CN112180851B - 生产流水线的控制方法、装置、计算机设备和存储介质 - Google Patents
生产流水线的控制方法、装置、计算机设备和存储介质 Download PDFInfo
- Publication number
- CN112180851B CN112180851B CN202010915697.0A CN202010915697A CN112180851B CN 112180851 B CN112180851 B CN 112180851B CN 202010915697 A CN202010915697 A CN 202010915697A CN 112180851 B CN112180851 B CN 112180851B
- Authority
- CN
- China
- Prior art keywords
- production
- production line
- control strategy
- target
- energy consumption
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000004519 manufacturing process Methods 0.000 title claims abstract description 596
- 238000000034 method Methods 0.000 title claims abstract description 104
- 238000003860 storage Methods 0.000 title claims abstract description 15
- 238000011217 control strategy Methods 0.000 claims abstract description 184
- 238000005265 energy consumption Methods 0.000 claims description 198
- 230000007613 environmental effect Effects 0.000 claims description 157
- 230000002159 abnormal effect Effects 0.000 claims description 99
- 230000008569 process Effects 0.000 claims description 48
- 230000009467 reduction Effects 0.000 claims description 18
- 238000004590 computer program Methods 0.000 claims description 15
- 238000007726 management method Methods 0.000 description 61
- 239000000047 product Substances 0.000 description 44
- 238000001514 detection method Methods 0.000 description 12
- 238000004458 analytical method Methods 0.000 description 11
- 239000003344 environmental pollutant Substances 0.000 description 10
- 231100000719 pollutant Toxicity 0.000 description 10
- 238000004891 communication Methods 0.000 description 6
- 238000010586 diagram Methods 0.000 description 6
- 230000000694 effects Effects 0.000 description 6
- 239000011265 semifinished product Substances 0.000 description 5
- 239000002351 wastewater Substances 0.000 description 5
- 238000012544 monitoring process Methods 0.000 description 4
- 238000005457 optimization Methods 0.000 description 4
- 238000004364 calculation method Methods 0.000 description 3
- 238000012545 processing Methods 0.000 description 3
- 230000003044 adaptive effect Effects 0.000 description 2
- 238000012790 confirmation Methods 0.000 description 2
- 238000013500 data storage Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 230000004044 response Effects 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 238000012351 Integrated analysis Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 239000012467 final product Substances 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 239000004973 liquid crystal related substance Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 238000000746 purification Methods 0.000 description 1
- 239000010865 sewage Substances 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 238000005303 weighing Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/418—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
- G05B19/41865—Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B2219/00—Program-control systems
- G05B2219/30—Nc systems
- G05B2219/32—Operator till task planning
- G05B2219/32252—Scheduling production, machining, job shop
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/02—Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Quality & Reliability (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Automation & Control Theory (AREA)
- General Factory Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010915697.0A CN112180851B (zh) | 2020-09-03 | 2020-09-03 | 生产流水线的控制方法、装置、计算机设备和存储介质 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010915697.0A CN112180851B (zh) | 2020-09-03 | 2020-09-03 | 生产流水线的控制方法、装置、计算机设备和存储介质 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112180851A CN112180851A (zh) | 2021-01-05 |
CN112180851B true CN112180851B (zh) | 2022-03-08 |
Family
ID=73925325
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010915697.0A Active CN112180851B (zh) | 2020-09-03 | 2020-09-03 | 生产流水线的控制方法、装置、计算机设备和存储介质 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112180851B (zh) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113421005B (zh) * | 2021-07-01 | 2022-12-06 | 润联软件系统(深圳)有限公司 | 工序数据和管理协同方法、装置、计算机设备及存储介质 |
WO2023039729A1 (zh) * | 2021-09-14 | 2023-03-23 | 西门子(中国)有限公司 | 一种生产计划的评估方法、装置及计算机可读存储介质 |
CN114449023B (zh) | 2022-04-11 | 2022-06-17 | 成都秦川物联网科技股份有限公司 | 双前分平台式工业物联网及其控制方法 |
CN114462895A (zh) * | 2022-04-12 | 2022-05-10 | 青岛华正信息技术股份有限公司 | 用于企业的数字化转型管理方法及系统 |
CN115035504B (zh) * | 2022-06-01 | 2024-06-21 | 浙江衣拿智能科技股份有限公司 | 一种烘干运载系统的控制方法、装置及电子设备 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002100548A (ja) * | 2000-09-21 | 2002-04-05 | Hitachi Ltd | 半導体デバイスの歩留り予測システム、歩留り予測方法、半導体デバイスの設計方法 |
CN101055635A (zh) * | 2006-04-04 | 2007-10-17 | 日立环球储存科技荷兰有限公司 | 生产计划方法和生产计划系统 |
CN103679322A (zh) * | 2012-10-24 | 2014-03-26 | 杭州金色能源科技有限公司 | 生产数据处理方法、装置及系统 |
CN108121306A (zh) * | 2016-11-28 | 2018-06-05 | 财团法人资讯工业策进会 | 排程系统及方法 |
CN207586733U (zh) * | 2017-12-11 | 2018-07-06 | 日立楼宇技术(广州)有限公司 | 生产线控制系统 |
CN109034671A (zh) * | 2018-09-06 | 2018-12-18 | 深圳百胜扬工业电子商务平台发展有限公司 | 工厂产线目标产品生产时长确定方法及装置 |
CN109741210A (zh) * | 2018-12-25 | 2019-05-10 | 安徽三马信息科技有限公司 | 一种智慧工业综合能源管理系统 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003141214A (ja) * | 2001-10-30 | 2003-05-16 | Mitsubishi Electric Corp | 生産計画作成システム、生産計画作成方法、および生産計画の作成をコンピュータに実行させるためのプログラム |
-
2020
- 2020-09-03 CN CN202010915697.0A patent/CN112180851B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002100548A (ja) * | 2000-09-21 | 2002-04-05 | Hitachi Ltd | 半導体デバイスの歩留り予測システム、歩留り予測方法、半導体デバイスの設計方法 |
CN101055635A (zh) * | 2006-04-04 | 2007-10-17 | 日立环球储存科技荷兰有限公司 | 生产计划方法和生产计划系统 |
CN103679322A (zh) * | 2012-10-24 | 2014-03-26 | 杭州金色能源科技有限公司 | 生产数据处理方法、装置及系统 |
CN108121306A (zh) * | 2016-11-28 | 2018-06-05 | 财团法人资讯工业策进会 | 排程系统及方法 |
CN207586733U (zh) * | 2017-12-11 | 2018-07-06 | 日立楼宇技术(广州)有限公司 | 生产线控制系统 |
CN109034671A (zh) * | 2018-09-06 | 2018-12-18 | 深圳百胜扬工业电子商务平台发展有限公司 | 工厂产线目标产品生产时长确定方法及装置 |
CN109741210A (zh) * | 2018-12-25 | 2019-05-10 | 安徽三马信息科技有限公司 | 一种智慧工业综合能源管理系统 |
Also Published As
Publication number | Publication date |
---|---|
CN112180851A (zh) | 2021-01-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112180851B (zh) | 生产流水线的控制方法、装置、计算机设备和存储介质 | |
US11900287B2 (en) | Model predictive maintenance system with budgetary constraints | |
US11409274B2 (en) | Model predictive maintenance system for performing maintenance as soon as economically viable | |
US8155795B2 (en) | Demand control system, demand controller, demand program, and demand controlling method | |
JP5602878B2 (ja) | 発電プラントに対する負荷スケジューリングを最適化する方法及び制約解析モジュール | |
JP5276294B2 (ja) | 負荷低減計画策定システム及びデマンド制御システム | |
AU2010337991B2 (en) | Method and control system for scheduling load of a power plant | |
US20120319642A1 (en) | Power supply device, power storage device, and power control device | |
JP2007018322A (ja) | 省エネルギー量推定装置、方法、およびプログラム | |
JP4512074B2 (ja) | エネルギー需要予測方法、予測装置、プログラム及び記録媒体 | |
US6988024B2 (en) | Cogeneration system, operation controller for cogeneration facility, and operation program for cogeneration facility | |
Hummen et al. | When to replace products with which (circular) strategy? An optimization approach and lifespan indicator | |
JP2007104775A (ja) | 複合電源におけるエネルギー需給方法、および、エネルギー需給装置 | |
CN116187549A (zh) | 能耗预测方法、计算设备及计算机存储介质 | |
CN110442170B (zh) | 设备运行及监测方法、装置、设备及介质 | |
CN102722754B (zh) | 焦化行业基于专家系统的煤气动态平衡调度方法及系统 | |
CN112134275B (zh) | 一种计算含风电场电力系统的可靠性方法及系统 | |
CN115940301A (zh) | 一种功率因数的控制方法、装置、设备及存储介质 | |
CN115879655A (zh) | 一种电网企业的减排方案优化方法及系统 | |
CN114696328A (zh) | 电力线损分析方法、系统及存储介质 | |
JP6606368B2 (ja) | 熱源電源機器の運転計画演算方法及び運転計画演算サーバー | |
CN202647189U (zh) | 基于动态平衡调度的煤气系统 | |
JP2018182990A (ja) | 発電機運転制御装置、及び発電機運転制御方法 | |
JP7125383B2 (ja) | 情報処理装置、情報処理方法、および情報処理プログラム | |
CN116505593B (zh) | 综合能源设备控制方法、装置、电子设备及存储介质 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information |
Inventor after: Liu Dong Inventor after: Huang Jinfu Inventor after: Lu Tingjie Inventor after: Wang Xinjun Inventor after: Ma Pengyu Inventor after: Yu Jiaxin Inventor after: Li Zhiwu Inventor before: Liu Dong Inventor before: Huang Jinfu Inventor before: Lu Tingjie Inventor before: Wang Xinjun Inventor before: Ma Pengyu Inventor before: Yu Jiaxin |
|
CB03 | Change of inventor or designer information |