CN112177296B - External wall heat insulation construction device and construction method - Google Patents

External wall heat insulation construction device and construction method Download PDF

Info

Publication number
CN112177296B
CN112177296B CN202010850074.XA CN202010850074A CN112177296B CN 112177296 B CN112177296 B CN 112177296B CN 202010850074 A CN202010850074 A CN 202010850074A CN 112177296 B CN112177296 B CN 112177296B
Authority
CN
China
Prior art keywords
assembly
roller
hole
guardrail
suspension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010850074.XA
Other languages
Chinese (zh)
Other versions
CN112177296A (en
Inventor
张亚光
沈兵
曹玉良
胡恩玮
穆佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC Tiangong Group Corp Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN202010850074.XA priority Critical patent/CN112177296B/en
Publication of CN112177296A publication Critical patent/CN112177296A/en
Application granted granted Critical
Publication of CN112177296B publication Critical patent/CN112177296B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/18Implements for finishing work on buildings for setting wall or ceiling slabs or plates
    • E04F21/1838Implements for finishing work on buildings for setting wall or ceiling slabs or plates for setting a plurality of similar elements
    • E04F21/1844Implements for finishing work on buildings for setting wall or ceiling slabs or plates for setting a plurality of similar elements by applying them one by one
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/02Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
    • E04F21/023Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls for applying adhesive, e.g. glue or mortar, on the covering elements, in particular tiles
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/18Implements for finishing work on buildings for setting wall or ceiling slabs or plates
    • E04F21/1838Implements for finishing work on buildings for setting wall or ceiling slabs or plates for setting a plurality of similar elements
    • E04F21/1844Implements for finishing work on buildings for setting wall or ceiling slabs or plates for setting a plurality of similar elements by applying them one by one
    • E04F21/1861Implements for finishing work on buildings for setting wall or ceiling slabs or plates for setting a plurality of similar elements by applying them one by one for setting insulating panels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • E04G3/32Hoisting devices; Safety devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/003Devices for storing material on the scaffold
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

An external wall heat insulation construction device and a construction method are provided, wherein the construction device comprises: the coating scraping device comprises a suspension assembly, a guardrail assembly, an inner bin assembly, an outer bin assembly, a coating storage assembly, a winding assembly, a coating scraping assembly and a pedal. According to the external wall heat insulation construction device and the construction method, the storage space of the heat insulation board can be expanded or reduced through the inner bin and the outer bin, and the damage rate of the heat insulation board is greatly reduced; keep off the material roller and strickle the roller off through setting up, can clear up in advance the wall body surface, the roller of strickleing off of coating storehouse upper end simultaneously is strickleed off the coating automation that adheres on the wall body with the tendency, and the efficiency of construction is high, and job stabilization nature is high, can effectively utilize the space, avoids the heated board to damage.

Description

External wall heat insulation construction device and construction method
Technical Field
The invention belongs to the technical field of external wall construction, and particularly relates to an external wall heat insulation construction device and a construction method.
Background
At present, the external wall insulation board mainly bears constructor through linkage in the work progress and applies paint (mortar) with a brush, then the laminating external wall insulation board, and paint solidifies the back and fixes external wall insulation board on the outer wall, and the work progress is loaded down with trivial details, especially linkage poor stability, needs to install the solid nail of card in addition and fixes it.
In addition, the space utilization rate of the traditional suspension device is very low, the space on the pedal cannot be fully utilized, the storage quantity of the heat-insulation plates is limited, and the heat-insulation plates are mutually stacked to easily cause damage to the heat-insulation plates.
Disclosure of Invention
In order to solve the above problems, the present invention provides an external wall insulation construction device, comprising:
the suspension assembly is used for bearing each part; the suspension assembly having opposed first and second ends;
a guardrail assembly for protecting an operator; the guardrail component is arranged on the suspension component;
the inner bin assembly is used for placing the heat insulation board; the inner bin assembly is arranged at the first end of the suspension assembly;
the outer bin assembly is used for placing the heat insulation plate; the outer bin assembly is arranged at the first end of the suspension assembly;
a paint storage assembly for storing paint; the paint storage component is arranged at the second end of the suspension component;
the hoisting component is used for driving the suspension component to lift; the winding assembly is arranged on the outer wall and is connected with the guardrail assembly;
a paint scraper assembly for scraping excess paint from the exterior wall; the coating scraping assembly is arranged at the second end of the suspension assembly;
the pedal is used for supporting the heat insulation plate; the pedal is arranged at the second end of the suspension component.
Preferably, the suspension assembly comprises: the joist, the guardrail subassembly, interior storehouse subassembly with outer storehouse subassembly set up in on the joist.
Preferably, the guardrail assembly comprises: the suspension assembly comprises a ring beam, a stop lever and a rubber sleeve, wherein the first end of the stop lever is connected with a supporting beam in the suspension assembly, the second end of the stop lever is connected with the ring beam, and the rubber sleeve wraps the ring beam.
Preferably, the inner cartridge assembly comprises: first flexible arm, first support frame, first adjustable shelf, spacing ring, slide bar and gyro wheel, wherein, first flexible arm respectively with annular roof beam in the guardrail subassembly first support frame first adjustable shelf with the spacing ring is connected, the slide bar set up in just support on the annular roof beam first adjustable shelf, the gyro wheel with first adjustable shelf is connected, and sliding support in on the footboard.
Preferably, the outer cartridge assembly comprises: second elasticity telescopic boom, second support frame, guide bar, adapter sleeve, pressure cap, reset spring, go-between and uide bushing, wherein, the adapter sleeve respectively with annular roof beam in the guardrail subassembly with the second elasticity telescopic boom is connected, second elasticity telescopic boom respectively with the second support frame with press the cap to connect, the second support frame with the guide bar is connected, the go-between respectively with press the cap with reset spring connects, the uide bushing with the annular roof beam is connected, the guide bar set up in the uide bushing.
Preferably, the paint storage assembly comprises: the connecting device comprises a connecting seat, a connecting hole, a connecting plate, a connecting pin and a barrel frame body, wherein the connecting seat is connected with an annular beam in the guardrail assembly, the connecting hole is formed in the connecting seat, the connecting plate is connected with the barrel frame body, and the connecting pin is arranged on the connecting plate and inserted into the connecting hole.
Preferably, the hoisting assembly comprises: gear box, backup pad, locating hole, supporting seat, output shaft, bearing, spool, main cable, branch cable, be responsible for, sleeve pipe and barrier disc, wherein, the locating hole set up in the backup pad, the screw passes the locating hole will the backup pad sets up on the outer wall, the gear box set up in the backup pad, the supporting seat sets up on the outer wall, the output shaft with the gear box is connected, the bearing housing is located on the output shaft, and support on the supporting seat, the spool pipe box is located on the output shaft, main cable with divide the cable to twine in on the spool, be responsible for respectively with the sleeve pipe with the barrier disc is connected, the sleeve pipe with annular beam in the guardrail subassembly is connected, the barrier disc respectively with main cable with divide the cable to connect.
Preferably, the paint scraper assembly comprises: the device comprises a guide rail, a coating bin, a material blocking roller, a scraping roller, a sliding block, a connecting rod, a thrust spring, a positioning block, a long hole 709, a roller shaft, a roller, a blocking ring, a pressing ring 713, a positioning threaded hole, a guiding through hole and a blocking ring, wherein the guide rail is arranged on a supporting beam in the suspension assembly, a screw passes through the positioning threaded hole to arrange the positioning block on the guide rail, the guiding through hole is arranged on the positioning block, the sliding block is arranged on the guide rail, a first end of the connecting rod is connected with the sliding block, a second end of the connecting rod passes through the guiding through hole, the blocking ring is arranged at the second end of the connecting rod, the thrust spring is sleeved on the connecting rod, the coating bin is arranged on the sliding block, the material blocking roller is arranged on the coating bin, the pressing ring is respectively connected with the coating bin and the roller shaft, and the blocking ring is connected with the roller shaft, the strip hole is arranged on the baffle ring, and the roller is connected with the roller shaft.
The invention also provides an external wall heat insulation construction method, which comprises the following steps:
loading paint into a paint storage assembly;
the insulation boards are arranged in the inner bin assembly and the outer bin assembly;
using a hoisting component to lift or lower the suspension component to a preset height of the outer wall;
outputting the heat insulation plates in the outer bin assembly and the inner bin assembly to a pedal;
outputting the paint in the paint storage assembly to a heat insulation plate on the pedal;
installing the heat insulation board on the pedal on an outer wall;
excess paint on the exterior wall is scraped using a paint scraper assembly.
According to the external wall heat insulation construction device and the construction method, the storage space of the heat insulation board can be expanded or reduced through the inner bin and the outer bin, and the damage rate of the heat insulation board is greatly reduced; keep off the material roller and strickle the roller off through setting up, can clear up in advance the wall body surface, the roller of strickleing off of coating storehouse upper end simultaneously is strickleed off the coating automation that adheres on the wall body with the tendency, and the efficiency of construction is high, and job stabilization nature is high, can effectively utilize the space, avoids the heated board to damage.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a schematic view of the overall structure of an external wall insulation construction device according to the present invention;
FIG. 2 is a schematic view of a partial structure of an external wall insulation construction device provided by the present invention;
FIG. 3 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 4 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 5 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 6 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 7 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 8 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 9 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 10 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 11 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 12 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 13 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 14 is a schematic view of a partial structure of an exterior wall insulation construction device according to the present invention;
FIG. 15 is a schematic view of a partial structure of an exterior wall thermal insulation construction device according to the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in further detail with reference to the accompanying drawings in conjunction with the following detailed description. It should be understood that the description is intended to be exemplary only, and is not intended to limit the scope of the present invention. Moreover, in the following description, descriptions of well-known structures and techniques are omitted so as to not unnecessarily obscure the concepts of the present invention.
As shown in fig. 1 to 15, in an embodiment of the present application, there is provided an exterior wall insulation construction device including: the suspension assembly 100, the barrier assembly 200, the inner bin assembly 300, the outer bin assembly 400, the paint storage assembly 500, the winch assembly 600, the paint scraper assembly 700, and the step plate 800, each of which will be described in detail below.
Referring to fig. 1 to 15, in an embodiment of the present application, an external wall thermal insulation construction device provided by the present invention includes:
a suspension assembly 100 for carrying the parts; the suspension assembly 100 has opposing first and second ends;
a guardrail assembly 200 for protecting an operator; the guardrail assembly 200 is disposed on the suspension assembly 100;
the inner bin assembly 300 is used for placing insulation boards; the inner bin assembly 300 is disposed at a first end of the suspension assembly 100;
the outer bin assembly 400 is used for placing insulation boards; the outer bin assembly 400 is disposed at a first end of the suspension assembly 100;
a paint storage assembly 500 for storing paint; the paint storage assembly 500 is disposed at a second end of the suspension assembly 100;
a hoisting assembly 600 for driving the suspension assembly 100 to ascend and descend; the winding assembly 600 is arranged on the outer wall and connected with the guardrail assembly 200;
a paint scraper assembly 700 for scraping excess paint off of an exterior wall; the coating scraping assembly 700 is disposed at a second end of the suspension assembly 100;
a pedal 800 for supporting the insulation board; the pedal 800 is disposed at a second end of the suspension assembly 100.
When the external wall heat-insulation construction device is used, heat-insulation plates are arranged in the inner bin assembly 300 and the outer bin assembly 400 in advance, meanwhile, coating is arranged in the coating storage assembly 500, an operator stands on the suspension assembly 100, then the hoisting assembly 600 is opened, the hoisting assembly 600 controls the suspension assembly 100 to move downwards from the top of the external wall, the operator coats the coating in the coating storage assembly 500 on the heat-insulation plates in the inner bin assembly 300 and the outer bin assembly 400, then the heat-insulation plates are arranged on the external wall, then the hoisting assembly 600 is opened again, the hoisting assembly 600 controls the suspension assembly 100 to move downwards from the top of the external wall, meanwhile, the coating scraping assembly 700 can pre-clean the surface of the wall, and coating with different thicknesses and adhered to the wall can be automatically scraped to be flat along with the trend, the construction efficiency is high, and the safety coefficient is high.
As shown in fig. 1 to 15, in the present embodiment, the suspension assembly 100 includes: the joist 101, the guardrail assembly 200, the inner bin assembly 300 and the outer bin assembly 400 are arranged on the joist 101. The joist 101 is made of steel plate, so that the intensity is high, and an operator can stand on the joist 101.
1-15, in the present embodiment, the guardrail assembly 200 comprises: the suspension assembly comprises a ring-shaped beam 201, a stop lever 202 and a rubber sleeve 203, wherein the stop lever 202 is connected with the joist 101 in the suspension assembly 100 at a first end and connected with the ring-shaped beam 201 at a second end, and the rubber sleeve 203 wraps the ring-shaped beam 201. The stop lever 202 connects the ring beam 201 with the joist 101, and the rubber sleeve 203 is wrapped on the ring beam 201, so that the ring beam 201 can be conveniently held by an operator.
1-15, in the present embodiment, the inner cartridge assembly 300 comprises: first elasticity telescopic boom 301, first support frame 302, first adjustable shelf 303, spacing ring 304, slide bar 305 and gyro wheel 306, wherein, first elasticity telescopic boom 301 respectively with annular roof beam 201 in guardrail subassembly 200, first support frame 302 first adjustable shelf 303 with spacing ring 304 is connected, slide bar 305 set up in on the annular roof beam 201 and support first adjustable shelf 303, gyro wheel 306 with first adjustable shelf 303 is connected, and sliding support in on the footboard 800. The stacked heat insulation plates are placed on the first movable frame 303, when an operator installs the heat insulation plates, the first elastic telescopic arm 301 can be operated to extend out of the first movable frame 303, and the first movable frame 303 is close to the outer wall on the pedal 800 under the support of the rollers 306.
As shown in fig. 1-15, in the present embodiment, the outer cartridge assembly 400 comprises: second elasticity telescopic arm 401, second support frame 402, guide bar 403, adapter sleeve 404, pressure cap 405, reset spring 406, go-between 407 and uide bushing 408, wherein, adapter sleeve 404 respectively with annular roof beam 201 in the guardrail subassembly 200 with second elasticity telescopic arm 401 is connected, second elasticity telescopic arm 401 respectively with second support frame 402 with press cap 405 to connect, second support frame 402 with guide bar 403 connects, go-between 407 respectively with pressure cap 405 with reset spring 406 connects, uide bushing 408 with annular roof beam 201 connects, uide bushing 403 set up in the uide bushing 408. The second support frame 402 is provided with a stacked heat insulation board, when an operator installs the heat insulation board, the second elastic telescopic arm 401 can be operated to stretch out the second support frame 402 and approach the pedal 800, and the heat insulation board is conveyed to the pedal 800. After the insulation board is output, the return spring 406 pulls the second support frame 402 to move towards the second elastic telescopic arm 401, and the second support frame 402 resets.
1-15, in an embodiment of the present application, the paint storage assembly 500 includes: the guardrail comprises a connecting seat 501, a connecting hole 502, a connecting plate 503, a connecting pin 504 and a barrel frame body 505, wherein the connecting seat 501 is connected with the annular beam 201 in the guardrail assembly 200, the connecting hole 502 is arranged on the connecting seat 501, the connecting plate 503 is connected with the barrel frame body 505, and the connecting pin 504 is arranged on the connecting plate 503 and inserted into the connecting hole 502. A paint bucket is loaded into the bucket rack 505, and paint is loaded into the paint bucket.
As shown in fig. 1 to 15, in the embodiment of the present application, the hoisting assembly 600 includes: gear box 601, support plate 602, positioning hole 603, support base 604, output shaft 605, bearing 606, winding pipe 607, main cable 608, branch cable 609, main pipe 610, sleeve 611 and stop disk 612, wherein the positioning holes 603 are disposed on the supporting plate 602, screws pass through the positioning holes 603 to dispose the supporting plate 602 on an outer wall, the gear box 601 is arranged on the supporting plate 602, the supporting seat 604 is arranged on the outer wall, the output shaft 605 is connected with the gear box 601, the bearing 606 is sleeved on the output shaft 605, and supports the supporting seat 604, the winding pipe 607 is sleeved on the output shaft 605, the main cable 608 and the branch cable 609 are wound on the winding pipe 607, the main pipe 610 is connected with the sleeve 611 and the blocking disk 612 respectively, the sleeve 611 is connected to the ring beam 201 of the guardrail assembly 200 and the blocking disk 612 is connected to the main cable 608 and the branch cable 609, respectively.
In the embodiment of the present application, when the suspension assembly 100 is controlled to ascend or descend, the gear box 601 controls the output shaft 605 to rotate forward or backward, the output shaft 605 drives the winding pipe 607 to rotate forward or backward, and the main rope 608 and the branch rope 609 drive the stop disc 612 to ascend or descend, thereby driving the suspension assembly 100 to ascend or descend.
As shown in fig. 1-15, in the present embodiment, the paint scraper assembly 700 includes: a guide rail 701, a paint bin 702, a material blocking roller 703, a leveling roller 704, a sliding block 705, a connecting rod 706, a thrust spring 707, a positioning block 708, a long hole 709, a roller shaft 710, a roller barrel 711, a blocking ring 712, a pressing ring 713, a positioning threaded hole 714, a guiding through hole 715 and a blocking ring 716, wherein the guide rail 701 is arranged on a joist 101 in the suspension assembly 100, a screw passes through the positioning threaded hole 714 to arrange the positioning block 708 on the guide rail 701, the guiding through hole 715 is arranged on the positioning block 708, the sliding block 705 is arranged on the guide rail 701, a first end of the connecting rod 706 is connected with the sliding block 705, a second end of the connecting rod passes through the guiding through hole 715, the blocking ring 716 is arranged on a second end of the connecting rod 706, the thrust spring 707 is sleeved on the connecting rod 706, the paint bin 702 is arranged on the sliding block 705, the material blocking roller 703 is arranged on the paint bin 702, the compression ring is respectively connected with the coating bin 702 and the roller shaft 710, the baffle ring 712 is connected with the roller shaft 710, the strip hole is formed in the baffle ring 712, and the roller 711 is connected with the roller shaft 710.
In the embodiment of the application, when an operator scrapes off excessive paint on an outer wall, the hoisting assembly 600 controls the suspension assembly 100 to slowly move downwards, at this time, the operator can push the connecting rod 706 outwards, the connecting rod 706 pushes the sliding block 705 on the guide rail 701 to the outer wall, the paint bin 702 is close to the outer wall, at this time, the material blocking roller 703 and the leveling roller 704 are in contact with the outer wall, the leveling roller 704 scrapes off the paint exceeding a preset thickness on the outer wall, and the paint enters the paint bin 702 through the blocking of the material blocking roller 703; when the scraping is completed, the external force is stopped, and the thrust spring 707 pulls the slider 705 to move toward the positioning block 708 to be reset.
In the embodiment of the application, the invention also provides an external wall heat insulation construction method, which comprises the following steps:
loading paint into the paint storage assembly 500;
the insulation boards are loaded into the inner bin assembly 300 and the outer bin assembly 400;
raising or lowering the suspension assembly 100 to a predetermined height of the outer wall using the winding assembly 600;
outputting the heat insulation plates in the outer bin assembly 400 and the inner bin assembly 300 to a pedal 800;
outputting the coating in the coating storage assembly 500 to the heat insulation plate on the pedal 800;
installing the heat insulation board on the pedal 800 on an outer wall;
paint scraper assembly 700 is used to scrape excess paint from the exterior wall.
In the embodiment of the application, the external wall heat insulation construction method provided by the invention can be realized by the external wall heat insulation construction device as shown in fig. 1-15.
According to the external wall heat insulation construction device and the construction method, the storage space of the heat insulation board can be expanded or reduced through the inner bin and the outer bin, and the damage rate of the heat insulation board is greatly reduced; keep off the material roller and strickle the roller off through setting up, can clear up in advance the wall body surface, the roller of strickleing off of coating storehouse upper end simultaneously is strickleed off the coating automation that adheres on the wall body with the tendency, and the efficiency of construction is high, and job stabilization nature is high, can effectively utilize the space, avoids the heated board to damage.
It is to be understood that the above-described embodiments of the present invention are merely illustrative of or explaining the principles of the invention and are not to be construed as limiting the invention. Therefore, any modification, equivalent replacement, improvement and the like made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. Further, it is intended that the appended claims cover all such variations and modifications as fall within the scope and boundaries of the appended claims or the equivalents of such scope and boundaries.

Claims (7)

1. The utility model provides an outer wall heat preservation construction equipment which characterized in that includes:
the suspension assembly is used for bearing each part; the suspension assembly having opposed first and second ends;
a guardrail assembly for protecting an operator; the guardrail component is arranged on the suspension component;
the inner bin assembly is used for placing the heat insulation board; the inner bin assembly is arranged at the first end of the suspension assembly;
the outer bin assembly is used for placing the heat insulation plate; the outer bin assembly is arranged at the first end of the suspension assembly;
a paint storage assembly for storing paint; the paint storage component is arranged at the second end of the suspension component;
the hoisting component is used for driving the suspension component to lift; the winding assembly is arranged on the outer wall and is connected with the guardrail assembly;
a paint scraper assembly for scraping excess paint from the exterior wall; the coating scraping assembly is arranged at the second end of the suspension assembly;
the pedal is used for supporting the heat insulation plate; the pedal is arranged at the second end of the suspension component;
wherein, interior storehouse subassembly includes: first flexible arm, first support frame, first adjustable shelf, spacing ring, slide bar and gyro wheel, wherein, first flexible arm respectively with annular roof beam in the guardrail subassembly first support frame first adjustable shelf with the spacing ring is connected, the slide bar set up in just support on the annular roof beam first adjustable shelf, the gyro wheel with first adjustable shelf is connected, and sliding support in on the footboard.
2. The exterior wall insulation construction device according to claim 1, wherein the suspension assembly comprises: the joist, the guardrail subassembly, interior storehouse subassembly with outer storehouse subassembly set up in on the joist.
3. The exterior wall insulation construction device according to claim 1, wherein the guardrail assembly comprises: the suspension assembly comprises a ring beam, a stop lever and a rubber sleeve, wherein the first end of the stop lever is connected with a supporting beam in the suspension assembly, the second end of the stop lever is connected with the ring beam, and the rubber sleeve wraps the ring beam.
4. The exterior wall insulation construction device of claim 1, wherein the outer bin assembly comprises: second elasticity telescopic boom, second support frame, guide bar, adapter sleeve, pressure cap, reset spring, go-between and uide bushing, wherein, the adapter sleeve respectively with annular roof beam in the guardrail subassembly with the second elasticity telescopic boom is connected, second elasticity telescopic boom respectively with the second support frame with press the cap to connect, the second support frame with the guide bar is connected, the go-between respectively with press the cap with reset spring connects, the uide bushing with the annular roof beam is connected, the guide bar set up in the uide bushing.
5. The exterior wall insulation construction device of claim 1, wherein the paint storage assembly comprises: the connecting device comprises a connecting seat, a connecting hole, a connecting plate, a connecting pin and a barrel frame body, wherein the connecting seat is connected with an annular beam in the guardrail assembly, the connecting hole is formed in the connecting seat, the connecting plate is connected with the barrel frame body, and the connecting pin is arranged on the connecting plate and inserted into the connecting hole.
6. The exterior wall insulation construction device according to claim 1, wherein the winding assembly comprises: gear box, backup pad, locating hole, supporting seat, output shaft, bearing, spool, main cable, branch cable, be responsible for, sleeve pipe and barrier disc, wherein, the locating hole set up in the backup pad, the screw passes the locating hole will the backup pad sets up on the outer wall, the gear box set up in the backup pad, the supporting seat sets up on the outer wall, the output shaft with the gear box is connected, the bearing housing is located on the output shaft, and support on the supporting seat, the spool pipe box is located on the output shaft, main cable with divide the cable to twine in on the spool, be responsible for respectively with the sleeve pipe with the barrier disc is connected, the sleeve pipe with annular beam in the guardrail subassembly is connected, the barrier disc respectively with main cable with divide the cable to connect.
7. The exterior wall insulation construction device of claim 1, wherein the paint scraper assembly comprises: the device comprises a guide rail, a coating bin, a material blocking roller, a scraping roller, a sliding block, a connecting rod, a thrust spring, a positioning block, a long hole, a roller shaft, a roller barrel, a blocking ring, a pressing ring, a positioning threaded hole, a guiding through hole and a blocking ring, wherein the guide rail is arranged on a supporting beam in the suspension assembly, a screw penetrates through the positioning threaded hole to arrange the positioning block on the guide rail, the guiding through hole is arranged on the positioning block, the sliding block is arranged on the guide rail, the first end of the connecting rod is connected with the sliding block, the second end of the connecting rod penetrates through the guiding through hole, the blocking ring is arranged at the second end of the connecting rod, the thrust spring is sleeved on the connecting rod, the coating bin is arranged on the sliding block, the material blocking roller is arranged on the coating bin, the pressing ring is respectively connected with the coating bin and the roller shaft, and the blocking ring is connected with the roller shaft, the strip hole is arranged on the baffle ring, and the roller is connected with the roller shaft.
CN202010850074.XA 2020-08-21 2020-08-21 External wall heat insulation construction device and construction method Active CN112177296B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010850074.XA CN112177296B (en) 2020-08-21 2020-08-21 External wall heat insulation construction device and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010850074.XA CN112177296B (en) 2020-08-21 2020-08-21 External wall heat insulation construction device and construction method

Publications (2)

Publication Number Publication Date
CN112177296A CN112177296A (en) 2021-01-05
CN112177296B true CN112177296B (en) 2022-05-13

Family

ID=73925101

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010850074.XA Active CN112177296B (en) 2020-08-21 2020-08-21 External wall heat insulation construction device and construction method

Country Status (1)

Country Link
CN (1) CN112177296B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117967089A (en) * 2024-04-02 2024-05-03 中国建筑设计研究院有限公司 Reinforcing construction device for external heat insulation board

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201679103U (en) * 2010-05-12 2010-12-22 合肥乐千年涂料有限公司 Movable outer-wall heat preservation plate on-site slurry wiping machine
US8448959B1 (en) * 2011-12-20 2013-05-28 Scissor Works Accessories, LLC Toolbox and tool mount for aerial work platform
CN110541542A (en) * 2019-08-19 2019-12-06 惠州市鸿泰建筑工程有限公司 Environment-friendly inner wall and construction method thereof

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ATE185182T1 (en) * 1996-01-12 1999-10-15 Marmorit Gmbh STORAGE DEVICE FOR PROVIDING STACKABLE BUILDING MATERIAL, IN PARTICULAR THERMAL INSULATION BOARDS, ON A BUILDING OR FACADE SCAFFOLDING
US7266933B2 (en) * 2004-04-14 2007-09-11 Pasek Mark E Sheet material handling device
CN103924777B (en) * 2014-04-18 2016-07-06 武汉理工大学 The decorating outer wall of building special suspension platform of construction
CN107642227A (en) * 2017-11-10 2018-01-30 中国三冶集团有限公司 Multi-functional suspension platform in exterior-wall heat insulation construction
CN209556331U (en) * 2019-01-30 2019-10-29 吴奇 A kind of building hanging basket for house construction engineering
CN210888014U (en) * 2019-08-02 2020-06-30 中冶天工集团有限公司 Electric hanging basket auxiliary operation platform
CN110894752A (en) * 2019-12-20 2020-03-20 沈阳航空航天大学 A installation device for building external wall insulation board
CN111364748A (en) * 2020-03-30 2020-07-03 王永竹 A outer wall whitewashes hanging flower basket structure for construction

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201679103U (en) * 2010-05-12 2010-12-22 合肥乐千年涂料有限公司 Movable outer-wall heat preservation plate on-site slurry wiping machine
US8448959B1 (en) * 2011-12-20 2013-05-28 Scissor Works Accessories, LLC Toolbox and tool mount for aerial work platform
CN110541542A (en) * 2019-08-19 2019-12-06 惠州市鸿泰建筑工程有限公司 Environment-friendly inner wall and construction method thereof

Also Published As

Publication number Publication date
CN112177296A (en) 2021-01-05

Similar Documents

Publication Publication Date Title
US4103795A (en) Lifting and loading device
CN112177296B (en) External wall heat insulation construction device and construction method
CN105600582A (en) Cable pay-off device and use method thereof
JP6639928B2 (en) Pump lifting device and pump lifting method
CN110054404A (en) A kind of auxiliary system of glass cutting machine
CN112209264B (en) Battery hoisting accessory is used in new energy automobile processing
CN211949482U (en) Adjustable supporting vehicle for construction engineering construction
CN209297829U (en) A kind of lifting tray of high winch
CN112441523B (en) Material lifting device for constructional engineering
CN104192269B (en) A kind of seatainer positioning guide rail mechanism
CN217498316U (en) Line protection mechanism for electromechanical equipment installation
CN219585041U (en) Novel high-level heavy storage shelf
CN112850536A (en) Building machinery hoist engine
CN212009410U (en) Take humiture automatically regulated's power dispatching platform
CN220611773U (en) Inverted disc pay-off rack convenient to install and limit
CN221102897U (en) Automatic pay-off support of cable for cable laying
CN215478801U (en) Cable pay-off rack
CN216583607U (en) Marine shore power cable winding and unwinding devices
CN219950118U (en) Anti-rolling device for assembling and disassembling cable drum
CN215248662U (en) Pay-off is used to 5G communication cable
CN219009818U (en) Dedicated elevating gear of clean laboratory water and electricity installation
CN219031347U (en) Cable paying-off device with braking mechanism
CN214604298U (en) Portable tower section of thick bamboo is work box for installation
CN214616425U (en) Pressure control device for drilling field equipment management
CN220078133U (en) Mobilizable construction pay off rack

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant