CN110055972A - Dry dock foundation ditch construction method and dry dock foundation pit structure - Google Patents

Dry dock foundation ditch construction method and dry dock foundation pit structure Download PDF

Info

Publication number
CN110055972A
CN110055972A CN201910348638.7A CN201910348638A CN110055972A CN 110055972 A CN110055972 A CN 110055972A CN 201910348638 A CN201910348638 A CN 201910348638A CN 110055972 A CN110055972 A CN 110055972A
Authority
CN
China
Prior art keywords
foundation pit
slope
ponding
cut
dry dock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910348638.7A
Other languages
Chinese (zh)
Inventor
刘建兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEPCO Electric Power Construction Co Ltd
Original Assignee
SEPCO Electric Power Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SEPCO Electric Power Construction Co Ltd filed Critical SEPCO Electric Power Construction Co Ltd
Priority to CN201910348638.7A priority Critical patent/CN110055972A/en
Publication of CN110055972A publication Critical patent/CN110055972A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/10Restraining of underground water by lowering level of ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/22Lining sumps in trenches or other foundation pits

Abstract

The invention discloses a kind of dry dock foundation ditch construction methods, comprising: cut-pff wall A, is built except foundation pit construction region, cut-pff wall surrounds foundation pit construction region, and the bottom of cut-pff wall reaches impermeable stratum;The drainage trenching in the earth's surface except cut-pff wall;Multiple vertical dewatering wells are dug between cut-pff wall and foundation pit construction region;Excavation of foundation pit;It is laid with drainage pad layer at Foundation Pit bottom, drainpipe is installed in drainage pad layer, then in the upper surface casting concrete layer of drainage pad layer.Also disclosing can be using the dry dock foundation pit structure of above method construction.The present invention can prevent rainwater, underground water, surface water etc. from entering foundation pit and generate ponding, carry out construction continuously normally, be conducive to improve construction efficiency, guarantee construction quality.

Description

Dry dock foundation ditch construction method and dry dock foundation pit structure
Technical field
The present invention relates to dry dock technical field of construction, and in particular to a kind of dry dock foundation ditch construction method and dry dock base Cheat structure.
Background technique
Dry dock is suitable for the closed basin that ship water outlet is checked, repaired.Dry dock is typically set up by the sea, underground Water, rainwater are abundant, when carrying out foundation pit construction to dry dock, the case where foundation pit intakes and generates ponding, ponding leaching often occur It steeps oneself-meeting and adverse effect is caused to foundation pit, reduce the construction quality of foundation pit;When foundation pit water inlet, suction pump is usually used and takes out ponding Out, foundation pit construction progress is influenced.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of dry dock foundation ditch construction method of good waterproof performance and dry ships Depressed place foundation pit structure improves the quality of foundation pit construction.
The technical proposal for solving the technical problem of the invention is: dry dock foundation ditch construction method, comprising the following steps:
A, cut-pff wall is built except foundation pit construction region, cut-pff wall surrounds foundation pit construction region, and the bottom of cut-pff wall is arrived Up to impermeable stratum;
B, the drainage trenching in the earth's surface except cut-pff wall;
C, multiple vertical dewatering wells are dug between cut-pff wall and foundation pit construction region;
D, the side slope of excavation of foundation pit, foundation pit is Slope with multi-step, and Slope with multi-step includes multiple inclined slopes, and adjacent two inclined slope is logical It crosses horizontal slope platform to be connected, after often digging out a slope platform, ponding ditch is dug on the slope platform of inclined slope bottom;
E, it is laid with drainage pad layer at Foundation Pit bottom, drainpipe is installed in drainage pad layer, then in drainage pad layer Upper surface casting concrete layer.
Further, in step D, on each slope platform, a ponding well, ponding ditch and product are dug every 30m-40m Well connection;The ponding well depth of lower layer's slope platform is greater than the ponding well depth of upper layer slope platform.
Further, it is reinforced using the borehole wall of the plank to ponding well, spreads metalling in the bottom of ponding well.
Further, in step D, in the side wall and bottom applying mortar or laying plank of each ponding ditch.
Further, in step C, the internal diameter of each dewatering well is greater than or equal to 600mm, adjacent two dewatering well center away from It is located at below bottom of foundation ditch at 6m under from the bottom less than or equal to 25m, dewatering well.
Further, in step D, in inclined slope and slope platform upper berth steel wire and sandblasting slurry.
Further, in step D, when digging using machinery to away from bottom of foundation ditch absolute altitude 300mm, clear bottom, clear bottom are manually carried out The sandy soil of generation are transported by trolley.
Dry dock foundation pit structure, including gutter, cut-pff wall and the foundation pit ontology set gradually from outside to inside, the antiseepage Multiple vertical dewatering wells are provided between wall and foundation pit ontology, the side slope of the foundation pit ontology includes multiple inclined slopes, adjacent It is connected between two inclined slopes by horizontal slope platform, is provided with ponding ditch on the slope platform of the inclined slope bottom;Institute The bottom for stating foundation pit ontology is equipped with drainage pad layer, is provided with multiple drainpipes in drainage pad layer, drainage pad layer it is upper Surface is provided with concrete layer.
Further, multiple ponding wells are provided on each slope platform, the distance between adjacent two ponding well is 30m- 40m, ponding ditch are connected to ponding well;The ponding well depth of lower layer's slope platform is greater than the ponding well depth of upper layer slope platform.
Further, the gradient of the inclined slope is 0.5.
Compared with prior art, the beneficial effects of the present invention are: the present invention is by building cut-pff wall, drainage trenching, digging drop Well digs the measures such as ponding ditch, it is ensured that during foundation pit construction, prevents rainwater, underground water, surface water etc. from entering foundation pit and produces Raw ponding, carries out construction continuously normally, is conducive to improve construction efficiency, guarantees construction quality.
Detailed description of the invention
Fig. 1 is the whole schematic top plan view of dry dock foundation pit structure of the present invention;
Fig. 2 is the enlarged diagram of part A in Fig. 1;
Fig. 3 is the schematic cross-sectional view of dry dock foundation pit structure of the present invention;
Fig. 4 is the enlarged diagram of part B in Fig. 3;
Fig. 5 is the enlarged diagram of C portion in Fig. 3;
Appended drawing reference: 1-cut-pff wall;2-gutters;3-inclined slopes;4-slope platforms;5-ponding ditches;6-precipitation Well;7-drainage pad layers;8-drainpipes;9-concrete layers;10-ponding wells;20-foundation pit ontologies.
Specific embodiment
Present invention will be further explained below with reference to the attached drawings and examples.
Dry dock foundation ditch construction method of the invention, comprising the following steps:
A, cut-pff wall 1 is built except foundation pit construction region, cut-pff wall 1 surrounds foundation pit construction region, the bottom of cut-pff wall 1 Reach impermeable stratum.The position that cut-pff wall 1 is determined according to foundation pit construction region keeps cut-pff wall 1 moderate to the distance of margin of foundation pit. This cut-pff wall 1 uses wallboard type concrete continuous wall, grabs the soil body using hydraulic grab bucket grooving machine, while injecting mud and carrying out slot Holes protecting wall, wait dig to projected depth, into slot, concrete perfusion is at wall.The bottom of cut-pff wall 1 reaches impermeable stratum, guarantees outer Water in portion stratum penetrates into inside cut-pff wall 1 from 1 bottom of cut-pff wall, to improve waterproof effect.
B, the drainage trenching 2 in the earth's surface except cut-pff wall 1.Gutter 2 can also be dug multiple apart from cut-pff wall 1m or so Plash makes the water energy in gutter 2 enough flow into plash, and when raining causes earth's surface water flow occur, water flow flows into gutter 2, so that the water of earth's surface be avoided to flow into inside foundation pit.
C, multiple vertical dewatering wells 6 are dug between cut-pff wall 1 and foundation pit construction region.Due to adjoining seashore, water penetration Coefficient is larger, therefore, carries out precipitation using dewatering well 6, after the water around foundation pit construction region in soil layer penetrates into dewatering well 6, edge Dewatering well 6 flow downward, to reduce the water content in soil.Specifically, the internal diameter of each dewatering well 6 is greater than or equal to 600mm, the distance at adjacent two dewatering wells, 6 center are less than or equal to 25m, and the bottom of dewatering well 6 is located at below bottom of foundation ditch at 6m Hereinafter, guaranteeing preferable dewatering effect.Chimney filter of the bottom setting length not less than 5m and length of dewatering well 6 are not less than 1m's Sediment tube.Dewatering well 6 continues precipitation in Excavation Process, and the water surface in dewatering well 6 should be lower than Foundation Pit bottom absolute altitude 500mm More than.
D, excavation of foundation pit.Utilize excavating machinery shoveling muck haulage.The side slope of foundation pit is Slope with multi-step, and Slope with multi-step includes multiple Inclined slope 3, adjacent two inclined slope 3 are connected by horizontal slope platform 4, and the quantity of inclined slope 3 is specially 5 grades, the top Inclined slope 3 is connected with earth's surface, and the inclined slope 3 of bottom is connected with bottom of foundation ditch.It is Slope with multi-step by Slope Design, reduces side slope The gradient, the risk of slope failure can be reduced.After every construction for completing an inclined slope 3 or slope platform 4, in inclined slope 3 or 4 upper berth steel wire of slope platform, then sandblasting is starched, and prevents side slope sand grains wind-engaging, rainwater and mechanical oscillation effect from generating stream erosion existing As playing the role of slope protection, preventing slope failure, landslide.
When raining heavily, rainwater may flow on slope platform 4 along inclined slope 3, and ponding is then formed in foundation pit, The construction quality of construction speed and foundation pit is influenced, therefore, after often digging out a slope platform 4, the slope in 3 bottom of inclined slope is flat Ponding ditch 5 is dug on platform 4,5 depth of ponding ditch is 500mm, width 500mm, when rainwater is flowed down from inclined slope 3, can enter ponding Ditch 5 will not generate ponding in foundation pit, it is ensured that construction is normally carried out.
In order to increase reservoir storage, on each slope platform 4, every 30m-40m dig a ponding well 10, ponding ditch 5 with Ponding well 10 is connected to, and 10 oral area of ponding well is the square of 800mm*800mm, and depth is greater than 500mm, and lower layer's slope platform 4 10 depth of ponding well be greater than upper layer slope platform 4 10 depth of ponding well.In order to guarantee that the water energy in ponding ditch 5 enough flows into product Well 10 can set inclined-plane for the bottom surface of ponding ditch 5.
The side wall and bottom wall of current scour ponding ditch 5 and ponding well 10 in order to prevent, the side wall of each ponding ditch 5 and bottom Portion's applying mortar is laid with plank, is reinforced using the borehole wall of the plank to ponding well 10, and in the bottom of ponding well 10, paving is broken Rock layers.The side wall and bottom wall for playing the role of protecting ponding ditch 5 and ponding well 10, avoid water flow from directly washing away 5 He of ponding ditch The side wall and bottom wall of ponding well 10 prevent the side wall of ponding ditch 5 and ponding well 10 from being washed away, avoid ponding ditch 5 and ponding well 10 bottom wall is rushed out hole.
The machinery wieght digged pit is big, and when operation generates biggish vibration, may make into disturbance with local methods to ground, because This, digs foundation pit first with machinery, and when machinery is dug to away from bottom of foundation ditch absolute altitude 300mm, using clear bottom is manually carried out, clear bottom is used Spade soil, the sandy soil that clear bottom generates are transported by trolley, can avoid mechanical damage substrate undisturbed soil and phenomenon of backbreaking occur.
E, after the completion of excavation of foundation pit, it is laid with drainage pad layer 7 at Foundation Pit bottom as quickly as possible, bottom of foundation ditch is avoided to be grown Time is exposed to the sun or rainwater impregnates and influences bearing capacity.Drainpipe 8 is installed, drainpipe 8 is embedded in drainage pad in drainage pad layer 7 In layer 7, then in the upper surface casting concrete layer 9 of drainage pad layer 7.
In above-mentioned work progress, due to having built cut-pff wall 1, while gutter 2, dewatering well 6,5 and of ponding ditch have been dug Ponding well 10 can obstruct and drain the water outside foundation pit, while reduce the rainwater for flowing into bottom of foundation ditch, play good anti- Water, drainage avoid in the construction process, large-scale ponding occur inside foundation pit and influence construction speed and construction quality The case where.
The dry dock foundation pit structure that above-mentioned construction method is constructed can be used, as shown in Figure 1, Figure 2, Fig. 3, Fig. 4 and Fig. 5 institute Show, including gutter 2, cut-pff wall 1 and the foundation pit ontology 20 set gradually from outside to inside, the cut-pff wall 1 and foundation pit ontology 20 Between be provided with multiple vertical dewatering wells 6, the side slope of the foundation pit ontology 20 includes multiple inclined slopes 3, adjacent two inclined slope 3 Between by horizontal slope platform 4 be connected, be provided with ponding ditch 5 on the slope platform 4 of 3 bottom of inclined slope;The base The bottom of hole ontology 20 is equipped with drainage pad layer 7, and multiple drainpipes 8 are provided in drainage pad layer 7, drainage pad layer 7 Upper surface is provided with concrete layer 9.
Gutter 2 and cut-pff wall 1 are closed ring-type, surround foundation pit ontology 20, play good blocking water, draining effect Fruit.The bottom of cut-pff wall 1 reaches impermeable stratum, guarantees that the water in external stratum penetrates into inside cut-pff wall 1 from 1 bottom of cut-pff wall, To improve waterproof effect.Gutter 2 can also dig multiple plashes apart from cut-pff wall 1m or so, make the water energy in gutter 2 Plash is enough flowed into, when raining causes earth's surface water flow occur, water flow flows into gutter 2, so that the water of earth's surface be avoided to flow into base Hole is internal.
Drainage pad layer 7 and drainpipe 8 are used to that the water below bottom of foundation ditch in soil to be discharged, and prevent concrete layer 9 from seeping water.
After water around foundation pit construction region in soil layer penetrates into dewatering well 6, flow downward along dewatering well 6, to reduce Water content in soil.Specifically, the internal diameter of each dewatering well 6 be greater than or equal to 600mm, adjacent two dewatering wells, 6 center away from It is located at below bottom of foundation ditch at 6m from the bottom less than or equal to 25m, dewatering well 6 hereinafter, guaranteeing preferable dewatering effect.Precipitation Chimney filter of the bottom setting length not less than 5m and length of well 6 are not less than the sediment tube of 1m.Dewatering well 6 is in Excavation Process In continue precipitation, the water surface in dewatering well 6 should be lower than Foundation Pit bottom absolute altitude 500mm or more.
The gradient of inclined slope 3 determines, it is preferred that inclined slope 3 of the present invention between 0.35 to 0.7 according to geological conditions The gradient is 0.5.

Claims (10)

1. dry dock foundation ditch construction method, which comprises the following steps:
A, cut-pff wall (1) is built except foundation pit construction region, cut-pff wall (1) surrounds foundation pit construction region, the bottom of cut-pff wall (1) Portion reaches impermeable stratum;
B, the drainage trenching (2) in the earth's surface except cut-pff wall (1);
C, multiple vertical dewatering wells (6) are dug between cut-pff wall (1) and foundation pit construction region;
D, the side slope of excavation of foundation pit, foundation pit is Slope with multi-step, and Slope with multi-step includes multiple inclined slopes (3), adjacent two inclined slope (3) It is connected by horizontal slope platform (4), the slope platform after often digging out a slope platform (4), in inclined slope (3) bottom (4) ponding ditch (5) are dug on;
E, drainage pad layer (7) are laid at Foundation Pit bottom, drainpipe (8) are installed in drainage pad layer (7), then in drainage pad The upper surface casting concrete layer (9) of layer (7).
2. dry dock foundation ditch construction method according to claim 1, which is characterized in that in step D, in each slope platform (4) on, a ponding well (10) is dug every 30m-40m, ponding ditch (5) is connected to ponding well (10);Lower layer's slope platform (4) Ponding well (10) depth is greater than ponding well (10) depth of upper layer slope platform (4).
3. dry dock foundation ditch construction method according to claim 2, which is characterized in that using plank to ponding well (10) The borehole wall is reinforced, and spreads metalling in the bottom of ponding well (10).
4. dry dock foundation ditch construction method according to claim 1, which is characterized in that in step D, in each ponding ditch (5) side wall and bottom applying mortar or laying plank.
5. dry dock foundation ditch construction method according to claim 1, which is characterized in that in step C, each dewatering well (6) Internal diameter be greater than or equal to 600mm, the distance at adjacent two dewatering well (6) center is less than or equal to 25m, the bottom of dewatering well (6) At 6m below bottom of foundation ditch under.
6. dry dock foundation ditch construction method according to claim 1, which is characterized in that in step D, in inclined slope (3) and Slope platform (4) upper berth steel wire and sandblasting slurry.
7. dry dock foundation ditch construction method according to claim 1, which is characterized in that in step D, using machinery dig to away from When bottom of foundation ditch absolute altitude 300mm, clear bottom is manually carried out, the sandy soil that clear bottom generates are transported by trolley.
8. dry dock foundation pit structure, which is characterized in that including gutter (2), cut-pff wall (1) and the base set gradually from outside to inside It cheats ontology (20), multiple vertical dewatering wells (6), the foundation pit is provided between the cut-pff wall (1) and foundation pit ontology (20) The side slope of ontology (20) includes multiple inclined slopes (3), is connected between adjacent two inclined slope (3) by horizontal slope platform (4), Ponding ditch (5) are provided on the slope platform (4) of inclined slope (3) bottom;The bottom of the foundation pit ontology (20) is equipped with Drainage pad layer (7) is provided with multiple drainpipes (8) in drainage pad layer (7), and the upper surface of drainage pad layer (7) is provided with Concrete layer (9).
9. dry dock foundation pit structure according to claim 8, which is characterized in that be provided on each slope platform (4) more A ponding well (10), the distance between adjacent two ponding well (10) are 30m-40m, and ponding ditch (5) is connected to ponding well (10);Under Ponding well (10) depth of layer slope platform (4) is greater than ponding well (10) depth of upper layer slope platform (4).
10. dry dock foundation pit structure according to claim 8, which is characterized in that the gradient of the inclined slope (3) is 0.5.
CN201910348638.7A 2019-04-28 2019-04-28 Dry dock foundation ditch construction method and dry dock foundation pit structure Pending CN110055972A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910348638.7A CN110055972A (en) 2019-04-28 2019-04-28 Dry dock foundation ditch construction method and dry dock foundation pit structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910348638.7A CN110055972A (en) 2019-04-28 2019-04-28 Dry dock foundation ditch construction method and dry dock foundation pit structure

Publications (1)

Publication Number Publication Date
CN110055972A true CN110055972A (en) 2019-07-26

Family

ID=67319454

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910348638.7A Pending CN110055972A (en) 2019-04-28 2019-04-28 Dry dock foundation ditch construction method and dry dock foundation pit structure

Country Status (1)

Country Link
CN (1) CN110055972A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110685292A (en) * 2019-09-25 2020-01-14 广东乾兴建设工程有限公司 Foundation pit drainage system and construction method thereof
CN111364466A (en) * 2020-03-20 2020-07-03 中交第三航务工程局有限公司 Construction method of dry dock bottom plate
CN112627311A (en) * 2020-12-11 2021-04-09 上海宝冶集团有限公司 Drainage method for building construction in mountainous region with large precipitation
CN113106926A (en) * 2021-05-12 2021-07-13 中国二十二冶集团有限公司 Construction method for foundation backfill of blown-fill sand reclamation foundation in coastal region

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207143981U (en) * 2017-08-01 2018-03-27 中铁第一勘察设计院集团有限公司 3rd is rich water half diagenesis Sandstone Section Metro station excavation discharge structure
CN109113076A (en) * 2018-10-12 2019-01-01 中国电建集团贵阳勘测设计研究院有限公司 A kind of sinking tunnel Support of Foundation Pit Excavation near a river and drop water-stopping method and its structure
CN210031827U (en) * 2019-04-28 2020-02-07 中国电建集团山东电力建设有限公司 Dry dock foundation pit structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207143981U (en) * 2017-08-01 2018-03-27 中铁第一勘察设计院集团有限公司 3rd is rich water half diagenesis Sandstone Section Metro station excavation discharge structure
CN109113076A (en) * 2018-10-12 2019-01-01 中国电建集团贵阳勘测设计研究院有限公司 A kind of sinking tunnel Support of Foundation Pit Excavation near a river and drop water-stopping method and its structure
CN210031827U (en) * 2019-04-28 2020-02-07 中国电建集团山东电力建设有限公司 Dry dock foundation pit structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张斌梁: "海河沉管隧道干坞关键施工技术", 铁道建筑技术, no. 4, pages 32 - 35 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110685292A (en) * 2019-09-25 2020-01-14 广东乾兴建设工程有限公司 Foundation pit drainage system and construction method thereof
CN111364466A (en) * 2020-03-20 2020-07-03 中交第三航务工程局有限公司 Construction method of dry dock bottom plate
CN111364466B (en) * 2020-03-20 2021-12-14 中交第三航务工程局有限公司 Construction method of dry dock bottom plate
CN112627311A (en) * 2020-12-11 2021-04-09 上海宝冶集团有限公司 Drainage method for building construction in mountainous region with large precipitation
CN113106926A (en) * 2021-05-12 2021-07-13 中国二十二冶集团有限公司 Construction method for foundation backfill of blown-fill sand reclamation foundation in coastal region

Similar Documents

Publication Publication Date Title
CN110055972A (en) Dry dock foundation ditch construction method and dry dock foundation pit structure
CN101705691B (en) Construction method of dewatering well under foundation slab in foundation pit
CN100464055C (en) Construction method of shallow buried underground excavating tunnel super large section using PBA method
CN107700511A (en) Open caisson and its construction method under the conditions of a kind of phreatic high
CN104131575A (en) Plugging and drainage method for dam foundation on karst highly developed stratum
CN113463670A (en) Water pumping and draining method and water pumping and draining structure for deep foundation pit bottom plate construction
CN106087953A (en) A kind of drainage and construction method preventing and treating large-scale spoil ground, mountain area mud-rock flow
KR101256265B1 (en) Construction method of the pier without the temporary dike
CN104314092A (en) Open caisson construction method based on substitution method
CN113957913A (en) Construction method of film bag sand filling combined steel sheet pile cofferdam
CN105714748A (en) Excavating construction method for surge shaft in gravel and sandy soil layer
CN110093971A (en) The Combined water pump house and its construction method of subterranean tunnel
CN111411639B (en) Shallow foundation pit dewatering construction method for water-rich pebble layer
CN1063518C (en) Drainage cut-off (deep ditch high-building method) drainage and supplying optimization combination for preventing and harnessing groud water
CN105155421B (en) Complete embedding circular construction method in a kind of single pile Single column pier river course shallow water
CN109024711B (en) Underground structure anti-floating system and construction method thereof
CN210031827U (en) Dry dock foundation pit structure
CN207143965U (en) Steel plate concrete combined type anti-floating water sealing structure
CN207003458U (en) Foundation ditch publicly price-reduction water system in a kind of basic engineering construction
CN110185051A (en) Deep narrow excavation water discharge method
CN108277815A (en) The cofferdam structure and its construction method constructed for water intaking header structure in river
CN204435321U (en) A kind of steam power station water intaking open channel
CN108867542A (en) A kind of tailings recycling water desilting system and its dredging method
CN216551791U (en) Riprap reinforcing structure for shield tunnel to pass through lake or river
CN217231641U (en) Marine structure for climbing submarine cable on rock coast

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination