CN112081118A - A kind of pile-anchor support foundation pit deepening reinforcement support structure and construction method thereof - Google Patents
A kind of pile-anchor support foundation pit deepening reinforcement support structure and construction method thereof Download PDFInfo
- Publication number
- CN112081118A CN112081118A CN202011045839.9A CN202011045839A CN112081118A CN 112081118 A CN112081118 A CN 112081118A CN 202011045839 A CN202011045839 A CN 202011045839A CN 112081118 A CN112081118 A CN 112081118A
- Authority
- CN
- China
- Prior art keywords
- pile
- support
- original
- piles
- newly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 25
- 230000002787 reinforcement Effects 0.000 title claims description 36
- 238000009412 basement excavation Methods 0.000 claims abstract description 15
- 238000000034 method Methods 0.000 claims description 22
- 230000008569 process Effects 0.000 claims description 7
- 230000003014 reinforcing effect Effects 0.000 abstract description 5
- 230000002708 enhancing effect Effects 0.000 abstract 1
- 238000013461 design Methods 0.000 description 23
- 239000002689 soil Substances 0.000 description 10
- 229910000831 Steel Inorganic materials 0.000 description 7
- 239000010959 steel Substances 0.000 description 7
- 238000003466 welding Methods 0.000 description 6
- 230000008901 benefit Effects 0.000 description 5
- 238000006073 displacement reaction Methods 0.000 description 5
- 238000005553 drilling Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 238000012544 monitoring process Methods 0.000 description 3
- 239000013049 sediment Substances 0.000 description 3
- 238000004088 simulation Methods 0.000 description 3
- 239000002002 slurry Substances 0.000 description 3
- 238000005728 strengthening Methods 0.000 description 3
- 238000012360 testing method Methods 0.000 description 3
- 238000011161 development Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000000203 mixture Substances 0.000 description 2
- 230000009466 transformation Effects 0.000 description 2
- 238000004458 analytical method Methods 0.000 description 1
- 238000004873 anchoring Methods 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 210000002435 tendon Anatomy 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
- 230000003313 weakening effect Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/76—Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
技术领域technical field
本发明涉及基坑工程支护加固技术领域,尤其涉及一种桩锚支护基坑增深加固支护结构及其施工方法。The invention relates to the technical field of foundation pit engineering support and reinforcement, in particular to a pile-anchor support foundation pit deepening reinforcement support structure and a construction method thereof.
背景技术Background technique
随着经济与城市化的快速发展,可供建筑用地越来越少,为满足人们生活、工作空间的各种需求,城市地下空间的利用和开发成为越来越多人关注的热点。基坑开挖规模与深度越来越大,随之而来的是基坑支护的难度与周边环境的复杂情况的增加。当基坑支护结构本已或将要施工完成,但是由于设计规划的修改,例如地下室增层设计等,致使基坑需在原设计基础上增深开挖。With the rapid development of economy and urbanization, there is less and less land available for construction. In order to meet the various needs of people's living and working space, the utilization and development of urban underground space has become a hot spot that more and more people pay attention to. The excavation scale and depth of the foundation pit are getting larger and larger, and the difficulty of supporting the foundation pit and the complexity of the surrounding environment have also increased. When the foundation pit supporting structure has been or will be completed, but due to the modification of the design plan, such as the basement addition layer design, etc., the foundation pit needs to be further excavated on the basis of the original design.
而基坑增深开挖引起的基坑内力值会超过最初基坑支护方案的内力值设计值,必将导致原有基坑支护设计不能满足支护强度要求,对于基坑的整体安全稳定性影响巨大。这就使得现有基坑面临两种选择:一种是放弃现有基坑重新进行支护设计,再或者在原有支护基础上进行设计加强。对于建设单位来说,基坑安全和经济效益是主要考虑的方面。显然,现有基坑支护结构如果废弃,将会造成大量资源浪费,加大工程成本,但是如果能利用已有基坑支护结构进行设计加强,与此同时,合理设计改造,减小造价成本,必然为工程取得良好效益。因此,在原有支护结构上进行支护结构的设计加强并保证施工过程中基坑安全与稳定,具有重要价值。However, the internal force value of the foundation pit caused by the deepening and excavation of the foundation pit will exceed the design value of the internal force value of the original foundation pit support plan, which will inevitably lead to the original foundation pit support design cannot meet the support strength requirements. The stability impact is huge. This makes the existing foundation pit face two choices: one is to give up the existing foundation pit and re-design the support, or to design and strengthen on the basis of the original support. For the construction unit, the safety and economic benefits of the foundation pit are the main considerations. Obviously, if the existing foundation pit supporting structure is abandoned, it will cause a lot of waste of resources and increase the project cost, but if the existing foundation pit supporting structure can be used for design and strengthening, at the same time, reasonable design and transformation can reduce the cost. The cost is bound to achieve good benefits for the project. Therefore, it is of great value to strengthen the design of the support structure on the original support structure and ensure the safety and stability of the foundation pit during the construction process.
在现有技术中,针对原支护方式为桩锚支护的基坑全部增深开挖后的支护结构加固方式,主要为锚索增层加固方式,即:当原设计中支护桩与预应力锚索在施工完毕后,再在合适位置增设一层预应力锚索的加固方法。其中,传统桩锚支护体系主要包含:支护桩、锚索、腰梁、冠梁等。支护桩竖直打入基坑侧壁土层;冠梁与支护桩在桩顶处浇筑在一起;预应力锚索穿过腰梁打入土层,腰梁沿基坑侧壁设置,使锚索与支护桩、冠梁形成可以协同变形的整体。In the prior art, the reinforcement method of the supporting structure after the excavation of all the foundation pits where the original supporting method is the pile-anchor support is mainly the reinforcement method of adding layers of anchor cables, that is, when the supporting piles are in the original design After the construction of the prestressed anchor cable is completed, a reinforcement method of adding a layer of prestressed anchor cable in a suitable position. Among them, the traditional pile-anchor support system mainly includes: support piles, anchor cables, waist beams, crown beams, etc. The supporting pile is vertically driven into the soil layer on the side wall of the foundation pit; the crown beam and the supporting pile are poured together at the top of the pile; the prestressed anchor cable is driven into the soil layer through the waist beam, and the waist beam is set along the side wall of the foundation pit to make The anchor cable, the supporting pile and the crown beam form a whole that can be deformed cooperatively.
上述锚索增层加固方式虽然可以在一定程度上弥补由于基坑加深开挖造成的原支护桩嵌固深度不足而带来的原支护体系载力不足的情况,但是其有以下几个方面缺点:Although the above anchor cable reinforcement method can make up for the insufficient bearing capacity of the original support system caused by the insufficient depth of the original support pile due to the deepening and excavation of the foundation pit to a certain extent, it has the following aspects: Disadvantages:
(1)增设锚索的作用在于加强支护桩桩身与坑壁土体的连接强度,通过支护桩来间接限制坑壁土体的位移,可以减少支护桩底部嵌固端的位移过大,弥补其承载力减弱的问题,但仍未在根本上解决原支护桩嵌固深度不足的问题,在某些工况中,比如当基坑加深开挖深度较大、基坑侧向土压力较大时,此种加固方法很容易失效,给施工造成极大的安全隐患。(1) The function of adding anchor cables is to strengthen the connection strength between the supporting pile body and the soil on the pit wall, and indirectly limit the displacement of the soil on the pit wall through the supporting pile, which can reduce the excessive displacement of the embedded end of the supporting pile. , to make up for the weakening of its bearing capacity, but it has not fundamentally solved the problem of insufficient embedding depth of the original support piles. When the pressure is high, this reinforcement method is easy to fail, causing great safety hazards to the construction.
发明内容SUMMARY OF THE INVENTION
本发明所要解决的技术问题是提供一种加固效果更好的桩锚支护基坑增深加固支护结构及其施工方法,以解决桩锚支护体系由于基坑增深开挖导致的支护强度不足的问题。The technical problem to be solved by the present invention is to provide a pile-anchor support foundation pit deepening reinforcement support structure and a construction method thereof with better reinforcement effect, so as to solve the problem of the pile-anchor support system caused by the deepening and excavation of the foundation pit. The problem of insufficient protective strength.
