CN112593693A - Overhanging type external scaffold convenient for repairing wall and construction method thereof - Google Patents

Overhanging type external scaffold convenient for repairing wall and construction method thereof Download PDF

Info

Publication number
CN112593693A
CN112593693A CN202011411271.8A CN202011411271A CN112593693A CN 112593693 A CN112593693 A CN 112593693A CN 202011411271 A CN202011411271 A CN 202011411271A CN 112593693 A CN112593693 A CN 112593693A
Authority
CN
China
Prior art keywords
wall
mounting piece
square column
building
connecting rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011411271.8A
Other languages
Chinese (zh)
Other versions
CN112593693B (en
Inventor
朱建伟
何永富
潘圣洁
洪蕾
陈杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Tiande Construction Engineering Co ltd
Original Assignee
Jiangsu Tiande Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Tiande Construction Engineering Co ltd filed Critical Jiangsu Tiande Construction Engineering Co ltd
Priority to CN202011411271.8A priority Critical patent/CN112593693B/en
Publication of CN112593693A publication Critical patent/CN112593693A/en
Application granted granted Critical
Publication of CN112593693B publication Critical patent/CN112593693B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/20Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/001Safety or protective measures against falling down relating to scaffoldings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/046Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)

Abstract

The application relates to an overhanging type external scaffold convenient for repairing a wall body and a construction method thereof, which relate to the technical field of building construction and comprise a frame body and a plurality of wall connecting pieces, wherein the wall connecting pieces are arranged at an external wall needing to be overhung of a building and comprise a first mounting piece, a second mounting piece and a third mounting piece, the first mounting piece is vertical to the external wall and is pre-embedded in the external wall, and two ends of the first mounting piece are correspondingly leveled with two side walls in the thickness direction of the external wall; the second mounting piece penetrates through the first mounting piece and is connected with the first mounting piece in a sealing mode, and one end of the second mounting piece extends out of the outer side of the building outer wall; one end of the third mounting piece is sleeved on one side of the second mounting piece extending out of the outer wall and is detachably connected with the second mounting piece; the frame body is correspondingly erected on the third installation part on the same layer. This application has the repair degree of difficulty lower to be convenient for reduce the effect of the work load of outer wall body repair.

Description

Overhanging type external scaffold convenient for repairing wall and construction method thereof
Technical Field
The application relates to the field of building construction, in particular to an overhanging type outer scaffold convenient for repairing a wall body and a construction method thereof.
Background
At present in the building engineering field, for making things convenient for workman's operation construction and guarantee workman's personal safety, can set up the scaffold frame in the building periphery usually, the high-rise building field can set up overhanging type outer scaffold frame.
In the overhanging type external scaffold in the related art, a riveting ring is embedded in an overhanging layer, then I-shaped steel is installed, one end of the I-shaped steel is fixed with a building through the riveting ring, the other end of the I-shaped steel extends out of the building, and finally, the external scaffold is erected on the I-shaped steel at the extending end. In order to stabilize the outer scaffolding, the outer scaffolding should be securely connected to the building structure. One of the connection methods in the related art is to embed a steel pipe fastener, usually a steel sleeve, in advance when the concrete is poured into the upper structure of the building, the steel sleeve is perpendicular to the wall surface and is away from the top of the wall by a certain distance, and when the scaffold is built, the wall connecting rod penetrates through the steel sleeve and is vertically fixed relative to the wall surface by using the fixing frames on two sides of the wall respectively. During construction, the steel sleeve cannot protrude out of the wall surface, and the top of the steel sleeve is more than the wall surface.
In view of the above-mentioned related technologies, the inventor thinks that after the scaffold and the i-steel are removed, the opening left on the outer wall by the steel sleeve and the i-steel needs to be filled to repair the wall surface so as to complete the wall body, but because the opening left on the outer wall by the steel sleeve and the i-steel is straight-through, the repair difficulty is high, and thus the workload of repairing the wall body is high.
Disclosure of Invention
The application provides a cantilever type outer scaffold convenient to wall body is repaired and construction method thereof in order to improve that steel casing and I-steel are the through type at the entrance to a cave that leaves on the outer wall, and the repair degree of difficulty is great to lead to the great problem of work load of wall body repair easily.
On the one hand, the utility model provides an outer scaffold frame of overhanging type convenient to wall body is repaired adopts following technical scheme:
an overhanging type external scaffold convenient for repairing a wall body comprises a frame body and a plurality of wall connecting pieces, wherein the wall connecting pieces are arranged at an outer wall of a building needing to be overhung, the wall connecting pieces located on the same floor are arranged in parallel and at the same height, and the wall connecting pieces located at the upper position and the lower position are correspondingly arranged;
the wall connecting piece comprises a first mounting piece, a second mounting piece and a third mounting piece, the first mounting piece is vertical to the outer wall and is pre-embedded in the outer wall, and two ends of the first mounting piece are correspondingly flush with two side walls in the thickness direction of the outer wall;
the second mounting piece penetrates through the first mounting piece and is connected with the first mounting piece in a sealing mode, one end, facing the inner wall of the outer wall, of the second mounting piece is embedded in the outer wall of the building, and the other end of the second mounting piece extends out of the outer side of the outer wall of the building;
one end of the third mounting piece is sleeved on one side, extending out of the outer wall, of the second mounting piece and is detachably connected with the second mounting piece, and the other end of the third mounting piece is far away from the outer wall;
the frame body is correspondingly erected on the third installation part on the same layer.
Through adopting above-mentioned technical scheme, can prefabricate wall spare and support body in advance, the length of support body needs to satisfy and can erect at least on the adjacent wall spare that links of same floor. The first installation part is used for protecting the outer wall, and abrasion to the outer wall when the second installation part is installed is reduced. The third support body is used for prolonging second installed part and object supporting support body. After support body, third installed part are demolishd, can saw the one side that the second installed part stretches out the outer wall, because the second installed part insert locate in the first installed part and with first installed part sealing connection, through-hole and waterproof performance that can the shutoff first installed part leave through the second installed part are better, only need paint the interior outer wall department of outer wall through cement mortar this moment, the outer wall can be repaired completely at shutoff first installed part and second installed part both ends. The method has the effect of reducing the workload of wall body repair due to lower repair difficulty.
Optionally, the first mounting part comprises a connecting sleeve and a first flaring part located at one end of the connecting sleeve, the first flaring part is located at the inner side of the outer wall, and the large end of the first flaring part is flush with the inner wall of the outer wall; the second mounting piece comprises a second flaring piece and a connecting rod connected with the second flaring piece, the second flaring piece is a solid piece, and the second flaring piece is embedded in the first flaring piece and blocks the first flaring piece; the connecting rod is arranged in the connecting sleeve in a penetrating mode, the peripheral wall of the connecting rod is connected with a sealing layer, and the sealing layer is connected with the connecting sleeve in a sealing mode.
Through adopting above-mentioned technical scheme, second flaring spare and first flaring spare cooperation can reduce the connecting rod and break away from the hidden danger of outer wall when exerting the pulling force to the connecting rod in the outer side of outer wall. The connecting rod is connected with the connecting sleeve in a sealing manner, so that the waterproof performance between the connecting rod and the connecting sleeve is convenient to promote.
Optionally, the sealing layer adopts a water-swelling water stop member.
Through adopting above-mentioned technical scheme, when the outer wall infiltration, meet water inflation stagnant water spare and meet water inflation for be connected between connecting rod and the adapter sleeve inseparabler, promote the holistic leakproofness of outer wall body, also can delay or avoid the condition of outer wall infiltration.
Optionally, the connecting rod is in threaded connection with the connecting sleeve, the sealing layer is made of a sealing glue, and the sealing glue is coated on the peripheral wall of the connecting rod.
Through adopting above-mentioned technical scheme, reinforcing connecting rod that connecting rod and connecting sleeve threaded connection can be better and connecting sleeve's joint strength reduces the risk that the connecting rod breaks away from the outer wall.
Optionally, the third mounting part is a square column, and one side of the square column facing the outer wall is sleeved on the circumferential direction of the connecting rod and is in threaded connection with the connecting rod; a plane on one side of the square column faces the ground; one side of the square column, which is far away from the frame body, is connected with a fourth mounting piece which is arranged in parallel with the outer wall; the fourth installation part comprises a screw rod, a threaded sleeve is connected to one side of the screw rod, facing the upper layer of square column, in a threaded mode, and the screw rod located at the upper position and the lower position is connected through threads of the threaded sleeve.
Through adopting above-mentioned technical scheme, the third installed part adopts the square column, can be convenient for better erect the support body, promote the stationarity of support body installation. The fourth installed part is used for connecting the square column that is located position from top to bottom, because construction worker is the successive layer and is under construction to the outer wall under the most of the circumstances when the construction, and less probably all stands constructor on every layer of support body, so when standing on the one deck support body and having personnel, the square column that is located position from top to bottom can be through the common atress of connection of fourth installed part. The fourth installation part can be conveniently connected and installed at the upper position and the lower position by combining a screw rod and a threaded sleeve.
Optionally, an inclined strut is arranged on the square column at the bottommost layer, and one side, far away from the square column, of the inclined strut is connected with the outer wall of the next floor.
Through adopting above-mentioned technical scheme, the diagonal brace is used for the whole outer scaffold of auxiliary stay, and diagonal brace, square column and outer wall form the triangle structure, and the support of outer scaffold is comparatively stable.
Optionally, one side that the outer wall was kept away from to the support body is provided with the safety net, the space between the support body that the safety net sealed the position about being located.
Through adopting above-mentioned technical scheme, the safety net is used for sealing the support body and keeps away from one side of outer wall, reduces the unexpected risk that falls from the support body of constructor.
On the other hand, the construction method provided by the application adopts the following technical scheme:
a construction method comprises the following steps:
the method comprises the following steps: embedding a first installation part in the building outer wall of a floor where a scaffold is required to be erected, installing a second installation part in the first installation part, and installing a third installation part on one side of the second installation part, which extends out of the outer wall;
step two: mounting a frame body, and mounting a fourth mounting piece on one side of the third mounting piece, which is far away from the outer wall, through the frame body;
step three: hanging a safety net;
step four: installing diagonal braces at the square columns at the bottommost layer;
step five: checking and accepting;
step six: detecting and maintaining in the using process;
step seven: sequentially removing the safety net, the fourth installation piece, the frame body and the third installation piece of each floor, and then cutting off the connecting rod extending out of the outer wall along the outer side surface of the outer wall of the building;
step eight: repairing the inner and outer sides of the outer wall.
Through adopting above-mentioned technical scheme, can comparatively convenient carry out the shutoff to the outer wall after demolising outer scaffold, and can reduce the injury that waterproof nature that the installation outer scaffold led to the fact the outer wall caused.
In summary, the present application includes at least one of the following beneficial technical effects:
1. through the arrangement of the frame body, the first mounting piece, the second mounting piece and the third mounting piece, the repairing difficulty of the outer wall can be reduced, so that the effect of reducing the workload of wall repairing is facilitated;
2. through the arrangement of the fourth mounting part, the effect that square columns located at the upper and lower positions can be stressed and dispersed together can be achieved;
3. through the setting of diagonal brace, can play comparatively stable auxiliary stay outer scaffolding, be convenient for promote the effect of outer scaffolding's security.
Drawings
Fig. 1 is a schematic view of a connection structure of an overhanging type external scaffold and an external wall according to an embodiment of the present application.
Fig. 2 is a partially enlarged schematic view of a portion a in fig. 1.
Description of reference numerals: 1. a frame body; 2. a wall connecting piece; 3. a first mounting member; 31. a connecting sleeve; 32. a first flared member; 4. a second mount; 41. a second flared member; 411. an inner hexagonal groove; 42. a connecting rod; 5. a third mount; 51. a square column; 6. a fourth mount; 61. a screw; 62. a threaded sleeve; 63. locking the nut; 7. a diagonal brace; 8. a safety net; 9. and (5) an outer wall.
Detailed Description
The present application is described in further detail below with reference to figures 1-2.
The embodiment of the application discloses outer scaffold frame of overhanging type convenient to wall body is repaired. Referring to fig. 1, the overhanging type external scaffold convenient for repairing the wall comprises a scaffold body 1 and a plurality of wall connecting pieces 2, wherein the wall connecting pieces 2 are installed at an outer wall 9 needing to be overhung of a building, the wall connecting pieces 2 located on the same floor are arranged in parallel and at the same height, and the wall connecting pieces 2 located at the upper position and the lower position are correspondingly arranged. The support body 1 corresponds the setting and is located the outside of building outer wall 9 with the floor, and support body 1 is installed on the wall spare 2 that links at each layer. Support body 1 through even wall spare 2, constructor stands and constructs to outer wall 9 on support body 1.
Referring to fig. 1 and 2, the wall connecting member 2 includes a first mounting member 3, a second mounting member 4, a third mounting member 5, and a fourth mounting member 6. Wherein, first installed part 3 is pre-buried in the outer wall 9 of each floor, and is located the first installed part 3 of the same floor and is located same height and parallel to each other. Including first flaring spare 32 and the connecting sleeve 31 that is connected, first flaring spare 32 adopts conical sleeve, and first flaring spare 32 is connected with connecting sleeve 31 with the coaxial setting of connecting sleeve 31 and the tip of first flaring spare 32, and the main aspects flushes with the inner wall of outer wall 9, and one side that first flaring spare 32 was kept away from to connecting sleeve 31 flushes with the outer wall of outer wall 9.
Referring to fig. 1 and 2, the second mounting member 4 comprises a second flaring member 41 and a connecting rod 42 which are connected, the second flaring member 41 is a conical solid member, and the second flaring member 41 is embedded in the first flaring member 32 and is arranged to close off the first flaring member 32. To facilitate the application of the interior of the outer wall 9 when the outer scaffolding is to be removed, the large end of the second flaring 41 is spaced from the large end of the first flaring 32 by a distance of about 1 cm. The connecting rod 42 is arranged in the connecting sleeve 31 in a penetrating manner, and one side of the connecting rod 42, which is far away from the second flaring piece 41, extends out of the outer wall 9. The outer wall of the connecting rod 42 is coated with a sealing layer which can be a water-swelling water stop belt and can also be coated with sealant, so that the connecting rod 42 and the connecting sleeve 31 can be connected in a sealing mode. In this embodiment, the periphery of the connecting rod 42 is coated with a sealant, and the connecting rod 42 is in threaded connection with the connecting sleeve 31, so that the connection stability between the connecting sleeve 31 and the connecting rod 42 is improved. In order to facilitate the second flaring component 41 to be embedded into the first flaring component 32, an inner hexagonal groove 411 is formed in one side, away from the connecting rod 42, of the second flaring component 41, so that the second mounting component 4 of the ginger can be screwed into the first mounting component 3 by using an inner hexagonal wrench.
Referring to fig. 1, the third mounting member 5 may be a square column 51, the square column 51 is located outside the outer wall 9, one end of the square column 51 is connected with the connecting rod 42 by screw threads, and the other end extends towards the side far away from the outer wall 9. When the square column 51 is installed at the connection rod 42, one side of the square column 51 is disposed toward the ground. The frame body 1 can be erected on the square column 51 of the same layer and is fixed through bolts. The frame body 1 can be welded into a whole by adopting a plurality of criss-cross steel pipes.
Referring to fig. 1, the fourth mounting member 6 employs a screw 61, a threaded sleeve 62 and a locking bolt, the screw 61 is located on the side of the square column 51 away from the outer wall 9, and the screw 61 is perpendicular to the square column 51 and penetrates through the square column 51. The locking nut 63 is screwed with the screw 61 and is located on the side of the square column 51 facing the ground and away from the ground to fix the position of the screw 61 on the square column 51. The screw sleeve 62 is in threaded connection with one side of the screw 61 far away from the ground, and the screw 61 at the upper and lower positions is connected into a whole through the screw sleeve 62.
Referring to fig. 1, a safety net 8 is provided at one side of the frame body 1, which is far from the outer wall 9, and the safety net 8 seals a space between the frame bodies 1 at upper and lower positions. Stand and to install fourth installed part 6 on support body 1 after, can open between the support body 1 that is located the upper and lower position and hang safety net 8 to promote the security of outer scaffold, reduce the unexpected hidden danger that drops of constructor.
Referring to fig. 1, a diagonal brace 7 is provided on the square pillar 51 located at the lowermost layer, one end of the diagonal brace 7 is welded to a lock nut 63 below the square pillar 51, and the other end abuts against the wall surface of the outer wall 9 below the square pillar 51. The diagonal brace 7 can form a triangular support structure with the wall surface and the square column 51, and can assist in supporting the outer scaffold and reducing the offset of the outer scaffold when being stressed.
The implementation principle of the overhanging type outer scaffold convenient for repairing the wall body is as follows: before construction, stress analysis is carried out, and whether the pre-point meets the construction parameters is determined according to a calculation result. And (3) strictly auditing a building construction drawing and a structure construction drawing before the concrete of the main structure of the building is poured, and carrying out electronic layout arrangement on the embedded points and reasonably optimizing. After the pre-embedding position is determined, the first installation part 3 is installed on a steel bar mesh of the building, and the steel bar mesh is poured to enable the first installation part 3 to be pre-embedded in an outer wall 9 of the building.
Subsequently, a sealant is applied to the outer periphery of the connecting rod 42 at a portion to be connected to the connecting sleeve 31, and the second mounting element 4 is screwed into the first mounting element 3 by a socket wrench after the sealant is solidified. Next, a square column 51 is installed at one end of the connecting rod 42 away from the outer wall 9, and when the square column 51 is close to the outer wall of the outer wall 9 as much as possible, the direction of the square column 51 is adjusted so that one side of the square column 51 faces the ground and is parallel to the ground.
Next, the frame body 1 is placed on the square column 51, and the frame body 1 is supported by the square column 51 and the frame body 1 is fixed to the square column 51 by bolts. The constructor can then stand on the just erected frame 1 with the safety line tied up to install the fourth installation element 6. Firstly, a locking bolt is screwed off, a screw 61 is vertically inserted into a hole reserved on the square column 51 which is positioned on the same layer as the frame body 1, then the locking bolt is screwed on the screw 61 on one side of the square column 51 facing the ground, and a locking nut 63 positioned at the upper position and the lower position of the square column 51 on the screw 61 is abutted towards the square column 51 after the position of the screw 61 is adjusted. And then, after all the screws 61 are installed, the threaded sleeves 62 on the screws 61 are in threaded connection with the nearest screws 61 above the threaded sleeves 62, so that the screws 61 positioned at the upper and lower positions are connected into a whole, and the whole external scaffold is further formed into a whole.
And finally, a safety net 8 can be hung on one side of the frame body 1 far away from the outer wall 9, and an inclined stay bar 7 is installed below the bottommost square column 51 to assist in improving the safety of the outer scaffold. When the external scaffold is dismantled, after the overhanging scaffold is dismantled, the part of the connecting rod 42 extending out of the external wall 9 is cut off along the wall surface of the external wall 9 of the building by adopting oxyacetylene, and after the cutting is finished, the two sides of the external wall 9 are repaired by adopting cement mortar.
Compared with the traditional construction technology of the cantilever scaffold, the embedded first installation part 3 of the embodiment has small influence on masonry construction, and the first installation part 3 is matched with the second installation part 4, so that the potential safety hazard that the wall connecting rod is detached by leakage hidden danger caused by hole reservation and worker construction during masonry is reduced, the influence on a building structure is small, and the difficulty and the workload of repairing the outer wall 9 are reduced conveniently.
The embodiment of the application also discloses a construction method, which comprises the following steps with reference to fig. 1:
the method comprises the following steps: pre-buried first installed part 3 in the building outer wall 9 of the floor department of scaffold frame needs to be set up, second installed part 4 is installed in first installed part 3, stretches out one side installation third installed part 5 of outer wall 9 at second installed part 4.
Step two: the frame body 1 is installed, and the fourth installation part 6 is installed on one side of the third installation part 5 far away from the outer wall 9 through the frame body 1.
Step three: a safety net 8 is hung.
Step four: installing a diagonal brace 7 at the square column 51 at the bottommost layer;
step five: and (6) checking and accepting.
Step six: and detecting and maintaining in the using process. After the external scaffold is erected, the external scaffold can be put into use after being qualified by inspection and acceptance, and the external scaffold is required to be frequently inspected and maintained in the using process; checking whether the external scaffold is overloaded for use or not and whether concentrated load conditions exist or not; the outer scaffold can only be used as an operation frame and cannot be used as a template support frame; and checking whether the bolt at the joint is loosened and the nut is lost.
Step seven: and (3) dismantling the safety net 8, the fourth installation part 6, the frame body 1 and the third installation part 5 of each floor in sequence, and then cutting off a connecting rod 42 extending out of the outer wall 9 along the outer side surface of the outer wall 9 of the building by adopting oxyacetylene.
Step eight: and adopting cement mortar to repair and repair the inner side and the outer side of the outer wall 9.
The preferred embodiments of the present application do not limit the scope of the present application, and therefore: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides an outer scaffold frame of overhanging type convenient to wall body is repaired which characterized in that: the building wall connecting piece comprises a frame body (1) and a plurality of wall connecting pieces (2), wherein the wall connecting pieces (2) are arranged at an outer wall (9) needing to be cantilevered of a building, the wall connecting pieces (2) positioned on the same floor are arranged in parallel and at the same height, and the wall connecting pieces (2) positioned at the upper position and the lower position are correspondingly arranged;
the wall connecting piece (2) comprises a first mounting piece (3), a second mounting piece (4) and a third mounting piece (5), the first mounting piece (3) is perpendicular to the outer wall (9) and is embedded in the outer wall (9), and two ends of the first mounting piece (3) are correspondingly flush with two side walls in the thickness direction of the outer wall (9);
the second mounting piece (4) penetrates through the first mounting piece (3) and is connected with the first mounting piece (3) in a sealing mode, one end, facing the inner wall of the outer wall (9), of the second mounting piece (4) is embedded in the outer wall (9) of the building, and the other end of the second mounting piece extends out of the outer side of the outer wall (9) of the building;
one end of the third mounting piece (5) is sleeved on one side, extending out of the outer wall (9), of the second mounting piece (4) and is detachably connected with the second mounting piece (4), and the other end of the third mounting piece (5) is far away from the outer wall (9);
the frame body (1) is correspondingly erected on the third installation part (5) on the same layer.
2. The overhanging type external scaffold convenient for wall repair of claim 1, wherein: the first mounting part (3) comprises a connecting sleeve (31) and a first flaring part (32) positioned at one end of the connecting sleeve (31), the first flaring part (32) is positioned at the inner side of the outer wall (9), and the large end of the first flaring part (32) is arranged flush with the inner wall of the outer wall (9); the second mounting part (4) comprises a second flaring part (41) and a connecting rod (42) connected with the second flaring part (41), the second flaring part (41) is a solid part, and the second flaring part (41) is embedded in the first flaring part (32) and is used for plugging the first flaring part (32); the connecting rod (42) penetrates through the connecting sleeve (31), the peripheral wall of the connecting rod (42) is connected with a sealing layer, and the sealing layer is connected with the connecting sleeve (31) in a sealing mode.
3. The overhanging type external scaffold convenient for wall repair of claim 2, wherein: the sealing layer adopts a water-swelling water stop piece.
4. The overhanging type external scaffold convenient for wall repair of claim 2, wherein: the connecting rod (42) is in threaded connection with the connecting sleeve (31), the sealing layer is made of sealing glue, and the sealing glue is coated on the peripheral wall of the connecting rod (42).
5. The overhanging type external scaffold convenient for wall repair of claim 4, wherein: the third mounting piece (5) adopts a square column (51), and one side, facing the outer wall (9), of the square column (51) is sleeved on the circumferential direction of the connecting rod (42) and is in threaded connection with the connecting rod (42); one side plane of the square column (51) faces the ground; one side of the square column (51) far away from the frame body (1) is connected with a fourth mounting piece (6) which is arranged in parallel with the outer wall (9); the fourth installation part (6) comprises a screw rod (61), one side, facing the upper layer of square column (51), of the screw rod (61) is connected with a threaded sleeve (62) in a threaded mode, and the screw rod (61) located at the upper position and the lower position are connected in a threaded mode through the threaded sleeve (62).
6. The overhanging type external scaffold convenient for wall repair of claim 5, wherein: an inclined strut (7) is arranged on the square column (51) at the bottommost layer, and one side, far away from the square column (51), of the inclined strut (7) is connected with the outer wall (9) of the next floor.
7. The overhanging type external scaffold convenient for wall repair of claim 5, wherein: one side of the frame body (1) far away from the outer wall (9) is provided with a safety net (8), and the safety net (8) seals the space between the frame bodies (1) which are located at the upper position and the lower position.
8. A construction method is characterized in that: the method comprises the following steps:
the method comprises the following steps: embedding a first installation part (3) in an outer wall (9) of a building at a floor where a scaffold is required to be erected, installing a second installation part (4) in the first installation part (3), and installing a third installation part (5) on one side, extending out of the outer wall (9), of the second installation part (4);
step two: the frame body (1) is installed, and a fourth installation part (6) is installed on one side, far away from the outer wall (9), of the third installation part (5) through the frame body (1);
step three: a safety net (8) is hung;
step four: a diagonal brace (7) is arranged at the square column (51) at the bottommost layer;
step five: checking and accepting;
step six: detecting and maintaining in the using process;
step seven: sequentially dismantling the safety net (8), the fourth installation part (6), the frame body (1) and the third installation part (5) of each floor, and then cutting off a connecting rod (42) extending out of the outer wall (9) along the outer side surface of the outer wall (9) of the building;
step eight: the inner and outer sides of the outer wall (9) are repaired.
CN202011411271.8A 2020-12-04 2020-12-04 Overhanging type external scaffold convenient for repairing wall and construction method thereof Active CN112593693B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011411271.8A CN112593693B (en) 2020-12-04 2020-12-04 Overhanging type external scaffold convenient for repairing wall and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011411271.8A CN112593693B (en) 2020-12-04 2020-12-04 Overhanging type external scaffold convenient for repairing wall and construction method thereof

Publications (2)

Publication Number Publication Date
CN112593693A true CN112593693A (en) 2021-04-02
CN112593693B CN112593693B (en) 2022-01-14

Family

ID=75188388

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011411271.8A Active CN112593693B (en) 2020-12-04 2020-12-04 Overhanging type external scaffold convenient for repairing wall and construction method thereof

Country Status (1)

Country Link
CN (1) CN112593693B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB191127586A (en) * 1911-12-08 1912-10-10 Emil Schaerer Improvements in Scaffolding for Buildings.
CN109779225A (en) * 2019-03-13 2019-05-21 中国十七冶集团有限公司 A kind of change overhanging type external scaffold and construction method
CN110952763A (en) * 2019-11-21 2020-04-03 成都建工第二建筑工程有限公司 Construction method of externally-hung type externally-hung overhanging scaffold
CN211341679U (en) * 2019-08-21 2020-08-25 中国十七冶集团有限公司 Cantilever scaffold puts up wall bolt pre-buried device
CN211949549U (en) * 2020-03-11 2020-11-17 浙江工业职业技术学院 Building scaffold wall connecting component

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB191127586A (en) * 1911-12-08 1912-10-10 Emil Schaerer Improvements in Scaffolding for Buildings.
CN109779225A (en) * 2019-03-13 2019-05-21 中国十七冶集团有限公司 A kind of change overhanging type external scaffold and construction method
CN211341679U (en) * 2019-08-21 2020-08-25 中国十七冶集团有限公司 Cantilever scaffold puts up wall bolt pre-buried device
CN110952763A (en) * 2019-11-21 2020-04-03 成都建工第二建筑工程有限公司 Construction method of externally-hung type externally-hung overhanging scaffold
CN211949549U (en) * 2020-03-11 2020-11-17 浙江工业职业技术学院 Building scaffold wall connecting component

Also Published As

Publication number Publication date
CN112593693B (en) 2022-01-14

Similar Documents

Publication Publication Date Title
CN110805257B (en) Flower basket overhanging type section steel bearing beam structure and construction method
CN204098463U (en) Builder's jack
CN109779225A (en) A kind of change overhanging type external scaffold and construction method
CN103206089A (en) Fabricated aluminum alloy formwork system construction method
CN205400024U (en) Instrument formula external scaffolding bolt that can dismantle used repeatedly links wall spare
CN211622528U (en) Basket type outer vertical surface scaffold inclined-pulling type I-steel cantilever beam
CN111236604A (en) Safe construction method for cantilever platform on cylinder main body structure
CN112144854A (en) Anchor pulling type section steel overhanging support operation scaffold combined system and construction method
CN113605771B (en) Prestress assembly type frame structure system
CN109457965B (en) High-efficiency installation method and device of precast concrete wall panel
CN110821156A (en) Sinking type toilet hanging die structure and construction method thereof
CN212613769U (en) Outer wall formwork reinforcing bracket at connecting position of shear wall floors
CN111997352A (en) Rapid installation method for scaffold wall connecting piece
CN203531365U (en) Bolt anchor stiffness wall connecting piece
CN114673336A (en) Novel detachable embedded bolt type cantilever frame construction method
CN112593693B (en) Overhanging type external scaffold convenient for repairing wall and construction method thereof
CN107268978B (en) The fixed device of towering structure constructor's row ladder sustaining wall and construction method
CN212613640U (en) Improved generation building scaffold frame of encorbelmenting
CN210217085U (en) Building large hole safety sealing construction platform
CN113323359A (en) Novel flower basket pull rod tool type overhanging frame construction method
CN111851987A (en) Construction method of attached short-limb I-steel flower basket pull rod knot type cantilever frame
CN104989092B (en) A kind of construction method of high-altitude overhanging superposed type steel truss bearing platform
CN110821147A (en) Expansion joint shear wall combination template capable of being assembled and disassembled quickly
CN213597442U (en) Elevator shaft template operation platform that encorbelments
CN108868107A (en) A kind of pre-buried wall attaching parts of postposition and its erection construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant