CN112523162A - Assembled revetment and construction method - Google Patents

Assembled revetment and construction method Download PDF

Info

Publication number
CN112523162A
CN112523162A CN202011156623.XA CN202011156623A CN112523162A CN 112523162 A CN112523162 A CN 112523162A CN 202011156623 A CN202011156623 A CN 202011156623A CN 112523162 A CN112523162 A CN 112523162A
Authority
CN
China
Prior art keywords
bottom plate
pile
pile head
prefabricated
prefabricated bottom
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011156623.XA
Other languages
Chinese (zh)
Inventor
马如彬
董学刚
邹恒
顾威
黄璟
曹坤
王弘元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN202011156623.XA priority Critical patent/CN112523162A/en
Publication of CN112523162A publication Critical patent/CN112523162A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G9/00Cultivation in receptacles, forcing-frames or greenhouses; Edging for beds, lawn or the like
    • A01G9/02Receptacles, e.g. flower-pots or boxes; Glasses for cultivating flowers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/08Structures of loose stones with or without piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental Sciences (AREA)
  • Revetment (AREA)

Abstract

The invention discloses an assembled revetment, which comprises a pile foundation inserted into soil, wherein a pile head is arranged at the top of the pile foundation, a groove is formed in the side part of the pile head, a bracket is arranged at the bottom of the pile head, an opening matched with the pile head is formed in a prefabricated bottom plate, an upward extending vertical baffle is arranged at one side of the prefabricated bottom plate, a downward extending lower vertical plate is arranged at the other side of the prefabricated bottom plate, the prefabricated bottom plate is horizontally placed, the reserved opening penetrates through the pile foundation, the lower vertical plate is tightly attached to the pile foundation and inserted into the soil, the prefabricated bottom plate is erected above the bracket of the pile foundation, the pile head extends out of the prefabricated bottom plate, fasteners are arranged at the groove positions on two sides of the pile head, tenons of the fasteners are tightly attached to the groove on the side part of the pile head, the bottoms of the fasteners are abutted. The assembled revetment structure is reliable, the members can be orderly dismantled according to requirements, waste concrete is not left in the soil body, and the influence on ecology is reduced.