为解决上述问题,本发明所述的一种桩锚支护基坑增深加固支护结构,包括原桩锚支护体系中的原支护桩、设在所述原支护桩上的腰梁和外端固定在所述腰梁上的原预应力锚索,以及新增长支护桩、新增预应力锚索和新设冠梁;所述新增长支护桩在所述原支护桩桩间布设且两者保持在同一平面,所述新增长支护桩贯穿整个基坑新的开挖深度,其顶部与所述原支护桩的顶部平齐并通过所述新设冠梁浇筑连接为一体;所述新增预应力锚索在所述原支护桩和所述新增长支护桩两种桩的桩间分布且其外端固定在所述腰梁上。In order to solve the above problems, the pile-anchor support foundation pit deepening and strengthening support structure according to the present invention includes the original support pile in the original pile-anchor support system, and the waistband arranged on the original support pile. The beam and the original prestressed anchor cables whose outer ends are fixed on the waist beam, as well as the new growth support piles, the newly added prestressed anchor cables and the new crown beams; the new growth support piles are in the original support The piles are arranged between the piles and the two are kept on the same plane. The newly increased support piles run through the new excavation depth of the entire foundation pit, and the tops of the new growth piles are flush with the tops of the original support piles and pass through the new crown beams. The pouring and connection are integrated; the newly added prestressed anchor cables are distributed between the original support piles and the newly increased support piles, and their outer ends are fixed on the waist beam.
优选的,所述新增长支护桩的桩径等于或者大于所述原支护桩的桩径。Preferably, the diameter of the newly grown support pile is equal to or greater than the diameter of the original support pile.
优选的,所述新增长支护桩间隔一根或者两根或者更多所述原支护桩布设。Preferably, the newly grown support piles are arranged at intervals of one or two or more of the original support piles.
本发明还相应提供了一种桩锚支护基坑增深加固支护结构的施工方法,该施工方法包括:The present invention also correspondingly provides a construction method for the pile-anchor support foundation pit to deepen and strengthen the support structure, and the construction method includes:
破除原桩锚支护体系中的原冠梁,并且在破除过程中尽量避免打断原支护桩的主筋;Break the original crown beam in the original pile anchor support system, and try to avoid breaking the main reinforcement of the original support pile during the breaking process;
按要求内插实施新增长支护桩;Interpolate and implement new growth support piles as required;
在所有所述新增长支护桩实施完毕后,完成新增预应力锚索的施工以及新设冠梁的浇筑,在浇筑过程中尽量顺直所述原支护桩的主筋并就近原则锚固浇筑于所述新设冠梁中。After all the new growth support piles are implemented, the construction of the newly added prestressed anchor cables and the pouring of the new crown beams are completed. in the new crown beam.
本发明与现有技术相比具有以下优点:Compared with the prior art, the present invention has the following advantages:
1、本发明采用“原支护桩桩间插入长支护桩+预应力锚索”的加固方式,新增长支护桩贯穿整个基坑开挖深度,通过腰梁、新设冠梁的连接,与原支护结构形成统一整体,能够有效增大围护结构的整体刚度和协同变形能力,加强围护结构承载力。并且本发明加固形式通过数值模拟与现场试验、监测证明基坑变形控制效果较好。2、本发明利用已有基坑支护结构进行设计加强,进行合理的设计改造和施工,减小造价成本,为工程取得良好效益。1. The present invention adopts the reinforcement method of "inserting long support piles + prestressed anchor cables between the original support piles", and the newly increased support piles run through the entire excavation depth of the foundation pit, and are connected by the waist beam and the newly installed crown beam. , forming a unified whole with the original supporting structure, which can effectively increase the overall stiffness and cooperative deformation capacity of the enclosure structure, and strengthen the bearing capacity of the enclosure structure. And the reinforcement form of the present invention proves that the deformation control effect of the foundation pit is better through numerical simulation, field test and monitoring. 2. The present invention utilizes the existing foundation pit supporting structure to carry out design enhancement, carries out reasonable design transformation and construction, reduces the cost of construction, and obtains good benefits for the project.
附图说明Description of drawings
下面结合附图对本发明的具体实施方式作进一步详细的说明。The specific embodiments of the present invention will be described in further detail below with reference to the accompanying drawings.
图1为本发明实施例提供的加固支护结构的示意图。FIG. 1 is a schematic diagram of a reinforced support structure provided by an embodiment of the present invention.
图2为本发明实施例提供的桩间分布的俯视图。FIG. 2 is a top view of distribution among piles according to an embodiment of the present invention.
图3为本发明实施例提供的预应力锚索施工剖面图。FIG. 3 is a sectional view of the construction of the prestressed anchor cable according to the embodiment of the present invention.
图中:1—原支护桩,2—新增长支护桩,3—腰梁,4—新增预应力锚索,5—新设冠梁。In the picture: 1—the original supporting pile, 2—the newly increased supporting pile, 3—the waist beam, 4—the newly added prestressed anchor cable, 5—the new crown beam.
具体实施方式Detailed ways
首先需要特别说明的是,虽然长短桩支护体系是现有技术中公知的,但这是一种基坑支护方式,而本发明所提出的是一种桩锚支护基坑增深加固支护结构,是一种基坑支护的加固方式,区别就在于前提是增深开挖、加固结构,应用原支护桩桩间插入长支护桩,前提不同涉及领域就不同。First of all, it should be noted that although the long and short pile support system is well known in the prior art, this is a foundation pit support method, and the present invention proposes a pile anchor support foundation pit depth reinforcement The support structure is a reinforcement method for foundation pit support. The difference lies in the premise of deepening the excavation, strengthening the structure, and inserting long supporting piles between the original supporting piles. Different premise involves different fields.
参考图1和图2,本发明实施例提供了一种桩锚支护基坑增深加固支护结构,主要包括原桩锚支护体系中的原支护桩1、设在原支护桩1上的腰梁3和外端固定在腰梁3上的原预应力锚索,以及新增长支护桩2、新增预应力锚索4和新设冠梁5。Referring to FIGS. 1 and 2 , an embodiment of the present invention provides a pile-anchor support foundation pit deepening reinforcement support structure, which mainly includes the
新增长支护桩2在原支护桩1桩间布设,两者内侧平齐且保持在同一平面,新增长支护桩2贯穿整个基坑新的开挖深度,其顶部与原支护桩1的顶部平齐并通过新设冠梁5浇筑连接为一体。其中,新增长支护桩2与原支护桩1保持在同一平面,不会对基坑开挖工作面造成影响。The new
新增预应力锚索4在原支护桩1和新增长支护桩2两种桩的桩间分布且其外端固定在腰梁3上。在实际应用中,预应力锚索锚索具体布置形式、间距和数量以及施加荷载视工程具体要求。The newly added
新增长支护桩2的桩径等于或者大于原支护桩1的桩径。在实际应用中,新增长支护桩2在满足足够的嵌固深度的同时可按设计增大截面尺寸以加强桩身刚度。The diameter of the newly grown supporting
新增长支护桩2间隔一根或者两根或者更多原支护桩1布设。在实际应用中,根据基坑实际情况,综合考虑基坑安全与经济效益,选择不同的布置间距,例如:可以选择间隔一根原支护桩布置或间隔两根原支护桩进行布置,在承载力较薄弱处可视情况适当加大密度。图1中示出的是“每隔两根原支护桩增设一根长支护桩”情况。The new
基于上述实施例公开的加固支护结构,本发明实施例相应提供了一种施工方法,该施工方法主要包括如下步骤:Based on the reinforced support structure disclosed in the above embodiments, the embodiments of the present invention provide a construction method correspondingly, and the construction method mainly includes the following steps:
1、破除原桩锚支护体系中的原冠梁,并且在破除过程中尽量避免打断原支护桩1的主筋。1. Remove the original crown beam in the original pile anchor support system, and try to avoid breaking the main reinforcement of the
2、按要求内插实施新增长支护桩2。2. Interpolate and implement new growth support piles 2 as required.
3、在所有新增长支护桩2实施完毕后,完成新增预应力锚索4的施工以及新设冠梁5的浇筑,在浇筑过程中尽量顺直原支护桩1的主筋并就近原则锚固浇筑于新设冠梁5中。3. After the implementation of all the new
其中,除了上文指出并强调的内容,关于步骤2中新增长支护桩2、步骤3中新增预应力锚索4以及新设冠梁5三者的施工工艺本身参考现有技术即可。不过,为便于本领域技术人员理解本方案内容,以下仍给出详细实施内容。Among them, in addition to the content pointed out and emphasized above, the construction technology of the newly increased
在上述步骤2中,新增长支护桩2的实施可以参考以下内容:In the
①成孔工艺及技术要求①Hole forming process and technical requirements
(1)成孔可采用泥浆护壁机械成孔;(1) The hole can be formed by mechanical mud retaining wall;
(2)开钻前应充分做好准备工作,成孔施工应一次不间断完成,不得无故停钻;成孔与灌注间隔时间不应超过24小时;(2) The preparation work should be fully prepared before drilling, the hole forming construction should be completed at one time without interruption, and the drilling should not be stopped for no reason; the interval between hole forming and pouring should not exceed 24 hours;
(3)开孔时应控制钻进速度,防止孔内坍塌和孔斜;(3) The drilling speed should be controlled when opening the hole to prevent collapse in the hole and inclination of the hole;
(4)桩位偏差≤50mm,垂直度偏差<1%,桩底沉渣厚度≤200mm;(4) The pile position deviation is less than or equal to 50mm, the verticality deviation is less than 1%, and the thickness of the sediment at the bottom of the pile is less than or equal to 200mm;
②钢筋笼制作②Rebar cage production
(1)钢筋笼外形尺寸应符合设计要求,其允许偏差如下:(1) The dimensions of the steel cage should meet the design requirements, and the allowable deviations are as follows:
主筋间距:±10mm 箍筋间距:±20mmSpacing between main bars: ±10mm Spacing between stirrups: ±20mm
钢筋笼直径:±10mm 钢筋笼总长:±100mmSteel cage diameter: ±10mm Total length of steel cage: ±100mm
钢筋笼保护层:±20mmReinforcing cage protection layer: ±20mm
(2)钢筋笼主筋可采用搭接焊连接,采用搭接焊时,搭接长度单面焊,焊缝长度不小于10倍钢筋直径,双面焊焊缝长度不小于5倍钢筋直径,钢筋笼内加强筋与主筋采用焊接连接方式,箍筋与主筋采用绑扎或点焊连接;(2) The main reinforcement of the reinforcement cage can be connected by lap welding. When using lap welding, the length of the lap joint shall be welded on one side, the length of the weld shall not be less than 10 times the diameter of the steel bar, and the length of the double-sided welding shall not be less than 5 times the diameter of the steel bar. The reinforcing bars in the cage and the main bars are connected by welding, and the stirrups and the main bars are connected by binding or spot welding;
(3)钢筋笼宜整段制作,在起吊、运输、安装中应采取措施防治变形,吊点部位应设置外箍或内箍加强钢筋,分段沉放时,纵筋的连接采用焊接,要特别注意焊接质量,同一截面上接头数量不得大于50%,相邻接头间距为35d且不小于500mm;钢筋笼放置方向与设计方向一致。(3) The steel cage should be made in a whole section. Measures should be taken to prevent deformation during lifting, transportation and installation. The outer hoop or inner hoop reinforcement should be set at the lifting point. Pay special attention to the welding quality. The number of joints on the same section shall not be greater than 50%, and the distance between adjacent joints shall be 35d and not less than 500mm; the placement direction of the reinforcement cage is consistent with the design direction.
③桩身砼浇注③Pile body concrete pouring
(1)钻孔桩达到孔底设计标高时,及时验收,验收合格后应及时浇灌桩身砼;(1) When the bored pile reaches the design elevation of the bottom of the hole, it shall be checked and accepted in time, and the pile body shall be poured in time after the acceptance is passed;
(2)砼配合比应通过计算或试配确定;(2) The concrete mix ratio should be determined by calculation or trial mix;
(3)使用材料应具有质量证明书和经检验合格后方可使用;(3) The materials used shall have quality certificates and have passed the inspection before they can be used;
(4)拌制砼时应按配合比严格计量;(4) When mixing concrete, it should be strictly measured according to the mixing ratio;
(5)桩身砼浇灌应采用导管法灌注,砼必须具有良好的和易性和流动性,坍落度一般为180~220mm,砼应连续一次灌注完毕,并保证密实度;(5) The concrete of the pile body should be poured by the conduit method. The concrete must have good workability and fluidity. The slump is generally 180~220mm.
(6)浇筑导管应埋入砼表面,严禁导管提出砼面,严格控制导管拆卸时间,砼浇注要连续进行,导管底部应固定振动器,将桩身混凝土捣实,边灌边振。在浇注砼同时,应有专门人员记录导管埋深和导管内外砼面高差,以便及时提升和拆卸导管。(6) The pouring conduit should be buried in the concrete surface. It is strictly forbidden for the conduit to lift the concrete surface. The dismantling time of the conduit should be strictly controlled. Concrete pouring should be carried out continuously. When pouring concrete, special personnel should record the buried depth of the conduit and the height difference between the inner and outer concrete surfaces of the conduit, so that the conduit can be lifted and removed in time.
(7)冠梁施工前,应将桩顶浮浆凿除清理干净,桩顶以上出露的钢筋长度符合锚固要求。(7) Before the construction of the crown beam, the floating slurry on the top of the pile should be chiseled and cleaned up, and the length of the exposed steel bars above the top of the pile should meet the anchoring requirements.
在上述步骤3中,新增预应力锚索4的实施可以参考以下内容:In the
①预应力锚索成孔①Prestressed anchor cable into hole
预应力锚索采用机械成孔,锚孔倾斜角为水平向12-20°,锚孔成孔需采用跟管钻进施工工艺以防止孔内坍塌;考虑沉渣的影响,为确保锚索深度,实际钻孔深度要大于设计深度0.50m。锚孔成孔后必须清理锚孔内的沉渣,力求清理干净。The prestressed anchor cable is made of mechanical holes, and the inclination angle of the anchor hole is 12-20° horizontally. The anchor hole should be drilled with a pipe to prevent the collapse in the hole; considering the influence of sediment, in order to ensure the depth of the anchor cable, The actual drilling depth should be greater than the design depth by 0.50m. After the anchor hole is formed, the sediment in the anchor hole must be cleaned, and strive to clean it up.
②预应力锚索设置②Prestressed anchor cable setting
预应力锚索杆体在使用前应平直、除锈、除油,并严格按设计尺寸下料;预应力锚索放入锚孔前尽可能对孔内残存及扰动的废土进行清除;预应力锚索连同注浆管放入锚孔中应沿锚孔中心线放入,避免孔壁土体扰动坍塌,若孔壁土体坍塌应拔出锚索清除坍塌土体;预应力锚索放入锚孔后应及时封堵、注浆。The rod body of the prestressed anchor cable should be straight, rust-removed, and oil-removed before use, and the material should be cut strictly according to the design size; When the stress anchor cable and grouting pipe are put into the anchor hole, they should be placed along the center line of the anchor hole to avoid the disturbance and collapse of the hole wall soil. If the hole wall soil collapses, the anchor cable should be pulled out to remove the collapsed soil; After entering the anchor hole, it should be blocked and grouted in time.
③预应力锚索注浆③ Prestressed anchor cable grouting
注浆体应严格按设计要求配制,不得随意变动。注浆时,注浆管应插至距孔底50-100mm,注浆压力达到0.60MPa,稳压2分钟,且直到浆液从孔口溢出为止,否则应进行补浆。灌浆后,浆体强度未达到设计要求前,锚索不得受到扰动。The grouting body should be prepared in strict accordance with the design requirements and must not be changed at will. When grouting, the grouting pipe should be inserted to 50-100mm from the bottom of the hole, the grouting pressure should reach 0.60MPa, and the pressure should be stabilized for 2 minutes, until the slurry overflows from the orifice, otherwise the grouting should be carried out. After grouting, the anchor cable shall not be disturbed until the strength of the grout does not meet the design requirements.
④预应力锚索张拉、锁定④Prestressed anchor cable tensioning and locking
当浆体强度达到设计强度85%后,进行张拉锁定,张拉锁定无异常后,不得切除外露的预应力筋,以便于后期进行补力张拉。When the strength of the slurry reaches 85% of the design strength, tensioning and locking are performed. After the tensioning and locking are normal, the exposed prestressed tendons shall not be removed, so as to facilitate the supplementary tensioning in the later stage.
实际案例actual case
兰州某增深开挖基坑工程,本工程采取了桩锚支护体系,由于后期设计变更(地下室增层),经讨论,要对原支护结构进行加固设计,遂采用现有技术中常用的“锚索增层加固设计”,但是基坑的变形控制是考验支护结构是否有效的重要指标,该加固方式并未取得理想的效果:使用此种加固方法后,基坑土体水平位移、竖向位移、支护桩深层土体位移等基坑变形指标均不符合要求,可见此种加固方案对某些基坑开挖较深且基坑侧向土压力较大的情况下并不适用。In a deep excavation foundation pit project in Lanzhou, the project adopts the pile-anchor support system. Due to the later design change (basement addition), after discussion, the original support structure should be reinforced and designed, so the commonly used in the existing technology is adopted. However, the deformation control of the foundation pit is an important indicator to test whether the supporting structure is effective, and this reinforcement method has not achieved the desired effect: after using this reinforcement method, the horizontal displacement of the foundation pit soil , vertical displacement, deep soil displacement of supporting piles and other foundation pit deformation indicators do not meet the requirements, it can be seen that this reinforcement scheme is not suitable for some foundation pits where the excavation is deep and the lateral soil pressure of the foundation pit is large. Be applicable.
所以,立足于基坑的实际情况(基坑开挖较深且基坑侧向土压力较大),探究到出现问题的本质是原支护桩嵌固深度不足,研究后采用可以提供更大承载力的加固方案,即本发明“原支护桩桩间插入长支护桩+预应力锚索”的加固方案:前期首先经过严谨的数值模拟分析,结果显示基坑变形指标均符合基坑相关规范的要求,指标在安全范围内。后期进行了现场试验即现场施工,并配合基坑变形的现场监测,通过监测数据进一步验证此种加固方式的加固效果,并与前期模拟结果对比,得出的结论为;此种“原支护桩桩间插入长支护桩+预应力锚索”的加固结构可以很好地控制基坑变形,可以为桩锚支护基坑的增深加固提供强有力保证。Therefore, based on the actual situation of the foundation pit (the excavation of the foundation pit is deep and the lateral earth pressure of the foundation pit is large), it is found that the essence of the problem is that the depth of the original support pile is insufficient. The reinforcement scheme of bearing capacity, that is, the reinforcement scheme of "inserting long supporting piles + prestressed anchor cables between the original supporting piles" of the present invention: after a rigorous numerical simulation analysis in the early stage, the results show that the deformation indicators of the foundation pit are consistent with the foundation pit. The requirements of relevant specifications, and the indicators are within the safe range. In the later stage, on-site testing was carried out, which is on-site construction, and in conjunction with on-site monitoring of foundation pit deformation, the reinforcement effect of this reinforcement method was further verified through monitoring data, and compared with the previous simulation results. The reinforcement structure of inserting long supporting piles + prestressed anchor cables between the piles can well control the deformation of the foundation pit, and can provide a strong guarantee for the deepening and reinforcement of the pile-anchor support foundation pit.
以上对本发明所提供的技术方案进行了详细介绍。本文中应用了具体个例对本发明的原理及实施方式进行了阐述,以上实施例的说明只是用于帮助理解本发明的方法及其核心思想。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以对本发明进行若干改进和修饰,这些改进和修饰也落入本发明权利要求的保护范围内。The technical solutions provided by the present invention have been introduced in detail above. The principles and implementations of the present invention are described herein by using specific examples, and the descriptions of the above embodiments are only used to help understand the method and the core idea of the present invention. It should be pointed out that for those skilled in the art, without departing from the principle of the present invention, several improvements and modifications can also be made to the present invention, and these improvements and modifications also fall within the protection scope of the claims of the present invention.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011045839.9A CN112081118A (en) | 2020-09-29 | 2020-09-29 | A kind of pile-anchor support foundation pit deepening reinforcement support structure and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011045839.9A CN112081118A (en) | 2020-09-29 | 2020-09-29 | A kind of pile-anchor support foundation pit deepening reinforcement support structure and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112081118A true CN112081118A (en) | 2020-12-15 |
Family
ID=73738824
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011045839.9A Pending CN112081118A (en) | 2020-09-29 | 2020-09-29 | A kind of pile-anchor support foundation pit deepening reinforcement support structure and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112081118A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114076418A (en) * | 2021-10-27 | 2022-02-22 | 中交第二公路勘察设计研究院有限公司 | Heat exchange system based on deep buried pipe energy support pile and construction process |
CN114197489A (en) * | 2021-12-31 | 2022-03-18 | 中国煤炭地质总局水文地质局 | Method for reinforcing slope protection pile during deepening of foundation pit |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006037633A (en) * | 2004-07-29 | 2006-02-09 | Taisei Corp | Basic structure and construction method |
CN105696602A (en) * | 2016-03-17 | 2016-06-22 | 中南勘察设计院(湖北)有限责任公司 | Composite pile-anchor supporting method and structure for deepening excavation |
CN206928300U (en) * | 2017-04-20 | 2018-01-26 | 中南勘察设计院(湖北)有限责任公司 | The foundation pit supporting construction that a kind of long-short pile combination passive area reinforces |
US20200291597A1 (en) * | 2019-08-08 | 2020-09-17 | Infrastructure Renewal Institute of Southern China | Assembled recyclable rectangular working well with preset detachable door opening and construction method thereof |
CN212506314U (en) * | 2020-09-29 | 2021-02-09 | 兰州理工大学 | A kind of pile-anchor support foundation pit deepening reinforcement support structure |
-
2020
- 2020-09-29 CN CN202011045839.9A patent/CN112081118A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2006037633A (en) * | 2004-07-29 | 2006-02-09 | Taisei Corp | Basic structure and construction method |
CN105696602A (en) * | 2016-03-17 | 2016-06-22 | 中南勘察设计院(湖北)有限责任公司 | Composite pile-anchor supporting method and structure for deepening excavation |
CN206928300U (en) * | 2017-04-20 | 2018-01-26 | 中南勘察设计院(湖北)有限责任公司 | The foundation pit supporting construction that a kind of long-short pile combination passive area reinforces |
US20200291597A1 (en) * | 2019-08-08 | 2020-09-17 | Infrastructure Renewal Institute of Southern China | Assembled recyclable rectangular working well with preset detachable door opening and construction method thereof |
CN212506314U (en) * | 2020-09-29 | 2021-02-09 | 兰州理工大学 | A kind of pile-anchor support foundation pit deepening reinforcement support structure |
Non-Patent Citations (2)
Title |
---|
徐希伟: "某增深基坑桩锚支护加固设计与模拟分析", 中国优秀硕士学位论文, no. 01, 15 January 2022 (2022-01-15), pages 038 - 1609 * |
许庆仁;范春青;: "广昊大厦深基坑再增深设计与施工关键技术", 施工技术, no. 13, 10 July 2017 (2017-07-10), pages 35 - 42 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114076418A (en) * | 2021-10-27 | 2022-02-22 | 中交第二公路勘察设计研究院有限公司 | Heat exchange system based on deep buried pipe energy support pile and construction process |
CN114076418B (en) * | 2021-10-27 | 2024-04-23 | 中交第二公路勘察设计研究院有限公司 | Heat exchange system based on deep buried pipe energy support pile and construction process |
CN114197489A (en) * | 2021-12-31 | 2022-03-18 | 中国煤炭地质总局水文地质局 | Method for reinforcing slope protection pile during deepening of foundation pit |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101250886B (en) | Method for reinforcing masonry structure building base | |
CN107542108A (en) | A kind of reverse construction method of building basement structure | |
CN111119198A (en) | A reinforced structure that is used for SMW worker method stake to strut system | |
CN110055973B (en) | Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method | |
CN105672450A (en) | Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure | |
CN104264683B (en) | Building concave shape ultra-deep foundation pit subregion supporting method is protected for three around literary composition | |
CN112081118A (en) | A kind of pile-anchor support foundation pit deepening reinforcement support structure and construction method thereof | |
CN108118689B (en) | Partially recyclable prefabricated underground diaphragm wall, spreader and construction method | |
CN113738399A (en) | Underground excavation tunnel large pipe shed guide wall structure and construction method thereof | |
CN211816279U (en) | New and old ground is wall interface processing structure even | |
CN212506314U (en) | A kind of pile-anchor support foundation pit deepening reinforcement support structure | |
CN111485560A (en) | Supporting structure of deep foundation pit under ultra-wide pipeline and construction method of deep foundation pit under ultra-wide pipeline | |
CN108221955B (en) | A prefabricated underground diaphragm wall, spreader and construction method that can be recycled as a whole | |
CN105484270A (en) | Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit | |
CN215860219U (en) | Large pipe shed guide wall structure of underground excavation tunnel | |
CN113685190B (en) | Reinforcing system for shield to penetrate shallow soft clay and construction method | |
CN112507424B (en) | A construction method for shield tunneling under expansive soil strata to pass through railway tracks | |
CN211312225U (en) | Pile-column integrated structure based on bridge transformed from existing road surface | |
CN115404885A (en) | Gradual retaining construction method suitable for multi-step high and steep slopes | |
CN210122735U (en) | Underground structure anti-floating system based on outward-protruding wing foot plate | |
CN209816867U (en) | A supporting construction for peripheral foundation ditch of existing building | |
CN221399033U (en) | Miniature steel-pipe pile pipeline foundation pit supporting structure | |
CN221919358U (en) | Premixed flow state solidification geotechnical pile | |
CN218233492U (en) | A Supporting Structure for Deep Foundation Pit in Binary Stratum of Upper Soil and Lower Rock | |
CN117822640B (en) | Combined grouting steel pipe pile unit, steel pipe pile foundation and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |