CN111005273A - 施工临时道路布置方法 - Google Patents
施工临时道路布置方法 Download PDFInfo
- Publication number
- CN111005273A CN111005273A CN201911293514.XA CN201911293514A CN111005273A CN 111005273 A CN111005273 A CN 111005273A CN 201911293514 A CN201911293514 A CN 201911293514A CN 111005273 A CN111005273 A CN 111005273A
- Authority
- CN
- China
- Prior art keywords
- road
- construction
- cross
- section
- temporary road
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C1/00—Design or layout of roads, e.g. for noise abatement, for gas absorption
- E01C1/002—Design or lay-out of roads, e.g. street systems, cross-sections ; Design for noise abatement, e.g. sunken road
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
本发明施工临时道路布置方法,属于道路施工领域,目的是提高临时道路工程量预算的准确性以及提高临时道路布置的科学合理性。包括以下步骤:步骤1、在实景公路地形三维模型中确定施工临时道路的线路中线以及边界;步骤2、选定施工临时道路的轴线;步骤3、沿选择i个横断面,各个横断面的挖方量为V1i,填方梁为V2i,纵向长度为Li;同时满足V1i=V2i,
Description
技术领域
本发明属于公路工程施工领域,具体的是施工临时道路布置方法。
背景技术
随着公路建设的推进,山区公路越来越多,特别对于交通不便的山区,由于公路为线型 结构,在施工过程中涉及的区域交缠,公路施工范围内的山谷、河流等影响施工临时道路的 布置,限制施工机械、材料等的运输,并且施工临时道路布置的优劣直接影响施工的进度以 及成本。目前施工临时道路的选线通常有以下两种方法。
第一种方法,采用二维等高线图纸结合现场踏勘结果依靠经验进行施工临时道路的选线 设计。该方式,无法考虑相邻等高线之间的地形变化,无法准确衡量临时道路施工工程量, 使临时道路实际施工费用与投标时造价相距巨大,造成其施工成本大大增加,尤其对于高速 公路项目,线路长且多在山区,临时道路施工量大,最终导致成本大幅度增加。
第二种方法,通过地勘报告中的地形高程数据导入BIM软件生成三维地形图,再进行临 时道路的选线设计。然而,由于地勘报告给出的等高线数据粗略,精度不高,同样无法准确 体现出相邻等高线之间的地形变化,导致设计的临时道路出现陡坡等现象,设计线路实际施 工时由于坡度过大,需要重新选线,造成返修等,最终导致临时道路实际施工费用与投标时 造价相距巨大,成本增加。
发明内容
本发明的目的是提供一种施工临时道路布置方法,提高临时道路工程量预算的准确性以 及提高临时道路布置的科学合理性。
本发明采用的技术方案是:施工临时道路布置方法,包括以下步骤:
步骤1、在实景公路地形三维模型中,根据地形特点、施工节段划分情况、施工机械要 求、拟建施工临时道路坡度要求、拟建施工临时道路转弯半径要求以及已有道路情况在原地 面上确定施工临时道路的线路中线以及边界;
步骤2、选定施工临时道路的轴线,轴线坡度小于或者等于15°,初步确定纵断面;
步骤3、沿施工临时道路的中线延伸方向,选择i个横断面并顺次编号,i=1,2…n,n 为大于或者等于2的正整数,设定各个横断面的挖方量为V1i,填方梁为V2i;各个横断面的纵向长度为Li,各个横断面的纵向长度之和等于临时道路的轴线总长度;各个横断面的运距 为Si;同时满足下列条件:
进一步的,步骤3中,相邻两个横断面之间沿线路中线延伸方向的距离为D,所述10m ≤D≤100m。
进一步的,横断面方量的确定方法为:横断面处地面线、路基面以及内侧边界包围形成 的区域为该横断面处的挖方区域,其断面面积为S挖;该横断面处地面线、路基面以及外侧边 界包围形成的区域为该横断面处的填方区域,其断面面积为S填;S挖=S填。
进一步的,实景公路地形三维模型的获取步骤如下:
首先,利用无人机搭载GIS软件进行航拍,采集拟修建公路线路上的所有地形图片;
接着,将采集的地形图片进行处理,提取地形图片中的三维坐标,生成三维点云数据;
然后,将三维点云数据导入BIM软件,通过BIM软件生成模拟的高精度实景地形图;
最后,将拟修建公路的BIM模型与实景地形图在BIM软件中进行融合,使实景地形图 中显示拟修建公路,从而得到实景公路地形三维模型。
本发明的有益效果是:本发明,通过实景公路地形三维模型能清楚准确展示拟修建公路 周围的地形环境情况,为选择临时道路路线提供准确的地形环境,提高临时道路选线的合理 性,并能保证临时道路选线时各种数据核算的准确性。待临时道路的位置确定后,通过初步 确定纵断面,然后,通过选取多处横断面,计算挖方量和填方量,根据横断面挖方量和填方 量相等原则调整纵断面标高,从而规划出最优的临时道路。还利于更精确的测算出临时施工 道路的工程量及成本。
具体实施方式
下面结合实施例对本发明做进一步的说明如下:
施工临时道路布置方法,包括以下步骤:
步骤1、在实景公路地形三维模型中,根据地形特点、施工节段划分情况、施工机械要 求、拟建施工临时道路坡度要求、拟建施工临时道路转弯半径要求以及已有道路情况在原地 面上确定施工临时道路的线路中线以及边界;
步骤2、选定施工临时道路的轴线,轴线坡度小于或者等于15°,初步确定纵断面;
步骤3、沿施工临时道路的中线延伸方向,选择i个横断面并顺次编号,i=1,2…n,n 为大于或者等于2的正整数,设定各个横断面的挖方量为V1i,填方梁为V2i;各个横断面的纵向长度为Li,各个横断面的纵向长度之和等于临时道路的轴线总长度;各个横断面的运距 为Si;同时满足下列条件:
本发明,所述实景公路地形三维模型是包括了拟修建公路以及拟修建公路线路上的地形 等的三维模型。通过实景公路地形三维模型能清楚准确展示拟修建公路周围的地形环境情况, 为选择临时道路路线提供准确的地形环境,提高临时道路选线的合理性,并能保证临时道路 选线时各种数据核算的准确性。待临时道路的位置确定后,再对临时道路进行优化设计,首 先选定施工临时道路的轴线,轴线坡度小于或者等于15°,初步确定纵断面,该坡度要求便 于车辆安全运输。然后,再对纵断面进行优化,通过选取多处横断面,计算挖方量和填方量, 若挖方量和填方量差距大,则调节纵断面上与该横断面对应处的标高直至挖方量等于填方量。 并对各个横断面选取合适的运距,运距是各横断面上挖方的土运输到填方处的距离,通过挖 方量与运距的乘积加上填方量与运距的乘积的和最小,选取合适的运距,最终,规划出最优 的临时道路路线以及最优的临时道路施工方案,并利于更精确的测算出临时施工道路的工程 量及成本。
其中,纵断面初步确定时,需要满足纵断面挖方量等于纵断面填方量,即沿临时道路轴 线方向的两个边界线内及临时道路路面线以上的挖方体积等于临时道路路面线下的填方体 积。
各个横断面的纵向长度之和等于临时道路的轴线总长度,同时要求各个横断面沿纵向没 有重合的公共区域。
为了提高计算放量的准确性,优选的,步骤3中,相邻两个横断面之间沿线路中线延伸 方向的距离为D,所述10m≤D≤100m。
优选的,横断面方量的确定方法为:横断面处地面线、路基面以及内侧边界包围形成的 区域为该横断面处的挖方区域,其断面面积为S挖;该横断面处地面线、路基面以及外侧边界 包围形成的区域为该横断面处的填方区域,其断面面积为S填;S挖=S填。
优选的,实景公路地形三维模型的获取步骤如下:
首先,利用无人机搭载GIS软件进行航拍,采集拟修建公路线路上的所有地形图片;
接着,将采集的地形图片进行处理,提取地形图片中的三维坐标,生成三维点云数据;
然后,将三维点云数据导入BIM软件,通过BIM软件生成模拟的高精度实景地形图;
最后,将拟修建公路的BIM模型与实景地形图在BIM软件中进行融合,使实景地形图 中显示拟修建公路,从而得到实景公路地形三维模型。
利用无人机搭载GIS软件采集拟修建公路线路上的所有地形图片;图片与实际的地形相 一致,提供真实的地形数据。地形图片通过密实的连贯的点形成,采集地形图片后,利用 Pix4Dmapper、smart3D等软件对地形图片进行处理,提取从地形图片上的密实点坐标,生成 三维点云数据,当然提取出的点坐标越多越精确。将三维点云数据通过BIM软件后生成实景 地形图,该实景地形图与实际的地形符合程度极高,精度能达到厘米级。将拟修建公路的BIM 模型与实景地形图在BIM软件中进行融合后得到实景公路地形三维模型。该实景公路地形三 维模型的准确度极高。
Claims (4)
1.施工临时道路布置方法,其特征在于:包括以下步骤:
步骤1、在实景公路地形三维模型中,根据地形特点、施工节段划分情况、施工机械要求、拟建施工临时道路坡度要求、拟建施工临时道路转弯半径要求以及已有道路情况在原地面上确定施工临时道路的线路中线以及边界;
步骤2、选定施工临时道路的轴线,轴线坡度小于或者等于15°,初步确定纵断面;
步骤3、沿施工临时道路的中线延伸方向,选择i个横断面并顺次编号,i=1,2…n,n为大于或者等于2的正整数,设定各个横断面的挖方量为V1i,填方梁为V2i;各个横断面的纵向长度为Li,各个横断面的纵向长度之和等于临时道路的轴线总长度;各个横断面的运距为Si;同时满足下列条件:
2.如权利要求1所述的施工临时道路布置方法,其特征在于:步骤3中,相邻两个横断面之间沿线路中线延伸方向的距离为D,所述10m≤D≤100m。
3.如权利要求1或2所述的施工临时道路布置方法,其特征在于:横断面方量的确定方法为:横断面处地面线、路基面以及内侧边界包围形成的区域为该横断面处的挖方区域,其断面面积为S挖;该横断面处地面线、路基面以及外侧边界包围形成的区域为该横断面处的填方区域,其断面面积为S填;S挖=S填。
4.如权利要求1所述的施工临时道路布置方法,其特征在于:实景公路地形三维模型的获取步骤如下:
首先,利用无人机搭载GIS软件进行航拍,采集拟修建公路线路上的所有地形图片;
接着,将采集的地形图片进行处理,提取地形图片中的三维坐标,生成三维点云数据;
然后,将三维点云数据导入BIM软件,通过BIM软件生成模拟的实景地形图;
最后,将拟修建公路的BIM模型与实景地形图在BIM软件中进行融合,使实景地形图中显示泥修建公路,从而得到实景公路地形三维模型。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911293514.XA CN111005273A (zh) | 2019-12-16 | 2019-12-16 | 施工临时道路布置方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911293514.XA CN111005273A (zh) | 2019-12-16 | 2019-12-16 | 施工临时道路布置方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111005273A true CN111005273A (zh) | 2020-04-14 |
Family
ID=70115395
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911293514.XA Pending CN111005273A (zh) | 2019-12-16 | 2019-12-16 | 施工临时道路布置方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111005273A (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111783190A (zh) * | 2020-06-12 | 2020-10-16 | 中国二十冶集团有限公司 | 基于倾斜摄影技术的道路土方量计算方法 |
CN111877068A (zh) * | 2020-05-26 | 2020-11-03 | 中建八局天津建设工程有限公司 | 一种装配式施工用临时道路的布置及施工方法 |
CN112150625A (zh) * | 2020-08-25 | 2020-12-29 | 金华送变电工程有限公司 | 一种用于临建的坡度过渡方法 |
CN112648974A (zh) * | 2020-12-29 | 2021-04-13 | 数字港湾科技(湖北)有限公司 | 一种基于航摄三维影像数据的工程量测算方法 |
CN112765707A (zh) * | 2021-01-04 | 2021-05-07 | 浙江交工集团股份有限公司 | 一种路基土石方方量的计算方法及系统 |
WO2024033981A1 (ja) * | 2022-08-08 | 2024-02-15 | 株式会社Earthbrain | 工事用道路経路設計装置、工事用道路経路設計方法及びプログラム |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005084740A (ja) * | 2003-09-04 | 2005-03-31 | Fukui Computer Kk | Cad装置、オフセット線描画方法、及びcadプログラム |
CN106202825A (zh) * | 2016-07-29 | 2016-12-07 | 上海宝冶集团有限公司 | 基于bim的地下综合管廊设计方法 |
CN108038265A (zh) * | 2017-11-17 | 2018-05-15 | 上海二十冶建设有限公司 | 一种基于bim的山地建筑群施工临时道路布置方法 |
CN109571769A (zh) * | 2018-11-20 | 2019-04-05 | 中国十九冶集团有限公司 | 混凝土拌合站设置方法 |
CN110411422A (zh) * | 2019-07-08 | 2019-11-05 | 中建五局土木工程有限公司 | 基于bim的施工便道的规划方法 |
-
2019
- 2019-12-16 CN CN201911293514.XA patent/CN111005273A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005084740A (ja) * | 2003-09-04 | 2005-03-31 | Fukui Computer Kk | Cad装置、オフセット線描画方法、及びcadプログラム |
CN106202825A (zh) * | 2016-07-29 | 2016-12-07 | 上海宝冶集团有限公司 | 基于bim的地下综合管廊设计方法 |
CN108038265A (zh) * | 2017-11-17 | 2018-05-15 | 上海二十冶建设有限公司 | 一种基于bim的山地建筑群施工临时道路布置方法 |
CN109571769A (zh) * | 2018-11-20 | 2019-04-05 | 中国十九冶集团有限公司 | 混凝土拌合站设置方法 |
CN110411422A (zh) * | 2019-07-08 | 2019-11-05 | 中建五局土木工程有限公司 | 基于bim的施工便道的规划方法 |
Non-Patent Citations (1)
Title |
---|
陈烈: "《公路工程项目管理》", 31 July 2000, 人民交通出版社 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111877068A (zh) * | 2020-05-26 | 2020-11-03 | 中建八局天津建设工程有限公司 | 一种装配式施工用临时道路的布置及施工方法 |
CN111783190A (zh) * | 2020-06-12 | 2020-10-16 | 中国二十冶集团有限公司 | 基于倾斜摄影技术的道路土方量计算方法 |
CN112150625A (zh) * | 2020-08-25 | 2020-12-29 | 金华送变电工程有限公司 | 一种用于临建的坡度过渡方法 |
CN112648974A (zh) * | 2020-12-29 | 2021-04-13 | 数字港湾科技(湖北)有限公司 | 一种基于航摄三维影像数据的工程量测算方法 |
CN112765707A (zh) * | 2021-01-04 | 2021-05-07 | 浙江交工集团股份有限公司 | 一种路基土石方方量的计算方法及系统 |
CN112765707B (zh) * | 2021-01-04 | 2024-04-26 | 浙江交工集团股份有限公司 | 一种路基土石方方量的计算方法及系统 |
WO2024033981A1 (ja) * | 2022-08-08 | 2024-02-15 | 株式会社Earthbrain | 工事用道路経路設計装置、工事用道路経路設計方法及びプログラム |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111005273A (zh) | 施工临时道路布置方法 | |
CN102506824B (zh) | 一种城市低空无人机系统生成数字正射影像图的方法 | |
CN103711050B (zh) | 一种激光雷达道路改扩建勘测设计方法 | |
Petzold et al. | Laser scanning—surveying and mapping agencies are using a new technique for the derivation of digital terrain models | |
CN101814102B (zh) | 一种基于高分辨卫星影像的公路测设方法 | |
CN101872376B (zh) | 真三维道路智能设计方法及系统 | |
CN111428306A (zh) | 一种道路精细化设计方法 | |
CN101159066A (zh) | 基于三维机载lidar的公路测设方法 | |
KR101884018B1 (ko) | 라이다 데이터를 이용한 도로의 곡선반경, 종단 및 횡단 경사도 산출 방법 | |
CN113570527B (zh) | 水上水下三维点云的融合方法 | |
Mihai et al. | High resolution landscape change analysis with CORONA KH-4B imagery. A case study from Iron Gates reservoir area | |
CN112818776A (zh) | 一种基于机载LiDAR点云的铁路既有线横断面测量方法 | |
CN113532509A (zh) | 一种基于空天地立体技术的大规模高陡边坡监测方法 | |
Şmuleac et al. | Comparative Study of the Volumetric Methods Calculation Using GNSS Measurements | |
CN114674277A (zh) | 全场测线联合的深部开采地表沉陷监测及土地复垦适宜性评价方法 | |
CN106197378A (zh) | 一种采用无人机测量的路基 | |
CN111783191A (zh) | 基于倾斜摄影技术的山区道路土方量计算方法 | |
Calina et al. | Study on Levelling Works Made for Drawing Tridimensional Models of Surface and Calculus of the Volume of Earthwork | |
Vichrová et al. | Digital Terrain Model of the Second Military Survey–Part of the Military Training Area Brdy | |
CN112766721B (zh) | 一种淤地坝规划选址和规模估算方法 | |
CN115909091A (zh) | 一种基于无人机三维扫描实景建模的土方量计算方法 | |
CN112733215A (zh) | 基于改进约束不规则三角网构建法的土方工程量计算方法 | |
Chen et al. | 3D road modeling via the integration of large-scale topomaps and airborne LIDAR data | |
CN112765707A (zh) | 一种路基土石方方量的计算方法及系统 | |
Amoo et al. | ROUTE SURVEY FROM AWERE STREAM TO EGBEDA LOOGUN VILLAGE, EDE, EDE SOUTH LOCAL GOVERNMENT AREA, OSUN STATE. |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200414 |
|
RJ01 | Rejection of invention patent application after publication |