Description

Assembled revetment and construction method
Technical Field
The invention relates to the technical field of river engineering construction, and discloses an assembled revetment and a construction method.
Background
The construction of bank protection projects on a river course often encounters the problems that the height difference between a riverbed and a rear land area is large, the slope space is small, a vertical type bank protection section or a combined type bank protection section needs to be constructed, a vertical type bank protection structure is constructed on a muddy foundation with relatively poor mechanical indexes, and foundation treatment or a deep foundation structure needs to be adopted to meet the requirement of ensuring the safety and stability of the structure.
Conventional vertical type shore protection or combined type shore protection have gravity type retaining wall structure, pile foundation cushion cap retaining wall structure etc. and are deep at silt, newly-built gravity type retaining wall structure on the relatively poor ground of foundation bearing capacity, need carry out ground processing on a large scale, compare pile foundation formula structure and be uneconomic. The conventional pile foundation bearing platform retaining wall construction usually needs cast-in-place concrete members below the water level elevation, the construction interface is large, the construction period is long, and a cofferdam needs to be filled to occupy a river channel for a long time. The functions of river navigation, flood transportation and the like are influenced. Therefore, it is urgently needed to find an assembled revetment suitable for poor geological conditions and a construction method thereof.
Disclosure of Invention
The invention aims to provide an assembled revetment and a construction method, which overcome the limitation of the application of a conventional revetment form on a poor foundation river channel and realize the industrialized construction of river channel revetment engineering. And the component recovery can be realized when the river bank protection is reconstructed again.
In order to solve the technical problem, the invention is solved by the following technical scheme:
the utility model provides an assembled shore protection, includes the pile foundation that inserts in the soil, its characterized in that: pile foundation top is equipped with the pile head, the pile head lateral part is equipped with the recess, the pile head bottom is equipped with the bracket, set up on the prefabricated bottom plate with pile head complex reservation trompil, one side of prefabricated bottom plate is equipped with the vertical baffle that upwards extends, the prefabricated bottom plate opposite side is equipped with downwardly extending's lower part riser, the prefabricated bottom plate level is placed, reservation trompil on the prefabricated bottom plate passes the pile foundation, the pile foundation is hugged closely to the lower part riser and is inserted in the soil, prefabricated bottom plate frame is on the pile foundation bracket, the pile head stretches out to prefabricated bottom plate top, pile head both sides recess position installation fastener, fastener tenon and the inseparable laminating of pile head lateral part recess, the fastener bottom offsets with the bottom plate, pile head external member cover is peripheral at pile head and fastener, make the three form wholly, die the pile head lock on.
Furthermore, the pile foundation adopts a prefabricated square pile, the cross section of the prefabricated square pile is 300mm x 300mm, the bracket of the pile foundation is 600mm away from the pile top, the height is 400mm, the width is 100mm, the groove at the side part of the pile head is 100mm in height and 50mm in depth; the fastener is L-shaped, the height is 200mm, the top width is 100mm, the bottom width is 150mm, and the fastener tenon is formed at the lower part of the fastener; the middle part of the pile head sleeve is provided with a square hole, and the side thickness of the square hole is 50 mm; the prefabricated bottom plate is 3m long, 0.9m wide and 400mm high, the lower part vertical plate is 1m long and 200mm thick, the vertical baffle is 0.5m long and 200mm thick, the reserved opening distance is 1m, and the opening side length is 350 mm.
Furthermore, cohesive soil is backfilled above the prefabricated bottom plate to form a side slope, the vertical baffle of the prefabricated bottom plate forms a retaining wall, turf protection is planted on the side slope above the retaining wall, and emergent aquatic plants are planted on the front beach surface of the retaining wall.
Furthermore, the fabricated revetment is suitable for a river channel with rear land area elevation higher than the designed high water level of the river channel.
The vertical baffle plate plays a main role in retaining soil, and the pile foundation plays a bearing capacity to bear upper load.
A construction method of an assembled revetment is characterized by comprising the following steps:
A. manufacturing a pile foundation, a prefabricated bottom plate, a fastener and a pile head external member, wherein the pile foundation top is provided with a pile head, the side part of the pile head is provided with a groove, the bottom of the pile head is provided with a bracket, the prefabricated bottom plate is provided with an opening matched with the pile head, one side of the prefabricated bottom plate is provided with an upward extending vertical baffle, the other side of the prefabricated bottom plate is provided with a downward extending lower vertical plate, the fastener is provided with a fastener tenon matched with the groove at the side part of the pile head, and the pile head external member is provided with a square hole matched with the;
B. the pile foundation is driven into the soil according to the designed pile position and elevation, and the orientation of the pile foundation is ensured to be consistent with the opening of the standard prefabricated base plate;
C. excavating and leveling a foundation trench, horizontally placing a prefabricated bottom plate, reserving a hole to penetrate through a pile foundation, inserting a lower vertical plate tightly attached to the pile foundation into the soil, erecting the prefabricated bottom plate on a bracket of the pile foundation, and extending a pile head to the position above the prefabricated bottom plate;
D. fasteners are arranged at the groove positions on the two sides of the pile head, the tenon of each fastener is tightly attached to the groove on the side part of the pile head, the bottom of each fastener is abutted against the bottom plate, and the pile head sleeve is sleeved on the periphery of the pile head and the fasteners to enable the pile head sleeve, the pile head sleeve and the fasteners to form a whole, so that the pile head is locked on the bottom plate;
E. and (3) backfilling cohesive soil above the prefabricated bottom plate to form a side slope, forming a retaining wall by the vertical baffle of the prefabricated bottom plate, planting a turf protection slope on the side slope above, and planting emergent aquatic plants on the front beach surface of the retaining wall.
Furthermore, when the river bank protection needs to be reconstructed again in the future, the bank protection member can be orderly dismantled, and waste concrete is not left in the soil body.
All components of the invention are prefabricated by factory standards, and several different specifications are set according to different engineering conditions. And after the prefabrication in the factory is finished and the design strength is reached, the steel plate is transported to the field for installation. Squeeze into appointed position with the pile foundation according to the pile position and the elevation that design is good, guarantee that the orientation of pile foundation is unanimous with the trompil of standard prefabricated bottom plate, the foundation ditch excavation carries out the flattening, places the bottom plate level, reserves the trompil and passes the pile foundation, during the pile foundation inserts soil is hugged closely to the afterbody, the bottom plate frame was on the pile foundation bracket, the vertical baffle of prefabricated bottom plate undertakes main fender soil effect, the pile foundation performance bearing capacity undertakes the upper portion load. Due to the adoption of the technical scheme, the invention has the following beneficial effects:
1. the assembled revetment is assembled by standard prefabricated pile foundation external member and prefabricated bottom plate and forms, adopts effective connection, can reach the requirement of retaining soil and bearing capacity, and structure safe and reliable.
2. The structure form is small, and disturbance to the bank slope of the natural river is reduced while the soil body behind the wall is kept stable; meanwhile, the layered planting is suitable for greening under different water level conditions, and has good ecological and landscape effects.
3. The whole revetment project is formed by assembling each component, can set up the barricade of different heights in order to adapt to the high requirement of different retaining soil.
4. When the river bank protection needs to be reformed again in future, the current bank protection member can be orderly dismantled, waste concrete is not left in the soil body, and the influence on ecology is reduced.
5. The bank protection member is prefabricated by adopting factory standards, and large-scale production is realized. The method has the advantages of low cost, good universality, capability of completely avoiding the construction steps of cast-in-place concrete on site, shortening the construction period on site, good construction quality and less environmental influence.
6. The bank protection member is installed on site without strict dry land construction conditions, and can even be constructed underwater, so that the influence on river channel shipping and flood discharge caused by long-time occupation of a river channel by a filled cofferdam is avoided.
Drawings
The invention will be further described with reference to the accompanying drawings in which:
FIG. 1 is a cross-sectional view of a fabricated revetment and method of construction of the present invention;
FIG. 2 is an assembled view of a square pile element assembly according to the present invention;
FIG. 3 is a schematic structural view of a pile foundation according to the present invention;
FIG. 4 is a schematic view of the fastener of the present invention;
fig. 5 is a schematic structural view of the pile head kit according to the present invention;
fig. 6 is a diagram of the pile placement on a standard prefabricated floor in accordance with the present invention.
In the figure: 1-pile foundation; 2-a fastener; 3-pile head kit; 4-prefabricating a bottom plate; 5-opening a hole on the bottom plate; 6-grass planting slope protection; 7-emergent aquatic plants; 8-riverbed side slopes; 9-bracket.
Detailed Description
The present invention will be more clearly and completely described in the following description of preferred embodiments, taken in conjunction with the accompanying drawings. . These embodiments are merely illustrative of the present invention and are not intended to limit the present invention.
The utility model provides an assembled shore protection, includes pile foundation 1 that inserts in the soil, its characterized in that: pile foundation 1 top is equipped with the pile head, the pile head lateral part is equipped with the recess, the pile head bottom is equipped with bracket 9, set up on prefabricated bottom plate 4 with pile head complex bottom plate trompil 5, one side of prefabricated bottom plate 4 is equipped with the vertical baffle that upwards extends, the prefabricated bottom plate opposite side is equipped with downwardly extending's lower part riser, the prefabricated bottom plate level is placed, reserve the trompil and pass the pile foundation, the lower part riser is hugged closely the pile foundation and is inserted in the soil, prefabricated bottom plate frame is on the pile foundation bracket, the pile head stretches out to prefabricated bottom plate top, pile head both sides groove position installation fastener, fastener tenon and the inseparable laminating of pile head lateral part recess, the fastener bottom offsets with the bottom plate, pile head external member cover is peripheral at pile head and fastener, make the three form wholly, die on the bottom plate with the pile.
The present invention is described in detail below according to one embodiment of the present invention.
As shown in fig. 1, a bank protection project is newly built on a river channel, and in order to meet the requirements of bearing capacity and overall stability, a low pile cap bank protection structure is often adopted. Carrying out slope-releasing excavation on the riverbed side slope 8, excavating a foundation trench, sinking piles by adopting a vibration pile sinking method, driving the standard prefabricated square piles 1 into a set elevation and a plane pile position, and sinking to a bracket position to be combined with manual local excavation and sinking. The standard prefabricated bottom plate 4 is lifted and installed, the lower bottom plate hole 9 penetrates through the pile head frame on the bracket under the assistance of constructors, and the tail part is tightly attached to the pile foundation and inserted into the soil. And installing standard precast pile head fasteners 2 and standard precast pile head external members 3 to effectively connect the pile foundation 1 and the base plate 4. And backfilling the soil behind the wall. And (3) arranging slopes in front of and behind the retaining wall, planting turf protection slopes 6 on the side slope above the retaining wall, and planting emergent aquatic plants 7 on the beach surface in front of the wall.
As shown in fig. 2 and 3, the fabricated low pile cap revetment components are completely prefabricated using factory standards and assembled on site without the need for cast-in-place concrete on site. The size of the pile foundation 1 is 300 x 300, the pile length is designed according to geological conditions, the distance between a pile foundation bracket and a pile top is 600mm, the height is 400mm, the width is 100mm, the height of a groove of the pile top is 100mm, and the depth is 50 mm. The fastener 2 is L-shaped, the height is 200mm, the top width is 100mm, the bottom width is 150mm, and the lower part of the fastener forms a fastener tenon. The middle part of the pile head external member 3 is provided with a square hole, and the side thickness is 50 mm. The prefabricated bottom plate 4 is 3m long, 0.9m wide and 400mm high, the lower part vertical plate is 1m long and 200mm thick, the vertical baffle is 0.5m long and 200mm thick, 5 intervals of reserved holes are 1m, and the side length of the holes is 350 mm. The reinforcing bars of the standard prefabricated parts all need to meet the strength requirement.
The construction method of the invention specifically comprises the following steps:
(1) survey lofting
Determining the arrangement position of a revetment structure on a riverway side slope according to the design requirements and the plane position of a drawing, determining the excavation range and elevation of the side slope on the basis of the arrangement position, and marking lines;
(2) excavation of foundation trench
Firstly, slope releasing and excavating are carried out on the side slope of the river channel, and a construction interface is created. The excavation method adopts layered excavation, and is carried out by a 0.5m3 backhoe excavator with a 5-ton dump truck, and earthwork is transported to a designated area. And leveling the foundation trench to ensure that the excavation elevation is accurate. The structure construction does not need cast-in-place concrete, and a small amount of water can be allowed to enter the foundation trench, so that a cofferdam does not need to be filled;
(3) standard prefabricated pile foundation construction
Selecting standard prefabricated square piles with reasonable sizes according to the bearing capacity requirement and the integral stability requirement of the side slope, sinking the piles by adopting a vibration pile sinking method under the condition of a deep sludge foundation, strictly controlling the driving elevation and the plane position of a pile foundation, and sinking the piles to a bracket position by combining manual local excavation and sinking to a specified elevation;
(4) construction of standard prefabricated bottom plate
And (3) conveying the standard prefabricated base plate to a construction site for hoisting and installation, hoisting the base plate in place, making the opening of the lower base plate penetrate through the pile head frame on the bracket under the assistance of constructors, and inserting the tail part of the lower base plate into the soil by clinging to the pile foundation. Installing standard prefabricated pile head fasteners and standard prefabricated pile head kits to effectively connect the pile foundation and the base plate;
(5) slope management and greening planting
And the cohesive soil is backfilled behind the wall to meet the design requirement. And (5) arranging slopes in front of and behind the retaining wall, and planting suitable greening.
In the description of the present invention, it is to be understood that the terms "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc., indicate orientations or positional relationships based on those shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, are not to be construed as limiting the present invention.
While specific embodiments of the invention have been described above, it will be appreciated by those skilled in the art that this is by way of example only, and that the scope of the invention is defined by the appended claims. Various changes and modifications to these embodiments may be made by those skilled in the art without departing from the spirit and scope of the invention, and these changes and modifications are within the scope of the invention.

Claims (5)

1. The utility model provides an assembled shore protection, includes the pile foundation that inserts in the soil, its characterized in that: pile foundation top is equipped with the pile head, the pile head lateral part is equipped with the recess, the pile head bottom is equipped with the bracket, set up on the prefabricated bottom plate with pile head complex reservation trompil, one side of prefabricated bottom plate is equipped with the vertical baffle that upwards extends, the prefabricated bottom plate opposite side is equipped with downwardly extending's lower part riser, the prefabricated bottom plate level is placed, reservation trompil on the prefabricated bottom plate passes the pile foundation, the pile foundation is hugged closely to the lower part riser and is inserted in the soil, prefabricated bottom plate frame is on the pile foundation bracket, the pile head stretches out to prefabricated bottom plate top, pile head both sides recess position installation fastener, fastener tenon and the inseparable laminating of pile head lateral part recess, the fastener bottom offsets with the bottom plate, pile head external member cover is peripheral at pile head and fastener, make the three form wholly, die the pile head lock on.
2. The fabricated revetment according to claim 1, wherein: and (3) backfilling cohesive soil above the prefabricated bottom plate to form a side slope, forming a retaining wall by the vertical baffle of the prefabricated bottom plate, planting a turf protection slope on the side slope above, and planting emergent aquatic plants on the front beach surface of the retaining wall.
3. The fabricated revetment according to claim 1, wherein: the fabricated revetment is suitable for river channels with rear land areas with elevations higher than the designed high water level of the river channels.
4. The fabricated revetment according to claim 1, wherein: the pile foundation adopts a prefabricated square pile, the cross section of the prefabricated square pile is 300 mm-300 mm, the bracket of the pile foundation is 600mm away from the pile top, the height is 400mm, the width is 100mm, the groove at the side part of the pile head is 100mm high, and the depth is 50 mm; the fastener is L-shaped, the height is 200mm, the top width is 100mm, the bottom width is 150mm, and the fastener tenon is formed at the lower part of the fastener; the middle part of the pile head sleeve is provided with a square hole, and the side thickness of the square hole is 50 mm; the prefabricated bottom plate is 3m long, 0.9m wide and 400mm high, the lower part vertical plate is 1m long and 200mm thick, the vertical baffle is 0.5m long and 200mm thick, the reserved opening distance is 1m, and the opening side length is 350 mm.
5. A construction method of an assembled revetment is characterized by comprising the following steps:
A. manufacturing a pile foundation, a prefabricated bottom plate, a fastener and a pile head external member, wherein the pile foundation top is provided with a pile head, the side part of the pile head is provided with a groove, the bottom of the pile head is provided with a bracket, the prefabricated bottom plate is provided with an opening matched with the pile head, one side of the prefabricated bottom plate is provided with an upward extending vertical baffle, the other side of the prefabricated bottom plate is provided with a downward extending lower vertical plate, the fastener is provided with a fastener tenon matched with the groove at the side part of the pile head, and the pile head external member is provided with a square hole matched with the;
B. the pile foundation is driven into the soil according to the designed pile position and elevation, and the orientation of the pile foundation is ensured to be consistent with the opening of the standard prefabricated base plate;
C. excavating and leveling a foundation trench, horizontally placing a prefabricated bottom plate, reserving a hole to penetrate through a pile foundation, inserting a lower vertical plate tightly attached to the pile foundation into the soil, erecting the prefabricated bottom plate on a bracket of the pile foundation, and extending a pile head to the position above the prefabricated bottom plate;
D. fasteners are arranged at the groove positions on the two sides of the pile head, the tenon of each fastener is tightly attached to the groove on the side part of the pile head, the bottom of each fastener is abutted against the bottom plate, and the pile head sleeve is sleeved on the periphery of the pile head and the fasteners to enable the pile head sleeve, the pile head sleeve and the fasteners to form a whole, so that the pile head is locked on the bottom plate;
E. and (3) backfilling cohesive soil above the prefabricated bottom plate to form a side slope, forming a retaining wall by the vertical baffle of the prefabricated bottom plate, planting a turf protection slope on the side slope above, and planting emergent aquatic plants on the front beach surface of the retaining wall.
CN202011156623.XA 2020-10-26 2020-10-26 Assembled revetment and construction method Pending CN112523162A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011156623.XA CN112523162A (en) 2020-10-26 2020-10-26 Assembled revetment and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011156623.XA CN112523162A (en) 2020-10-26 2020-10-26 Assembled revetment and construction method

Publications (1)

Publication Number Publication Date
CN112523162A true CN112523162A (en) 2021-03-19

Family

ID=74980384

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011156623.XA Pending CN112523162A (en) 2020-10-26 2020-10-26 Assembled revetment and construction method

Country Status (1)

Country Link
CN (1) CN112523162A (en)

Similar Documents

Publication Publication Date Title
CN102966108B (en) Construction method of deep foundation pit close to building and adopting underground structure as internal support
CN207003499U (en) A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN201762710U (en) Pile-wall combined enclosing structure for offshore deep foundation pit
CN111236260A (en) Variable-rigidity combined type prefabricated double-row pile supporting structure and construction method thereof
CN209923959U (en) Open caisson structure for dry-process operation of high-groundwater-level soft soil field
KR20110107888A (en) Construction method of the pier without the temporary dam in the sea or the river
CN111593757B (en) Line pole tower loop pile anchor composite foundation suitable for karst region and construction method thereof
CN214497366U (en) Assembled shore protection
CN110306589B (en) Method for forming assembled reinforced earth retaining wall
CN107700434A (en) A kind of dome grating formula armored concrete mud-rock flow blocking dam and its construction process
CN112523162A (en) Assembled revetment and construction method
KR100360462B1 (en) Method to construct a structure on soft soil and the structure thereof
CN214497380U (en) Assembled low pile cap shore protection suitable for silt foundation
JPS58120924A (en) Block for assembling retaining wall
CN202543946U (en) Supporting structure for drainage type fender posts in soft soil area
CN115506382A (en) Construction method for pile plate wall of island building platform
CN215715515U (en) Municipal pipe network construction supporting integrated structure under unfavorable geological conditions
CN204898700U (en) Bridge foundation structure
CN213773294U (en) Assembly type bridge sunken hydrophilic footpath
KR101119651B1 (en) The pro-environmental retaining wall using circular PHC pile with catch pit which is had and construction method using thereby
CN210459300U (en) Enclosure structure for covering and digging station
CN210887256U (en) Straight combined sheet pile-ground wall-connecting type frame of water retaining cofferdam
CN112376498A (en) Assembled low-pile bearing platform revetment suitable for muddy foundation and construction method
CN214497381U (en) Assembled ecological revetment
CN113585168A (en) Sheet pile shore-connection type high-pile wharf structure suitable for deep peat soil soft foundation and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination