CN112282407A - 一种工业抗爆墙结构加固的方法 - Google Patents
一种工业抗爆墙结构加固的方法 Download PDFInfo
- Publication number
- CN112282407A CN112282407A CN202010917280.8A CN202010917280A CN112282407A CN 112282407 A CN112282407 A CN 112282407A CN 202010917280 A CN202010917280 A CN 202010917280A CN 112282407 A CN112282407 A CN 112282407A
- Authority
- CN
- China
- Prior art keywords
- wall
- steel plates
- steel
- explosion
- blast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Electrochemistry (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
本发明公开了一种工业抗爆墙结构加固的方法,通过以下步骤实现:(1)根据墙壁的厚度和高度,选择合适的钢板;(2)在两钢板、抗爆墙及角钢上的相应的位置打孔,并清除抗爆墙两侧的灰尘;(3)在抗爆墙的两侧及两钢板上涂结构胶,并将钢板粘贴在抗爆墙上;(4)在抗爆墙内侧钢板上的固定角钢;(5)使用对拉螺栓将抗爆墙、角钢及两钢板固定为一个整体。本发明能够对抗爆墙进行加固,使其能够满足正常的工作要求。
Description
技术领域
本发明涉及一种工业抗爆墙结构加固的方法。
背景技术
在石油、化工、天然气接收站及储运库等行业中,工业抗爆墙加固应用案例很少,且目前我国在化工厂建设、使用中出现的各种缺陷、各种影响正常使用的问题日渐增多,现有的加固方案参差不齐,对施工水平的要求高低各异,导致加固效果往往不能达到预期。
发明内容
本发明提供了一种工业抗爆墙结构加固的方法,能够满足工业抗爆墙加固后的正常使用的要求。
为了解决上述技术问题,本发明提供了一种工业抗爆墙结构加固的方法,(1)计算分析抗爆墙的厚度和高度,并根据计算结果,选择两块厚度和宽度都匹配的钢板;(2)在抗爆墙、角钢以及两钢板的对应位置处进行打孔,并清理掉抗爆墙的内外两侧面灰尘;(3)分别在抗爆墙的两侧面和两钢板的其中一面上涂抹结构胶,将两钢板粘贴在抗爆墙的两侧面上粘贴钢板,并使两钢板上的开孔和抗爆墙上的开孔对准;(4)在抗爆墙的侧面粘贴的钢板的上下两边上固定角钢,固定角钢时,要保证角钢的开孔和两钢板的开孔对准;(5)将对拉螺栓分别穿入两钢板和抗爆墙上开孔所组成的通孔,以及抗爆墙、角钢和两钢板上的开孔所组成通孔内,在对拉螺栓的两端套接螺母,并锁紧,抗爆墙的加固即完成。
进一步的,在步骤(2)中,两钢板打孔的位置分别位于两钢板的中部和两钢板的上下两边上。
进一步的,在步骤(4)中,只在抗爆墙内侧面粘贴的钢板的上下两边上固定角钢。
本发明的技术效果在于:本发明旨在于解决抗爆墙的加固问题,首先对抗爆墙、钢板及角钢的相对应的位置进行打孔,对抗爆墙的两面进行灰尘清理,在抗爆墙的两面和钢板的一面涂抹结构胶,并把钢板粘贴在抗爆墙的两面上,并在钢板的上下两边上固定角钢,对拉螺栓穿过三者的通孔,并在对拉螺栓的两端套接螺母,本发明提供的加固方法,操作简单,能够满足抗爆墙加固要求和加固后抗爆墙正常使用的要求。
附图说明
图1是本发明中一个优选实施例中的主视图。
图2是本发明中一个优选实施例中的局部示意图(上部角钢位置)。
图3是本发明中一个优选实施例中的局部示意图(抗爆墙中部位置)。
图4是本发明中一个优选实施例中的局部示意图(下部角钢位置)
附图标记:抗爆墙-1;对拉螺栓-2;外侧钢板-3;角钢-4;内侧钢板-5。
具体实施方式
下面结合附图和具体实施例对本发明作进一步说明,以使本领域的技术人员可以更好的理解本发明并能予以实施,但所举实施例不作为对本发明的限定。
实施例,如图1到图4所示,本发明公开了一种工业抗爆墙结构加固的方法,通过以下步骤实现:(1)计算分析抗爆墙1的厚度和高度,并根据计算结果,选择两块厚度和宽度都匹配的钢板;(2)在抗爆墙1、角钢4以及两钢板(3、5)的对应位置处进行打孔,并清理掉抗爆墙1的内外两侧面灰尘;(3)分别在抗爆墙1的两侧面和两钢板(3、5)的其中一面上涂抹结构胶,将两钢板(3、5)粘贴在抗爆墙1的两侧面上粘贴钢板,并使两钢板(3、5)上的开孔和抗爆墙1上的开孔对准;(4)在抗爆墙1的侧面粘贴的钢板的上下两边上固定角钢4,固定角钢4时,要保证角钢4的开孔和两钢板(3、5)的开孔对准;(5)将对拉螺栓2分别穿入两钢板(3、5)和抗爆墙1上开孔所组成的通孔,以及抗爆墙1、角钢4和两钢板(3、5)上的开孔所组成通孔内,在对拉螺栓2的两端套接螺母,并锁紧,抗爆墙1的加固即完成。
