CN112290998A CN202010988033.7A CN202010988033A CN112290998A CN 112290998 A CN112290998 A CN 112290998A CN 202010988033 A CN202010988033 A CN 202010988033A CN 112290998 A CN112290998 A CN 112290998A
Authority
CN
China
Prior art keywords
optical fiber
optical
fiber
optical cable
fiber core
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010988033.7A
Other languages
Chinese (zh)
Inventor
李尚�
孟兆娜
李雅君
郑庆竹
丁光远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Tianjin Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Tianjin Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN202010988033.7A priority Critical patent/CN112290998A/en
Publication of CN112290998A publication Critical patent/CN112290998A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04BTRANSMISSION
    • H04B10/00Transmission systems employing electromagnetic waves other than radio-waves, e.g. infrared, visible or ultraviolet light, or employing corpuscular radiation, e.g. quantum communication
    • H04B10/07Arrangements for monitoring or testing transmission systems; Arrangements for fault measurement of transmission systems
    • H04B10/075Arrangements for monitoring or testing transmission systems; Arrangements for fault measurement of transmission systems using an in-service signal
    • H04B10/077Arrangements for monitoring or testing transmission systems; Arrangements for fault measurement of transmission systems using an in-service signal using a supervisory or additional signal
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04BTRANSMISSION
    • H04B10/00Transmission systems employing electromagnetic waves other than radio-waves, e.g. infrared, visible or ultraviolet light, or employing corpuscular radiation, e.g. quantum communication
    • H04B10/07Arrangements for monitoring or testing transmission systems; Arrangements for fault measurement of transmission systems
    • H04B10/075Arrangements for monitoring or testing transmission systems; Arrangements for fault measurement of transmission systems using an in-service signal
    • H04B10/077Arrangements for monitoring or testing transmission systems; Arrangements for fault measurement of transmission systems using an in-service signal using a supervisory or additional signal
    • H04B10/0773Network aspects, e.g. central monitoring of transmission parameters

Landscapes

  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Signal Processing (AREA)
  • Light Guides In General And Applications Therefor (AREA)

Abstract

The invention discloses an optical cable fiber core online management device and method, which can directly identify the plugging and unplugging actions of optical fibers by using an infrared sensing function, then transmit action signals to a computer room wireless gateway device by using a ZigBee technology, transmit the action signals to a background server, and generate optical fiber data information at a Client terminal, thereby realizing the online real-time management of the optical cable fiber cores. And the optical fiber clip is arranged on the fiber core of the optical cable and used for sensing the plugging action and controlling the operation condition of the optical core in real time. The method can set work order tasks in the background and comprehensively analyze the reasons of the action condition of the optical fiber: the optical fiber management system has the advantages that planned work, manual mistaken collision and the like are achieved, operation personnel can conveniently remotely control the operation field conditions, production safety is enhanced, real and reliable optical fiber operation data are provided by using a remote monitoring technology, the optical fiber operation data are automatically and correlatively analyzed, and the optical fiber core management efficiency is effectively improved.

Description

Optical cable fiber core online management method
Technical Field
The invention belongs to the technical field of information, and particularly relates to an optical cable fiber core online management method.
Background
Electric power is a major basic service type industry in the field of industrial construction in China and is related to the development of the national civilians. With the continuous development of electronic information technology, the information technology is rapidly fused with information communication management in the past without the breadth and depth, and the automatic intelligent requirement of the power system is continuously increased. How to scientifically and efficiently complete the electric power information communication management task, and more effectively realize the standardized, scientific, efficient and integrated management of the information communication machine room, and is of great importance for improving the business competitiveness of the information machine room management.
Optical cable fiber core data management is the most basic work content of information communication machine room management, and is a ring with higher technical difficulty in machine room management operation. The fiber core of the optical cable is a passive device, no effective remote online monitoring means exists at present, and fiber core resource management depends on offline data and cannot effectively manage the actual situation on site.
The fiber core of the optical cable is a passive device, no effective remote online monitoring means exists at present, and fiber core resource management depends on offline data and cannot effectively manage the actual situation on site. In order to ensure the safe operation of an electric power system, strengthen the comprehensive perception, dynamic analysis and timely feedback of the fiber core condition of the optical cable and help operation managers at all levels to more effectively control the optical cable resources, the management of the fiber core of the optical cable needs a management platform which is more convenient, intuitive, accurate and capable of real-time interaction.
Disclosure of Invention
The invention aims to provide an optical cable fiber core online management method, which is characterized in that action information of optical fiber clip changes is obtained based on an infrared sensing technology, the action information is accurately uploaded to gateway equipment by using a ZigBee wireless transmission technology, optical cable fiber core data are transmitted in real time, and field working conditions are associated with the optical cable fiber core and then displayed at a Cilent end.
In order to solve the technical problems, the invention adopts the following technical means:
an optical cable fiber core online management method specifically comprises the following steps:
s1, clamping the optical fiber clip at the spare fiber core flange head of the distribution box;
s2, when the optical fiber service is put into use and quit, the optical fiber needs to be plugged and unplugged, the infrared sensing function of the optical fiber clip is triggered, and an optical fiber change signal is generated;
s3, transmitting information to the machine room gateway equipment through the optical fiber plugging signal by a ZiBee wireless technology;
s4, the gateway equipment transmits data to the optical cable fiber core online management system server through the transmission network;
and S5, the optical cable fiber core online management system processes the data and displays the data in real time, dynamically and intuitively.
Further, equipment includes rack, distribution frame, instrument equipment and network equipment, instrument equipment includes the fiber clip, network equipment includes optic fibre, net twine, wireless gateway equipment, server, switch and router.
Further, in step S2, the optical fiber change signal is a signal generated by triggering an infrared sensing function of the fiber clamp with an optical fiber plug.
Further, the specific operation of step S5 is as follows:
s51, storing the data information of the change of the optical fiber clip into a database, and establishing a data storage table corresponding to the fiber core of the optical cable in the database;
s52, displaying time information and optical cable fiber core conditions on the Client side according to the contents in the data information, integrating the work order task setting in the current online management system, and comprehensively analyzing the optical fiber conditions;
the following advantages can be obtained by adopting the technical means:
the invention provides an optical cable fiber core online management device and method, which can directly identify the plugging and unplugging actions of optical fibers by using an infrared sensing function, then transmit action signals to a computer room wireless gateway device by using a ZigBee technology, transmit the action signals to a background server, and generate optical fiber data information at a Client terminal, thereby realizing the online real-time management of the optical cable fiber cores. And the optical fiber clip is arranged on the fiber core of the optical cable and used for sensing the plugging action and controlling the operation condition of the optical core in real time. The method can set work order tasks in the background and comprehensively analyze the reasons of the action condition of the optical fiber: the optical fiber management system has the advantages that planned work, manual mistaken collision and the like are achieved, operation personnel can conveniently remotely control the operation field conditions, production safety is enhanced, real and reliable optical fiber operation data are provided by using a remote monitoring technology, the optical fiber operation data are automatically and correlatively analyzed, and the optical fiber core management efficiency is effectively improved.
Drawings
FIG. 1 is a flow chart of the steps of an optical cable core online management method of the present invention.
Fig. 2 is a schematic front view of an optical fiber distribution frame.
Fig. 3 is a schematic diagram of a conventional optical fiber structure.
FIG. 4 is a schematic view of a fiber structure with a fiber clamp according to the present invention.
Wherein, 1 is ordinary optic fibre connection buckle, 2 is fiber clip box, and 3 are fiber clip sub-buckles, and 4 are ODF optical cable bending region, and 5 are ordinary connection tail optical fibers.
For a person skilled in the art, other relevant figures can be obtained from the above figures without inventive effort.
Detailed Description
The technical scheme of the invention is further explained by combining the accompanying drawings as follows:
the invention provides an optical cable fiber core online management method based on infrared rays and ZigBee.
As shown in fig. 1, the method of the present invention comprises the steps of:
s1, clamping the optical fiber clip at the spare fiber core flange head of the distribution box;
s2, when the optical fiber service is put into use and quit, the optical fiber needs to be plugged and unplugged, the infrared sensing function of the optical fiber clip is triggered, and an optical fiber change signal is generated;
s3, transmitting information to the machine room gateway equipment through the optical fiber plugging signal by a ZiBee wireless technology;
s4, the gateway equipment transmits data to the optical cable fiber core online management system server through the transmission network;
s5, the optical cable fiber core on-line management system processes the data and displays the data dynamically and intuitively in real time
As shown in fig. 2-4, the optical fiber clip obtained in the above steps is composed of a female optical fiber clip button and a male optical fiber clip button, and infrared sensing functions are provided in the female optical fiber clip button and the male optical fiber clip button, so that an optical fiber change signal can be generated when an optical fiber is plugged in or pulled out.
The method adopts an infrared sensing function to identify the optical fiber plugging and unplugging action, then uses the ZigBee technology to transmit an action signal to the machine room wireless gateway equipment, transmits the action signal to the background server, and generates optical fiber data information at the Client terminal, thereby realizing the online real-time management of the optical fiber core. And the optical fiber clip is arranged on the fiber core of the optical cable and used for sensing the plugging action and controlling the operation condition of the optical core in real time. The method can set work order tasks in the background and comprehensively analyze the reasons of the action condition of the optical fiber: the optical fiber management system has the advantages that planned work, manual mistaken collision and the like are achieved, operation personnel can conveniently remotely control the operation field conditions, production safety is enhanced, real and reliable optical fiber operation data are provided by using a remote monitoring technology, the optical fiber operation data are automatically and correlatively analyzed, and the optical fiber core management efficiency is effectively improved.
The embodiments of the present invention have been described in detail with reference to the drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge of those skilled in the art without departing from the gist of the present invention.

Claims (4)

1. An optical cable fiber core online management method is characterized by comprising the following steps:
s1, clamping the optical fiber clip at the spare fiber core flange head of the distribution box;
s2, when the optical fiber service is put into use and quit, the optical fiber needs to be plugged and unplugged, the infrared sensing function of the optical fiber clip is triggered, and an optical fiber change signal is generated;
s3, transmitting information to the machine room gateway equipment through the optical fiber plugging signal by a ZiBee wireless technology;
s4, the gateway equipment transmits data to the optical cable fiber core online management system server through the transmission network;
and S5, the optical cable fiber core online management system processes the data and displays the data in real time, dynamically and intuitively.
2. The method for on-line management of the fiber core of the optical cable according to claim 1, wherein: the equipment comprises a cabinet, a distribution frame, instrument equipment and network equipment, wherein the instrument equipment comprises an optical fiber clip, and the network equipment comprises an optical fiber, a network cable, wireless gateway equipment, a server, a switch and a router.
3. The method for on-line management of the fiber core of the optical cable according to claim 1, wherein: in step S2, the optical fiber change signal is a signal generated by triggering the infrared sensing function of the fiber clamp with the insertion and extraction of the optical fiber.
4. The method for on-line management of the fiber core of the optical cable according to claim 1, wherein: the specific operation of step S5 is as follows:
s51, storing the data information of the change of the optical fiber clip into a database, and establishing a data storage table corresponding to the fiber core of the optical cable in the database;
and S52, displaying time information and the fiber core condition of the optical cable on the Client terminal according to the content in the data information, integrating the work order task setting in the current online management system, and comprehensively analyzing the optical fiber condition.
CN202010988033.7A 2020-09-18 2020-09-18 Optical cable fiber core online management method Pending CN112290998A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010988033.7A CN112290998A (en) 2020-09-18 2020-09-18 Optical cable fiber core online management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010988033.7A CN112290998A (en) 2020-09-18 2020-09-18 Optical cable fiber core online management method

Publications (1)

Publication Number Publication Date
CN112290998A true CN112290998A (en) 2021-01-29

Family

ID=74420080

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010988033.7A Pending CN112290998A (en) 2020-09-18 2020-09-18 Optical cable fiber core online management method

Country Status (1)

Country Link
CN (1) CN112290998A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102346860A (en) * 2011-09-16 2012-02-08 烽火通信科技股份有限公司 Method for wiring and managing optical fiber with electronic and manual dual-identification capabilities
CN102944263A (en) * 2012-11-13 2013-02-27 武汉理工光科股份有限公司 Cable tunnel multistate on-line monitoring system based on fiber grating sensing
CN104102933A (en) * 2014-06-20 2014-10-15 国家电网公司 Communication intelligent wiring identification device and use method
WO2017118149A1 (en) * 2016-01-07 2017-07-13 烽火通信科技股份有限公司 Method and apparatus for rapidly collecting fibre interconnection information
CN106972976A (en) * 2017-05-19 2017-07-21 烽火通信科技股份有限公司 Intelligent optical fiber wiring system and the implementation method for replacing electronic tag with fibre optical sensor
CN108599842A (en) * 2018-05-21 2018-09-28 中山水木光华电子信息科技有限公司 A method of the optical fiber distributing intelligent recognition based on optical fiber code, diagnosis
CN111458607A (en) * 2020-05-08 2020-07-28 国网宁夏电力有限公司培训中心 High-voltage cable sheath grounding circulation on-line monitoring terminal and on-line monitoring system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102346860A (en) * 2011-09-16 2012-02-08 烽火通信科技股份有限公司 Method for wiring and managing optical fiber with electronic and manual dual-identification capabilities
CN102944263A (en) * 2012-11-13 2013-02-27 武汉理工光科股份有限公司 Cable tunnel multistate on-line monitoring system based on fiber grating sensing
CN104102933A (en) * 2014-06-20 2014-10-15 国家电网公司 Communication intelligent wiring identification device and use method
WO2017118149A1 (en) * 2016-01-07 2017-07-13 烽火通信科技股份有限公司 Method and apparatus for rapidly collecting fibre interconnection information
CN106972976A (en) * 2017-05-19 2017-07-21 烽火通信科技股份有限公司 Intelligent optical fiber wiring system and the implementation method for replacing electronic tag with fibre optical sensor
CN108599842A (en) * 2018-05-21 2018-09-28 中山水木光华电子信息科技有限公司 A method of the optical fiber distributing intelligent recognition based on optical fiber code, diagnosis
CN111458607A (en) * 2020-05-08 2020-07-28 国网宁夏电力有限公司培训中心 High-voltage cable sheath grounding circulation on-line monitoring terminal and on-line monitoring system

Similar Documents

Publication Publication Date Title
CN109669406A (en) A kind of remote online monitoring system and its workflow of industrial equipment
CN105337422B (en) Intelligence based on Internet of Things supplies Distribution Management System
CN105022369A (en) Intelligent monitoring system of sewage treatment plant
CN101902075A (en) Remote video monitoring system of intelligent substation based on electric power data network
CN109561155B (en) Remote centralized monitoring and operation and maintenance method for substation equipment
CN111459103A (en) Loom communication system based on MCGS configuration screen
CN110942163A (en) Intelligent maintenance method and system based on big data
CN201738931U (en) Shield remote monitoring system
CN201830020U (en) Remote video monitoring system of intelligent transformer substation based on electric power data network
CN105577428A (en) Intelligent substation virtual loop comprehensive monitoring system based on multidimensional information acquisition
CN101916082A (en) Remote monitoring system for shield machine
CN112290998A (en) Optical cable fiber core online management method
CN105048639A (en) SCD (substation configuration description) modeling-based substation power source system monitoring system
CN112612360A (en) Three-dimensional visualization equipment monitoring system and method based on VR technology
CN104064982A (en) Multi-dimensional display method for intelligent substation failure information
CN104965497B (en) Online creation data quickly generates and management method and system
CN204591275U (en) A kind of remote control for many stage casings ore pass ore drawing
CN104467174A (en) Transformer station monitoring alarm information auxiliary processing system
CN116131467A (en) Can monitor controllable thing networking block terminal
CN214795982U (en) Intelligent management system for drilling of coal mine
CN209803613U (en) Plastic mechanical equipment monitoring device and system
CN107920230A (en) Video monitoring image secondary-confirmation system and method
CN104092307A (en) Smart substation secondary device operation state monitoring method
CN103336213A (en) In-situ diagnostic method and device used for on-line monitoring of transformer substation
CN104868593B (en) Power utilization information acquisition terminal communication message local real-time monitoring method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210129

RJ01 Rejection of invention patent application after publication