CN207176727U CN201721080782.XU CN201721080782U CN207176727U CN 207176727 U CN207176727 U CN 207176727U CN 201721080782 U CN201721080782 U CN 201721080782U CN 207176727 U CN207176727 U CN 207176727U
Authority
CN
China
Prior art keywords
pile
support frame
equipment
prestressed pipe
power generation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721080782.XU
Other languages
Chinese (zh)
Inventor
张元海
陈鹏
吴林霞
陈再
张敬博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast Guangdong Hydropower Investment Co Ltd
Xuwen County Guangdong Hydropower Energy Co Ltd
Guangdong No 2 Hydropower Engineering Co Ltd
Original Assignee
Southeast Guangdong Hydropower Investment Co Ltd
Xuwen County Guangdong Hydropower Energy Co Ltd
Guangdong No 2 Hydropower Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast Guangdong Hydropower Investment Co Ltd, Xuwen County Guangdong Hydropower Energy Co Ltd, Guangdong No 2 Hydropower Engineering Co Ltd filed Critical Southeast Guangdong Hydropower Investment Co Ltd
Priority to CN201721080782.XU priority Critical patent/CN207176727U/en
Application granted granted Critical
Publication of CN207176727U publication Critical patent/CN207176727U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform, including pile for prestressed pipe, structural framing, equipment support frame and steel reinforced concrete bearing sheet, brace foundation is used as using pile for prestressed pipe, the setting structure framework on pile for prestressed pipe, structural framing is formed by the girder being fixed on pile for prestressed pipe and the secondary beam being connected between girder arrangement, the fixed equipment support frame on structural framing, equipment support frame is formed by the arrangement of T beams, shape size is adapted with the equipment bottom shape size of required supporting, for support apparatus, the bottom surface of structural framing is communicated to inside equipment support frame, form the cable aperture that current supply cable passes through, steel reinforced concrete bearing sheet includes floor support plate and concrete layer, floor support plate is laid on structural framing, concrete layer is cast on floor support plate, the top of equipment support frame is higher than concrete layer.The utility model has short efficiency of construction height, cycle, low cost, removes the characteristics of facilitating, and can be applied to the falling zones such as lake, reservoir.

Description

Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform
Technical field
It the utility model is related to the equipment platform of photovoltaic plant, more particularly to a kind of prefabricated assembling steel and concrete structure light Lie prostrate generating equipment platform.
Background technology
In photovoltaic plant, electrical control equipment and photovoltaic power generation equipment etc. are typically mounted on equipment platform, at present light Overhead utility uses traditional armored concrete equipment platform, including half buried and frame structure equipment platform, this equipment Platform is there is long construction period, cost are higher, and the problem of power station demolishing process is numerous and diverse.
Utility model content
The utility model is in order to solve the above-mentioned technical problem, there is provided a kind of prefabricated assembling steel and concrete structure photovoltaic generation is set Standby platform, it has short efficiency of construction height, cycle, low cost, removes the characteristics of facilitating, and can be applied to lake, reservoir etc. Falling zone.
In order to realize the purpose of this utility model, used technical scheme is:Prefabricated assembling steel and concrete structure photovoltaic is sent out Electric equipment platform, it is characterised in that:Including pile for prestressed pipe, structural framing, equipment support frame and steel reinforced concrete bearing sheet, in advance should Solenoid stake is as brace foundation, and the setting structure framework on pile for prestressed pipe, the structural framing is by being fixed on pile for prestressed pipe On girder and be connected between girder secondary beam arrangement form, the fixed equipment support frame on structural framing, the equipment Support frame is formed by the arrangement of T beams, and shape size is adapted with the equipment bottom shape size of required supporting, is set for supporting It is standby, the bottom surface of structural framing is communicated to inside the equipment support frame, forms the cable aperture that current supply cable passes through, the steel reinforced concrete is held Platen includes floor support plate and concrete layer, and the floor support plate is laid on structural framing, and the concrete layer is cast in floor support plate On, the top of the equipment support frame is higher than concrete layer.
As further improvement of the utility model, in addition to netted ground structure, the netted ground structure includes flat Platform grounded screen, the first grounding body, the second grounding body and the photovoltaic field grounded screen for being embedded in underground, the platform grounded screen is along pre- Stress pile tube is set to form the entirety of a closure, and first grounding body is connected in platform grounded screen, and is upward through steel Mixed bearing sheet is used to be connected with the reserved earthing pole of equipment, second grounding body at pile for prestressed pipe with platform grounded screen Connection, and it is linked into photovoltaic field grounded screen down through underground along pile for prestressed pipe.
As further improvement of the utility model, in addition to conversion backing plate, circular hole is provided with the conversion backing plate, it is described The top of pile for prestressed pipe is provided with end plate, and the conversion backing plate is fixed by circular hole and end plate plug welding, is fixed on it pre- On the end plate of stress pile tube, the conversion backing plate is provided with connecting screw, and the connecting screw is provided with fixing nut and tune Flush nut, the girder are provided with corresponding screw, and girder is fixed on conversion backing plate by fixing nut, when fixed, The leveling nut is located at the lower section of girder, the leveling for girder.
As further improvement of the utility model, in addition to oil sump, the concrete surface is provided with slave unit The slope that support frame surrounding tilts down toward equipment support frame direction, sewer pipe is provided with the bottom on slope, under described Waterpipe is communicated to oil sump.
As further improvement of the utility model, the gradient on the slope is 2~3%.
As further improvement of the utility model, the diameter of the sewer pipe is no less than 100mm.
As further improvement of the utility model, in addition to it is fixed on the cable that structural framing bottom is used to fix cable Bracket.
As further improvement of the utility model, in addition to remaining cable protection well, the remaining cable protection well are set on the ground, The remaining cable protection well is formed with brick masonry, and well is interior to be used to place remaining cable, and the top surface of the borehole wall is higher than remaining cable face, fills and be always or usually as specified in well Soil or medium-fine sand are so that remaining cable to be covered.
As further improvement of the utility model, the top surface of the borehole wall is higher than remaining 20~30cm of cable face.
As further improvement of the utility model, in addition to safe fence, the safe fence surrounds steel reinforced concrete bearing sheet Surrounding set, the bottom of the safe fence is welded with floor support plate and is embedded in concrete layer.
It is of the present utility model effectively effect be:
First, the utility model site operation speed is fast, short time limit.Pile for prestressed pipe, structural framing, equipment support frame and Floor support plate can be prefabricated in factory process, is assembled after transporting scene to.Traditional reinforced concrete structure need to be waited to mix Equipment is installed again after solidifying soil solidification, the traditional reinforced concrete structure of analogy, piling of the present utility model, structural framing, equipment The installation energy seamless connection of support frame and floor support plate, equipment support frame, which is fixed on structural framing, to be used to install equipment, is mixed Solidifying soil layer can be constructed and be conserved again after equipment is installed in place, do not delayed the engineering main duration, made the equipment platform construction period It is greatly reduced.
2nd, the utility model has the characteristics of simple installation.Pile tube uses hydraulic vibration piling machine or static pressure pile foundation construction , structural framing, equipment support frame and floor support plate pass through welding or bolt connection.
3rd, equipment platform described in the utility model, which has, removes the characteristics of facilitating, and recycles high.Design of photovoltaic power station Service life is generally 25 years, and the dismounting efficiency of equipment platform described in the utility model and recycling are high after expiring, and such as remove Construction control is proper, and pile tube and each component can recycle.
4th, the utility model low cost.The utility model is simple in construction, component is few, and installing engineering amount is low, can be significantly Reduce cost.
5th, the utility model can be applied to the falling zones such as lake, reservoir.
Brief description of the drawings
Fig. 1 is the utility model overall structure diagram;
Fig. 2 is that pile for prestressed pipe described in the utility model arranges schematic diagram;
Fig. 3 is structural framing schematic diagram described in the utility model;
Fig. 4 is steel reinforced concrete bearing sheet schematic diagram described in the utility model;
Fig. 5 is conversion backing plate schematic diagram described in the utility model;
Description of symbols:1- pile for prestressed pipe, 11- end plates, 2- structural framings, 21- girders, 22- secondary beams, the support of 3- equipment Framework, 31- cable aperture, 4- steel reinforced concretes bearing sheet, 41- floor support plates, 42- concrete layers, 421- slopes, 422- sewer pipes, 5- turn Backing plate, 51- circular holes, 52- full threads connecting screw, 53- fixing nuts, 54- leveling nuts, the netted ground structures of 6-, 61- is changed to put down Platform grounded screen, the grounding bodies of 62- first, the grounding bodies of 63- second, cable protection well, 8- safe fences, 9- stair, 10- equipment more than 7-.
Embodiment
With reference to specific embodiment and accompanying drawing, the utility model is described in further detail.
As Figure 1-5, prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform, for equipment 10 in photovoltaic generation field Mounting arrangements, including pile for prestressed pipe 1, structural framing 2, equipment support frame 3, steel reinforced concrete bearing sheet 4, conversion backing plate 5, netted Ground structure 6, oil collecting structure, cable tray, remaining cable protection well 7, safe fence 8 and stair 9.
Pile for prestressed pipe 1 is used as brace foundation, and pile-type, stake spacing, depth of burying are determined according to relevant design data and specification Degree, be unearthed length and height of pile top etc. and related mechanical property parameters, and it adapts to the topography and geomorphology that falling zone height rises and falls.This In embodiment, the quantity of pile for prestressed pipe 1 is the six roots of sensation, and be square arrangement between pile for prestressed pipe 1, passes through hydraulic vibration piling machine Or static pressure pile foundation is driven into stratum.
Structural framing 2 includes some girders 21 and secondary beam 22, and girder 21 selects H-shaped steel with secondary beam 22, according to top The arrangement form of equipment 10, the combining form of girder 21 and secondary beam 22 is determined, in primary-secondary beam Design of length, reserved equipment 10 is examined The space of equating platform.Between secondary beam 22 is welded on into girder 21 according to specification, be square arrangement between girder 21 and secondary beam 22, from And structural framing 2 is formed, in structural framing 2, the support level of component devices support frame 3 is gone back between girder 21 and secondary beam 22. When mounted, girder 21 is fixed on pile for prestressed pipe 1 by full thread connecting screw 52, fixing nut 53, so that structure Framework 2 is fixed on pile for prestressed pipe 1.
Equipment support frame 3 is formed by the arrangement of steel T beams, shape size and the bottom shape size of equipment 10 of required supporting It is adapted, for support apparatus 10.Equipment support frame 3 is welded in the support level of structural framing 2, in equipment support frame 3 Portion leaves the bottom surface that space is communicated to structural framing 2, forms the cable aperture 31 that current supply cable passes through.
Steel reinforced concrete bearing sheet 4 includes floor support plate 41 and concrete layer 42.Floor support plate 41 is mutually fitted with the shape size of structural framing 2 Match somebody with somebody, be laid on structural framing 2, do not laid on the position of equipment support frame 3.Concrete layer 42 is cast in floor support plate 41 On, while ensure that the top of equipment support frame 3 is higher than concrete layer 42.
Pile for prestressed pipe 1, structural framing 2, equipment support frame 3 and floor support plate 41 can be prefabricated in factory's progress, so After transport to scene after assembled.When assembling equipment platform, by pile for prestressed pipe 1 by hydraulic vibration piling machine or Static pressure pile foundation is driven into stratum, then mounting structure framework 2, equipment support frame 3 successively by way of screw rod or welding With floor support plate 41, now, equipment platform is basically completed, and can install equipment 10 in equipment support frame 3, and concrete layer 42 can be Equipment 10 is constructed and conserved again after installing in place, does not delay the engineering main duration, has fast, simple to operate, short time limit of constructing The characteristics of.
The top of existing pile for prestressed pipe 1 is provided with end plate 11 mostly, be not suitable for girder 21 and pile for prestressed pipe 1 it Between fixation, for the connected mode of the end plate 11 of converting prestress pile tube 1, be easy to fix the girder 21 on top, using conversion Backing plate 5.Backing plate 5 is changed as round iron plate, thickness is calculated according to upper load and determined, a diameter of end plate 11 of pile for prestressed pipe 1 Diameter+4cm.Circular hole 51 is provided with conversion backing plate 5, is fixed by circular hole 51 and the plug welding of end plate 11, it is fixed on prestressing force On the end plate 11 of pile tube 1.The conversion upside equal strength of backing plate 5 is welded with full thread connecting screw 52, full thread connecting screw 52 On fixing nut 53 and leveling nut 54 are installed, girder 21 is provided with matching screw, will be main by fixing nut 53 Beam 21 is fixed on conversion backing plate 5, so that pile for prestressed pipe 1 is fixed with girder 21, when fixed, leveling nut 54 is located at girder 21 lower section, the leveling for girder 21.Conversion backing plate 5 is welded direct to the end of converting prestress pile tube 1 when can be prefabricated in the factory In head plate 11, in order to live quick assembling.
Netted ground structure 6 includes platform grounded screen 61, the first grounding body 62, the second grounding body 63 and is embedded in underground Photovoltaic field grounded screen (not indicated in figure), platform grounded screen 61, the first grounding body 62, the second grounding body 63 are made using band iron Form.Platform grounded screen 61 sets the square entirety for forming a closure along six roots of sensation pile for prestressed pipe 1, and the first grounding body 62 welds It is connected in platform grounded screen 61, and is upward through steel reinforced concrete bearing sheet 4 and is used to be connected with the reserved earthing pole of equipment 10, second connects Ground body 63 welds at pile for prestressed pipe 1 with platform grounded screen 61, and is linked into light down through underground along pile for prestressed pipe 1 Field grounded screen is lied prostrate, photovoltaic field grounded screen is prior art, is not repeated here.
Photovoltaic plant low-tension transformer is located in each photovoltaic arrays, and majority uses oil-filled transformer, therefore needs to thing Therefore it is collected with maintenance oil leak.Oil collecting structure includes oil sump (not indicated in figure), slope 421 and sewer pipe 422.Oil-collecting Pond is arranged on underground, and slope 421 is located on the surface of concrete layer 42, and the surrounding of slave unit support frame 3 is toward the side of equipment support frame 3 To tilting down, the gradient is 2~3%, and the sewer pipe 422 that diameter is no less than 100mm, lower water are provided with the bottom on slope 421 Pipeline 422 is communicated to oil sump.
Cable tray (not indicated in figure) is arranged for centralized photovoltaic generating system.Low-pressure cabinet becomes and inverter is arranged On equipment platform.Square formation direct current cables enters inverter after buried from cable aperture 31, and direct current is needed through electricity after ac converter Cable is sent into the low-pressure side of transformer, and the cable is laid along mesa base, and the middle pressure exchange after boosting collects electrical cables from transformer bottom Portion's cable aperture carries out current collection behind 31 times ground.Equipment platform bottom cable needs cable tray to be fixed in whole process.This reality Apply in example, cable tray is processed with angle with equal legs, the fixed briquetting of band, is welded on the bottom of structural framing 2.
Can be in the reserved maintenance length in end both ends, the long cable (letter therefore equipment platform bottom is had a surplus in cabling process Claim " remaining cable ").Remaining cable is coiled on the ground below equipment platform by the utility model according to the minimum bending radius of cable, and Cable protection well 7 more than being set in remaining cable periphery.Remaining cable protection well 7 is set on the ground, is formed with brick masonry, remaining for placing in well Cable, the top surface of the borehole wall are higher than remaining 20~30cm of cable face, are filled in well and be always or usually as specified native or medium-fine sand so that remaining cable to be covered.Pass through the knot Structure can be effectively protected to remaining cable, and be easy to dig out maintenance.
Safe fence 8 provides certain safety guarantee for staff.Safe fence 8 surrounds the surrounding of steel reinforced concrete bearing sheet 4 Set, bottom and the floor support plate 41 of the safe fence 8 are welded and be embedded in concrete layer 42, the height symbol of safe fence 8 Close relevant safety regulations.
Stair 9 are easy to staff to enter on equipment platform, and one end of stair 9 is fixed on the ground, and the other end is fixed On structural framing 2.
The utility model has been successfully applied to Xuwen County of Guangdong carp pool photovoltaic project, and achieves corresponding effect.
In summary, such as specification and diagramatic content actual sample is made and through test is used for multiple times in the utility model, In terms of the effect using test, provable the utility model can reach its desired purpose, and practical value is unquestionable. Embodiment provided above is only used for convenient illustration the utility model, not makees any formal limit to the utility model System, any those of ordinary skill in the art, if in the range of not departing from the utility model and carrying technical characteristic, Using the equivalent embodiment for locally changing or modifying made by the utility model disclosed technology content, and without departing from this practicality New technical feature content, in the range of still falling within the utility model technical characteristic.

Claims (10)

1. prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform, it is characterised in that:Including pile for prestressed pipe, structural framing, Equipment support frame and steel reinforced concrete bearing sheet, using pile for prestressed pipe as brace foundation, the setting structure framework on pile for prestressed pipe, The structural framing is formed by the girder being fixed on pile for prestressed pipe and the secondary beam being connected between girder arrangement, in structural frames Fixed equipment support frame on frame, the equipment support frame are formed by the arrangement of T beams, shape size and the equipment of required supporting Bottom shape size is adapted, and for support apparatus, the bottom surface of structural framing is communicated to inside the equipment support frame, is formed The cable aperture that current supply cable passes through, the steel reinforced concrete bearing sheet include floor support plate and concrete layer, and the floor support plate is laid on structural frames On frame, the concrete layer is cast on floor support plate, and the top of the equipment support frame is higher than concrete layer.
2. prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform according to claim 1, it is characterised in that:Also include Netted ground structure, the netted ground structure include platform grounded screen, the first grounding body, the second grounding body and are embedded in underground Photovoltaic field grounded screen, the platform grounded screen set along pile for prestressed pipe to be formed one closure entirety, described first connects Ground body is connected in platform grounded screen, and is upward through steel reinforced concrete bearing sheet and is used to be connected with the reserved earthing pole of equipment, described Second grounding body is connected at pile for prestressed pipe with platform grounded screen, and is linked into light down through underground along pile for prestressed pipe Lie prostrate field grounded screen.
3. prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform according to claim 1, it is characterised in that:Also include Backing plate is changed, circular hole is provided with the conversion backing plate, the top of the pile for prestressed pipe is provided with end plate, and the conversion backing plate leads to Cross circular hole to fix with end plate plug welding, it is fixed on the end plate of pile for prestressed pipe, the conversion backing plate is provided with connection Screw rod, the connecting screw are provided with fixing nut and leveling nut, and the girder is provided with corresponding screw, passes through fixation Girder is fixed on conversion backing plate by nut, and when fixed, the leveling nut is located at the lower section of girder, the leveling for girder.
4. prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform according to claim 1, it is characterised in that:Also include Oil sump, the concrete surface tilt down oblique provided with slave unit support frame surrounding toward equipment support frame direction Slope, sewer pipe is provided with the bottom on slope, the sewer pipe is communicated to oil sump.
5. prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform according to claim 4, it is characterised in that:It is described oblique The gradient on slope is 2~3%.
6. prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform according to claim 4, it is characterised in that:Under described The diameter of waterpipe is no less than 100mm.
7. prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform according to claim 1, it is characterised in that:Also include It is fixed on the cable tray that structural framing bottom is used to fix cable.
8. prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform according to claim 1, it is characterised in that:Also include Remaining cable protection well, the remaining cable protection well are set on the ground, and the remaining cable protection well is formed with brick masonry, remaining for placing in well Cable, the top surface of the borehole wall are higher than remaining cable face, are filled in well and be always or usually as specified native or medium-fine sand so that remaining cable to be covered.
9. prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform according to claim 8, it is characterised in that:The borehole wall Top surface is higher than remaining 20~30cm of cable face.
10. prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform according to claim 1, it is characterised in that:Also wrap Safe fence is included, the safe fence is set around the surrounding of steel reinforced concrete bearing sheet, and bottom and the floor support plate of the safe fence weld Connect and be embedded in concrete layer.
CN201721080782.XU 2017-08-28 2017-08-28 Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform Active CN207176727U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721080782.XU CN207176727U (en) 2017-08-28 2017-08-28 Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721080782.XU CN207176727U (en) 2017-08-28 2017-08-28 Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform

Publications (1)

Publication Number Publication Date
CN207176727U true CN207176727U (en) 2018-04-03

Family

ID=61739162

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721080782.XU Active CN207176727U (en) 2017-08-28 2017-08-28 Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform

Country Status (1)

Country Link
CN (1) CN207176727U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503368A (en) * 2017-08-28 2017-12-22 广东水电二局股份有限公司 Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503368A (en) * 2017-08-28 2017-12-22 广东水电二局股份有限公司 Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform

Similar Documents

Publication Publication Date Title
EP2302136A1 (en) Foundation for wind turbine
CN103225304B (en) A kind of marine foundation supporting structure and construction method thereof
US10968894B2 (en) Wind turbine foundation and method of constructing a wind turbine foundation
US20110027100A1 (en) Mobile wind power station
CN103790175A (en) Intense weathered rock formation prestress expanded-base anchor bolt foundation of wind generating set
CN207176727U (en) Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform
CN215367377U (en) Fully-assembled wind generating set foundation and wind generating set
CN203594041U (en) Piled raft structure with good resistance to seepage and buoyancy
CN203238659U (en) Wind driven generator steel strand prestress foundation structure
CN203498859U (en) Novel prestress steel stranded wire foundation
CN107503368A (en) Prefabricated assembling steel and concrete structure photovoltaic power generation equipment platform
CN112575789A (en) Diagonal space truss foundation pit inner support system
CN110219300B (en) Construction process of partially-bonded prestressed uplift anchor rod
CN216108675U (en) High-performance wind power tower cylinder foundation reinforcing device
CN212896435U (en) Combined prefabricated bearing platform pile foundation
CN106400832A (en) Environment-friendly assembling type post-grouting steel cylinder pile foundation and construction method thereof
CN218779526U (en) Fixing device for wind power plant distributed energy storage system
CN205259206U (en) Column foot basis
CN214574126U (en) Anti-floating device of power communication combined pipeline
CN220013756U (en) Transmission line assembled cross steel skeleton rock crowd anchor basis
CN220789839U (en) Prefabricated foundation of wind generating set box transformer substation
CN220335866U (en) Water surface photovoltaic box flattening platform foundation template
CN218622301U (en) Foundation structure of steel-concrete tower of wind generating set
CN217902059U (en) Substation earthquake monitoring substation
CN115095226B (en) Light high-large fence and erection method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant