CN112482226B - Construction method for changing height and span length of upstroke movable formwork - Google Patents

Construction method for changing height and span length of upstroke movable formwork Download PDF

Info

Publication number
CN112482226B
CN112482226B CN202011300745.1A CN202011300745A CN112482226B CN 112482226 B CN112482226 B CN 112482226B CN 202011300745 A CN202011300745 A CN 202011300745A CN 112482226 B CN112482226 B CN 112482226B
Authority
CN
China
Prior art keywords
bottom die
die
section
installing
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011300745.1A
Other languages
Chinese (zh)
Other versions
CN112482226A (en
Inventor
刘宏达
杨龙
杨党国
赵进文
李源
黄德利
皮军云
季袁飞
朱雷
郑权
卯利君
张志选
杨文杰
李鑫
靳旭东
张小锋
张小平
林文强
钟祺
张路伟
徐菲
许进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
4th Engineering Co Ltd of MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
4th Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC, 4th Engineering Co Ltd of MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN202011300745.1A priority Critical patent/CN112482226B/en
Publication of CN112482226A publication Critical patent/CN112482226A/en
Application granted granted Critical
Publication of CN112482226B publication Critical patent/CN112482226B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a construction method for lengthening an overhead variable cross of an upstroke type movable formwork. The construction method comprises the following steps: (1) carrying out construction preparation before span change; (2) connecting the hanging system and the side mold supporting system to be high: the method comprises the steps of connecting a hanging system to be high and connecting a side mould supporting system to be high; (3) longitudinally lengthening the bottom die system; (4) vertically passing a hole through the movable mould frame; and (5) a step of die-jointing the side die to be high and long. The invention modifies and adjusts the upstroke movable mould frame to realize the construction of box girders with different spans, shortens the construction period of the box girders, improves the construction efficiency and quality of the box girders and saves the construction cost of the box girders compared with the two movable mould frames with corresponding spans. Corresponding hanging systems, supporting systems and template systems are added through adjustment, the box girder construction with different spans can be realized without changing the structural structure of the original formwork by a large amount, and the changing mode is simple and feasible.

Description

Construction method for changing height and span length of upstroke movable formwork
Technical Field
The invention relates to the technical field of bridge construction, in particular to a construction method for lengthening an overhead variable cross of an upstroke type movable formwork.
Background
A highway-railway dual-purpose bridge for a quan and a strait is the first highway-railway dual-purpose bridge across straits in China. The strait bridge is different from a previously constructed gulf bridge, the construction of the strait bridge is under severe conditions such as high wind, wave height, surge, strong typhoon, complex geology and the like, especially the plunge pool strait is one of three famous storm sea areas in the world, and huge challenges and ultrahigh risks are brought to the construction of the strait bridge. The bridge is the first attempt at the cross-strait bridge field in China, and the technical challenges and construction risks, regardless of the environment severity, far exceed other cross-bay bridges built or built in China. A highway-railway highway bridge with a plunge pool and a strait is a highway-railway highway bridge constructed in a complex storm surge environment for the first time in the world, and the safety operation of the highway bridge under the environment of ten grades of strong winds (land eight-grade wind operation) of an offshore bridge deck can be met after the highway-railway highway bridge is constructed.
The movable formwork is one large bridge building apparatus with self-moving formwork between bridge spans for bridge construction to complete the cast-in-situ concrete bridge construction. At present, the movable formwork is widely applied to the construction of continuous beam bridges, and more bridge superstructure adopts a movable formwork cast-in-place construction method. However, in the actual construction process, due to different geographic environments, the span of the continuous beam bridge also changes. When the movable formwork is adopted to construct continuous beam bridges with different spans, the conventional treatment mode is to adopt two sets of different movable formworks to construct the bridge with the corresponding span. However, the conventional treatment method greatly increases the construction cost in actual construction, increases the workload of mounting and dismounting the movable formwork, reduces the construction efficiency and increases the risk coefficient of construction.
Therefore, it is necessary to provide a reliable, efficient, economical and safe construction method for changing the span length of the movable formwork in the overhead operation.
Disclosure of Invention
In order to solve the technical problems, the invention provides an overhead variable cross-section length construction method for an upstroke type movable formwork.
The invention provides the following technical scheme:
an ascending type movable formwork aerial variable cross-span construction method comprises the following steps:
(1) carrying out construction preparation before span change;
(2) connecting the hanging system and the side mold supporting system to be higher: the method comprises the steps of connecting a hanging system to be high and connecting a side die supporting system to be high;
(3) longitudinally lengthening the bottom die system;
(4) vertically passing a hole through the movable mould frame; and
(5) and (3) die-jointing the side die to be high and long.
Preferably, in the step (2), the hanging system is connected with a height of 50-60cm by installing a 50-60cm extension section of the hanging system.
Preferably, the step of raising the hanging system comprises:
(21) installing a temporary long pull rod: installing a temporary long pull rod on the flange of the concrete box girder and locking the temporary long pull rod; and
(22) and (3) connecting the height after disconnection: and removing the connecting bolt of the hanging system, integrally jacking the main beam and the hanging rack, and then installing a 50-60cm extension section of the hanging system.
Preferably, the step of lifting the side mould supporting system comprises the following steps:
(23) and (3) mounting a temporary short pull rod: releasing the temporary long pull rod, and installing and locking the temporary short pull rod;
(24) connecting the height after disconnecting: removing the bolt constraint of the side mold stay bar, utilizing a jacking oil cylinder to drop the whole mold frame, and then installing the side mold stay bar extension section; and
(25) and releasing all temporary pull rods.
Preferably, the step (3) includes:
(31) splitting the middle section of the bottom die: removing bolts at the middle section of the bottom die after independently passing through holes at the middle section of the bottom die, then dividing the middle section of the bottom die into two sections at the top of the middle pier, continuously moving the front section to the front pier and temporarily drilling a tip, and supporting the rear section on the middle pier and a bottom die working vehicle;
(32) installing a middle section extension section of the bottom die: connecting the middle section extension section of the bottom die with the middle section rear section of the bottom die to form a connecting body;
(33) combining the bodies: retreating the connecting body, and retreating the middle section front section of the bottom die to the middle pier to be connected with the connecting body.
Preferably, the step (4) includes:
(41) and (3) passing through holes in the bottom die: independently passing the lengthened middle section of the bottom die through a hole to the next variable span by using the leg-reversing trolley and the bottom die working trolley, and supporting two ends of the bottom die longitudinal beam on the bridge pier;
(42) lifting the bottom die working vehicle: the bottom die working vehicle moves to the reverse conveying device, the connection between the middle of the cross beam of the bottom die working vehicle is released, the bottom die working vehicle and the hanging system are folded in half respectively, the bottom die working vehicle is dismantled and connected, and the bottom die working vehicle is lifted by the reverse conveying device;
(43) moving the whole machine of the movable mould frame longitudinally through the hole: and the main middle support leg longitudinal moving oil cylinder is utilized, the whole movable formwork longitudinally moves the through hole to the front pier position and is anchored, and the mold opening oil cylinder is started after the through hole is in place, so that the formwork is closed and the transverse position of the formwork is adjusted.
Preferably, the step (4) further comprises: step (45): and installing a bottom die working trolley.
Preferably, the step (5) comprises:
(51) jacking the main middle supporting leg and the fixed middle supporting leg, adjusting the elevation of the die set, transporting the front supporting leg to the advanced pier by using the leg-reversing trolley, and installing and anchoring the front supporting leg; and
(52) and (3) closing the bottom die, and assembling and installing the heightened part and the longitudinal lengthened section of the side die in a scattered manner.
Preferably, the step (1) comprises:
(11) the step of performing the first part of the preparation: constructing the concrete of the last span box girder before span change, and embedding a pull rod hole in the end part area of the flange of the concrete box girder;
(12) the step of performing a second part of the preparation: checking whether the hydraulic station is normal; checking whether the position of the supporting trolley is normal; removing the constraint influencing the vertical movement, and enabling the die carrier and the jacking oil cylinder to be in a free state; and
(13) the step of performing the third part preparation: preparing a temporary long pull rod and a temporary short pull rod; and releasing the pull rod at the middle section of the bottom die system.
Preferably, the method further comprises the step (6): pre-pressing the die carrier, and adjusting the pre-camber of the die carrier according to the pre-pressing result; locking a main box girder, installing a loose die and binding bottom web steel bars; and binding a top plate steel bar, installing an end die, and reporting and checking the cast concrete.
Advantageous effects
The technical scheme of the invention has the following advantages:
the method adopts an up-going movable formwork, and can realize the construction of the box girder with different spans through certain modification and adjustment.
The method provided by the invention can realize the construction of box girders with different spans without changing the structural structure of the original formwork by a large amount, and the transformation mode is simple and feasible.
In order to adapt to the construction of box girders with different heights, the temporary hanging device is arranged on the flange of the box girder, so that the formwork hanging system and the formwork supporting system can be connected to be high, the construction efficiency is improved, and manpower and material resources are saved.
According to the method, only a temporary pull rod is needed to be installed on a poured concrete box girder to slightly fix a template, the template frame can be lifted through the lifting and descending of a main girder, the middle section of the bottom template can be lengthened through a leg-reversing trolley and a bottom template working vehicle, the span-changing step can be safely and efficiently carried out, and the synchronous span-changing of the template frame and the template construction can be ensured.
The middle section of the bottom die is independently lengthened through holes, the span-variable construction speed is high after the complete die frame machine is completed through the holes, the construction procedure is compact and feasible, the labor division in management is clear, and the continuity of the span-variable construction of the movable die frame is ensured.
Drawings
FIG. 1 is a flow chart of a construction method provided by the present invention;
FIG. 2 is a schematic view of the installation of a temporary long pull rod;
FIG. 3 is a schematic view of an extended section of the installation hanger system;
FIG. 4 is a schematic view of the installation of a short tie rod;
FIG. 5 is a schematic view of an extended section of an installation side mold;
fig. 6 to 8 are diagrams illustrating a longitudinal extension step of the bottom mold;
FIG. 6 is a schematic diagram of the separation of the front section of the bottom die and the rear section of the bottom die;
FIG. 7 is a schematic view of the installation of the front section of the bottom die and the intermediate extension section of the bottom die;
FIG. 8 is a schematic view of the installation of the rear section of the bottom die with the front section of the bottom die and the middle and middle long sections;
fig. 9 is a schematic view of the completion of the ascending type movable formwork high altitude variable span lengthening construction.
In the figure: 1: moving the mold frame; 2: bottom die; 3: performing side die; 4: a hanging system extension section; 5: a temporary long pull rod; 6: a side form stay bar extension section; 7: a temporary short pull rod; 8: a front section of the bottom die; 9: a rear section of a bottom die; 10: the middle section of the bottom die; 11: a bridge pier; 12: and (4) longitudinally lengthening the section.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the technical solutions of the present invention will be clearly and completely described below with reference to the embodiments of the present invention. It is to be understood that the embodiments described are only a few embodiments of the present invention, and not all embodiments. All other embodiments, which can be obtained by a person skilled in the art without making any creative effort based on the embodiments in the present invention, belong to the protection scope of the present invention.
The movable mould frame can be divided into an upper movable mould frame, a lower movable mould frame and a composite movable mould frame in different modes of via holes. The main beam of the movable formwork is arranged above the cast-in-place box beam, and the upward movable formwork is moved by the box beam and the pier. The upward moving type movable mould frame used by the invention can be an upward moving type movable mould frame of TMS49.2 model number of Wuhan Unicom mechanical technology Limited company, and structurally comprises front auxiliary supporting legs, fixed middle supporting legs, main middle supporting legs, a rear traveling mechanism, a main box girder and a cross connection thereof, a guide beam, a cantilever beam system, a hanger, an outer mould and a supporting system thereof, a bottom mould cross beam, a bottom mould longitudinal beam, an inner mould and a supporting system thereof, a lower trolley and a track thereof, a bottom surface working vehicle and a reverse transportation device thereof, a leg-reversing trolley, a hydraulic system and an electrical appliance system. The invention provides an upstroke type movable formwork aerial variable cross lengthening construction method, which comprises the following steps with reference to figure 1:
(1) carrying out construction preparation before span change;
(2) connecting the hanging system and the side mold supporting system to be higher: the method comprises the steps of connecting a hanging system to be high and connecting a side mould supporting system to be high;
(3) longitudinally lengthening the bottom die system;
(4) vertically passing a hole through the movable mould frame; and
(5) and (3) die-jointing the side die to be high and long.
For step (1), it is preferable to include the steps of:
(11) the step of performing the first part of the preparation: constructing the concrete of the last span box girder before span change, and embedding a pull rod hole in the end part area of the flange of the concrete box girder;
(12) the step of performing a second part of the preparation: the working personnel of each hydraulic station are in position and check whether the hydraulic stations are normal; the personnel at each supporting position take place and check whether the position of the supporting trolley is normal; removing the constraint which influences the vertical movement, and enabling the die carrier and the jacking oil cylinder to be in a free state; and
(13) the step of performing the third part preparation: preparing a temporary long pull rod and a temporary short pull rod; and releasing the pull rod at the middle section of the bottom die system.
In a preferred embodiment, the step of raising the suspension system comprises:
(21) installing a temporary long pull rod: installing a temporary long pull rod on the flange of the concrete box girder through a pull rod hole and locking, and temporarily hanging the bottom die, the side die and the side die supporting system on the flange plate of the concrete box girder, wherein the finished state is shown in fig. 2;
(22) connecting the height after disconnecting: and (3) removing the connecting bolts of the hanging system, jacking the main beam and the hanging rack integrally, and then installing the lengthened section of the hanging system, wherein the length of the lengthened section of the hanging system is preferably 50-60cm, so that the hanging system is lengthened by 50-60cm, and the finished state is shown in figure 3.
In some preferred embodiments, the step of raising the side form support system comprises:
(23) and (3) mounting a temporary short pull rod: releasing the temporary long pull rod, and installing and locking the temporary short pull rod;
(24) and (3) connecting the height after disconnection: releasing the bolt constraint of the side mold stay bar, using a jacking oil cylinder to drop the whole mold frame as shown in figure 4 after the completion, and then installing the side mold stay bar extension section as shown in figure 5 after the completion; and
(25) and releasing all temporary pull rods.
In some preferred embodiments, the step (3) comprises:
(31) splitting the middle section of the bottom die: removing bolts at the middle section of the bottom die after independently passing through holes at the middle section of the bottom die, then dividing the middle section of the bottom die into two sections at the top of the middle pier, continuously traveling the front section to the front pier and temporarily drilling a tip, and supporting the rear section on the middle pier and a bottom die working vehicle, as shown in fig. 6;
(32) installing a middle section extension section of the bottom die: connecting the extension section of the middle section of the bottom die with the rear section of the middle section of the bottom die to form a connector, as shown in fig. 7;
(33) and (3) integrating: and (4) retreating the connecting body, and then retreating the front section of the middle section of the bottom die to the middle pier to be connected with the connecting body, as shown in fig. 8.
In some preferred embodiments, the step (4) comprises:
(41) and (3) passing through holes in the bottom die: independently passing the lengthened middle section of the bottom die through a hole to the next variable span by using the leg-reversing trolley and the bottom die working trolley, and supporting two ends of the bottom die longitudinal beam on the bridge pier; (42) lifting the bottom die working vehicle: the bottom die working vehicle moves to the reverse conveying device, the connection between the middle of the cross beam of the bottom die working vehicle is released, the bottom die working vehicle and the hanging system are folded in half respectively, the bottom die working vehicle is dismantled and connected, and the bottom die working vehicle is lifted by the reverse conveying device; (43) moving the whole machine of the movable mould frame longitudinally through the hole: and the main middle support leg longitudinal moving oil cylinder is utilized, the whole movable formwork longitudinally moves the through hole to the front pier position and is anchored, and the mold opening oil cylinder is started after the through hole is in place, so that the formwork is closed and the transverse position of the formwork is adjusted. May further comprise step (44): and mounting a bottom die working trolley.
In some preferred embodiments, the step (5) comprises:
(51) jacking the main middle supporting leg and the fixed middle supporting leg, adjusting the elevation of the mold frame, transporting the front supporting leg to the front pier by using the leg-reversing trolley, and installing and anchoring the front supporting leg and the fixed middle supporting leg; (52) and (3) closing the bottom die, and assembling and mounting the heightened parts and the longitudinal lengthened sections of the side dies in a scattered manner, wherein the finished state is shown in fig. 9.
Of course, the subsequent processing may also be performed, including the following steps: pre-pressing the die carrier, and adjusting the pre-camber of the die carrier according to the pre-pressing result; locking a main box girder, installing a loose die and binding bottom web steel bars; and (5) binding the steel bars of the top plate, installing an end die, and reporting and checking to pour concrete.
And after the construction is finished, entering the next hole for construction.
The following are examples of the present invention.
Referring to fig. 1, an embodiment of the present invention provides an overhead variable-span lengthening construction method for an upstroke type mobile formwork, including the following steps:
s0: before the construction of moving the formwork 1 across the hole is performed, preparation work is performed.
The preparation work includes:
1. before the construction of the movable formwork 1 crossing the hole, a pre-buried pull rod hole needs to be reserved at the end part of the flange of the box girder of the last-span continuous girder bridge before the construction of the crossing.
2. Preparing long and short pull rods for lifting and hanging the die frame bottom die 2 and the side die 3.
3. And releasing all the constraints influencing the vertical movement, so that the movable die carrier 1 and the jacking oil cylinder are in a free state.
S1: completing the hanging and the height connection of the side mold supporting system.
Referring to fig. 2 to 5, the hanging and side form supporting system comprises the following steps:
1. as shown in fig. 2 and 3, the hanging system extension section is firstly installed: firstly, installing a temporary long pull rod 5 on a cast-span concrete box girder flange plate and locking the temporary long pull rod, then temporarily hanging a bottom die 2, a side die 3 and a side die supporting system on the concrete box girder flange plate, sequentially removing connecting bolts of a hanging system, finally integrally jacking a girder and a hanging frame for a distance by using a jacking oil cylinder, and then sequentially installing a hanging system extension section 6.
2. As shown in fig. 4 and 5, installing the extended section of the side mold supporting system: the method comprises the steps of firstly removing a temporary long pull rod 5 on the outer side of the end part of a flange plate, installing a temporary short pull rod 7 and locking, then removing bolt restraint of a side mold stay rod, utilizing a jacking oil cylinder to integrally drop a mold of a mold frame for a certain distance, finally installing a side mold stay rod extension section 8, and removing all temporary pull rods.
S2: and finishing the longitudinal extension of the bottom die system.
Referring to fig. 6 to 8, the longitudinal extension of the bottom mold includes the following steps:
1. and (3) independently passing holes through the bottom die 2 by using the leg-reversing trolley and the bottom die working vehicle, detaching bolts in the middle of the bottom die 2, dividing the bottom die 2 into two sections at the top of a middle pier, continuously walking the front section 8 of the bottom die to a front pier and temporarily beating the front end, and supporting the rear section 9 of the bottom die on the middle pier and the bottom die working vehicle.
2. And (3) mounting a middle extension section 10 of the bottom die by using a tower crane and connecting the middle extension section with an original bottom die 9, screwing template connecting bolts at a middle pier, retreating the connected middle sections 10 and 9 of the bottom die after connection is finished, retreating a middle section front section 8 of the middle section of the bottom die to the middle pier, connecting the middle section with the connected template connecting bolts of 10 and 9 to form a whole, and finishing longitudinal system extension of the bottom die.
S3: and completing the longitudinal via hole, side die height connection and longitudinal extension of the movable die frame.
Referring to fig. 9, the step of side die-jointing and longitudinally lengthening includes the following steps:
1. and (3) independently passing the lengthened bottom die 2 through a hole to the next variable span by using the inverted leg trolley and the bottom die working vehicle, and supporting two ends of the longitudinal beam of the bottom die 2 on the front pier and the pier 11.
2. And (3) longitudinally moving the oil cylinder by using the main middle support leg, longitudinally moving the whole machine of the movable die frame to the position of the front pier and anchoring, starting the die opening oil cylinder after the through hole is in place, closing the die of the die frame, accurately adjusting the transverse position of the die frame, and installing the bottom die working trolley.
3. Jacking the main middle supporting leg and fixing the middle supporting leg, adjusting the elevation of the mold frame, transporting the front supporting leg to the front pier by using the leg-reversing trolley, and installing and anchoring the front supporting leg.
4. After the whole die carrier is subjected to hole passing in place, the bottom die is closed, the heightened part of the side die and the longitudinal lengthened section 12 are assembled and installed in a scattered mode through the truck crane, and the whole die carrier system is changed to the next variable span position.
Finally, it should be noted that: the above examples are only intended to illustrate the technical solution of the present invention, but not to limit it; although the present invention has been described in detail with reference to the foregoing embodiments, it should be understood by those of ordinary skill in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions of the embodiments of the present invention.

Claims (10)

1. An overhead variable-span length construction method for an upstroke movable formwork is characterized by comprising the following steps of:
(1) carrying out construction preparation before span change;
(2) connecting the hanging system and the side mold supporting system to be higher: the method comprises the steps of connecting a hanging system to be high and connecting a side die supporting system to be high;
(3) longitudinally lengthening the bottom die system;
(4) vertically passing a hole through the movable mould frame; and
(5) and (3) die-jointing the side die to be high and long.
2. The construction method according to claim 1, wherein in the step (2), the hanging system is raised by 50-60cm by installing a 50-60cm extended section of the hanging system.
3. The construction method according to claim 2, wherein the step of raising the hanging system comprises:
(21) installing a temporary long pull rod: installing a temporary long pull rod on the flange of the concrete box girder and locking; and
(22) connecting the height after disconnecting: and removing the connecting bolt of the hanging system, integrally jacking the main beam and the hanging rack, and then installing a 50-60cm extension section of the hanging system.
4. The construction method according to claim 3, wherein the step of raising the side form supporting system comprises:
(23) and (3) mounting a temporary short pull rod: the temporary long pull rod is released, and the temporary short pull rod is installed and locked;
(24) and (3) connecting the height after disconnection: removing the bolt constraint of the side mold stay bar, utilizing a jacking oil cylinder to drop the whole mold frame, and then installing the side mold stay bar extension section; and
(25) and releasing all temporary pull rods.
5. The construction method according to claim 4, wherein the step (3) comprises:
(31) splitting the middle section of the bottom die: removing bolts at the middle section of the bottom die after independently passing through holes at the middle section of the bottom die, then dividing the middle section of the bottom die into two sections at the top of a middle pier, continuously traveling the front section to a front pier and temporarily drilling a tip, and supporting the rear section on a working vehicle of the middle pier and the bottom die;
(32) installing a middle section extension section of the bottom die: connecting the middle section extension section of the bottom die with the middle section rear section of the bottom die to form a connecting body;
(33) and (3) integrating: retreating the connecting body, and retreating the middle section front section of the bottom die to the middle pier to be connected with the connecting body.
6. The construction method according to claim 5, wherein the step (4) comprises:
(41) and (3) bottom die via hole drilling: independently passing the lengthened middle section of the bottom die through a hole to the next variable span by using the leg-reversing trolley and the bottom die working trolley, and supporting two ends of the bottom die longitudinal beam on the bridge pier;
(42) lifting a bottom die working vehicle: the bottom die working vehicle moves to the transporting device, the connection between the middle beams of the bottom die working vehicle is released, the bottom die working vehicle is folded in half, the bottom die working vehicle is detached to be connected with a hanging system, and the bottom die working vehicle is lifted by the transporting device;
(43) longitudinally moving the hole through the whole machine of the movable mould frame: and the main middle support leg longitudinal moving oil cylinder is utilized, the whole movable formwork longitudinally moves the through hole to the front pier position and is anchored, and the mold opening oil cylinder is started after the through hole is in place, so that the formwork is closed and the transverse position of the formwork is adjusted.
7. The construction method according to claim 6, wherein the step (4) further comprises: step (45): and mounting a bottom die working trolley.
8. Construction method according to claim 7, wherein said step (5) comprises:
(51) jacking the main middle supporting leg and the fixed middle supporting leg, adjusting the elevation of the mold frame, transporting the front supporting leg to the front pier by using the leg-reversing trolley, and installing and anchoring the front supporting leg and the fixed middle supporting leg; and
(52) and (3) closing the bottom die, and assembling and installing the heightened part and the longitudinal lengthened section of the side die in a scattered manner.
9. The construction method according to claim 8, wherein the step (1) comprises:
(11) a step of performing a first partial preparation: constructing the last span box girder concrete before span change, and embedding a pull rod hole in the end area of the flange of the concrete box girder;
(12) a step of performing a second partial preparation: checking whether the hydraulic station is normal; checking whether the position of the supporting trolley is normal; removing the constraint influencing the vertical movement, and enabling the die carrier and the jacking oil cylinder to be in a free state; and
(13) the step of performing the third part preparation: preparing a temporary long pull rod and a temporary short pull rod; and releasing the pull rod at the middle section of the bottom die system.
10. The construction method according to claim 9, further comprising the step (6): pre-pressing the die carrier, and adjusting the pre-camber of the die carrier according to the pre-pressing result; locking a main box girder, installing a loose die and binding bottom web steel bars; and (5) binding the steel bars of the top plate, installing an end die, and reporting and checking to pour concrete.
CN202011300745.1A 2020-11-19 2020-11-19 Construction method for changing height and span length of upstroke movable formwork Active CN112482226B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011300745.1A CN112482226B (en) 2020-11-19 2020-11-19 Construction method for changing height and span length of upstroke movable formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011300745.1A CN112482226B (en) 2020-11-19 2020-11-19 Construction method for changing height and span length of upstroke movable formwork

Publications (2)

Publication Number Publication Date
CN112482226A CN112482226A (en) 2021-03-12
CN112482226B true CN112482226B (en) 2022-07-15

Family

ID=74931783

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011300745.1A Active CN112482226B (en) 2020-11-19 2020-11-19 Construction method for changing height and span length of upstroke movable formwork

Country Status (1)

Country Link
CN (1) CN112482226B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117230701B (en) * 2023-10-24 2024-05-28 中铁四局集团有限公司 Overweight load arc V pier bridge sector bracket and construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2240678C3 (en) * 1972-08-18 1975-02-13 Dyckerhoff & Widmann Ag, 8000 Muenchen Device for the section-by-section front construction of bridge structures made of reinforced or prestressed concrete
CN101324056B (en) * 2008-08-06 2011-01-12 中铁大桥局股份有限公司 Upside suspension type moving die carrier
CN205348004U (en) * 2016-01-27 2016-06-29 中铁十四局集团第一工程发展有限公司 Moving die carrier
CN106192761B (en) * 2016-08-12 2017-09-12 中铁二十五局集团第三工程有限公司 A kind of method for disassembling mobile formwork in the narrow short transition time section of bridge tunnel
CN108103945B (en) * 2017-12-21 2019-10-22 中国电建集团铁路建设有限公司 A kind of whole landing mould bases of cast-in-situ box girder
CN109338894B (en) * 2018-11-22 2020-05-12 中铁十二局集团第一工程有限公司 Construction method for pouring wide and narrow box girder by movable formwork

Also Published As

Publication number Publication date
CN112482226A (en) 2021-03-12

Similar Documents

Publication Publication Date Title
CN102121234B (en) Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
CN100441779C (en) Bridge construction method for air prefabrication and translation in place
KR20140084107A (en) Self-Launching Movable Scaffolding System
WO2018133045A1 (en) Method for mounting self-anchored suspension bridge
CN107558378B (en) Bridge girder erection machine for erecting full precast girder and bridge girder erection method thereof
CN111485500B (en) Construction method and structure for transversely lengthening and reinforcing by retreating and dismantling diamond hanging basket
CN111139749A (en) Large-span bearing type continuous steel truss girder cantilever erection construction method
CN212714544U (en) Rhombus is hung basket and is retreated and demolishd horizontal extension reinforcement construction structure
CN106988229A (en) A kind of hybrid structure of arch and beam continuous rigid frame bridge button hangs branch convolution constructing device and method
CN111749140A (en) Truss integral lifting type bridge high pier creeping formwork device and construction method
CN112482226B (en) Construction method for changing height and span length of upstroke movable formwork
CN211420881U (en) Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam
CN110344334B (en) Construction method for two-span continuous steel-concrete composite bridge by adopting back cable type bridge girder erection machine
CN110847052B (en) Porous large-section cast-in-situ box girder and construction method
CN209907208U (en) Wave form steel web continuous beam bridge side span folds cast-in-place supporting structure
CN111851307A (en) Large-span prefabricated assembly type corrugated web combined box girder transportation frame construction method
CN114933247B (en) Intelligent construction equipment and construction process thereof
CN215164712U (en) Movable platform system for construction of large-span concrete-filled steel tube arch
CN115961549A (en) Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge
CN212270702U (en) Truss integral lifting type bridge high pier creeping formwork device
CN221218513U (en) Frame-lifting type reverse mould structure of bridge constant-section thin-wall pier
CN219548382U (en) Empty layer hanging template system of granulating tower
CN219175028U (en) Double-limb pier climbing formwork
CN212769526U (en) Lower bearing lifting type bridge floor crane
CN220301178U (en) Hanging basket suspension casting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant