CN112538856A - Deep basal pit concrete placement chute - Google Patents

Deep basal pit concrete placement chute Download PDF

Info

Publication number
CN112538856A
CN112538856A CN202011402784.2A CN202011402784A CN112538856A CN 112538856 A CN112538856 A CN 112538856A CN 202011402784 A CN202011402784 A CN 202011402784A CN 112538856 A CN112538856 A CN 112538856A
Authority
CN
China
Prior art keywords
chute
channel
section steel
level
concrete pouring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011402784.2A
Other languages
Chinese (zh)
Inventor
王春冉
杜治衡
姜浩
谢连仲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 5 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
No 5 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 5 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical No 5 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority to CN202011402784.2A priority Critical patent/CN112538856A/en
Publication of CN112538856A publication Critical patent/CN112538856A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/04Devices for both conveying and distributing
    • E04G21/0481Concrete chutes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Mechanical Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a concrete pouring chute for a deep foundation pit, which comprises an enclosure structure steel sheet pile, a primary chute and a secondary chute; the first-level chute is connected with the enclosure structure steel sheet pile through the clamping ring, the first-level chute can rotate up and down along the joint of the clamping ring, the second-level chute is connected with the first-level chute through the rotating shaft assembly, and the second-level chute can rotate 360 degrees along the horizontal plane of the joint. The deep foundation pit concrete pouring chute disclosed by the invention is matched with a primary chute and a secondary chute which rotate in a grading manner, so that the continuous construction of concrete can be ensured, and the concrete pouring construction quality is ensured.

Description

Deep basal pit concrete placement chute
Technical Field
The invention relates to a concrete pouring chute for a deep foundation pit, and belongs to the field of concrete pouring.
Background
Conventional deep foundation pit concrete placement is mostly the pumping, mostly is day pump or ground pump. When the pumping equipment fails and cannot be repaired in time, the concrete pouring construction is interrupted, concrete cannot be poured continuously, and construction quality problems such as cold joints, faults and the like are easily caused.
Disclosure of Invention
Aiming at the problems in the prior art, the invention provides the deep foundation pit concrete pouring graded rotating chute, which ensures the continuous construction of concrete and the quality of concrete pouring construction.
In order to achieve the purpose, the deep foundation pit concrete pouring chute comprises an enclosure structure steel sheet pile, a first-stage chute and a second-stage chute;
the first-level chute is connected with the enclosure structure steel sheet pile through the clamping ring, the first-level chute can rotate up and down along the joint of the clamping ring, the second-level chute is connected with the first-level chute through the rotating shaft assembly, and the second-level chute can rotate 360 degrees along the horizontal plane of the joint.
Further, the rotating shaft assembly comprises an upper rotating shaft, an upper channel steel, a lower rotating shaft and a lower channel steel; go up the channel-section steel and install the bottom at the one-level chute, go up pivot horizontal installation and just can follow the axis rotation of last pivot in last channel-section steel, the one end vertical welding of pivot is on last pivot down, and the elliptical aperture that the other end passed last channel-section steel bottom is connected with lower channel-section steel, and gasket and nut are installed with the tip that lower channel-section steel is connected to lower pivot down, open at the both ends of channel-section steel down has the second grade chute connecting hole.
Furthermore, the upper channel steel is welded at the bottom of the first-stage chute.
Furthermore, the first-level chute is formed by processing section steel, and the second-level chute is of a wood structure.
Furthermore, the inclination angle of the first-stage chute is 27-36 degrees, and the inclination angle of the second-stage chute is 15-26 degrees.
Compared with the prior art, the deep foundation pit concrete pouring chute disclosed by the invention adopts the matching use of the primary chute and the secondary chute which rotate in a grading manner, so that the continuous construction of concrete can be ensured, and the concrete pouring construction quality is ensured.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural view of a joint of a primary chute and a secondary chute in the invention;
in the figure: 1. the concrete transportation vehicle comprises a crawler crane, 2, a concrete transportation vehicle, 3, an enclosure structure steel sheet pile, 4, a first-stage chute, 5, a second-stage chute, 6, an upper rotating shaft, 7, an upper channel steel, 8, a lower rotating shaft, 9, a nut, 10, a gasket, 11, a lower channel steel, 12 and a second-stage chute connecting hole.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below. It should be understood, however, that the description herein of specific embodiments is only intended to illustrate the invention and not to limit the scope of the invention.
Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs, and the terms used herein in the specification of the present invention are for the purpose of describing particular embodiments only and are not intended to limit the present invention.
As shown in fig. 1 and 2, the deep foundation pit concrete pouring chute comprises an enclosure structure steel sheet pile 3, a primary chute 4 and a secondary chute 5; the one-level chute 4 is connected with the enclosure structure steel sheet pile 3 through the snap ring, the one-level chute 4 can rotate from top to bottom along the snap ring joint, the second-level chute 5 is connected with the one-level chute 4 through the rotating shaft assembly, and the second-level chute 5 can rotate 360 degrees along the horizontal plane of the joint.
As a modification of the embodiment, the rotating shaft assembly comprises an upper rotating shaft 6, an upper channel steel 7, a lower rotating shaft 8 and a lower channel steel 11;
go up the bottom of channel-section steel 7 welding at one-level chute 4, go up 6 horizontal installation of pivot and can follow the axis rotation of last pivot 6 in last channel-section steel 7, the one end vertical welding of pivot 8 is on last pivot 6 down, and the elliptical aperture of the other end extension going up 7 bottoms of channel-section steel is connected with lower channel-section steel 11, and gasket 10 and nut 9 are installed to the tip that lower pivot 8 and lower channel-section steel 11 are connected, open at the both ends of channel-section steel 11 down has second grade chute connecting hole 12.
The invention uses section steel as a first-level chute 4 and a light wood structure as a second-level chute 5. The two-stage chute is connected through the rotating shaft component. Because second grade chute 5 adopts the wooden structure of lightweight, the manual work can be rotatory, and the convenience is better, and the work efficiency is higher.
When the chute is used, the first-stage chute 4 is lifted by the crawler crane 1 and is matched with the concrete transport vehicle 2 to transport concrete, the top end of the first-stage chute 4 is connected with the enclosure structure steel sheet pile 3 through a clamping ring to form hinged connection, and the first-stage chute 4 can be ensured to rotate up and down under the condition of ensuring safety and stability; the upper end of the second-stage chute 5 is connected with the lower end of the first-stage chute 4 through a rotating shaft assembly, and the second-stage chute 5 can rotate 360 degrees in the horizontal plane. The first-stage chute 4 is adjustable up and down, the second-stage chute 5 is adjustable in level, and the chute structure is graded and rotated, so that the coverage range of chute pouring is greatly enlarged.
The processing parameters of the chute need to be determined according to the width and the depth of the foundation pit, and the chute angle needs to be determined according to the slump, the workability and other performances of the concrete. The construction conditions and chute parameters which are successfully applied to the casting process of the concrete of the bottom plate of the river bottom of the Kanapu river under the project S1 segment EJD-6 in the great harbor of Bengal at present are as follows:
the depth of the foundation pit is 7.7m, and the horizontal maximum coverage range of the chute is 17.5 m. The concrete strength grade is C50P10, and the slump is 200 +/-20 mm. The length of the first-stage chute is 10m, the U750X 250 type steel sheet pile (when no available resource exists, the steel sheet pile is processed by section steel), and the chute angle is 27-36 degrees.
The length of the secondary chute is 6m, the batten and the multilayer board are nailed, and the use angle is 15-26 degrees. The efficiency of pouring concrete by the chute is about 40 m/h.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents or improvements made within the spirit and principle of the present invention should be included in the scope of the present invention.

Claims (5)

1. The deep foundation pit concrete pouring chute comprises an enclosure structure steel sheet pile (3), and is characterized by further comprising a first-stage chute (4) and a second-stage chute (5);
one-level chute (4) are connected with envelope steel sheet pile (3) through the snap ring, and one-level chute (4) can be followed the snap ring junction and rotated from top to bottom, second grade chute (5) are connected through pivot subassembly with one-level chute (4), and 360 rotations can be made along the junction horizontal plane in second grade chute (5).
2. The deep foundation pit concrete pouring chute according to claim 1, characterized in that the rotating shaft assembly comprises an upper rotating shaft (6), an upper channel (7), a lower rotating shaft (8) and a lower channel (11);
go up channel-section steel (7) and install the bottom at one-level chute (4), go up pivot (6) horizontal installation and can follow the axis rotation of last pivot (6) in last channel-section steel (7), the one end vertical welding of lower pivot (8) is on last pivot (6), and the elliptical hole that the other end passed last channel-section steel (7) bottom is connected with lower channel-section steel (11), and gasket (10) and nut (9) are installed to tip that lower pivot (8) and lower channel-section steel (11) are connected, open at the both ends of lower channel-section steel (11) has second grade chute connecting hole (12).
3. The deep foundation pit concrete pouring chute according to claim 2, characterized in that the upper channel (7) is welded to the bottom of the primary chute (4).
4. The deep foundation pit concrete pouring chute according to claim 1, characterized in that the primary chute (4) is formed by processing section steel, and the secondary chute (5) is of a wood structure.
5. The deep foundation pit concrete pouring chute according to claim 1, characterized in that the inclination angle of the primary chute (4) is 27-36 degrees and the inclination angle of the secondary chute (5) is 15-26 degrees.
CN202011402784.2A 2020-12-04 2020-12-04 Deep basal pit concrete placement chute Pending CN112538856A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011402784.2A CN112538856A (en) 2020-12-04 2020-12-04 Deep basal pit concrete placement chute

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011402784.2A CN112538856A (en) 2020-12-04 2020-12-04 Deep basal pit concrete placement chute

Publications (1)

Publication Number Publication Date
CN112538856A true CN112538856A (en) 2021-03-23

Family

ID=75015837

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011402784.2A Pending CN112538856A (en) 2020-12-04 2020-12-04 Deep basal pit concrete placement chute

Country Status (1)

Country Link
CN (1) CN112538856A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114059542A (en) * 2021-11-16 2022-02-18 中国建筑第七工程局有限公司 Unit assembled elephant trunk system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114059542A (en) * 2021-11-16 2022-02-18 中国建筑第七工程局有限公司 Unit assembled elephant trunk system
CN114059542B (en) * 2021-11-16 2023-05-26 中国建筑第七工程局有限公司 Unit assembled chute system

Similar Documents

Publication Publication Date Title
US8678455B2 (en) Lifting fitting
AU2004324827B2 (en) A tower part for a wind turbine, an aperture cover system, a method for manufacturing a tower part and uses hereof
CN106438212B (en) A kind of folding spelling formula tubbiness tower
US8782979B2 (en) Method and arrangement for attaching a tower-like structure to a foundation
EP2767654A1 (en) Flange assistant for connecting adjacent tower sections
US8607508B2 (en) Stayed connection for wind turbine
CN112538856A (en) Deep basal pit concrete placement chute
CN216195506U (en) Angle-adjustable beam-column bolt connection node
US8904738B2 (en) Wind turbine tower supporting structure
CN103216103A (en) Pre-deformation construction method for mounting oblique-arc-shaped combined steel-structured column of annular roof
CH715604B1 (en) Support structure system for an offshore wind turbine.
CN214401793U (en) Deep foundation pit concrete pouring chute
CN205346632U (en) Pipe truss lifting device
CN108383016A (en) Assembling steel construction tower crane platform and its construction method
CN211368353U (en) Steel trestle steel pipe pile concrete abutment
KR102045025B1 (en) Roundness Maintaining Device of Large Cylindrical Structure and Manufacturing Method Thereof
CN114233036B (en) Through type angle steel transmission tower reinforcing apparatus
CN110469130B (en) Pipe truss girder and pipe truss column flange plate mounting die and mounting method
CN209618732U (en) Weight tower crane conversion section
CN211312582U (en) Tower structure and tower pile foundation adapter
CN113062348A (en) Concrete foundation structure of tower crane
CN217896554U (en) Be used for pre-buried positioner of different model tower crane foundations
CN202954578U (en) Structure for connecting tilted stair with rest platform of prefabricated assembled detachable type foundation pit ladder
CN111779347A (en) Door-shaped guyed tower leg reinforcing device and reinforcing method
CN111962549A (en) Anti-overturning construction method for existing tower crane under working condition of adjacent foundation pile

Legal Events