CN112177338A - Concrete production and processing is with mechanism of pouring fast - Google Patents

Concrete production and processing is with mechanism of pouring fast Download PDF

Info

Publication number
CN112177338A
CN112177338A CN202011064629.4A CN202011064629A CN112177338A CN 112177338 A CN112177338 A CN 112177338A CN 202011064629 A CN202011064629 A CN 202011064629A CN 112177338 A CN112177338 A CN 112177338A
Authority
CN
China
Prior art keywords
pouring
concrete
hopper
quick
processing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011064629.4A
Other languages
Chinese (zh)
Inventor
张鼎伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Feiqiang Concrete Co ltd
Original Assignee
Chongqing Feiqiang Concrete Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Feiqiang Concrete Co ltd filed Critical Chongqing Feiqiang Concrete Co ltd
Priority to CN202011064629.4A priority Critical patent/CN112177338A/en
Publication of CN112177338A publication Critical patent/CN112177338A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/04Devices for both conveying and distributing
    • E04G21/0418Devices for both conveying and distributing with distribution hose
    • E04G21/0436Devices for both conveying and distributing with distribution hose on a mobile support, e.g. truck
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28CPREPARING CLAY; PRODUCING MIXTURES CONTAINING CLAY OR CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28C5/00Apparatus or methods for producing mixtures of cement with other substances, e.g. slurries, mortars, porous or fibrous compositions
    • B28C5/08Apparatus or methods for producing mixtures of cement with other substances, e.g. slurries, mortars, porous or fibrous compositions using driven mechanical means affecting the mixing
    • B28C5/10Mixing in containers not actuated to effect the mixing
    • B28C5/12Mixing in containers not actuated to effect the mixing with stirrers sweeping through the materials, e.g. with incorporated feeding or discharging means or with oscillating stirrers
    • B28C5/16Mixing in containers not actuated to effect the mixing with stirrers sweeping through the materials, e.g. with incorporated feeding or discharging means or with oscillating stirrers the stirrers having motion about a vertical or steeply inclined axis
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/025Buckets specially adapted for use with concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a quick pouring mechanism for concrete production and processing, which comprises a pouring receiving hopper, wherein the bottom of the pouring receiving hopper is provided with a workbench, the top of the workbench is provided with a buffer device, a partition plate is embedded in the bottom end of the pouring receiving hopper, the bottom of the partition plate is provided with an upper cavity, the bottom of the upper cavity is provided with a lower cavity, the inside of the upper cavity is provided with a rotating motor, one side of the partition plate, which is far away from the rotating motor, is provided with a rotating shaft, the side surface of the workbench is provided with a first control switch, the inside of the lower cavity is provided with a quick discharging device, one side of the pouring receiving hopper is provided with a conveying device, and; according to the rapid pouring mechanism for producing and processing concrete, the conveying device is arranged, so that the rubber tube can be moved to a pouring position more conveniently, and labor is saved; through the buffer that sets up, can cushion the hopper effectively.

