CN112095644A - Deep foundation pit water intercepting and draining device and construction method thereof - Google Patents

Deep foundation pit water intercepting and draining device and construction method thereof Download PDF

Info

Publication number
CN112095644A
CN112095644A CN202011086499.4A CN202011086499A CN112095644A CN 112095644 A CN112095644 A CN 112095644A CN 202011086499 A CN202011086499 A CN 202011086499A CN 112095644 A CN112095644 A CN 112095644A
Authority
CN
China
Prior art keywords
pit
foundation pit
deep foundation
drainage
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011086499.4A
Other languages
Chinese (zh)
Inventor
苗恩新
余健
高兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd, Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN202011086499.4A priority Critical patent/CN112095644A/en
Publication of CN112095644A publication Critical patent/CN112095644A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • E03F5/101Dedicated additional structures, interposed or parallel to the sewer system

Abstract

The invention discloses a deep foundation pit water intercepting and draining device and a construction method thereof, wherein the device comprises fender posts arranged along the periphery of a deep foundation pit, and an out-pit dewatering well and an in-pit dewatering well which are respectively arranged outside the deep foundation pit and inside the deep foundation pit, a supporting structure connected with the fender posts is arranged at the opening part of the deep foundation pit, crown beams are poured at the tops of the fender posts, retaining walls are built on the crown beams, drainage ditches are buried in a slope top backfill soil side outside the retaining walls, meanwhile, water collecting wells are buried at certain intervals, and the drainage ditches are connected with the water collecting wells. The invention breaks through the traditional mode of adopting brick drainage ditches and water collecting wells, adopts half-corrugated pipe drainage ditches and steel water collecting wells to replace, overcomes the defects of material waste and long construction period of the traditional mode, and the water interception and drainage device is made of shaped recyclable materials, and is convenient, rapid and efficient to install; the requirements of water interception and drainage of the slope top of the foundation pit can be met, sustainable use is facilitated, and the purposes of energy conservation and environmental protection are achieved.

Description

Deep foundation pit water intercepting and draining device and construction method thereof
Technical Field
The invention relates to a deep foundation pit water intercepting and draining device and a construction method thereof, belonging to the technical field of industrial and civil building engineering.
Background
In the deep foundation pit constructional engineering work process, the internal and external precipitation of foundation pit and ground water interception facility have certainly existed for the internal and external water level of deep foundation pit keeps at certain elevation, at the drainage in-process that falls, foundation pit sloping top must set up and cut drainage system, and traditional way adopts brick drainage ditch and water collection well as cutting drainage system, and this kind of mode construction speed is slow, with high costs.
Disclosure of Invention
The invention aims to provide a deep foundation pit water intercepting and draining device and a construction method thereof, wherein the device is convenient, rapid and efficient to install, meets the construction requirements of water drainage and ground interception, and can ensure the safety control of deep foundation pit construction.
In order to achieve the purpose, the invention adopts the following technical scheme: the utility model provides a deep basal pit cuts drainage device, includes the fender pile that arranges along the deep basal pit periphery and sets up respectively at the outside pit precipitation well and the pit in the pit inside of deep basal pit outside and deep basal pit, is provided with the bearing structure who is connected with the fender pile in the oral area of deep basal pit, has pour the hat roof beam at the top of fender pile, has built by laying bricks or stones retaining wall on the hat roof beam, has buried the escape canal in the slope top backfill earthwork in the retaining wall outside, has buried the sump pit according to the certain interval simultaneously, escape canal and sump pit connection, pour the slope top sclerosis layer in the slope top backfill earthwork, and slope top sclerosis layer has a certain slope and inclines to the escape canal direction, all is provided with the immersible pump in pit outer precipitation well and the pit in the precipitation well, and the immersible pump in pit outer precipitation well and the pit in the pit all is connected with the sump pit through the drain pipe.
Further, the retaining wall is higher than the slope top backfill earthwork outside the deep foundation pit.
Further, the elevation of escape canal and the oral area parallel and level of sump pit.
Meanwhile, the invention also provides a deep foundation pit water intercepting and draining construction method based on the deep foundation pit water intercepting and draining device, which comprises the following steps:
firstly, enclosing piles are arranged along the periphery of a deep foundation pit, an out-pit dewatering well and an in-pit dewatering well are respectively arranged outside the deep foundation pit and inside the deep foundation pit, then a top beam is poured on the top of the enclosing piles, a retaining wall is built on the top beam, and foundation pit slope top earthwork backfilling is carried out on the outer side of the retaining wall; burying drainage ditches on the slope top backfill earthwork outside the retaining wall, burying water collecting wells at certain intervals, connecting the drainage ditches with the water collecting wells, and then pouring a slope top hardened layer on the slope top backfill earthwork to ensure that the slope top hardened layer has a certain gradient and inclines towards the drainage ditches, so as to facilitate water interception;
before earth excavation, putting submersible pumps into the precipitation well outside the pit and the precipitation well inside the pit, connecting the submersible pumps with the water collecting well through drain pipes, pumping water in the precipitation well outside the pit and the precipitation well inside the pit into the water collecting well, enabling water overflowing from the water collecting well to flow into a third-stage sedimentation tank through drainage ditches, purifying the water by the third-stage sedimentation tank, and discharging the purified water into a municipal pipe network;
and step three, after the rainfall reaches the design requirement, arranging a supporting structure connected with the guard post at the opening part of the deep foundation pit, continuously excavating earthwork in the deep foundation pit after the supporting structure reaches the design strength until the underground structure is constructed, and stopping the rainfall after the earthwork of the deep foundation pit is backfilled.
In the method, the drainage ditch is a half-bellows drainage ditch which is manufactured by cutting a bellows with the diameter of 300-350 mm from the middle; the water collecting well is a steel water collecting well formed by welding stainless steel plates, semicircular notches are symmetrically formed in two sides of the opening of the water collecting well, and the drainage ditch is connected to the semicircular notches.
In the method, the fender pile is a row pile, a waterproof curtain, an underground continuous wall, an SMW construction pile or a TRD and I-steel, the supporting structure is a concrete support, a steel support or an anchor cable, and the retaining wall is a brick retaining wall, a concrete retaining wall or a spray anchor.
Due to the adoption of the technical scheme, the invention has the following advantages: the invention breaks through the traditional mode of adopting brick drainage ditches and water collecting wells, adopts half-corrugated pipe drainage ditches and steel water collecting wells to replace, overcomes the defects of material waste and long construction period of the traditional mode, and the water interception and drainage device is made of shaped recyclable materials, and is convenient, rapid and efficient to install; the requirements of water interception and drainage of the slope top of the foundation pit can be met, sustainable use is facilitated, and the purposes of energy conservation and environmental protection are achieved.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic view of a connection structure of a drainage ditch and a collector well.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
The embodiment of the invention comprises the following steps: referring to fig. 1, a deep foundation pit intercepting and draining device and a construction method thereof includes fender posts 1 arranged along the periphery of a deep foundation pit, and an out-pit dewatering well 4 and an in-pit dewatering well 5 respectively disposed outside and inside the deep foundation pit, a supporting structure 2 connected with the fender post 1 is arranged at the opening part of the deep foundation pit, a crown beam 3 is poured at the top part of the fender post 1, a retaining wall 6 is built on the crown beam 3, a drainage ditch 8 is buried in the slope top backfill earthwork outside the retaining wall 6, meanwhile, water collecting wells 7 are buried at certain intervals, the drainage ditch 8 is connected with the water collecting wells 7, a slope top hardened layer 9 is poured on the slope top backfill earthwork, the slope top hardened layer 9 has a certain gradient and inclines towards the drainage ditch 8, submersible pumps 10 are arranged in the precipitation well 4 outside the pit and the precipitation well 5 in the pit, and the submersible pumps 10 in the precipitation well 4 outside the pit and the precipitation well 5 in the pit are connected with the water collecting well 7 through drain pipes 11. And the retaining wall 6 is higher than the slope top backfill earthwork at the outer side of the deep foundation pit. The elevation of the drainage ditch 8 is flush with the opening of the water collecting well 7.
When the deep foundation pit water intercepting and draining device is used for deep foundation pit water intercepting and draining construction, the following steps can be adopted:
firstly, arranging fender posts 1 along the periphery of a deep foundation pit, respectively digging an out-pit dewatering well 4 and an in-pit dewatering well 5 outside the deep foundation pit and inside the deep foundation pit, then pouring a crown beam 3 on the top of the fender posts 1, building a retaining wall 6 on the crown beam 3, and backfilling the top earthwork of the foundation pit at the outer side of the retaining wall 6; burying drainage ditches 8 in the slope top backfilling earthwork outside the retaining wall 6, burying water collecting wells 7 at certain intervals, connecting the drainage ditches 8 with the water collecting wells 7, and pouring a slope top hardened layer 9 on the slope top backfilling earthwork to ensure that the slope top hardened layer 9 has a certain gradient and inclines towards the drainage ditches 8 so as to facilitate water interception;
before earth excavation, putting a submersible pump 10 into the out-of-pit dewatering well 4 and the in-pit dewatering well 5, connecting the submersible pump 10 with the water collecting well 7 through a drain pipe 11, pumping water in the out-of-pit dewatering well 4 and the in-pit dewatering well 5 into the water collecting well 7, and then enabling water overflowing from the water collecting well 7 to flow into a third-stage sedimentation tank through a drainage ditch 8 and be discharged into a municipal pipe network after being purified by the third-stage sedimentation tank;
and step three, after the rainfall reaches the design requirement, arranging a supporting structure 2 connected with the fender post 1 at the opening part of the deep foundation pit, continuously excavating earthwork in the deep foundation pit after the supporting structure 2 reaches the design strength until the underground structure is constructed, and stopping the rainfall after the earthwork of the deep foundation pit is backfilled.
Referring to fig. 2, in the embodiment, the drainage ditch 8 is a half-bellows drainage ditch manufactured by cutting a corrugated pipe with a diameter of 300-350 mm from the middle; the water collecting well 7 is a steel water collecting well formed by welding stainless steel plates, semicircular notches are symmetrically formed in two sides of an opening of the water collecting well 7, and the drainage ditch 8 is connected to the semicircular notches.
In this embodiment, fender pile 1 is campshed + waterproof curtain, underground continuous wall, SMW worker method stake or TRD + I-steel, bearing structure 2 is concrete support, steel shotcrete or anchor rope, retaining wall 6 is brick retaining wall, concrete retaining wall or spray anchor.
In conclusion, the invention breaks through the traditional mode of adopting brick drainage ditches and water collecting wells, adopts half-corrugated pipe drainage ditches and steel water collecting wells to replace, overcomes the defects of material waste and long construction period of the traditional mode, and the water interception and drainage device is made of shaped recyclable materials, and is convenient, rapid and efficient to install; the requirements of water interception and drainage of the slope top of the foundation pit can be met, sustainable use is facilitated, and the purposes of energy conservation and environmental protection are achieved.

Claims (6)

1. The utility model provides a deep basal pit cuts drainage device, includes fender pile (1) and the interior precipitation well (5) of pit (4) and pit that set up respectively outside the deep basal pit and inside the deep basal pit along the peripheral fender post (1) of arranging of deep basal pit, its characterized in that: be provided with bearing structure (2) of being connected with fender pile (1) at the oral area of deep basal pit, pour crown beam (3) at the top of fender pile (1), build by laying bricks or stones retaining wall (6) on crown beam (3), bury drainage ditch (8) underground on the slope top backfill earthwork in the retaining wall (6) outside, bury sump pit (7) according to a determining deviation simultaneously, drainage ditch (8) and sump pit (7) be connected, pour slope top sclerosis layer (9) on the slope top backfill earthwork, and slope top sclerosis layer (9) have certain slope and to the slope of drainage ditch (8) direction, all be provided with immersible pump (10) in precipitation well (5) outside the pit and in the pit, and immersible pump (10) in precipitation well (4) outside the pit and the pit in precipitation well (5) all are connected with sump pit (7) through drain pipe (11).
2. The deep foundation pit intercepting drainage device of claim 1, wherein: and the retaining wall (6) is higher than the slope top backfill earthwork at the outer side of the deep foundation pit.
3. The deep foundation pit intercepting drainage device of claim 1, wherein: the elevation of the drainage ditch (8) is flush with the opening of the water collecting well (7).
4. A deep foundation pit water intercepting and draining construction method based on the deep foundation pit water intercepting and draining device of any one of claims 1-3 is characterized by comprising the following steps:
firstly, retaining piles (1) are arranged along the periphery of a deep foundation pit, an out-pit dewatering well (4) and an in-pit dewatering well (5) are respectively arranged outside the deep foundation pit and inside the deep foundation pit, then a top beam (3) is poured on the top of each retaining pile (1), a retaining wall (6) is built on each top beam (3), and foundation pit slope top earthwork backfilling is carried out on the outer side of each retaining wall (6); burying drainage ditches (8) in the slope top backfill earthwork on the outer side of the retaining wall (6), burying water collecting wells (7) at certain intervals, connecting the drainage ditches (8) with the water collecting wells (7), and pouring a slope top hardened layer (9) in the slope top backfill earthwork to ensure that the slope top hardened layer (9) has a certain gradient and inclines towards the drainage ditches (8) so as to facilitate water interception;
before earth excavation, putting a submersible pump (10) into the out-of-pit dewatering well (4) and the in-pit dewatering well (5), connecting the submersible pump (10) with the water collecting well (7) through a drainage pipe (11), pumping water in the out-of-pit dewatering well (4) and the in-pit dewatering well (5) into the water collecting well (7), enabling water overflowing from the water collecting well (7) to flow into a three-stage sedimentation tank through a drainage ditch (8), and discharging the water into a municipal pipe network after being purified by the three-stage sedimentation tank;
and step three, after the precipitation reaches the design requirement, arranging a supporting structure (2) connected with the fender post (1) at the opening part of the deep foundation pit, continuing excavating earthwork in the deep foundation pit after the supporting structure (2) reaches the design strength until the underground structure is constructed, and stopping the precipitation after backfilling the earthwork of the deep foundation pit.
5. The deep foundation pit water interception and drainage construction method according to claim 4, characterized in that: the drainage ditch (8) is a half-corrugated-pipe drainage ditch which is manufactured by cutting a corrugated pipe with the diameter of 300-350 mm from the middle; the water collecting well (7) is a steel water collecting well formed by welding stainless steel plates, semicircular notches are symmetrically formed in two sides of the opening of the water collecting well (7), and the drainage ditch (8) is connected to the semicircular notches.
6. The deep foundation pit water interception and drainage construction method according to claim 4, characterized in that: fender pile (1) is row pile + stagnant water curtain, underground continuous wall, SMW worker method stake or TRD + I-steel, bearing structure (2) are concrete support, steel shotcrete or anchor rope, retaining wall (6) are brick retaining wall, concrete retaining wall or spray anchor.
CN202011086499.4A 2020-10-12 2020-10-12 Deep foundation pit water intercepting and draining device and construction method thereof Pending CN112095644A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011086499.4A CN112095644A (en) 2020-10-12 2020-10-12 Deep foundation pit water intercepting and draining device and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011086499.4A CN112095644A (en) 2020-10-12 2020-10-12 Deep foundation pit water intercepting and draining device and construction method thereof

Publications (1)

Publication Number Publication Date
CN112095644A true CN112095644A (en) 2020-12-18

Family

ID=73784095

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011086499.4A Pending CN112095644A (en) 2020-10-12 2020-10-12 Deep foundation pit water intercepting and draining device and construction method thereof

Country Status (1)

Country Link
CN (1) CN112095644A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115217134A (en) * 2022-08-31 2022-10-21 中国二十二冶集团有限公司 Water reducing method for ground surface pore water in pebble bed and weathered rock region in narrow region
CN115341560A (en) * 2022-10-19 2022-11-15 中国建筑第六工程局有限公司 Construction method of temporary drainage system in deep foundation pit engineering construction site

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4020902A (en) * 1975-07-03 1977-05-03 R. L. Gould Well point system
CN205804380U (en) * 2016-06-12 2016-12-14 中国十七冶集团有限公司 A kind of Deep Foundation Pit Well-Point Dewatering and the wastewater recycling system of pile tube subsoil water
CN108677981A (en) * 2018-04-18 2018-10-19 中国十七冶集团有限公司 A kind of discharge structure and its construction method of ultra-deep piping lane foundation pit
CN212896422U (en) * 2020-10-12 2021-04-06 中国建筑第四工程局有限公司 Deep foundation pit water intercepting and draining device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4020902A (en) * 1975-07-03 1977-05-03 R. L. Gould Well point system
CN205804380U (en) * 2016-06-12 2016-12-14 中国十七冶集团有限公司 A kind of Deep Foundation Pit Well-Point Dewatering and the wastewater recycling system of pile tube subsoil water
CN108677981A (en) * 2018-04-18 2018-10-19 中国十七冶集团有限公司 A kind of discharge structure and its construction method of ultra-deep piping lane foundation pit
CN212896422U (en) * 2020-10-12 2021-04-06 中国建筑第四工程局有限公司 Deep foundation pit water intercepting and draining device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115217134A (en) * 2022-08-31 2022-10-21 中国二十二冶集团有限公司 Water reducing method for ground surface pore water in pebble bed and weathered rock region in narrow region
CN115341560A (en) * 2022-10-19 2022-11-15 中国建筑第六工程局有限公司 Construction method of temporary drainage system in deep foundation pit engineering construction site

Similar Documents

Publication Publication Date Title
CN212896422U (en) Deep foundation pit water intercepting and draining device
CN111733828A (en) Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
CN102418347B (en) Drainage construction method for blind drain and sump wells in deep foundation pit
CN100510281C (en) Semi-inverse construction method of super large diameter, ultra-burial depth storage pond
CN104711994A (en) Foundation pit deep well rainfall and plugging construction method
CN102454167A (en) Construction method for large ultra-deep well
CN113266392B (en) Pipe jacking construction method for penetrating through existing anchor cable group
CN110438999A (en) A kind of deep basal pit slope excavation construction method of rich groundwater
CN110847199A (en) Construction method for drainage of underground water of deep foundation pit
CN112095644A (en) Deep foundation pit water intercepting and draining device and construction method thereof
CN111236284A (en) Basement bottom and periphery underground water drainage method and structure
CN110700280A (en) Narrow zone foundation pit supporting construction flow guide device and construction method
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
CN215105880U (en) Concrete inverted well suitable for connecting new and old water supply and drainage pipelines
CN101824825B (en) Deep foundation pit open cutting construction method
CN104775439A (en) Foundation pit support and water stop integrated structure and construction method thereof
CN112282029B (en) Connection construction method for urban high-water-level large-diameter reinforced concrete sewage pipeline
CN212641685U (en) Underground garage drainage open ditch and blind ditch combine antiseep system
CN203530924U (en) Green and ecological revetment retaining wall structure of river channel
CN112302136A (en) Connecting structure of new and old drainage pipelines under non-closure working condition and construction method thereof
CN104328836B (en) A kind of environment-friendly type prefabricated pair of case deep hole type catch pit and construction method thereof
CN104846837B (en) The construction method of ultra-deep well in a kind of bright draining foundation ditch
CN103866787B (en) A kind of spacious reverse masonry method concrete cut that digs builds construction technology
CN110093965A (en) A kind of water discharge method of construction site
CN110616719B (en) Quick construction method for U-shaped groove of upper-span existing culvert

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination