Construction method for reinforcing transformer substation equipment foundation

Country Status (1)

Country Link
CN (1) CN112854290A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101250886A (en) * 2008-04-09 2008-08-27 武汉大学 Method for reinforcing masonry structure building base
CN104532853A (en) * 2014-12-30 2015-04-22 武汉中力岩土工程有限公司 Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN105604100A (en) * 2016-01-04 2016-05-25 青岛理工大学 External anchoring method for non-metal anti-floating anchor rod
CN109458196A (en) * 2019-01-15 2019-03-12 西南交通大学 A kind of environment-friendlydurable durable single shell lining structure suitable for Support System in Soft Rock Tunnels
CN209212273U (en) * 2018-12-22 2019-08-06 山东科技大学 A kind of basalt fibre reinforcing body anchor pole
CN111537351A (en) * 2020-06-28 2020-08-14 青岛理工大学 Method for testing bearing performance of anchor rod under coupling action of load and erosion environment
CN111962545A (en) * 2020-08-10 2020-11-20 南京市园林规划设计院有限责任公司 Soft foundation treatment method for compaction foundation soil with FRP (fiber reinforced plastic) wood piles stuck inside

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101250886A (en) * 2008-04-09 2008-08-27 武汉大学 Method for reinforcing masonry structure building base
CN104532853A (en) * 2014-12-30 2015-04-22 武汉中力岩土工程有限公司 Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN105604100A (en) * 2016-01-04 2016-05-25 青岛理工大学 External anchoring method for non-metal anti-floating anchor rod
CN209212273U (en) * 2018-12-22 2019-08-06 山东科技大学 A kind of basalt fibre reinforcing body anchor pole
CN109458196A (en) * 2019-01-15 2019-03-12 西南交通大学 A kind of environment-friendlydurable durable single shell lining structure suitable for Support System in Soft Rock Tunnels
CN111537351A (en) * 2020-06-28 2020-08-14 青岛理工大学 Method for testing bearing performance of anchor rod under coupling action of load and erosion environment
CN111962545A (en) * 2020-08-10 2020-11-20 南京市园林规划设计院有限责任公司 Soft foundation treatment method for compaction foundation soil with FRP (fiber reinforced plastic) wood piles stuck inside

Similar Documents

Publication Publication Date Title
CN108035376B (en) Anti-deformation rectification foundation applicable to goaf site wind turbine generator and construction method thereof
CN104652443A (en) Construction method for temporary horizontal supports serving as permanent structural beams simultaneously of deep foundation pit
CN109295994B (en) Full-assembly type wind power tower cylinder foundation with combined structure
CN104179249A (en) Assembled composite-structure earthquake-resistant wall and assembly method thereof
CN105386454A (en) United assembled foundation for power transmission tower
CN108360901A (en) Novel low layer assembled wallboard structure energy dissipating bolt joint
CN210946866U (en) Prefabricated shell spiral anchor composite foundation
CN112575797A (en) Assembled profile steel-concrete support rod piece for foundation pit support
CN112854290A (en) Construction method for reinforcing transformer substation equipment foundation
CN112575789A (en) Diagonal space truss foundation pit inner support system
CN210002443U (en) prefabricated combined reinforced concrete shaft
CN214695645U (en) Supporting structure capable of applying prestress
CN205046569U (en) Annular wind -powered electricity generation foundation structure based on shaping of two ripple steel cylinder
Chen On the Influence of Pile Foundation Settlement of Existing High‐Rise Buildings on the Surrounding Buildings
CN210289224U (en) Steel wire cloth reinforced structure for building restoration
CN210597380U (en) Underground utility tunnel construction structure
CN204023774U (en) A kind of assembling composite construction seismic structural wall, earthquake resistant wall
CN205259206U (en) Column foot basis
CN207176727U (en) Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform
CN218622301U (en) Foundation structure of steel-concrete tower of wind generating set
CN215594097U (en) Fan foundation reinforcing structure
CN221168826U (en) Shock insulation reinforcing structure of newly added steel hoop of existing frame structure
CN214741845U (en) Precast concrete pipe sheet connecting structure for steel-concrete tower cylinder
CN216787196U (en) Fan foundation capable of reducing base disengagement area
Xie et al. Structural design of the power distribution building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20210528