Description

Concrete production and processing is with mechanism of pouring fast
Technical Field
The invention relates to the technical field of construction equipment, in particular to a quick pouring mechanism for concrete production and processing.
Background
Due to the rapid development of the urban scale, a large number of farmers and civilians rush into the city, the urban land is more and more in short supply, and the development of high-rise buildings is promoted. For the construction of the floor slab of the high-rise building, the concrete precast slab is not used, and the reinforcing mesh concrete is poured and formed to ensure enough strength. The concrete pouring is a process of pouring concrete into a mold until the concrete is plasticized, and in the civil engineering and construction work, the concrete and other materials are poured into the mold to form a preset shape, the free height of the concrete is not more than 2m when the concrete is poured, and corresponding measures are taken when the free height of the concrete exceeds 3 m. At present, a chestnut conveying vehicle is used for pouring concrete to an upstairs construction position, a rubber pipe is used as a pouring pipe at a discharge end of the chestnut conveying vehicle, the rubber pipe is manually held in the construction process and is moved to a pouring position, and the concrete is poured into the pouring position from the inside of the rubber pipe.
In the existing device, concrete needs to be stored in the receiving hopper for caching, and in the process, the concrete impacts the receiving hopper, so that the receiving hopper generates rigid vibration and is abraded, and the service life of the receiving hopper is shortened; in the existing device, if concrete is placed in the receiving hopper for a long time, a solidification state occurs, which is not beneficial to the use of the concrete; in the existing device, a switch of pumping equipment is positioned on a workbench, if the pumping equipment is required to be closed, another operator is required to close the pumping equipment, and the operation is very troublesome; the existing device has the disadvantages that the rubber tube is heavy, and particularly, when concrete flows out of the rubber tube, the rubber tube has large impact force, so that the rubber tube can be moved to a pouring position by a plurality of persons exerting force simultaneously, time and labor are wasted, and the labor intensity is high.
Disclosure of Invention
The invention aims to provide a quick pouring mechanism for concrete production and processing aiming at the defects of the prior art, and the quick pouring mechanism is used for solving the problems that a receiving hopper is abraded due to rigid vibration, concrete is placed in the receiving hopper for a long time, a solidification state and pumping equipment are troublesome to close, and a rubber pipe is moved to a pouring position, so that time and labor are wasted, and the labor intensity is high.
In order to achieve the purpose, the invention provides the following technical scheme: including pouring and connect the hopper, the bottom of pouring and connecting the hopper is provided with the workstation, the top of workstation is provided with buffer, it has the baffle to pour the inside inlaying in bottom that connects the hopper, the bottom of baffle is provided with the cavity, the bottom of going up the cavity is provided with down the cavity, the inside of going up the cavity is provided with the rotating electrical machines, one side that the rotating electrical machines was kept away from to the baffle is provided with the rotation axis, the side surface of workstation is provided with first control switch, the inside of cavity is provided with quick discharging device down, it is provided with conveyer to pour one side that connects the hopper, conveyer's top is provided with fixed establishment.
As a preferred technical scheme of the invention, the buffer device consists of a sliding groove, a sliding block and a buffer spring, wherein the sliding groove is arranged at one side of the workbench close to the pouring receiving hopper in a penetrating manner, the sliding block is arranged inside the sliding groove, and the buffer spring is arranged at one side of the sliding block close to the pouring receiving hopper.
According to the preferable technical scheme, the number of the buffer devices is two, the buffer devices are symmetrically arranged relative to the pouring receiving hopper, the sliding block is in a convex shape, the size of the outer surface of the sliding block is matched with the size of the inner diameter of the sliding groove, one end of the buffer spring is fixedly connected with the side surface of the sliding block, the other side of the buffer spring is fixedly connected with the side surface of the pouring receiving hopper, a groove is arranged in the center of the top of the workbench in a penetrating mode, and the pouring receiving hopper is sleeved and connected with the inner portion of the groove.
As a preferred technical scheme of the invention, the number of the partition plates is three, the partition plates sequentially include an upper partition plate, a middle partition plate and a lower partition plate from top to bottom, an upper chamber is arranged between the upper partition plate and the middle partition plate, a lower chamber is arranged between the middle partition plate and the lower partition plate, the rotating motor is arranged in the upper chamber and fixedly connected with the middle partition plate, an output end of the rotating motor penetrates through the pouring receiving hopper and extends into the pouring receiving hopper, and is fixedly connected with the center of the bottom of the rotating shaft, and the first control switch is electrically connected with the rotating motor.
As a preferred technical solution of the present invention, the rapid discharging device comprises a liquid pump, a liquid pumping pipe, a liquid outlet pipe, a rubber pipe, a mounting ring and a second control switch, wherein the liquid pumping pump is arranged inside the lower cavity, the liquid pumping pipe is fixedly connected to the right side of the liquid pumping pump, the liquid outlet pipe is fixedly connected to the left side of the liquid pumping pump, the rubber pipe is arranged at the bottom of the lower cavity, the mounting ring is fixedly connected to one end of the rubber pipe, which is far away from the lower cavity, and the second control switch is arranged at the top of the mounting ring.
As a preferred technical solution of the present invention, the liquid pump is fixedly connected to the top center of the lower partition plate, the other end of the liquid pumping pipe penetrates through the upper cavity and extends into the pouring hopper, the other end of the liquid outlet pipe penetrates through the rubber pipe and extends into the rubber pipe, the inner diameter of the mounting ring is matched with the outer surface of the rubber pipe, and the second control switch is electrically connected to the liquid pump.
According to the preferable technical scheme, the conveying device comprises a track conveying plate, a sleeve, a lifting column, a limiting hole and a positioning pin, the track conveying plate is arranged on one side of the pouring receiving hopper, the sleeve is fixedly connected to the top of the track conveying plate, the lifting column is arranged on one side, away from the track conveying plate, of the sleeve, the limiting hole penetrates through the side surface of the lifting column, and the positioning pin is arranged on the outer surface of the sleeve.
As a preferred technical scheme, the inner diameter of the sleeve is matched with the outer surface of the lifting column, the number of the limiting holes is a plurality of groups, the limiting holes are linearly distributed on the side surface of the lifting column at equal intervals, the side surface of the sleeve is also provided with the limiting holes in a penetrating mode, the limiting holes in the outer surface of the sleeve are matched with the limiting holes in the outer surface of the lifting column, and the inner diameter of the limiting holes is matched with the outer surface of the positioning pins.
As a preferred technical scheme, the fixing mechanism comprises a clamping block, a fixing spring and a threaded column, the top of the lifting column is fixedly connected with the fixing mechanism, the clamping block is arranged inside the fixing mechanism, the fixing spring is arranged at one end, close to the fixing mechanism, of the clamping block, and the threaded column is arranged at the top of the fixing mechanism.
As a preferred technical scheme of the invention, the fixing mechanism is annular, the inner diameter of the fixing mechanism is larger than the outer surface of the rubber tube, the clamping block is semicircular, the inner diameter of the clamping block is matched with the outer surface of the rubber tube, two groups of fixing springs are arranged and are symmetrically arranged relative to the threaded columns, one end of each fixing spring is fixedly connected with the inner side wall of the fixing mechanism, the other end of each fixing spring is fixedly connected with the top of the clamping block, a threaded hole penetrates through the center of the top of the fixing mechanism, and the threaded columns are in threaded connection with the threaded holes.
Compared with the prior art, the invention provides a quick pouring mechanism for concrete production and processing, which has the following beneficial effects:
