CN112832233A - 一种改良cfg桩施工方法 - Google Patents
一种改良cfg桩施工方法 Download PDFInfo
- Publication number
- CN112832233A CN112832233A CN202011633164.XA CN202011633164A CN112832233A CN 112832233 A CN112832233 A CN 112832233A CN 202011633164 A CN202011633164 A CN 202011633164A CN 112832233 A CN112832233 A CN 112832233A
- Authority
- CN
- China
- Prior art keywords
- steel
- pipe
- cfg pile
- steel sleeve
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/385—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
Abstract
一种改良CFG桩施工方法,属于建筑工程的地基处理技术领域。施工步骤:CFG桩混凝土浇筑完毕;用挖掘机吊运钢套管,放入CFG桩的空孔内;将预埋在CFG桩中的钢管下入钢套管中;用挖掘机将销管顶入钢套管内,预埋的钢管被顶入CFG桩中;销管与预埋的钢管直径、规格相同;施工完毕,将钢套管(2)、销管(1)吊出。优点在于,提高了CFG桩的抗剪强度,降低了断桩率,节约了成本。
Description
技术领域
本发明属于建筑工程的地基处理技术领域,特别是提供了一种改良 CFG桩施工方法,有效降低CFG桩断桩率。
背景技术
在建筑工程中,CFG桩的施工成本较低、施工简单,技术难度小, 在地基处理上应用非常普遍。
现在的CFG桩施工方法单一,设计上比较传统,多年来没有技术突 破。CFG桩易产生断桩的缺点,在沿海等地基条件差的地区被放大。在 土方开挖时,稍有不慎就产生断桩。对工程进度、施工质量、社会上对 施工单位的评价造成了比较坏的影响。
发明内容
本发明的目的在于提供一种改良CFG桩施工技术方法,解决了因为 CFG断桩造成挖桩、补桩、地基验收不合格等问题。实现了易施工、效 果好、技术难度低,方便、快捷,能较好的保证CFG桩和土方开挖施工 质量。
本发明所用的材料包括Φ89的销管1(Φ89)、Φ630的钢套管2、 Φ89mm长4m的钢管3、CFG桩4、200型挖掘机5;施工步骤如下:
1)CFG桩混凝土浇筑完毕。见图3。
2)用挖掘机吊运钢套管2,放入CFG桩4的空孔内。钢套管2采用 2根直径不同的钢管制作而成;1根直径与CFG桩4直径相近的钢管作为 钢套管的外壁,1根直径率大于预埋钢管直径的钢管,做为钢套管2的 内管,与外壁采用钢筋焊接固定;钢套管2上端装有钢丝绳,以便挖掘 机5吊运。见图4、图5
3)将预埋在CFG桩4中的钢管3下入钢套管2中,钢管直径89mm, 长度4000mm。见图6。
4)用挖掘机5将销管1顶入钢套管2内,预埋的钢管3被顶入CFG 桩4中;销管1与预埋的钢管3直径、规格相同;销管1的长度,根据 空孔的长度而定。见图7。
5)施工完毕,将钢套管2、销管1吊出。见图8。
由于CFG桩的抗剪强度低,特别是在土质较差的环境中,挖土时稍 有不慎就造成断桩。在CFG桩中插入直径89mm钢管,钢管顶标高与CFG 桩顶设计标高一致。这样提高了CFG桩的抗剪强度,降低了断桩率。 本发明的有益效果是:
1、先进性:具有施工便捷的特点。
2、必要性:有效的降低了CFG断桩率。
3、节约成本:有效减少了补桩的数量,节约成本。
附图说明
图1为本发明的改良CFG桩施工示意图。
图2为施工完成后成品图。
图3为施工步骤:第一步CFG桩浇筑完毕示意图。
图4为施工步骤:第二步吊入钢套管示意图。
图5为钢套管制作图。
图6为施工步骤:第三步下入钢管示意图。
图7为施工步骤:第四步插入销管示意图。
图8为施工步骤:第五步施工完成示意图。
其中,销管1、钢套管2、钢管3、CFG桩4、挖掘机5
具体实施方式
为了使本发明专利的施工工法更容易被清楚理解,下面结合附图和 改良CFG桩实施例作详细说明。
1)CFG桩混凝土浇筑完毕。见图3。
2)用挖掘机吊运钢套管2,放入CFG桩4的空孔内。钢套管2采用 2根直径不同的钢管制作而成;1根直径与CFG桩4直径相近的钢管作为 钢套管的外壁,1根直径率大于预埋钢管直径的钢管,做为钢套管2的 内管,与外壁采用钢筋焊接固定;钢套管上端装有钢丝绳,以便挖掘机 5吊运。见图4、图5
3)将预埋在CFG桩4中的钢管3下入钢套管2中,钢管直径89mm, 长度4000mm。见图6。
4)用挖掘机5将销管1顶入钢套管2内,预埋的钢管3被顶入CFG 桩4中;销管1与预埋的钢管3直径、规格相同;销管1的长度,根据 空孔的长度而定。见图7。
5)施工完毕,将钢套管2、销管1吊出。见图8。
Claims (1)
1.一种改良CFG桩施工方法,其特征在于,施工步骤如下:
1)CFG桩(4)混凝土浇筑完毕;
2)用挖掘机吊运钢套管(2),放入CFG桩(4)的空孔内;钢套管(2)采用2根直径不同的钢管制作而成;1根直径与CFG桩(4)直径相近的钢管作为钢套管(2)的外壁,1根直径率大于预埋钢管(3)直径的钢管,做为钢套管(2)的内管,与外壁采用钢筋焊接固定;钢套管(2)上端装有钢丝绳,以便挖掘机5吊运;
3)将预埋在CFG桩(4)中的钢管(3)下入钢套管(2)中,钢管直径89mm,长度4000mm;
4)用挖掘机(5)将销管(1)顶入钢套管(2)内,预埋的钢管(3)被顶入CFG桩(4)中;销管(1)与预埋的钢管(3)直径、规格相同;
5)施工完毕,将钢套管(2)、销管(1)吊出。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011633164.XA CN112832233A (zh) | 2020-12-31 | 2020-12-31 | 一种改良cfg桩施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011633164.XA CN112832233A (zh) | 2020-12-31 | 2020-12-31 | 一种改良cfg桩施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112832233A true CN112832233A (zh) | 2021-05-25 |
Family
ID=75925908
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011633164.XA Pending CN112832233A (zh) | 2020-12-31 | 2020-12-31 | 一种改良cfg桩施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112832233A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113431035A (zh) * | 2021-07-23 | 2021-09-24 | 北京爱地地质勘察基础工程公司 | 一种cfg桩反插钢管装置及其施工方法 |
CN114657976A (zh) * | 2022-04-19 | 2022-06-24 | 北京首钢建设集团有限公司 | 一种预应力钢管混凝土桩及其施工工艺 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1614157A (zh) * | 2004-12-06 | 2005-05-11 | 雷玉华 | 水泥土插芯复合桩施工机械 |
CN2753797Y (zh) * | 2004-12-29 | 2006-01-25 | 雷玉华 | 长螺旋压灌混凝土插芯组合桩 |
WO2011089666A1 (ja) * | 2010-01-25 | 2011-07-28 | 株式会社テノックス | 水硬性固化材液置換コラムの築造方法および水硬性固化材液置換コラムの施工装置 |
CN209538174U (zh) * | 2018-12-21 | 2019-10-25 | 兰州有色冶金设计研究院有限公司 | 消除胀缩土层摩擦力的套管预制桩 |
CN111088796A (zh) * | 2019-12-08 | 2020-05-01 | 王琪 | 一种地层原位加固的减阻式植桩与长距送桩方法 |
-
2020
- 2020-12-31 CN CN202011633164.XA patent/CN112832233A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1614157A (zh) * | 2004-12-06 | 2005-05-11 | 雷玉华 | 水泥土插芯复合桩施工机械 |
CN2753797Y (zh) * | 2004-12-29 | 2006-01-25 | 雷玉华 | 长螺旋压灌混凝土插芯组合桩 |
WO2011089666A1 (ja) * | 2010-01-25 | 2011-07-28 | 株式会社テノックス | 水硬性固化材液置換コラムの築造方法および水硬性固化材液置換コラムの施工装置 |
CN209538174U (zh) * | 2018-12-21 | 2019-10-25 | 兰州有色冶金设计研究院有限公司 | 消除胀缩土层摩擦力的套管预制桩 |
CN111088796A (zh) * | 2019-12-08 | 2020-05-01 | 王琪 | 一种地层原位加固的减阻式植桩与长距送桩方法 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113431035A (zh) * | 2021-07-23 | 2021-09-24 | 北京爱地地质勘察基础工程公司 | 一种cfg桩反插钢管装置及其施工方法 |
CN114657976A (zh) * | 2022-04-19 | 2022-06-24 | 北京首钢建设集团有限公司 | 一种预应力钢管混凝土桩及其施工工艺 |
CN114657976B (zh) * | 2022-04-19 | 2024-01-05 | 北京首钢建设集团有限公司 | 一种预应力钢管混凝土桩及其施工工艺 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112832233A (zh) | 一种改良cfg桩施工方法 | |
CN105649083B (zh) | 全套管一次性旋切式清桩装置及其清桩方法 | |
CN102383431B (zh) | 中掘预应力离心管桩沉桩装置及其沉桩法 | |
CN105569560A (zh) | 全套管式长螺旋钻孔桩机及利用该桩机施工的方法 | |
WO2022021634A1 (zh) | 旋挖钻机切除支护桩内半侵入预应力锚索的方法 | |
CN111119180A (zh) | 一种复杂环境下的地下桩基清除施工方法 | |
CN112647495A (zh) | 一种预制端承管桩的施工方法 | |
CN111877344A (zh) | 一种旧管桩破除方法 | |
CN110629757A (zh) | 一种smw工法桩型钢拔除方法 | |
CN215105278U (zh) | 一种地下空间拓建锚杆桩定位器 | |
CN110725305A (zh) | 一种提高斜向钢管桩承载力的施工方法 | |
CN102758434B (zh) | 中掘预应力离心管桩沉桩装置及其沉桩法 | |
CN214994477U (zh) | 一种基坑内管道改迁结构 | |
CN111778969A (zh) | 双套管式全回转超长桩施工工具及施工工法 | |
CN108301404B (zh) | Smw工法桩型钢拔除与高压注浆同步施工方法 | |
CN107023008B (zh) | 护壁及反力用沉井平台拔桩方法及系统 | |
CN109881722A (zh) | 一种利用大直径钢沉井纠偏施工方法 | |
CN219621757U (zh) | 一种用于抗拔桩断桩处理的抗拔装置 | |
JP7466044B1 (ja) | アンダーピニング杭と検査用アンカー杭の施工方法 | |
CN212223855U (zh) | 双套管式全回转超长桩施工工具 | |
CN220099894U (zh) | 一种双套管施工的矩形截面灌注桩 | |
CN212896321U (zh) | 一种超深大直径桩孔的回填结构 | |
CN213836627U (zh) | 一种膨胀钢管扩体桩 | |
CN217027108U (zh) | 一种钻孔灌注桩后压浆的桩端注浆器 | |
CN214497495U (zh) | 杂填土区域施工灌注桩用的超长钢护筒 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20210525 |