本实施例中,在步骤(2)中,两钢板打孔(3、5)的位置分别位于两钢板(3、5)的中部和两钢板(3、5)的上下两边上。
本实施例中,在步骤(4)中,只在抗爆墙1内侧面粘贴的钢板的上下两边上固定角钢4。
本实施例中,钢板厚度及宽度须经结构力学公式确定N≤fy0As0+fspAsp。公式中:N--由爆炸荷载引起的墙体截面内力;fy0--墙体中受力钢筋的抗拉强度设计值;fsp--加固钢板的抗拉强度;AS0、Asp--分别为墙体钢筋与加固钢板的截面面积。
计算原理:在设计爆炸荷载作用下,墙体截面手拉区域由钢筋承担拉应力,受压区由混凝土承担压应力,此时墙体结构处于弹性工作阶段,自身没有发生变形,可继续正常使用;一旦实际的爆炸荷载超出设计荷载,或者存在不可遇见性的荷载工况(例如高于本地区设防烈度的地震)与爆炸工况同时作用,则抗暴墙体可能会进入弹塑性工作状态,墙体产生竖向裂缝,此时通过加固钢板通过粘结与对拉的作用,与墙体内外面有效的结合,增加了钢筋与墙体协调工作的能力,避免由于局部开裂引起钢筋退出工作的情况发生,加固之后,设计爆炸产生的截面拉应力N由墙体钢筋AS0与加固钢板ASP共同承担。加固钢板的截面面积按照上述公式,由已知条件(N、fy0、AS0、Asp)计算得出。
本实施例中,如图1所示,抗爆墙1内侧面为图中右侧,外侧面为图中左侧,值得说明的是,本实施例中,抗爆墙1的内侧面顶部设有向左延伸的墙体,在安装角钢4时,角钢4的两个互相垂直的平面分别紧贴抗爆墙1的内侧面和抗爆墙1顶部向左延伸的墙体上。
本实施例中,在步骤(2)中在抗爆墙1、角钢4及两钢板(3、5)对应位置处打孔,具体来说,打孔的高度、间距以及孔径都是相同,以保证步骤(3)和步骤(4)在安装时抗爆墙1、角钢4以及两钢板(3、5)上同一位置的孔能够重合。
本实施例中,在步骤(2)中,在对抗爆墙1、角钢4及两钢板(3、5)进行打孔后,需要对抗爆墙1进行除灰尘处理,以保证让贴合的钢板更加牢固。
本实施例中,在步骤(5)中,在抗爆墙1、角钢4及两钢板(3、5)所形成的通孔中插入对拉螺栓2,对拉螺栓2的两端伸出角钢4或两钢板(3、5)之外,以保证对拉螺栓2上能够安装螺母。
本实施例中,在抗爆墙1上打6排孔,其中最上层的一排孔和最下层的一排孔的位置分别安装角钢4。
可以理解的是,本发明具体通过以下步骤实现:(1)通过对墙体的裂缝的位置确认,结合原设计推出爆炸作用力的影响范围,此范围即为钢板的宽度,根据结构力学公式,N≤fy0As0+fspAsp,由已经条件N、fy0、AS0、Asp,计算出加固钢板的厚度。
(2)在抗爆墙1上自上而下依次打4排孔,并在两钢板(3、5)和角钢4上,同间距、同数量及同位置的地方进行相应的打孔,并在打孔后清除抗爆墙1两侧面的灰尘;(3)在抗爆墙1的两侧面上均匀涂抹结构胶,并在两钢板(3、5)的其中一面上涂抹结构胶,将两钢板(3、5)和抗爆墙1涂抹结构胶的平面贴合在一起,并清除抗爆墙1和两钢板(3、5)开口处的结构胶,以保证对拉螺栓2能够穿入通孔中;(4)在内侧钢板5的上下边缘处焊接固定角钢4,外侧钢板3不固定角钢4,焊接时要保证角钢4上的孔与抗爆墙1和两钢板(3、5)形成的通孔重合;(5)将对拉螺栓2插入到抗爆墙1、角钢4及两钢板(3、5)上的通孔内,并保证对拉螺栓2的两端伸出钢板或角钢4之外,将螺母旋接于对拉螺栓2的两端,并锁紧,如图2、图3和图4所示,螺母压靠于角钢4或内侧钢板5上。
以上所述实施例仅是为充分说明本发明而所举的较佳的实施例,本发明的保护范围不限于此。本技术领域的技术人员在本发明基础上所作的等同替代或变换,均在本发明的保护范围之内。本发明的保护范围以权利要求书为准。
Claims (3)
1.一种工业抗爆墙结构加固的方法,通过以下步骤实现,其特征在于:
(1)计算分析抗爆墙的厚度和高度,并根据计算结果,选择两块厚度和宽度都匹配的钢板;
(2)在抗爆墙、角钢以及两钢板的对应位置处进行打孔,并清理掉抗爆墙的内外两侧面灰尘;
(3)分别在抗爆墙的两侧面和两钢板的其中一面上涂抹结构胶,将两钢板粘贴在抗爆墙的两侧面上粘贴钢板,并使两钢板上的开孔和抗爆墙上的开孔对准;
(4)在抗爆墙的侧面粘贴的钢板的上下两边上固定角钢,固定角钢时,要保证角钢的开孔和两钢板的开孔对准;
(5)将对拉螺栓分别穿入两钢板和抗爆墙上开孔所组成的通孔,以及抗爆墙、角钢和两钢板上的开孔所组成通孔内,在对拉螺栓的两端套接螺母,并锁紧,抗爆墙的加固即完成。
2.根据权利要求1所述的工业抗爆墙结构加固的方法,其特征在于:在步骤(2)中,两钢板打孔的位置分别位于两钢板的中部和两钢板的上下两边上。
3.根据权利要求1所述的工业抗爆墙结构加固的方法,其特征在于:在步骤(4)中,只在抗爆墙内侧面粘贴的钢板的上下两边上固定角钢。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010917280.8A CN112282407A (zh) | 2020-09-03 | 2020-09-03 | 一种工业抗爆墙结构加固的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010917280.8A CN112282407A (zh) | 2020-09-03 | 2020-09-03 | 一种工业抗爆墙结构加固的方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112282407A true CN112282407A (zh) | 2021-01-29 |
Family
ID=74419707
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010917280.8A Pending CN112282407A (zh) | 2020-09-03 | 2020-09-03 | 一种工业抗爆墙结构加固的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112282407A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114856242A (zh) * | 2021-11-17 | 2022-08-05 | 天津大学 | 墙体用抗爆加固结构及其抗爆墙体 |
CN114935515A (zh) * | 2022-05-18 | 2022-08-23 | 南京理工大学 | 一种防护门的抗爆性能测试装置 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20040123541A1 (en) * | 2002-12-27 | 2004-07-01 | Jewett Scott E. | Reinforced wall structure for blast protection |
CN104790684A (zh) * | 2015-05-07 | 2015-07-22 | 山东建筑大学 | 采用外包角钢法的墙体开洞施工方法 |
CN109812046A (zh) * | 2019-03-27 | 2019-05-28 | 中建四局第一建筑工程有限公司 | 一种对拉式钢板剪力墙加固施工结构及方法 |
CN111236726A (zh) * | 2019-02-19 | 2020-06-05 | 广东菲力绿色板业有限公司 | 一种抗爆墙 |
-
2020
- 2020-09-03 CN CN202010917280.8A patent/CN112282407A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20040123541A1 (en) * | 2002-12-27 | 2004-07-01 | Jewett Scott E. | Reinforced wall structure for blast protection |
CN104790684A (zh) * | 2015-05-07 | 2015-07-22 | 山东建筑大学 | 采用外包角钢法的墙体开洞施工方法 |
CN111236726A (zh) * | 2019-02-19 | 2020-06-05 | 广东菲力绿色板业有限公司 | 一种抗爆墙 |
CN109812046A (zh) * | 2019-03-27 | 2019-05-28 | 中建四局第一建筑工程有限公司 | 一种对拉式钢板剪力墙加固施工结构及方法 |
Non-Patent Citations (1)
Title |
---|
唐红元: "《既有建筑结构检测鉴定与加固》", 30 June 2017, 西南交通大学出版社 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114856242A (zh) * | 2021-11-17 | 2022-08-05 | 天津大学 | 墙体用抗爆加固结构及其抗爆墙体 |
CN114935515A (zh) * | 2022-05-18 | 2022-08-23 | 南京理工大学 | 一种防护门的抗爆性能测试装置 |
CN114935515B (zh) * | 2022-05-18 | 2023-03-14 | 南京理工大学 | 一种防护门的抗爆性能测试装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112282407A (zh) | 一种工业抗爆墙结构加固的方法 | |
KR101253519B1 (ko) | 콘크리트 충전 강관기둥을 이용한 기존 건축물의 내진보강 공법 | |
KR100665967B1 (ko) | 복공판 | |
US20120297720A1 (en) | Building Metal Frame, and Method of Making, and Components Therefor Including Column Assemblies and Full-Length Beam Assemblies | |
JP4992479B2 (ja) | 柱部材、ufc製プレキャスト型枠および当該ufc製プレキャスト型枠を用いた柱部材の耐震補強方法 | |
US20150191904A1 (en) | Composite structure | |
Dubina et al. | Cyclic tests of double-sided beam-to-column joints | |
US20100043348A1 (en) | Building metal frame, and method of making, and components therefor including column assemblies and full-length beam assemblies | |
Tsavdaridis et al. | FE parametric study of RWS/WUF-B moment connections with elliptically-based beam web openings under monotonic and cyclic loading | |
JP6717782B2 (ja) | 既設フーチングの補強方法 | |
CN216405826U (zh) | 一种l形单角码装配加劲的双钢板混凝土组合剪力墙 | |
KR101991938B1 (ko) | 콘크리트 기둥 내진 보강장치 및 그 방법 | |
KR20210051586A (ko) | 와이어 및 보강판을 이용한 철근콘크리트 구조물의 보강공법 | |
EP1948877A2 (en) | Suspended deck for liquid natural gas tank | |
JP6996544B2 (ja) | 既存構造物の耐震改修方法 | |
JP4377808B2 (ja) | 耐震補強パネル及びそれを用いた耐震補強方法 | |
US8122672B2 (en) | Building metal frame, and method of making, and components therefor including column assemblies and full-length beam assemblies | |
CN220394910U (zh) | 一种加强型工业抗爆墙 | |
CN103669587A (zh) | 钢骨构造物制造方法 | |
JP2010229801A (ja) | 建築工法 | |
KR20090115097A (ko) | 강관 버팀보 연결구조 | |
JP2004353319A (ja) | 円筒型タンクの構築方法 | |
JP7360039B2 (ja) | 鋼矢板壁および鋼矢板壁の製造方法 | |
Kitano et al. | Experimental study on the strengthening and repair of R/C wall-frame structures with an opening by CF-sheets or CF-grids | |
JP6070009B2 (ja) | 煙突筒身設置方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20210129 |
|
RJ01 | Rejection of invention patent application after publication |