1. this concrete production and processing is with mechanism of pouring fast, when pouring the concrete and connect the hopper, its side surface fixed connection's buffer spring will pour and connect some conduction of the impact force that the hopper received to go out, and the impact force of its another part will drive the slider at the inside removal of spout, through the buffer who sets up, can be effectively with the impact force conduction to the reduction connects the wearing and tearing of hopper.
2. This concrete production and processing is with mechanism of pouring fast connects when pouring the inside concrete of hopper and place for a long time, opens the rotating electrical machines through first control switch, and the rotating electrical machines will drive the rotation axis rotation this moment to will pour and connect the inside concrete of hopper to stir, in order to prevent that its inside concrete from solidifying.
3. This concrete production and processing is with mechanism of pouring fast through opening second control switch to this opens the drawing liquid pump, then will pour the inside concrete of connecing the hopper through its drawing liquid pipe and carry the rubber tube intraduct, pour the assigned position by the rubber tube, through the drawing liquid pump that sets up, can be quick take out the concrete, and the top of its second control switch setting and rubber tube makes things convenient for operating personnel to open and close.
4. This concrete production and processing is with mechanism of pouring fast, extract the sleeve with the locating pin earlier, then draw and drag the lift post, make and reach suitable height, then peg graft the locating pin in spacing hole, thereby price lift post is fixed inside the sleeve, later peg graft the rubber tube in fixed establishment's inside, rotate the screw thread post this moment, make and drive the grip block and move down, thereby fix the rubber tube inside fixed establishment, because of the conveyer of its setting is track transport plate, make things convenient for it to drive the rubber tube and reach and pour the position.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic view of the top structure of the workbench according to the present invention;
FIG. 3 is a schematic view of the internal structure of the pouring hopper according to the present invention;
FIG. 4 is a schematic view of the structure of the transportation device of the present invention;
fig. 5 is a schematic structural diagram of the fixing mechanism of the present invention.
In the figure: 1. pouring a receiving hopper; 2. a work table; 3. a buffer device; 31. a chute; 32. a slider; 33. a buffer spring; 4. a partition plate; 5. an upper chamber; 6. a lower chamber; 7. a rotating electric machine; 8. a rotating shaft; 9. a first control switch; 10. a liquid pump; 11. a liquid pumping pipe; 12. a liquid outlet pipe; 13. a rubber tube; 14. a mounting ring; 15. a second control switch; 16. a transportation device; 161. a track transport plate; 162. a sleeve; 163. a lifting column; 164. a limiting hole; 165. positioning pins; 17. a fixing mechanism; 171. a clamping block; 172. fixing the spring; 173. a threaded post.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-5, in this embodiment: the utility model provides a concrete production and processing is with mechanism of pouring fast, connect hopper 1 including pouring, the bottom of pouring and connecting hopper 1 is provided with workstation 2, the top of workstation 2 is provided with buffer 3, it has baffle 4 to pour the inside inlaying in bottom that connects hopper 1, the bottom of baffle 4 is provided with cavity 5, the bottom of going up cavity 5 is provided with down cavity 6, the inside of going up cavity 5 is provided with rotating electrical machines 7, one side that rotating electrical machines 7 was kept away from to baffle 4 is provided with rotation axis 8, the side surface of workstation 2 is provided with first control switch 9, the inside of lower cavity 6 is provided with quick discharging device, it is provided with conveyer 16 to pour one side that connects hopper 1, the top of conveyer 16 is provided with fixed establishment 17.
In this embodiment, the buffer device 3 is composed of a chute 31, a slide block 32 and buffer springs 33, the chute 31 is arranged on one side of the workbench 2 close to the casting receiving hopper 1 in a penetrating way, the slide block 32 is arranged inside the chute 31, the buffer springs 33 are arranged on one side of the slide block 32 close to the casting receiving hopper 1, the number of the buffer devices 3 is two, the pouring material receiving hopper 1 is symmetrically arranged, the slide block 32 is in a convex shape, the size of the outer surface of the slide block 32 is matched with the size of the inner diameter of the chute 31, one end of a buffer spring 33 is fixedly connected with the side surface of the slide block 32, the other side of the buffer spring 33 is fixedly connected with the side surface of the pouring material receiving hopper 1, a groove is arranged at the center of the top of the workbench 2 in a penetrating way, the pouring material receiving hopper 1 is sleeved and connected with the inner part of the groove, a part of impact force can be conducted out through the buffer spring 33 arranged on the sliding block, and the other part of impact force drives the sliding block 32 to move in the sliding groove 31; the number of the partition boards 4 is three, the partition boards are an upper partition board, a middle partition board and a lower partition board in sequence from top to bottom, an upper cavity 5 is arranged between the upper partition board and the middle partition board, a lower cavity 6 is arranged between the middle partition board and the lower partition board, the rotating motor 7 is arranged in the upper cavity 5 and fixedly connected with the middle partition board, the output end of the rotating motor 7 penetrates through the pouring receiving hopper 1 and extends into the pouring receiving hopper 1, and is fixedly connected with the center of the bottom of the rotating shaft 8, the first control switch 9 is electrically connected with the rotating motor 7, and the rotating shaft 8 is driven to rotate through the arranged rotating motor 7, so that concrete is prevented from being solidified in the pouring receiving hopper 1; the quick discharging device comprises a liquid pump 10, a liquid pumping pipe 11, a liquid outlet pipe 12, a rubber pipe 13, a mounting ring 14 and a second control switch 15, the liquid pumping pump 10 is arranged in the lower cavity 6, the liquid pumping pipe 11 is fixedly connected to the right side of the liquid pumping pump 10, the liquid outlet pipe 12 is fixedly connected to the left side of the liquid pumping pump 10, the rubber pipe 13 is arranged at the bottom of the lower cavity 6, the mounting ring 14 is fixedly connected to one end of the rubber pipe 13 far away from the lower cavity 6, the second control switch 15 is arranged at the top of the mounting ring 14, the liquid pumping pump 10 is fixedly connected with the center of the top of the lower partition plate, the other end of the liquid pumping pipe 11 penetrates through the upper cavity 5 and extends into the pouring receiving hopper 1, the other end of the liquid outlet pipe 12 penetrates through the inside of the rubber pipe 13, the inner diameter of the mounting ring 14 is matched with the outer surface size of the rubber pipe 13, the concrete in the pouring receiving hopper 1 is conveyed to the interior of the rubber tube 13 through the arranged liquid pump 10, and the second control switch 15 arranged at the top of the rubber tube 13 can control the liquid pump 10 to be opened and closed, so that the concrete pouring receiving hopper is convenient for an operator to use; the conveying device 16 comprises a track conveying plate 161, a sleeve 162, a lifting column 163, limiting holes 164 and positioning pins 165, wherein the track conveying plate 161 is arranged on one side of the pouring receiving hopper 1, the sleeve 162 is fixedly connected to the top of the track conveying plate 161, the lifting column 163 is arranged on one side, away from the track conveying plate 161, of the sleeve 162, the limiting holes 164 are formed in the side surface of the lifting column 163 in a penetrating mode, the positioning pins 165 are arranged on the outer surface of the sleeve 162, the inner diameter size of the sleeve 162 is matched with the outer surface size of the lifting column 163, the limiting holes 164 are arranged in a plurality of groups, the limiting holes 164 are linearly distributed on the side surface of the lifting column 163 at equal intervals, the limiting holes 164 are also formed in the side surface of the sleeve 162 in a penetrating mode, the limiting holes 164 on the outer surface of the sleeve 162 are matched with the limiting holes 164 on the outer surface of the lifting column 163, the inner diameter size of the, the device can move on complex terrain; the fixing mechanism 17 is composed of a clamping block 171, a fixing spring 172 and a threaded column 173, the top of the lifting column 163 is fixedly connected with the fixing mechanism 17, the clamping block 171 is arranged inside the fixing mechanism 17, one end of the clamping block 171 close to the fixing mechanism 17 is provided with the fixing spring 172, the top of the fixing mechanism 17 is provided with the threaded column 173, the fixing mechanism 17 is annular, the inner diameter of the fixing mechanism 17 is larger than the outer surface of the rubber tube 13, the clamping block 171 is semicircular and is matched with the outer surface of the rubber tube 13 in size, the number of the fixing springs 172 is two, the fixing springs are symmetrically arranged relative to the threaded column 173, one end of the fixing spring 172 is fixedly connected with the inner side wall of the fixing mechanism 17, the other end of the fixing spring 172 is fixedly connected with the top of the clamping block 171, a threaded hole is arranged at the center of the top of the fixing mechanism 17 in a penetrating, the rubber tube 13 is placed inside the fixing mechanism 17, and then the threaded column 173 is rotated to drive the clamping block 171 to move downwards, so that the rubber tube 13 is fixed on the conveying device 16, and the conveying device 16 is convenient to drive the rubber tube 13 to move to the pouring position
The working principle and the using process of the invention are as follows: firstly, the positioning pin 165 is pulled out of the sleeve 162, then the lifting column 163 is pulled to reach a proper height, then the positioning pin 165 is inserted into the limit hole 164, so that the price lifting column 163 is fixed inside the sleeve 162, then the rubber tube 13 is inserted inside the fixing mechanism 17, at the moment, the threaded column 173 is rotated, so that the clamping block 171 is driven to move downwards, so that the rubber tube 13 is fixed inside the fixing mechanism 17, when concrete is poured into the pouring receiving hopper 1, the buffer spring 33 fixedly connected with the side surface of the rubber tube conducts a part of the concrete received by the pouring receiving hopper 1, the impact force of the other part of the rubber tube drives the sliding block 32 to move inside the sliding groove 31, the impact force can be effectively conducted through the arranged buffer device 3, so that the abrasion of the receiving hopper is reduced, when the concrete in the pouring receiving hopper 1 is placed for a long time, the rotating motor 7 is opened through the first control switch 9, at this time, the rotating motor 7 drives the rotating shaft 8 to rotate, so as to stir the concrete in the pouring receiving hopper 1 to prevent the concrete in the pouring receiving hopper from being solidified, the liquid pump 10 is turned on by turning on the second control switch 15, and then the concrete in the pouring receiving hopper 1 is conveyed to the inside of the rubber tube 13 through the liquid suction pipe 11, so that the rubber tube 13 is moved to a pouring position.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that changes may be made in the embodiments and/or equivalents thereof without departing from the spirit and scope of the invention. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. The utility model provides a concrete production and processing is with mechanism of pouring fast which characterized in that: comprises a pouring receiving hopper (1), a workbench (2) is arranged at the bottom of the pouring receiving hopper (1), the top of the workbench (2) is provided with a buffer device (3), the bottom of the pouring receiving hopper (1) is internally embedded with a clapboard (4), an upper chamber (5) is arranged at the bottom of the clapboard (4), a lower chamber (6) is arranged at the bottom of the upper chamber (5), a rotating motor (7) is arranged in the upper chamber (5), a rotating shaft (8) is arranged on one side of the partition plate (4) far away from the rotating motor (7), a first control switch (9) is arranged on the side surface of the workbench (2), the quick discharging device is arranged inside the lower chamber (6), a conveying device (16) is arranged on one side of the pouring receiving hopper (1), and a fixing mechanism (17) is arranged at the top of the conveying device (16).
2. The quick pouring mechanism for the production and processing of concrete according to claim 1, characterized in that: buffer (3) comprise spout (31), slider (32) and buffer spring (33), one side that is close to pouring and connects hopper (1) of workstation (2) is run through and is provided with spout (31), the inside of spout (31) is provided with slider (32), one side that slider (32) are close to pouring and connect hopper (1) is provided with buffer spring (33).
3. The quick casting mechanism for the production and processing of concrete according to claim 1 or 2, characterized in that: the quantity of buffer (3) has two sets ofly, and connects hopper (1) symmetry setting about pouring, the shape of slider (32) is "protruding" shape piece, the external surface size of slider (32) and the internal diameter size phase-match of spout (31), the one end of buffer spring (33) and the side surface fixed connection of slider (32), the opposite side of buffer spring (33) and the side surface fixed connection who connects hopper (1) of pouring, the top center department of workstation (2) runs through and is provided with the recess, it connects hopper (1) to cup joint with inside the recess to pour.
4. The quick pouring mechanism for the production and processing of concrete according to claim 1, characterized in that: the quantity of baffle (4) has three groups, and from the top down is last baffle, intermediate bottom and lower baffle in proper order, it is provided with cavity (5) to go up between baffle and the intermediate bottom, be provided with down cavity (6) between intermediate bottom and the lower baffle, rotating electrical machines (7) set up with the inside of last cavity (5), and with intermediate bottom fixed connection, the output of rotating electrical machines (7) runs through and extends to the inside of pouring and connect hopper (1), and with the bottom center department fixed connection of rotation axis (8), first control switch (9) and rotating electrical machines (7) electric connection.
5. The quick pouring mechanism for the production and processing of concrete according to claim 1, characterized in that: quick discharging device comprises drawing liquid pump (10), drawing liquid pipe (11), drain pipe (12), rubber tube (13), collar (14) and second control switch (15), the inside of cavity (6) is provided with drawing liquid pump (10) down, the right side fixedly connected with drawing liquid pipe (11) of drawing liquid pump (10), the left side fixedly connected with drain pipe (12) of drawing liquid pump (10), the bottom of cavity (6) is provided with rubber tube (13) down, one end fixedly connected with collar (14) of cavity (6) are kept away from down in rubber tube (13), the top of collar (14) is provided with second control switch (15).
6. The quick casting mechanism for concrete production according to claim 1, 4 or 5, wherein: the utility model discloses a concrete pump, including drawing liquid pump (10), the other end of drawing liquid pipe (11) runs through cavity (5), and extends to the inside of pouring and connect hopper (1), the other end of drain pipe (12) runs through the inside that extends to rubber tube (13), the internal diameter size of collar (14) and the outer surface size phase-match of rubber tube (13), second control switch (15) and drawing liquid pump (10) electric connection.
7. The quick pouring mechanism for the production and processing of concrete according to claim 1, characterized in that: conveyer (16) comprise track transport plate (161), sleeve (162), lift post (163), spacing hole (164) and locating pin (165), one side of pouring and receiving hopper (1) is provided with track transport plate (161), the top fixedly connected with sleeve (162) of track transport plate (161), one side that track transport plate (161) were kept away from in sleeve (162) is provided with lift post (163), the side surface of lift post (163) runs through and is provided with spacing hole (164), the surface of sleeve (162) is provided with locating pin (165).
8. The quick casting mechanism for the production and processing of concrete according to claim 1 or 7, characterized in that: the internal diameter size of sleeve (162) and the outer surface size phase-match of lift post (163), the quantity of spacing hole (164) has a plurality of groups, spacing hole (164) are linear equidistant distribution at the side surface of lift post (163), the side surface of sleeve (162) also runs through and is provided with spacing hole (164), spacing hole (164) of sleeve (162) surface and the spacing hole (164) phase-match of lift post (163) surface, the internal diameter size of spacing hole (164) and the outer surface size phase-match of locating pin (165).
9. The quick casting mechanism for the production and processing of concrete according to claim 1 or 8, characterized in that: fixed establishment (17) comprises grip block (171), fixed spring (172) and screw post (173), the top fixedly connected with fixed establishment (17) of lift post (163), the inside of fixed establishment (17) is provided with grip block (171), the one end that grip block (171) is close to fixed establishment (17) is provided with fixed spring (172), the top of fixed establishment (17) is provided with screw post (173).
10. The quick casting mechanism for concrete production and processing according to claim 1 or 9, wherein: the shape of fixed establishment (17) is the ring form, and the internal diameter size is greater than the surface dimension of rubber tube (13), the shape of grip block (171) is the semicircle ring-type, and its internal diameter size and the surface dimension phase-match of rubber tube (13), there are two sets ofly the quantity of fixed spring (172), and set up about screw thread post (173) symmetry, the one end of fixed spring (172) and the inside wall fixed connection of fixed establishment (17), the other end of fixed spring (172) and the top fixed connection of grip block (171), the top center department of fixed establishment (17) runs through and is provided with the screw hole, screw thread post (173) and screw hole threaded connection.
CN202011064629.4A 2020-09-30 2020-09-30 Concrete production and processing is with mechanism of pouring fast Pending CN112177338A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011064629.4A CN112177338A (en) 2020-09-30 2020-09-30 Concrete production and processing is with mechanism of pouring fast

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011064629.4A CN112177338A (en) 2020-09-30 2020-09-30 Concrete production and processing is with mechanism of pouring fast

Publications (1)

Publication Number Publication Date
CN112177338A true CN112177338A (en) 2021-01-05

Family

ID=73948194

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011064629.4A Pending CN112177338A (en) 2020-09-30 2020-09-30 Concrete production and processing is with mechanism of pouring fast

Country Status (1)

Country Link
CN (1) CN112177338A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204781975U (en) * 2015-05-26 2015-11-18 中国建筑第八工程局有限公司 Concrete buffering connects hopper
CN207616894U (en) * 2017-10-30 2018-07-17 中建七局(上海)有限公司 A kind of device for casting of ultra-deep underground garage construction seam processing
WO2018130913A2 (en) * 2017-01-15 2018-07-19 Butler Michael George Apparatuses and systems for and methods of generating and placing zero-slump-pumpable concrete
CN207878287U (en) * 2018-01-30 2018-09-18 广州快速交通建设有限公司 A kind of box culvert construct concrete placing installation
CN108952169A (en) * 2018-06-08 2018-12-07 苏州蓝王机床工具科技有限公司 A kind of construction blanking device
CN209511274U (en) * 2018-12-22 2019-10-18 宁波永享不锈钢管道有限公司 A kind of load bearing wall pipeline jig
CN110984575A (en) * 2019-11-05 2020-04-10 广州文冲船厂有限责任公司 Concrete pouring hopper device and control method
CN210483065U (en) * 2019-04-08 2020-05-08 绍兴文理学院元培学院 Concrete hopper

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204781975U (en) * 2015-05-26 2015-11-18 中国建筑第八工程局有限公司 Concrete buffering connects hopper
WO2018130913A2 (en) * 2017-01-15 2018-07-19 Butler Michael George Apparatuses and systems for and methods of generating and placing zero-slump-pumpable concrete
CN207616894U (en) * 2017-10-30 2018-07-17 中建七局(上海)有限公司 A kind of device for casting of ultra-deep underground garage construction seam processing
CN207878287U (en) * 2018-01-30 2018-09-18 广州快速交通建设有限公司 A kind of box culvert construct concrete placing installation
CN108952169A (en) * 2018-06-08 2018-12-07 苏州蓝王机床工具科技有限公司 A kind of construction blanking device
CN209511274U (en) * 2018-12-22 2019-10-18 宁波永享不锈钢管道有限公司 A kind of load bearing wall pipeline jig
CN210483065U (en) * 2019-04-08 2020-05-08 绍兴文理学院元培学院 Concrete hopper
CN110984575A (en) * 2019-11-05 2020-04-10 广州文冲船厂有限责任公司 Concrete pouring hopper device and control method

Similar Documents

Publication Publication Date Title
CN207806612U (en) Pouring molten iron packet and its molten iron casting mechanism
CN213806632U (en) Rotary concrete pouring equipment
CN112177338A (en) Concrete production and processing is with mechanism of pouring fast
CN211440590U (en) Walking type concrete mixing and distributing machine with front-mounted feeding and discharging ports
CN202753283U (en) Movable concrete mixing device
CN206840424U (en) A kind of concrete entirety irrigation device
CN206154480U (en) Convertible concrete member make -up machine
CN210881047U (en) Stone slab imitation processing device for outer wall based on building waste
CN212715954U (en) Concrete placement device based on BIM technique is used
CN218092090U (en) Floor concrete placement's operation rack
CN209755673U (en) Construction is with multi-functional slip casting bucket that can stir cement
CN211221340U (en) Concrete mixing, molding and cleaning integrated device
CN209469015U (en) A kind of architectural engineering is with pouring device
CN210098179U (en) Sand screening installation
CN210289166U (en) Concrete automatic movement distributor
CN202030717U (en) Automatic open-type acetylene generator feeding system
CN209162762U (en) A kind of cement mortar for constructional engineering joint filling device
CN108748692B (en) Discharging mechanism of concrete mixer
CN208163973U (en) Concrete duct rapid molding device
CN213674790U (en) Building engineering pours device
CN220741671U (en) Concrete material mixes machine
CN219910012U (en) Concrete pouring equipment
CN210675048U (en) Raw materials mixing stirring device of nursing liquid lid stopper processing usefulness
CN215241808U (en) Intelligent high accuracy concrete dosing unit
CN214233608U (en) Water paint agitating unit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination