CN112733215A - 基于改进约束不规则三角网构建法的土方工程量计算方法 - Google Patents
基于改进约束不规则三角网构建法的土方工程量计算方法 Download PDFInfo
- Publication number
- CN112733215A CN112733215A CN202110058349.0A CN202110058349A CN112733215A CN 112733215 A CN112733215 A CN 112733215A CN 202110058349 A CN202110058349 A CN 202110058349A CN 112733215 A CN112733215 A CN 112733215A
- Authority
- CN
- China
- Prior art keywords
- triangulation network
- boundary
- triangular
- constrained
- earthwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2111/00—Details relating to CAD techniques
- G06F2111/04—Constraint-based CAD
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Geometry (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Computer Hardware Design (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110058349.0A CN112733215A (zh) | 2021-01-15 | 2021-01-15 | 基于改进约束不规则三角网构建法的土方工程量计算方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110058349.0A CN112733215A (zh) | 2021-01-15 | 2021-01-15 | 基于改进约束不规则三角网构建法的土方工程量计算方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112733215A true CN112733215A (zh) | 2021-04-30 |
Family
ID=75593382
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110058349.0A Pending CN112733215A (zh) | 2021-01-15 | 2021-01-15 | 基于改进约束不规则三角网构建法的土方工程量计算方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112733215A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113946980A (zh) * | 2021-11-04 | 2022-01-18 | 北京龙软科技股份有限公司 | 一种大型露天矿开挖工程台阶土石方量计算方法及系统 |
-
2021
- 2021-01-15 CN CN202110058349.0A patent/CN112733215A/zh active Pending
Non-Patent Citations (1)
Title |
---|
金权等: "《浙东山地区域场平工程土方量优化计算方法研究》", 《经纬天地》, 31 August 2020 (2020-08-31), pages 15 - 18 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113946980A (zh) * | 2021-11-04 | 2022-01-18 | 北京龙软科技股份有限公司 | 一种大型露天矿开挖工程台阶土石方量计算方法及系统 |
CN113946980B (zh) * | 2021-11-04 | 2022-07-12 | 北京龙软科技股份有限公司 | 一种大型露天矿开挖工程台阶土石方量计算方法及系统 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Yu et al. | Extensions to least-cost path algorithms for roadway planning | |
CN102819568B (zh) | 基于地形采样点位置的海底地形数据建立方法 | |
CN101838958B (zh) | 道路坡度的检测方法 | |
CN109191581A (zh) | 一种基于bim技术的道路工程土方量高精度计算方法 | |
CN107330140A (zh) | 基于bim技术实现变电站快速竖向布置的方法 | |
CN107885960A (zh) | 一种基于风电场场内施工道路自动选线的土方量估算系统及估算方法 | |
CN110175370A (zh) | 一种城市汇水潜力区识别方法 | |
CN107679337A (zh) | 一种工程测量中不规则土方计算的方法 | |
CN113235655B (zh) | 海底沉管隧道基槽分土质工程土方量计算方法 | |
CN111005273A (zh) | 施工临时道路布置方法 | |
CN112766721B (zh) | 一种淤地坝规划选址和规模估算方法 | |
CN117910285B (zh) | 库盆设计曲面模型的创建方法、装置、设备及存储介质 | |
CN106446910A (zh) | 一种复杂地质曲面特征提取与重构方法 | |
CN112242003B (zh) | 一种顾及地类与流向的城市子汇水区划分方法 | |
CN111353681A (zh) | 一种基于bim技术的场地内土石工程量高精度计算方法 | |
Amatya et al. | Application of LiDAR data for hydrologic assessments of low-gradient coastal watershed drainage characteristics | |
CN110955996A (zh) | 一种淹没过程模拟方法及系统 | |
CN105261067A (zh) | 一种基于真三维地上地下一体化的建模方法及系统 | |
CN111783194A (zh) | 山区道路土方量的优化计算方法 | |
CN114820957B (zh) | 一种铁路沿线场坪三维智能设计方法 | |
CN112733215A (zh) | 基于改进约束不规则三角网构建法的土方工程量计算方法 | |
CN106096129B (zh) | 一种基于山地汇水计算的山脚水面规模分析方法 | |
JP7030937B1 (ja) | 土木構造物の3次元モデルを生成するためのコンピュータプログラム、そのコンピュータプログラムがインストールされたコンピュータ及び土木構造物の3次元モデルの生成システム | |
CN111783191A (zh) | 基于倾斜摄影技术的山区道路土方量计算方法 | |
DraganA et al. | Geomorphological investigations and GIS approach of the Tamiš loess plateau, Banat region (Northern Serbia) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information |
Inventor after: Yang Yanting Inventor after: Shu Kai Inventor after: Yao Yan Inventor after: Zhou Dongjie Inventor after: Liu Yang Inventor after: Hu Huifeng Inventor after: Yu Mengdi Inventor before: Yang Yanting Inventor before: Shu Kai Inventor before: Yao Yan Inventor before: Zhou Dongjie Inventor before: Liu Yang Inventor before: Hu Huifeng Inventor before: Yu Mengdi |
|
CB03 | Change of inventor or designer information | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20210430 |
|
WD01 | Invention patent application deemed withdrawn after publication |