CN112627311A - Drainage method for building construction in mountainous region with large precipitation - Google Patents

Drainage method for building construction in mountainous region with large precipitation Download PDF

Info

Publication number
CN112627311A
CN112627311A CN202011448204.3A CN202011448204A CN112627311A CN 112627311 A CN112627311 A CN 112627311A CN 202011448204 A CN202011448204 A CN 202011448204A CN 112627311 A CN112627311 A CN 112627311A
Authority
CN
China
Prior art keywords
construction
drainage
field
precipitation
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011448204.3A
Other languages
Chinese (zh)
Inventor
张典
王兵
唐轩
李万军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN202011448204.3A priority Critical patent/CN112627311A/en
Publication of CN112627311A publication Critical patent/CN112627311A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/04Gullies inlets, road sinks, floor drains with or without odour seals or sediment traps
    • E03F5/0401Gullies for use in roads or pavements
    • E03F5/0403Gullies for use in roads or pavements with a sediment trap
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • E03F5/101Dedicated additional structures, interposed or parallel to the sewer system

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The invention relates to a drainage method for building construction in mountainous regions with large precipitation, which is characterized in that when flat construction is carried out in a field, a water intercepting ditch and a certain amount of precipitation wells in a ring field are built along the position of 50-100cm of a fence, then drainage ditches and a certain amount of precipitation wells along a main trunk are built on one side of the main trunk by utilizing a construction main trunk in the construction region, one drainage ditch is arranged at intervals of 30-50 meters, temporary steel plates are covered on the upper parts of the drainage ditches needing to enter and exit by large machinery and are used for vehicles and machinery to enter and exit the construction field, and the ordered construction and the smooth drainage in the field are ensured; finally, when a plurality of steps are constructed, the building plane on the same construction step looks for slopes towards the drainage facilities on two sides as much as possible, and the drainage facilities generally adopt a method of descending and connecting layer by layer from the upper layer to the lower layer. The invention reduces the influence of rainwater siltation on site construction, reduces the work waste of site workers and saves the construction period cost.

Description

Drainage method for building construction in mountainous region with large precipitation
Technical Field
The invention relates to the field of house construction, in particular to a drainage method for building construction in mountainous regions with large precipitation.
Background
With the rapid development of construction enterprises, the construction market of coastal areas is transferred to western areas, various construction technologies of the relatively flat coastal areas are mature, but the application of the construction technologies in southwest mountain areas is less, the requirements of enterprises and markets on construction quality, progress and benefit are gradually improved, a certain method of arranging intercepting ditches and drainage ditches in construction areas is generally adopted when the construction is carried out on hilly landforms such as western rainy mountain areas, the problem that soft foundation construction machinery cannot enter the field for construction due to accumulated water and poor drainage of foundations in part of the construction areas is generally caused at present, and if the problem cannot be solved properly, the enterprises have relatively large uncertain factors in project construction period and self profit, and great risks are generated.
Disclosure of Invention
The invention aims to overcome the defects of the prior art, provides a drainage method for building construction in mountainous regions with large precipitation, and solves the problem that the foundation of the building construction site in mountainous and waist regions with large precipitation is difficult to be constructed after being soaked by rainwater.
In order to solve the technical problem, the invention is realized as follows:
a drainage method for building construction in mountainous regions with large precipitation is characterized by comprising the following steps:
firstly, when the flat field construction is carried out in a field area, a water intercepting ditch (intercepting rainwater catchment from the outside of the field of a construction area) and a certain amount of precipitation wells (eliminating flowing water scouring stress in the water drainage process) of the ring field area are built (brick laying and low-standard concrete construction are both available) along the position of 50-100cm of enclosure protection, so that precipitation outside the construction area is prevented from flowing into the construction site and being discharged into surrounding drainage facilities uncontrollably and orderly;
secondly, drainage ditches and a certain number of dewatering wells along the main trunk road are built on one side of the construction main road in the construction area, one drainage ditch is arranged at intervals of 30-50 meters, temporary steel plates are covered on the upper parts of the drainage ditches needing to be accessed by large machinery and are used for vehicles and machinery to access the construction site, and the orderly construction and drainage in the site are ensured to be smooth;
finally, when a plurality of steps are constructed, the building plane on the same construction step looks for slopes towards the drainage facilities on two sides as much as possible, the drainage facilities generally adopt a method of reducing and connecting layer by layer from the upper layer to the lower layer, and the following points can be ensured:
1) normally working, if some parts are blocked by silt, workers need to be dispatched to clean the silted silt in time;
2) all the drainage facilities on the same floor, steps and high floors are positioned at the lowest elevation of the same floor;
3) the drainage facilities in the field are communicated and cannot be disconnected, and are arranged in a row to a three-stage sedimentation tank or a car washing tank arranged in the field.
The invention has the beneficial effects that: set up the combination precipitation system of escape canal and precipitation well at inside periphery in original construction area and construction main road next door, guarantee the certain drainage slope rate of this system, let the effectual getting rid of ponding in the place and holding back, problem that the foundation that can be great help is soaked by the water and is leaded to unable construction of machinery and very big time limit for a project that delays.
Compared with the common operation method, the method has the advantages that the field construction progress is accelerated, the influence of rainwater deposition on the field construction is reduced, the labor waste of field workers is reduced, and the construction period cost is saved.
Drawings
The invention is described in further detail below with reference to the following figures and embodiments:
fig. 1 is a schematic view of each floor of drainage facility.
Detailed Description
As shown in fig. 1: for the united villa buildings constructed in mountainous areas such as clouds, nobility, Sichuan and Yu, the height and the fall in the construction area are usually extremely large, the rainfall is abundant, and each layered platform is greatly influenced by the accumulated water when the multi-layer construction pile foundation is divided, and the drainage method for the buildings in the mountainous areas with large rainfall in the application has the following concrete method:
firstly, when the flat field construction is carried out in the field, a water intercepting ditch (intercepting rainwater catchment from the outside of the field of a construction area) and a certain amount of precipitation wells (eliminating flowing water scouring stress in the water drainage process) of the annular field are built (both brick laying and low-grade concrete construction) along the position of 50-100cm of the enclosure protection, so that precipitation outside the construction area is prevented from flowing into the construction site and is discharged into surrounding drainage facilities in an uncontrolled manner and in sequence.
Secondly, constructing drainage ditches 1 and a certain number of dewatering wells 2 (one every 30-50 meters) along the main road on one side of the main road by utilizing the construction main road in the construction area, wherein i is the water flow direction in the figure 1, and temporary steel plates are covered on the upper parts of the drainage ditches needing to be accessed by large-scale machinery for vehicles and machinery to enter and exit the construction site, so that the orderly construction and the smooth drainage in the site are ensured;
then, when a plurality of steps are constructed, the building plane on the same construction step looks for slopes towards the drainage facilities on two sides as much as possible, the drainage facilities generally adopt a method (drainage ditch, dewatering well and the like) of descending and connecting layer by layer from the upper layer to the lower layer, and the following points can be ensured:
1. normally working, if some parts are blocked by silt, workers need to be dispatched to clean the silted silt in time;
2. all the drainage facilities on the same floor, steps and high floors are positioned at the lowest elevation of the same floor;
3. the drainage facilities in the field are communicated and cannot be disconnected, and are arranged in a row to a three-stage sedimentation tank or a car washing tank arranged in the field.

Claims (1)

1. A drainage method for building construction in mountainous regions with large precipitation is characterized by comprising the following steps:
firstly, when the flat field construction is carried out in a field area, a water intercepting ditch (intercepting rainwater catchment from the outside of the field of a construction area) and a certain amount of precipitation wells (eliminating flowing water scouring stress in the water drainage process) of the ring field area are built (brick laying and low-standard concrete construction are both available) along the position of 50-100cm of enclosure protection, so that precipitation outside the construction area is prevented from flowing into the construction site and being discharged into surrounding drainage facilities uncontrollably and orderly;
secondly, drainage ditches and a certain number of dewatering wells along the main trunk road are built on one side of the construction main road in the construction area, one drainage ditch is arranged at intervals of 30-50 meters, temporary steel plates are covered on the upper parts of the drainage ditches needing to be accessed by large machinery and are used for vehicles and machinery to access the construction site, and the orderly construction and drainage in the site are ensured to be smooth;
finally, when a plurality of steps are constructed, the building plane on the same construction step looks for slopes towards the drainage facilities on two sides as much as possible, the drainage facilities generally adopt a method of reducing and connecting layer by layer from the upper layer to the lower layer, and the following points can be ensured:
1) normally working, if some parts are blocked by silt, workers need to be dispatched to clean the silted silt in time;
2) all the drainage facilities on the same floor, steps and high floors are positioned at the lowest elevation of the same floor;
3) the drainage facilities in the field are communicated and cannot be disconnected, and are arranged in a row to a three-stage sedimentation tank or a car washing tank arranged in the field.
CN202011448204.3A 2020-12-11 2020-12-11 Drainage method for building construction in mountainous region with large precipitation Pending CN112627311A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011448204.3A CN112627311A (en) 2020-12-11 2020-12-11 Drainage method for building construction in mountainous region with large precipitation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011448204.3A CN112627311A (en) 2020-12-11 2020-12-11 Drainage method for building construction in mountainous region with large precipitation

Publications (1)

Publication Number Publication Date
CN112627311A true CN112627311A (en) 2021-04-09

Family

ID=75310318

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011448204.3A Pending CN112627311A (en) 2020-12-11 2020-12-11 Drainage method for building construction in mountainous region with large precipitation

Country Status (1)

Country Link
CN (1) CN112627311A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03281826A (en) * 1990-03-30 1991-12-12 Toda Constr Co Ltd Excavation method in cohesive soil ground
CN205314118U (en) * 2016-01-15 2016-06-15 中国化学工程第七建设有限公司 Drainage system on large -scale basis
CN109555141A (en) * 2018-12-24 2019-04-02 上海建工二建集团有限公司 Strong drainage system for ultra-large deep foundation pit and construction method
CN110055972A (en) * 2019-04-28 2019-07-26 中国电建集团山东电力建设有限公司 Dry dock foundation ditch construction method and dry dock foundation pit structure
CN210395607U (en) * 2019-07-25 2020-04-24 中国建筑第八工程局有限公司 Side slope buried drainage structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03281826A (en) * 1990-03-30 1991-12-12 Toda Constr Co Ltd Excavation method in cohesive soil ground
CN205314118U (en) * 2016-01-15 2016-06-15 中国化学工程第七建设有限公司 Drainage system on large -scale basis
CN109555141A (en) * 2018-12-24 2019-04-02 上海建工二建集团有限公司 Strong drainage system for ultra-large deep foundation pit and construction method
CN110055972A (en) * 2019-04-28 2019-07-26 中国电建集团山东电力建设有限公司 Dry dock foundation ditch construction method and dry dock foundation pit structure
CN210395607U (en) * 2019-07-25 2020-04-24 中国建筑第八工程局有限公司 Side slope buried drainage structure

Similar Documents

Publication Publication Date Title
CN107938692B (en) Drainage and recharging construction method and structure
CN111560957B (en) Shield receiving well foundation pit excavation and supporting non-dewatering construction method
CN102449239A (en) Method for forming reclaimed land within seawall and construction equipment thereof
CN112095644A (en) Deep foundation pit water intercepting and draining device and construction method thereof
CN111519734B (en) Silt dredging method for river channel hidden culvert
CN112854228A (en) Confined space foundation pit earth excavation construction method
CN105332382B (en) Adjacent river foundation ditch builds island cofferdam clay water stop construction method
CN101049602B (en) The landfill having the drainage system against rain and the method for forming this landfill
CN207567892U (en) A kind of large size karst depression flood drainage system
CN112127390B (en) Construction technology for simply plugging reserved sleeve of outer wall in underground structure area
CN107700434B (en) Arch-shaped grid type reinforced concrete debris flow blocking dam and construction method thereof
CN112627311A (en) Drainage method for building construction in mountainous region with large precipitation
CN207828994U (en) It is a kind of draining and recharge constructing structure
CN110747861A (en) High-water-level deep foundation pit excavation construction method
CN110093939A (en) A kind of method of mining area slope ecological reparation
CN213038444U (en) Temporary device for screening sludge in river channel culvert
CN114790748A (en) Construction method for deep foundation pit near existing line
CN212175794U (en) Deep basal pit falls and arranges two unification sump pit structures
CN211973377U (en) Anti-impact pile protection plate combined structure
CN208949951U (en) A kind of riverway sludge cleaning plant
CN111395268A (en) Construction method for concrete gravity dam of mountain river during flood season
CN106120640A (en) A kind of construction method preventing and treating mountain stream bridge foundation washout
CN111827198A (en) Construction method for central control water replacement and filling in tidal lake water environment ecological restoration
CN219710339U (en) Deep foundation pit cross pipeline connection port supporting protection structure
CN103195103B (en) Drainage system of solid waste disposal site

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210409