CN112031018A - Assembly type light supporting and retaining structure and construction method - Google Patents

Assembly type light supporting and retaining structure and construction method Download PDF

Info

Publication number
CN112031018A
CN112031018A CN202010999455.4A CN202010999455A CN112031018A CN 112031018 A CN112031018 A CN 112031018A CN 202010999455 A CN202010999455 A CN 202010999455A CN 112031018 A CN112031018 A CN 112031018A
Authority
CN
China
Prior art keywords
anchor
retaining wall
anchors
construction
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010999455.4A
Other languages
Chinese (zh)
Inventor
胡伟
林志
陈洁
杨枭
杨瑶
王辉
张翰林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University of Science and Technology
Zhongkai University of Agriculture and Engineering
Original Assignee
Hunan University of Science and Technology
Zhongkai University of Agriculture and Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University of Science and Technology, Zhongkai University of Agriculture and Engineering filed Critical Hunan University of Science and Technology
Priority to CN202010999455.4A priority Critical patent/CN112031018A/en
Publication of CN112031018A publication Critical patent/CN112031018A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses an assembled light retaining structure and a construction method thereof. The method comprises the following steps: step one, leveling and paying off; step two, excavating a slot position; step three, pouring concrete; step four, construction of the retaining wall; fifthly, filling construction; step six, excavating a slot position; seventhly, installing an anchoring body and arranging transverse and vertical connecting anchor cables; step eight, repeating the step four to the step seven; step nine, tensioning and locking the anchor cable; step ten, building the retaining wall to reach the design height; and eleventh, finishing construction. Has the advantages that: the period is saved; the manufacturing cost is low; the reliability is high; the integrity is good; the applicability is strong.

Description

一种装配式轻型支挡结构及施工方法Assembled light-duty support structure and construction method

技术领域technical field

本发明涉及一种支挡结构及施工方法,特别涉及一种装配式轻型支挡结构及施工方法。The invention relates to a support structure and a construction method, in particular to an assembled light support structure and a construction method.

背景技术Background technique

近年来,随着中西部地区交通建设项目的推进,出现了大批山区公路、铁路项目,由此便需在山区进行大规模的挖方工程。基于降低投资、减少占地的理念,山区公路、铁路的设计一般本着挖、填平衡的原则,因此将产生大量的填方工程。In recent years, with the advancement of transportation construction projects in the central and western regions, a large number of mountain road and railway projects have appeared, which requires large-scale excavation projects in mountainous areas. Based on the concept of reducing investment and land occupation, the design of mountain roads and railways is generally based on the principle of balance between excavation and filling, so a large number of filling works will be generated.

目前,常用的填方工程支挡结构有重力式挡土墙、锚定板挡土墙、加筋土挡土墙等,但这些支护结构都有所不足,在实际工程的应用上有一定的局限性。重力式挡土墙造价高且只适用于高度较低的填方支挡工程;锚定板挡土墙施工程序较复杂(竖直设置的锚定板位置易偏离),且单一拉杆断裂会大幅增大临近拉杆拉力,容易引发连锁反应,造成局部破坏;加筋土挡土墙一般应用于地形较为平坦且宽敞的路段,地形陡峭的山坡则不利于布置拉筋。现有技术的局限性制约了工程建设的发展,现行规范所规定的用于填方工程的支挡结构难以适应大规模山区交通项目快速建设的要求。因此十分需要研究开发一种安全可靠、经济合理、技术先进的新型装配式轻型支挡结构,使其向小型化、轻型化、规模化、机械化方向发展,并能实现支挡高度最大化。At present, the commonly used supporting structures for filling engineering include gravity retaining wall, anchoring plate retaining wall, reinforced soil retaining wall, etc., but these supporting structures are all insufficient, and have certain advantages in practical engineering applications. limitations. Gravity retaining walls are expensive and only suitable for low-height filling and retaining projects; the construction procedures of anchor plate retaining walls are more complicated (the position of the vertically set anchor plate is easy to deviate), and the fracture of a single tie rod will greatly Increasing the tension of the adjacent tie rods is likely to cause a chain reaction and cause local damage; reinforced earth retaining walls are generally used in relatively flat and spacious road sections, and steep hillsides are not conducive to tie bars. The limitation of the existing technology restricts the development of engineering construction, and the support structure for filling engineering stipulated by the current specification is difficult to meet the requirements of rapid construction of large-scale mountain transportation projects. Therefore, it is very necessary to research and develop a new type of assembled light support structure that is safe, reliable, economical, reasonable and technologically advanced, so that it can develop in the direction of miniaturization, light weight, scale and mechanization, and can maximize the support height.

发明内容SUMMARY OF THE INVENTION

本发明的主要目的是为了解决现有填方工程中所用的支挡结构存在诸多问题而提供的一种装配式轻型支挡结构及施工方法。The main purpose of the present invention is to provide an assembled light-duty retaining structure and a construction method in order to solve many problems of the retaining structure used in the existing filling engineering.

本发明提供的装配式轻型支挡结构包括有基础、挡土墙、锚索、锚固体和连接杆,其中挡土墙设置在基础上,锚固体设在挡土墙后方的回填土内,锚索的前端穿设在挡土墙上,锚索的后端与挡土墙后方回填土内的锚固体相固连,相邻的锚固体之间由锚索和连接杆连接,挡土墙和锚固体形成一种立体的支挡结构。The assembled light-duty retaining structure provided by the present invention includes a foundation, a retaining wall, an anchor cable, an anchor and a connecting rod, wherein the retaining wall is arranged on the foundation, the anchor is arranged in the backfill behind the retaining wall, and the anchor The front end of the cable passes through the retaining wall, and the rear end of the anchor cable is fixedly connected with the anchor solid in the backfill behind the retaining wall. The adjacent anchor solids are connected by the anchor cable and the connecting rod. The anchor body forms a three-dimensional support structure.

基础为凹槽型构造,凹槽内设置有榫头,挡土墙为装配式的,挡土墙由预制块砌筑而成,每块预制块的上部均设置有榫头,每块预制块的底部均设置榫槽,榫头与榫槽的位置和尺寸相对应,榫头插入榫槽内实现拼接,挡土墙最下层预制块底部的榫槽插设在基础凹槽内的榫头上。The foundation is a groove-type structure with tenons in the grooves. The retaining wall is prefabricated. The retaining wall is made of prefabricated blocks. The upper part of each prefabricated block is provided with tenons, and the bottom of each prefabricated block is installed. Tongues and grooves are all provided, and the positions and sizes of the tenons correspond to the tenon grooves. The tenons are inserted into the tenon grooves to realize splicing. The tenon grooves at the bottom of the lowermost prefabricated blocks of the retaining wall are inserted into the tenons in the foundation grooves.

锚索的前端穿过挡土墙后的端头螺接在锚具上,锚索的后端螺接在挡土墙后方回填土内的锚固体上,上下相邻的锚固体也由锚索进行连接,沿挡土墙长度方向的纵向相邻的锚固体由连接杆进行连接。The front end of the anchor cable is screwed to the anchor after passing through the retaining wall, and the rear end of the anchor cable is screwed to the anchor in the backfill behind the retaining wall. For connection, the longitudinally adjacent anchors along the length of the retaining wall are connected by connecting rods.

穿设有锚索的预制块上预留有锚索孔。An anchor cable hole is reserved on the prefabricated block through which the anchor cable is passed.

本发明提供的装配式轻型支挡结构的施工方法,具体如下所述:The construction method of the assembled light-duty support structure provided by the present invention is specifically as follows:

步骤一、场地平整,测量放线:场地平整前,组织人员到场地进行现场勘察,了解场地地形、地貌和周围环境,根据设计要求及建设规划确定场地平整的范围,场地平整前将场地平整范围内的障碍物清理干净,场地通过机械或人工方式开挖土方,改造成支挡结构设计所要求的平面,并确保平整后场地平面上无膨胀土、盐渍土及有腐蚀作用的酸性土和有机质土;Step 1. Leveling the site, measuring and setting out the line: Before leveling the site, organize personnel to conduct on-site surveys to understand the topography, landform and surrounding environment of the site, and determine the scope of site leveling according to the design requirements and construction planning, and level the site before leveling. The obstacles in the site are cleaned up, and the site is excavated mechanically or manually to transform it into the plane required by the design of the supporting structure, and ensure that there is no expansive soil, saline soil, and corrosive acidic soil and soil on the site after leveling. organic soil;

工程开工后进行第一次放线,放线工具为“全站仪”,根据定位图进行定位,最后在施工现场确定定位桩,确定定位桩后,用“经纬仪”对基础工程和主体工程进行放线及测量,根据定位桩测出场地轴线控制桩,控制桩采用保护桩,高程引入现场,采用闭合回测法,设置场内水准点,轴线测定使用“经纬仪”,水准点测量用“水准仪”;After the start of the project, the first line-out is carried out. The line-out tool is "total station", and the positioning is carried out according to the positioning map. Finally, the positioning piles are determined at the construction site. Line-out and measurement, the site axis control pile is measured according to the positioning pile, the control pile adopts the protection pile, the elevation is introduced into the site, the closed back measurement method is adopted, and the level point in the site is set. ";

步骤二、开挖基础槽位:根据设计要求,采用人工开挖法开挖符合要求的基础槽位大小,为确保土坡稳定,开挖时采用放边坡方法,其坡度大小按设计坡度确定,基础槽位开挖前做好排水工作,严禁基础槽位长期被水浸泡,避免产生塌方现象;Step 2. Excavation of the foundation slot: According to the design requirements, the manual excavation method is used to excavate the required size of the foundation slot. In order to ensure the stability of the soil slope, the method of laying the side slope is adopted during the excavation, and the slope size is determined according to the design slope. , Drainage should be done before excavation of the foundation groove, and it is strictly forbidden for the foundation groove to be soaked in water for a long time to avoid the phenomenon of landslide;

步骤三、基础混凝土的浇筑:在步骤二中的基础槽位开挖前,根据工程施工图要求加工数片成型模板以及定型支撑,以便于现场支立模板;在步骤二中的基础槽位开挖后,需对开挖槽位进行测量,测量合格后,进行钢筋绑扎施工,首先,将主体钢筋焊接完毕后,安装基础四角主钢筋和全部箍筋,并用20#铁丝绑扎牢固,采用梅花型绑扎,钢筋绑扎需严格按照设计要求的数量和规格进行绑扎安装,完成钢筋绑扎后,按照设计给定的尺寸进行支立模板并用铆钉及时进行加固,模板在基础坑中支立的同时考虑需支立起与底层挡土墙预制块底部的榫槽相对应大小的榫头孔位,以便灌注混凝土时形成榫头,并与底层挡土墙直接连接安装,在完成模板支立后,进行混凝土的浇筑,为了加快施工进度,在混凝土中加入速凝剂,按重量份速凝剂掺量为混凝土重量的5%,基础混凝土灌注统一采用混凝土搅拌站集中拌制后用混凝土搅拌车运输至基础槽位前进行浇筑,混凝土强度要求为C30,混凝土灌入基础槽位前,在入口位置固定好溜筒进料口,并且续接溜筒至浇筑仓面位置并固定牢固,灌注混凝土时,一边将混凝土溜入仓面,然后用插入式软轴振捣器平仓、振捣,直至灌注完毕,并将表面混凝土收平、压光;Step 3. Pouring of foundation concrete: Before excavating the foundation slot in step 2, process several forming templates and shaping supports according to the requirements of the engineering construction drawings, so as to facilitate the erection of the template on site; in step 2, open the foundation slot. After excavation, it is necessary to measure the excavation groove. After the measurement is qualified, the reinforcement construction is carried out. First, after the main reinforcement is welded, install the main reinforcement at the four corners of the foundation and all the stirrups, and bind them firmly with 20 # iron wire. Binding, steel bar binding shall be bound and installed in strict accordance with the quantity and specifications required by the design. After the steel bar binding is completed, the formwork shall be erected according to the size given by the design and reinforced in time with rivets. When the formwork is erected in the foundation pit, consider the need for support. The tenon hole position corresponding to the tenon and groove at the bottom of the precast block of the bottom retaining wall is erected, so that the tenon can be formed when pouring concrete, and the tenon can be directly connected and installed with the bottom retaining wall. After the formwork is erected, the concrete is poured. In order to speed up the construction progress, an accelerator is added to the concrete. The amount of the accelerator is 5% of the weight of the concrete by weight. The foundation concrete is poured uniformly by a concrete batching station and then transported to the foundation tank by a concrete mixer truck. For pouring, the concrete strength is required to be C30. Before pouring the concrete into the foundation groove, fix the feeding port of the chute at the entrance, and connect the chute to the position of the pouring silo and fix it firmly. Enter the warehouse surface, and then use the plug-in flexible shaft vibrator to level and vibrate until the filling is completed, and the surface concrete is flattened and calendered;

步骤四、装配式挡土墙的施工:在步骤三中基础混凝土达到设计强度后,进行装配式挡土墙的施工,装配式挡土墙采用吊车吊装,人工配合,挡土墙安装通过上层预留榫槽与下层预留榫头并以“错位拼接”方式拼接,就位后加以稳固支撑,防止倾覆,每层挡土墙安装高度需高于本层锚固体设计高度,以便更好的发挥锚固体所提供的抗拔承载力作用;Step 4. Construction of the prefabricated retaining wall: After the foundation concrete reaches the design strength in step 3, the construction of the prefabricated retaining wall is carried out. The prefabricated retaining wall is hoisted by crane and manually coordinated. The tenon groove and the tenon on the lower layer are reserved and spliced in a "displacement splicing" method. After they are in place, they are firmly supported to prevent overturning. The installation height of each retaining wall should be higher than the design height of the anchoring body of this layer, so as to better perform the anchoring. The uplift bearing capacity provided by the body;

步骤五、挡土墙后方填土施工并压实:在每层挡土墙安装完毕后,待基础混凝土强度达到85%时,进行挡土墙后部的回填土的施工,采用人工回填,蛙式打夯机打夯的方法进行土方的回填,蛙式打夯机在打夯之前,对回填土进行初步平整,打夯机依次夯打,一夯压半夯,夯夯相接,行行相连,两遍纵横交叉,打夯不留间隙,行夯路线由周边开始,然后再夯向中间,填方施工必须按规定分层夯压密实,填方施工后要对每层回填土进行检验,用换砂法取样测定土的干密度,求出土的密实度,符合设计要求后,才能填筑上层,每层压实后的回填土高度应与该层锚固体设计高度齐平;Step 5. Backfill construction and compaction at the rear of the retaining wall: After the installation of each retaining wall is completed, when the strength of the foundation concrete reaches 85%, the construction of the backfill at the rear of the retaining wall is carried out. The backfill of earthwork is carried out by the method of ramming with a type rammer. Before ramming, the frog rammer will preliminarily level the backfilled soil. Connected, cross vertically and horizontally twice, ramming without leaving gaps, the ramming route starts from the periphery, and then rams to the middle. The filling construction must be compacted and compacted in layers according to the regulations. After the filling construction, the backfill soil of each layer shall be inspected. , use the sand-changing method to sample and measure the dry density of the soil, and find out the compactness of the soil. Only after meeting the design requirements can the upper layer be filled. The backfill height of each layer after compaction should be flush with the design height of the anchoring body of the layer;

步骤六、开挖锚固体、锚索和连接杆的槽位:在每层填方施工完成后,在压实平整的填方表面采用人工开挖的方法,进行锚固体、锚索和连接杆槽位的开挖,槽位开挖时确保开挖断面尺寸符合锚固体、锚索和连接杆的尺寸大小且槽位底部平直,槽内无塌方,无积水;Step 6. Excavate the slots for anchors, cables and connecting rods: After the construction of each layer of fill is completed, manually excavate the surface of the compacted and flat fill to carry out anchors, cables and connecting rods. When excavating the slot, ensure that the size of the excavation section conforms to the size of the anchor body, anchor cable and connecting rod, and the bottom of the slot is straight, and there is no collapse or water accumulation in the slot;

步骤七、安装锚固体、设置横向和竖向连接锚索,同层锚固体的连接杆的焊接:在步骤六中锚固体、锚索和连接杆的槽位开挖完成后,首先在设定锚固体的槽位处安装锚固体,再将锚索安装在锚索的槽位处,锚索的后端与锚固体通过锚具锁定,锚索的前端穿过挡土墙暂不进行锁定,土方回填完成后再进行锚索端头的封锚,待同层锚固体安装完毕后,同层锚固体之间通过连接杆进行连接,连接杆与锚固体之间通过焊接进行固定,使同层锚固体连接成一个整体,能够提供更大的承载力;Step 7: Install the anchors, set up the horizontal and vertical connecting cables, and weld the connecting rods of the same layer of anchors: After excavating the slots for the anchors, cables and connecting rods in step 6, first set the Install the anchor at the slot of the anchor, and then install the anchor cable in the slot of the anchor cable. The rear end of the anchor cable and the anchor are locked by the anchor, and the front end of the anchor cable passes through the retaining wall and is temporarily locked. After the earthwork is backfilled, the end of the anchor cable is sealed and anchored. After the installation of the anchors on the same layer is completed, the anchors on the same layer are connected by connecting rods, and the connecting rods and the anchors are fixed by welding. The anchors are connected as a whole, which can provide greater bearing capacity;

步骤八、重复上述步骤四至步骤七,上级锚固体安装时,应对下级锚固体进行初张拉:进行上层锚固体安装施工时,应对下层锚固体进行初张拉,在第一层初张拉完成后,可继续向上层进行挡土墙的砌筑及挡土墙后部的土方回填,达到第二层锚固体高度时,按第一层锚固体的施工方法重复上述施工;Step 8. Repeat the above steps 4 to 7. When the upper-level anchors are installed, the lower-level anchors should be initially tensioned: when the upper-level anchors are installed and constructed, the lower-level anchors should be initially tensioned. After that, the masonry of the retaining wall and the earthwork backfilling at the rear of the retaining wall can be continued to the upper layer. When the height of the second layer of anchors is reached, the above construction shall be repeated according to the construction method of the first layer of anchors;

步骤九、按设计层数要求,对竖向连接锚索张拉锁定:在步骤八中所述的锚固体完成初张拉后,根据设计层数要求,对数层锚固体竖向之间的连接锚索进行张拉,张拉荷载为设计荷载的10%,张拉时监测竖向锚固体的变化及回填土的变形,如果出现异常情况,立即停止张拉,查明原因,采取措施后再次进行张拉,待数层锚固体之间的连接锚索张拉完成后进行竖向锁定;Step 9. Tension and lock the vertical connection anchor cable according to the design layer requirements: after the initial tension of the anchor body described in step 8 is completed, according to the design layer number requirements Connect the anchor cable for tensioning. The tensioning load is 10% of the design load. During tensioning, monitor the change of the vertical anchor and the deformation of the backfill. If there is an abnormal situation, stop the tensioning immediately, find out the cause, and take measures. Tension is carried out again, and vertical locking is carried out after the tensioning of the connecting anchor cables between several layers of anchors is completed;

步骤十、重复上述步骤四至步骤九至挡土墙砌筑达到设计高度,按设计荷载对水平向锚索进行分级张拉:水平向锚索分级张拉荷载为设计荷载的10%,张拉时监测竖向锚固体的变化及回填土的变形,如果出现异常情况,立即停止张拉,查明原因,采取措施后再次进行张拉,直至所有水平向锚索张拉完成;Step 10. Repeat the above steps 4 to 9 until the retaining wall is built to the design height, and the horizontal anchor cables are graded and tensioned according to the design load: the graded tension load of the horizontal anchor cables is 10% of the design load. Monitor the change of the vertical anchor and the deformation of the backfill. If there is an abnormal situation, stop the tension immediately, find out the reason, and take measures to tension again until all the horizontal anchor cables are tensioned;

步骤十一、检查调试,锚头封锚,施工完成。Step 11. Check and debug, seal the anchor head, and complete the construction.

锚索采用预应力钢绞线制成,锚索的端头采用标准锚具紧固安装,再用千斤顶进行张拉调试,张拉按设计要求进行,在锚索分级张拉调试完成后即对穿过挡土墙处的锚索的端头进行锁定封锚。The anchor cable is made of prestressed steel strands, and the ends of the anchor cable are fastened and installed with standard anchors, and then the jack is used for tensioning and debugging. The tensioning is carried out according to the design requirements. Lock the anchor through the end of the anchor cable at the retaining wall.

步骤一中使用“全站仪”进行定位时最少确定六个定位桩,测量定位所用的“全站仪”、“经纬仪”、“水准仪”及控制质量检测设备在使用周期内的计量器具按二级计量标准进行计量标定控制。In step 1, when using the "total station" for positioning, at least six positioning piles are determined. Level metrology standard for metrological calibration control.

步骤三中的模板支立完成后进行吊点检测,模板之间偏差小于2cm,在模板完成支立后,将模板底部与基础槽位底部缝隙密封严密。After the template is erected in step 3, the lifting point is detected. The deviation between the templates is less than 2cm. After the template is erected, the gap between the bottom of the template and the bottom of the foundation groove is tightly sealed.

步骤五中的填方施工用翻斗车运土,由最低处开始回填,至下而上分层进行回填,每层回填土厚度不大于50cm,当天所回填土方必须在当天压实,以免漏夯,每回填50cm,压实一次,回填土方压实系数不小于0.97。For the filling construction in step 5, use a dump truck to transport soil, start backfilling from the lowest point, and backfill in layers from the bottom to the top. The thickness of each layer of backfill is not more than 50cm. The backfill soil must be compacted on the same day to avoid leakage. , Every 50cm of backfill, compaction once, the compaction coefficient of backfill earthwork is not less than 0.97.

步骤十一中的封锚采用C30混凝土对锚索的端头进行密封,保护层厚度为100mm。Sealing the anchor in step 11 uses C30 concrete to seal the end of the anchor cable, and the thickness of the protective layer is 100mm.

本发明的工作原理如下:The working principle of the present invention is as follows:

本发明提供的装配式轻型支挡结构由装配式挡土墙、锚索、锚固体、连接杆、基础以及填方组成,埋置在回填土中上下相邻的锚固体之间通过锚索连接,施加预应力进一步压实土体以获得更大的抗拔承载力;沿挡土墙长度方向的相邻锚固体之间使用连接杆螺接,形成空间锚固体。锚固体通过预埋锚索施加预应力后与挡土墙连接,形成空间受力体系,整体受力更加均匀、更加稳定。本发明提供的装配式轻型支挡结构所受到的土压力系由支挡结构后的回填土及外部荷载引起,装配式轻型支挡结构工作时支挡结构侧壁上的土压力先作用于装配式挡土墙上,接着以集中力的形式通过锚索传递到锚固体上,与锚固体所提供的抗拔承载力形成平衡,从而将荷载扩散到更大范围的土体中去,以达到稳定填土体的目的。本发明的施工采用“开挖—支护—回填—张拉连接—支护—回填”的多层循环作业方式,在实际施工时,“锚固体的安装”和“锚索的安装”两道工序可根据工程现场情况调换施工顺序。The assembled light-duty retaining structure provided by the present invention is composed of an assembled retaining wall, an anchor cable, an anchor, a connecting rod, a foundation and a filling, and the upper and lower adjacent anchors embedded in the backfill are connected by the anchor cable. , applying prestress to further compact the soil to obtain greater uplift bearing capacity; connecting rods are used between adjacent anchors along the length of the retaining wall to form space anchors. The anchor body is connected with the retaining wall after prestressing the embedded anchor cable to form a space stress system, and the overall stress is more uniform and stable. The earth pressure on the assembled light-duty retaining structure provided by the present invention is caused by the backfill and external load after the supporting structure. When the assembled light-duty supporting structure works, the earth pressure on the side wall of the supporting structure first acts on the assembly. The retaining wall is then transmitted to the anchoring body in the form of concentrated force through the anchor cable, which forms a balance with the uplift bearing capacity provided by the anchoring body, so as to spread the load to a wider range of soil to achieve The purpose of stabilizing the fill body. The construction of the present invention adopts the multi-layer cyclic operation mode of "excavation-support-backfill-tension connection-support-backfill". In actual construction, "anchor body installation" and "anchor cable installation" two The construction sequence can be changed according to the situation of the project site.

本发明的有益效果:Beneficial effects of the present invention:

1)节省施工周期。本发明以水平方形锚板作为锚固体并将其在空间上连接为一个整体,锚头封锚后即可提供承载力,相比于锚定板挡土墙由于锚定板竖直设置,影响施工且位置易偏离导致施工程序复杂、容易造成局部破坏;对于现浇重力式挡土墙需待混凝土达到一定强度后方可提供承载力而言,本发明能够有效节省施工周期。1) Save the construction period. In the present invention, the horizontal square anchor plate is used as the anchor body and is spatially connected as a whole, and the bearing capacity can be provided after the anchor head is sealed. Construction and easy position deviation lead to complicated construction procedures and local damage; for the cast-in-place gravity retaining wall, the bearing capacity can be provided only after the concrete reaches a certain strength, the invention can effectively save the construction period.

2)造价低。本发明除了基础外,所有构件均为工厂预制、现场拼装,相比于重力式挡土墙,对临时措施不稳定、边坡高度高、周边环境较复杂的支挡工程,本发明由于无需大量灌注混凝土,有效减小现场水泥的使用量,能够大大节省时间、人工和材料的成本。2) Low cost. In addition to the foundation, all components of the present invention are factory prefabricated and assembled on site. Compared with the gravity retaining wall, the present invention does not require a large number of supporting projects with unstable temporary measures, high slope height and complex surrounding environment. Pouring concrete can effectively reduce the amount of cement used on site, which can greatly save time, labor and material costs.

3)可靠性高。填土在竖向方向受到的压密作用也正是锚固体提供更大抗拔承载力所需的法向应力方向,这保证的承载力的可靠性。3) High reliability. The compaction effect of the fill in the vertical direction is also the normal stress direction required by the anchor to provide a greater pull-out bearing capacity, which ensures the reliability of the bearing capacity.

4)整体性好。本发明所有提供抗拔承载力的锚固体均连接形成一个三维整体,相比于锚定板支挡结构,其三维整体受力更加均匀、更加稳定,受力体系整体性较好。4) Good integrity. All the anchors that provide the pull-out bearing capacity of the present invention are connected to form a three-dimensional whole. Compared with the anchor plate support structure, the three-dimensional overall force is more uniform and stable, and the integrity of the force system is better.

5)适用性强。本发明相较于土钉墙支挡技术,本发明由锚索施加预应力,属于主动支护技术,可适用于工程条件更复杂、支挡高度更高的支护工程。5) Strong applicability. Compared with the soil nailing wall support technology, the present invention is prestressed by the anchor cable, belongs to the active support technology, and can be applied to support projects with more complex engineering conditions and higher support heights.

6)本发明提供的技术方案相比于锚定板挡土墙能够防止因局部失稳而导致的整体结构破坏。6) Compared with the anchor plate retaining wall, the technical solution provided by the present invention can prevent the overall structural damage caused by local instability.

附图说明Description of drawings

图1为本发明所述支挡结构主视图。FIG. 1 is a front view of the support structure according to the present invention.

图2为本发明所述支挡结构断面结构示意图。FIG. 2 is a schematic cross-sectional structural diagram of the support structure according to the present invention.

图3为本发明所述基础结构示意图。FIG. 3 is a schematic diagram of the basic structure of the present invention.

图4为本发明所述挡土墙所用预制块立体结构示意图。FIG. 4 is a schematic diagram of the three-dimensional structure of the prefabricated blocks used in the retaining wall according to the present invention.

图5为本发明所述挡土墙所用预制块主视图。Fig. 5 is a front view of the prefabricated blocks used in the retaining wall according to the present invention.

图6为本发明所述支挡结构施工方法流程示意图。FIG. 6 is a schematic flowchart of the construction method of the retaining structure according to the present invention.

上图中的标注如下所示:The annotations in the figure above are as follows:

1、基础 2、挡土墙 3、锚索 4、回填土 5、锚固体 6、榫头 7、预制块 8、榫槽 9、锚具 10、连接杆。1. Foundation 2. Retaining wall 3. Anchor cable 4. Backfill 5. Anchorage 6. Tenon 7. Prefabricated block 8. Tongue and groove 9. Anchor 10. Connecting rod.

具体实施方式Detailed ways

请参阅图1至图6所示:Please refer to Figures 1 to 6 as shown:

本发明提供的装配式轻型支挡结构包括有基础1、挡土墙2、锚索3、锚固体5和连接杆10,其中挡土墙2设置在基础1上,锚固体5设在挡土墙2后方的回填土4内,锚索3的前端穿设在挡土墙2上,锚索3的后端与挡土墙2后方回填土4内的锚固体5相固连,相邻的锚固体5之间由锚索3和连接杆10连接,挡土墙2和锚固体5形成一种立体的支挡结构。The assembled light-duty retaining structure provided by the present invention includes a foundation 1, a retaining wall 2, an anchor cable 3, an anchoring body 5 and a connecting rod 10, wherein the retaining wall 2 is arranged on the foundation 1, and the anchoring body 5 is arranged on the retaining soil In the backfill 4 behind the wall 2, the front end of the anchor cable 3 is worn on the retaining wall 2, and the rear end of the anchor cable 3 is fixedly connected with the anchor body 5 in the backfill 4 behind the retaining wall 2. The anchors 5 are connected by anchor cables 3 and connecting rods 10, and the retaining wall 2 and the anchors 5 form a three-dimensional support structure.

基础1为凹槽型构造,凹槽内设置有榫头6,挡土墙2为装配式的,挡土墙2由预制块7砌筑而成,每块预制块7的上部均设置有榫头6,每块预制块7的底部均设置榫槽8,榫头6与榫槽8的位置和尺寸相对应,榫头6插入榫槽8内实现拼接,挡土墙2最下层预制块7底部的榫槽8插设在基础1凹槽内的榫头6上。The foundation 1 is a groove-type structure, and the groove is provided with a tenon 6. The retaining wall 2 is an assembled type. The retaining wall 2 is made of prefabricated blocks 7, and the upper part of each prefabricated block 7 is provided with a tenon 6. , the bottom of each prefabricated block 7 is provided with a tongue and groove 8, the position and size of the tenon 6 and the tongue and groove 8 correspond, the tenon 6 is inserted into the tongue and groove 8 to realize splicing, and the tongue and groove at the bottom of the bottommost prefabricated block 7 of the retaining wall 2 8 is inserted into the tenon 6 in the groove of the foundation 1.

锚索3的前端穿过挡土墙2后的端头螺接在锚具9上,锚索3的后端螺接在挡土墙2后方回填土4内的锚固体5上,上下相邻的锚固体5也由锚索3进行连接,沿挡土墙2长度方向的纵向相邻的锚固体5由连接杆10进行连接。The front end of the anchor cable 3 is screwed on the anchor 9 after passing through the retaining wall 2, and the rear end of the anchor cable 3 is screwed on the anchor body 5 in the backfill 4 behind the retaining wall 2, and the upper and lower sides are adjacent to each other. The anchors 5 are also connected by anchor cables 3 , and the longitudinally adjacent anchors 5 along the length of the retaining wall 2 are connected by connecting rods 10 .

穿设有锚索的预制块上预留有锚索孔。An anchor cable hole is reserved on the prefabricated block through which the anchor cable is passed.

本发明提供的装配式轻型支挡结构的施工方法,其具体方法如下所述:The construction method of the assembled light-duty support structure provided by the present invention is as follows:

步骤一、场地平整,测量放线:场地平整前,组织人员到场地进行现场勘察,了解场地地形、地貌和周围环境,根据设计要求及建设规划确定场地平整的范围,场地平整前将场地平整范围内的障碍物清理干净,场地通过机械或人工方式开挖土方,改造成支挡结构设计所要求的平面,并确保平整后场地平面上无膨胀土、盐渍土及有腐蚀作用的酸性土和有机质土;Step 1. Leveling the site, measuring and setting out the line: Before leveling the site, organize personnel to conduct on-site surveys to understand the topography, landform and surrounding environment of the site, and determine the scope of site leveling according to the design requirements and construction planning, and level the site before leveling. The obstacles in the site are cleaned up, and the site is excavated mechanically or manually to transform it into the plane required by the design of the supporting structure, and ensure that there is no expansive soil, saline soil, and corrosive acidic soil and soil on the site after leveling. organic soil;

工程开工后进行第一次放线,放线工具为“全站仪”,根据定位图进行定位,最后在施工现场确定定位桩,确定定位桩后,用“经纬仪”对基础工程和主体工程进行放线及测量,根据定位桩测出场地轴线控制桩,控制桩采用保护桩,高程引入现场,采用闭合回测法,设置场内水准点,轴线测定使用“经纬仪”,水准点测量用“水准仪”;After the start of the project, the first line-out is carried out. The line-out tool is "total station", and the positioning is carried out according to the positioning map. Finally, the positioning piles are determined at the construction site. Line-out and measurement, the site axis control pile is measured according to the positioning pile, the control pile adopts the protection pile, the elevation is introduced into the site, the closed back measurement method is adopted, and the level point in the site is set. ";

步骤二、开挖基础1槽位:根据设计要求,采用人工开挖法开挖符合要求的基础1槽位大小,为确保土坡稳定,开挖时采用放边坡方法,其坡度大小按设计坡度确定,基础1槽位开挖前做好排水工作,严禁基础1槽位长期被水浸泡,避免产生塌方现象;Step 2. Excavate the foundation 1 slot: According to the design requirements, use the manual excavation method to excavate the foundation 1 slot size that meets the requirements. In order to ensure the stability of the soil slope, the method of laying the slope is used during excavation, and the slope size is designed according to the design. The slope is determined, and drainage work should be done before the excavation of the foundation 1 slot. It is strictly forbidden to soak the foundation 1 slot with water for a long time to avoid landslides;

步骤三、基础1混凝土的浇筑:在步骤二中的基础1槽位开挖前,根据工程施工图要求加工数片成型模板以及定型支撑,以便于现场支立模板;在步骤二中的基础1槽位开挖后,需对开挖槽位进行测量,测量合格后,进行钢筋绑扎施工,首先,将主体钢筋焊接完毕后,安装基础四角主钢筋和全部箍筋,并用20#铁丝绑扎牢固,采用梅花型绑扎,钢筋绑扎需严格按照设计要求的数量和规格进行绑扎安装,完成钢筋绑扎后,按照设计给定的尺寸进行支立模板并用铆钉及时进行加固,模板在基础1坑中支立的同时考虑需支立起与底层挡土墙2预制块7底部的榫槽8相对应大小的榫头6孔位,以便灌注混凝土时形成榫头6,并与底层挡土墙2直接连接安装,在完成模板支立后,进行混凝土的浇筑,为了加快施工进度,在混凝土中加入速凝剂,按重量份速凝剂掺量为混凝土重量的5%,基础1混凝土灌注统一采用混凝土搅拌站集中拌制后用混凝土搅拌车运输至基础1槽位前进行浇筑,混凝土强度要求为C30,混凝土灌入基础1槽位前,在入口位置固定好溜筒进料口,并且续接溜筒至浇筑仓面位置并固定牢固,灌注混凝土时,一边将混凝土溜入仓面,然后用插入式软轴振捣器平仓、振捣,直至灌注完毕,并将表面混凝土收平、压光;Step 3. Concrete pouring of foundation 1: Before excavating the slot of foundation 1 in step 2, process several forming templates and shaping supports according to the requirements of the engineering construction drawing, so as to facilitate the erection of the template on site; in step 2, foundation 1 After the slot is excavated, it is necessary to measure the excavated slot. After the measurement is passed, the reinforcement construction is carried out. First, after the main reinforcement is welded, install the main reinforcement at the four corners of the foundation and all the stirrups, and bind them firmly with 20 # iron wire. The plum-shaped binding is adopted. The binding and installation of the steel bars shall be carried out in strict accordance with the quantity and specifications required by the design. After the binding of the steel bars, the formwork shall be erected according to the size given by the design and reinforced in time with rivets. The formwork shall be erected in the foundation pit 1. At the same time, it is considered that the hole position of the tenon 6 corresponding to the tenon groove 8 at the bottom of the prefabricated block 7 of the bottom retaining wall 2 needs to be erected, so as to form the tenon 6 when pouring concrete, and directly connect and install with the bottom retaining wall 2. After the formwork is erected, the concrete is poured. In order to speed up the construction progress, an accelerator is added to the concrete, and the amount of the accelerator is 5% of the weight of the concrete. Then, the concrete mixer is transported to the foundation 1 slot for pouring, and the concrete strength is required to be C30. Before the concrete is poured into the foundation 1 slot, the chute feed port is fixed at the entrance position, and the chute is connected to the pouring silo surface. When pouring concrete, slip the concrete into the warehouse surface, and then use the plug-in flexible shaft vibrator to level and vibrate the warehouse until the pouring is completed, and the surface concrete is flattened and calendered;

步骤四、装配式挡土墙2的施工:在步骤三中基础1混凝土达到设计强度后,进行装配式挡土墙2的施工,装配式挡土墙2采用吊车吊装,人工配合,挡土墙2安装通过上层预留榫槽8与下层预留榫头6并以“错位拼接”方式拼接,就位后加以稳固支撑,防止倾覆,每层挡土墙2安装高度需高于本层锚固体5设计高度,以便更好的发挥锚固体5所提供的抗拔承载力作用;Step 4. Construction of the prefabricated retaining wall 2: After the concrete of the foundation 1 reaches the design strength in step 3, the construction of the prefabricated retaining wall 2 is carried out. The prefabricated retaining wall 2 is hoisted by a crane and manually coordinated. 2. Install the reserved tenon groove 8 on the upper layer and the reserved tenon 6 on the lower layer and splicing them together in a "dislocation splicing" method. After they are in place, they are firmly supported to prevent overturning. The installation height of each retaining wall 2 should be higher than the anchoring body 5 of this layer. Design height, so as to better exert the anti-pulling bearing capacity provided by anchor 5;

步骤五、挡土墙2后方填土施工并压实:在每层挡土墙2安装完毕后,待基础1混凝土强度达到85%时,进行挡土墙2后部的回填土4的施工,采用人工回填,蛙式打夯机打夯的方法进行土方的回填,蛙式打夯机在打夯之前,对回填土4进行初步平整,打夯机依次夯打,一夯压半夯,夯夯相接,行行相连,两遍纵横交叉,打夯不留间隙,行夯路线由周边开始,然后再夯向中间,填方施工必须按规定分层夯压密实,填方施工后要对每层回填土4进行检验,用换砂法取样测定土的干密度,求出土的密实度,符合设计要求后,才能填筑上层,每层压实后的回填土4高度应与该层锚固体5设计高度齐平;Step 5. Backfill construction and compaction at the rear of the retaining wall 2: After each layer of the retaining wall 2 is installed, when the concrete strength of the foundation 1 reaches 85%, the construction of the backfill 4 at the rear of the retaining wall 2 is carried out, Backfill the earthwork by manual backfilling and ramming by frog-type rammer. Before the frog-type rammer ramming, the backfill soil 4 is preliminarily leveled. The ramming is connected, the rows are connected, and the two passes are crossed vertically and horizontally. The ramming route does not leave any gap. The ramming route starts from the periphery, and then rams to the middle. The filling construction must be compacted and compacted in layers according to the regulations. Each layer of backfill soil 4 is inspected, and the dry density of the soil is measured by the sand replacement method, and the compactness of the soil is obtained. Only after meeting the design requirements can the upper layer be filled. Body 5 is designed to be flush in height;

步骤六、开挖锚固体5、锚索3和连接杆10的槽位:在每层填方施工完成后,在压实平整的填方表面采用人工开挖的方法,进行锚固体5、锚索3和连接杆10槽位的开挖,槽位开挖时确保开挖断面尺寸符合锚固体5、锚索3和连接杆10的尺寸大小且槽位底部平直,槽内无塌方,无积水;Step 6: Excavate the slots for anchors 5, anchor cables 3 and connecting rods 10: After the construction of each layer of fill is completed, manually excavate the surface of the compacted and flat fill to carry out anchors 5, anchors When excavating the slot of cable 3 and connecting rod 10, make sure that the size of the excavation section conforms to the dimensions of anchor body 5, anchor cable 3 and connecting rod 10, and the bottom of the slot is straight, and there is no collapse in the slot. stagnant water;

步骤七、安装锚固体5、设置横向和竖向连接锚索3,同层锚固体5的连接杆10的焊接:在步骤六中锚固体5、锚索3和连接杆10的槽位开挖完成后,首先在设定锚固体5的槽位处安装锚固体5,再将锚索3安装在锚索3的槽位处,锚索3的后端与锚固体5通过锚具9锁定,锚索3的前端穿过挡土墙2暂不进行锁定,土方回填完成后再进行锚索3端头的封锚,待同层锚固体5安装完毕后,同层锚固体5之间通过连接杆10进行连接,连接杆10与锚固体5之间通过焊接进行固定,使同层锚固体5连接成一个整体,能够提供更大的承载力;Step 7: Install the anchors 5, set up the horizontal and vertical connection anchor cables 3, and weld the connecting rods 10 of the anchors 5 on the same layer: in step 6, the slots of the anchors 5, the anchor cables 3 and the connecting rods 10 are excavated After completion, first install the anchor 5 at the slot where the anchor 5 is set, and then install the anchor cable 3 in the slot of the anchor cable 3. The rear end of the anchor cable 3 and the anchor 5 are locked by the anchor 9, The front end of the anchor cable 3 passes through the retaining wall 2 and is not locked temporarily. After the earthwork is backfilled, the end of the anchor cable 3 is sealed and anchored. After the installation of the anchors 5 on the same layer is completed, the anchors 5 on the same layer are connected by The rods 10 are connected, and the connecting rods 10 and the anchors 5 are fixed by welding, so that the anchors 5 of the same layer are connected as a whole, which can provide greater bearing capacity;

步骤八、重复上述步骤四至步骤七,上级锚固体5安装时,应对下级锚固体5进行初张拉:进行上层锚固体5安装施工时,应对下层锚固体5进行初张拉,在第一层初张拉完成后,可继续向上层进行挡土墙2的砌筑及挡土墙2后部的土方回填,达到第二层锚固体5高度时,按第一层锚固体5的施工方法重复上述施工;Step 8. Repeat the above-mentioned steps 4 to 7. When the upper-level anchor 5 is installed, the lower-level anchor 5 should be initially tensioned: when the upper-level anchor 5 is installed and constructed, the lower-level anchor 5 should be initially tensioned. After the initial tension is completed, the masonry of the retaining wall 2 and the earthwork backfilling at the rear of the retaining wall 2 can be continued to the upper layer. When the height of the second layer of anchors 5 is reached, the construction method of the first layer of anchors 5 can be repeated. the above construction;

步骤九、按设计层数要求,对竖向连接锚索3张拉锁定:在步骤八中所述的锚固体5完成初张拉后,根据设计层数要求,对数层锚固体5竖向之间的连接锚索3进行张拉,张拉荷载为设计荷载的10%,张拉时监测竖向锚固体5的变化及回填土4的变形,如果出现异常情况,立即停止张拉,查明原因,采取措施后再次进行张拉,待数层锚固体5之间的连接锚索3张拉完成后进行竖向锁定;Step 9. Tension and lock the vertical connection anchor cable 3 according to the requirements of the design layer number: after the initial tension of the anchor body 5 described in step 8 is completed, according to the design layer number requirements, the vertical connection anchor body 5 The connecting anchor cable 3 between them is tensioned, and the tension load is 10% of the design load. During tension, monitor the change of the vertical anchor 5 and the deformation of the backfill soil 4. If there is an abnormal situation, immediately stop the tension and check. If the reason is clear, after taking measures, tension is performed again, and vertical locking is performed after the connection anchor cable 3 between several layers of anchors 5 is tensioned;

步骤十、重复上述步骤四至步骤九至挡土墙2砌筑达到设计高度,按设计荷载对水平向锚索3进行分级张拉:水平向锚索3分级张拉荷载为设计荷载的10%,张拉时监测竖向锚固体5的变化及回填土4的变形,如果出现异常情况,立即停止张拉,查明原因,采取措施后再次进行张拉,直至所有水平向锚索3张拉完成;Step 10. Repeat the above steps 4 to 9 until the retaining wall 2 is built to the design height, and the horizontal anchor cable 3 is graded and tensioned according to the design load: the graded tension load of the horizontal anchor cable 3 is 10% of the design load, Monitor the changes of the vertical anchors 5 and the deformation of the backfill 4 during tensioning. If there is an abnormal situation, stop tensioning immediately, find out the cause, and take measures to tension again until all horizontal anchor cables are tensioned. ;

步骤十一、检查调试,锚头封锚,施工完成。Step 11. Check and debug, seal the anchor head, and complete the construction.

锚索3采用预应力钢绞线制成,锚索3的端头采用标准锚具9紧固安装,再用千斤顶进行张拉调试,张拉按设计要求进行,在锚索3分级张拉调试完成后即对穿过挡土墙2处的锚索3的端头进行锁定封锚。The anchor cable 3 is made of prestressed steel strands, and the end of the anchor cable 3 is fastened and installed with standard anchors 9, and then the jack is used for tensioning and debugging. The tensioning is carried out according to the design requirements. After completion, the end of the anchor cable 3 passing through the retaining wall 2 is locked and anchored.

步骤一中使用“全站仪”进行定位时最少确定六个定位桩,测量定位所用的“全站仪”、“经纬仪”、“水准仪”及控制质量检测设备在使用周期内的计量器具按二级计量标准进行计量标定控制。In step 1, when using the "total station" for positioning, at least six positioning piles are determined. Level metrology standard for metrological calibration control.

步骤三中的模板支立完成后进行吊点检测,模板之间偏差小于2cm,在模板完成支立后,将模板底部与基础槽位底部缝隙密封严密。After the template is erected in step 3, the lifting point is detected. The deviation between the templates is less than 2cm. After the template is erected, the gap between the bottom of the template and the bottom of the foundation groove is tightly sealed.

步骤五中的填方施工用翻斗车运土,由最低处开始回填,至下而上分层进行回填,每层回填土厚度不大于50cm,当天所回填土方必须在当天压实,以免漏夯,每回填50cm,压实一次,回填土方压实系数不小于0.97。For the filling construction in step 5, use a dump truck to transport soil, start backfilling from the lowest point, and backfill in layers from the bottom to the top. The thickness of each layer of backfill is not more than 50cm. The backfill soil must be compacted on the same day to avoid leakage. , Every 50cm of backfill, compaction once, the compaction coefficient of backfill earthwork is not less than 0.97.

步骤十一中的封锚采用C30混凝土对锚索3的端头进行密封,保护层厚度为100mm。The anchor seal in step eleven is to use C30 concrete to seal the end of the anchor cable 3, and the thickness of the protective layer is 100mm.

本发明的工作原理如下:The working principle of the present invention is as follows:

本发明提供的装配式轻型支挡结构由装配式挡土墙2、锚索3、锚固体5、连接杆10、基础1以及填方组成,将埋置在回填土4中的相邻锚固体5连接形成空间体,即通过锚索3施加预应力连接上下相邻的锚固体5,沿挡土墙2长度方向的相邻锚固体5之间使用连接杆10螺接。锚固体5通过预埋锚索3施加预应力后与挡土墙2连接,形成空间受力体系,整体受力更加均匀、更加稳定。本发明提供的装配式轻型支挡结构所受到的土压力系由支挡结构后的回填土4及外部荷载引起,装配式轻型支挡结构工作时支挡结构侧壁的土压力先作用于装配式挡土墙2上,然后以集中力的形式作用于锚索3上,接着通过锚索3传递到锚固体5上,与锚固体5所提供的抗拔承载力形成平衡,从而将荷载扩散到更大范围的土体中,以达到稳定填土体的目的。本发明的施工采用“开挖—支护—回填—张拉连接—支护—回填”的多层循环作业方式,在实际施工时,“锚固体5的安装”和“锚索3的安装”两道工序可根据工程现场情况调换施工顺序。The prefabricated light-duty retaining structure provided by the present invention is composed of prefabricated retaining walls 2, anchor cables 3, anchors 5, connecting rods 10, foundations 1 and fill, and the adjacent anchors embedded in the backfill 4 5 is connected to form a space body, that is, the anchors 5 are connected up and down by applying prestressing force through the anchor cable 3, and the adjacent anchors 5 along the length of the retaining wall 2 are connected by connecting rods 10. The anchor body 5 is connected with the retaining wall 2 after prestressing the pre-embedded anchor cable 3 to form a space force system, and the overall force is more uniform and stable. The earth pressure on the assembled light-duty retaining structure provided by the present invention is caused by the backfill soil 4 behind the supporting structure and the external load. When the assembled light-duty supporting structure works, the earth pressure of the side wall of the supporting structure first acts on the assembly. On the retaining wall 2, and then act on the anchor cable 3 in the form of concentrated force, and then transmit it to the anchor body 5 through the anchor cable 3, and form a balance with the pull-out bearing capacity provided by the anchor body 5, so as to spread the load. To a larger range of soil, in order to achieve the purpose of stabilizing the filling. The construction of the present invention adopts the multi-layer cycle operation mode of "excavation-support-backfill-tension connection-support-backfill". During actual construction, "installation of anchor body 5" and "installation of anchor cable 3" The construction sequence of the two processes can be exchanged according to the situation of the project site.

Claims (10)

1.一种装配式轻型支挡结构,其特征在于:包括有基础、挡土墙、锚索、锚固体和连接杆,其中挡土墙设置在基础上,锚固体设在挡土墙后方的回填土内,锚索的前端穿设在挡土墙上,锚索的后端与挡土墙后方回填土内的锚固体相固连,相邻的锚固体之间由锚索和连接杆连接,挡土墙和锚固体形成一种立体的支挡结构。1. An assembled light-duty retaining structure is characterized in that: comprising a foundation, a retaining wall, an anchor cable, an anchor and a connecting rod, wherein the retaining wall is arranged on the foundation, and the anchor is arranged at the rear of the retaining wall. In the backfill, the front end of the anchor cable passes through the retaining wall, the rear end of the anchor cable is fixedly connected with the anchor solid in the backfill soil behind the retaining wall, and the adjacent anchor solids are connected by the anchor cable and the connecting rod. , the retaining wall and the anchors form a three-dimensional retaining structure. 2.根据权利要求1所述的一种装配式轻型支挡结构,其特征在于:所述的基础为凹槽型构造,凹槽内设置有榫头,挡土墙为装配式的,挡土墙由预制块砌筑而成,每块预制块的上部均设置有榫头,每块预制块的底部均设置榫槽,榫头与榫槽的位置和尺寸相对应,榫头插入榫槽内实现拼接,挡土墙最下层预制块底部的榫槽插设在基础凹槽内的榫头上。2. An assembled light-duty retaining structure according to claim 1, characterized in that: the foundation is a groove-type structure, a tenon is arranged in the groove, the retaining wall is assembled, and the retaining wall It is made of prefabricated blocks. The upper part of each prefabricated block is provided with a tenon, and the bottom of each prefabricated block is provided with a tenon and groove. The position and size of the tenon and the tenon groove correspond to the tenon and the tenon groove. The tongue and groove at the bottom of the bottommost prefabricated block of the earth wall are inserted into the tenon in the foundation groove. 3.根据权利要求1所述的一种装配式轻型支挡结构,其特征在于:所述的锚索的前端穿过挡土墙后的端头螺接在锚具上,锚索的后端螺接在挡土墙后方回填土内的锚固体上,上下相邻的锚固体也由锚索进行连接,沿挡土墙长度方向的纵向相邻的锚固体由连接杆进行连接。3. An assembled light-duty retaining structure according to claim 1, wherein the front end of the anchor cable is screwed on the anchor after passing through the retaining wall, and the rear end of the anchor cable It is screwed on the anchors in the backfill behind the retaining wall, the upper and lower adjacent anchors are also connected by anchor cables, and the longitudinally adjacent anchors along the length of the retaining wall are connected by connecting rods. 4.根据权利要求2所述的一种装配式轻型支挡结构,其特征在于:所述的穿设有锚索的预制块上预留有锚索孔。4 . The assembled light-duty support structure according to claim 2 , wherein the anchor cable holes are reserved on the prefabricated blocks through which the anchor cables are pierced. 5 . 5.一种装配式轻型支挡结构的施工方法,其特征在于:其方法如下所述:5. A construction method for an assembled light-duty support structure, characterized in that: the method is as follows: 步骤一、场地平整,测量放线:场地平整前,组织人员到场地进行现场勘察,了解场地地形、地貌和周围环境,根据设计要求及建设规划确定场地平整的范围,场地平整前将场地平整范围内的障碍物清理干净,场地通过机械或人工方式开挖土方,改造成支挡结构设计所要求的平面,并确保平整后场地平面上无膨胀土、盐渍土及有腐蚀作用的酸性土和有机质土;Step 1. Leveling the site, measuring and setting out the line: Before leveling the site, organize personnel to conduct on-site surveys to understand the topography, landform and surrounding environment of the site, and determine the scope of site leveling according to the design requirements and construction planning, and level the site before leveling. The obstacles in the site are cleaned up, and the site is excavated mechanically or manually to transform it into the plane required by the design of the supporting structure, and ensure that there is no expansive soil, saline soil, and corrosive acidic soil and soil on the site after leveling. organic soil; 工程开工后进行第一次放线,放线工具为“全站仪”,根据定位图进行定位,最后在施工现场确定定位桩,确定定位桩后,用“经纬仪”对基础工程和主体工程进行放线及测量,根据定位桩测出场地轴线控制桩,控制桩采用保护桩,高程引入现场,采用闭合回测法,设置场内水准点,轴线测定使用“经纬仪”,水准点测量用“水准仪”;After the start of the project, the first line-out is carried out. The line-out tool is "total station", and the positioning is carried out according to the positioning map. Finally, the positioning piles are determined at the construction site. Line-out and measurement, the site axis control pile is measured according to the positioning pile, the control pile adopts the protection pile, the elevation is introduced into the site, the closed back measurement method is adopted, and the level point in the site is set. "; 步骤二、开挖基础槽位:根据设计要求,采用人工开挖法开挖符合要求的基础槽位大小,为确保土坡稳定,开挖时采用放边坡方法,其坡度大小按设计坡度确定,基础槽位开挖前做好排水工作,严禁基础槽位长期被水浸泡,避免产生塌方现象;Step 2. Excavation of the foundation slot: According to the design requirements, the manual excavation method is used to excavate the required size of the foundation slot. In order to ensure the stability of the soil slope, the method of laying the side slope is adopted during the excavation, and the slope size is determined according to the design slope. , Drainage should be done before excavation of the foundation groove, and it is strictly forbidden for the foundation groove to be soaked in water for a long time to avoid the phenomenon of landslide; 步骤三、基础混凝土的浇筑:在步骤二中的基础槽位开挖前,根据工程施工图要求加工数片成型模板以及定型支撑,以便于现场支立模板;在步骤二中的基础槽位开挖后,需对开挖槽位进行测量,测量合格后,进行钢筋绑扎施工,首先,将主体钢筋焊接完毕后,安装基础四角主钢筋和全部箍筋,并用20#铁丝绑扎牢固,采用梅花型绑扎,钢筋绑扎需严格按照设计要求的数量和规格进行绑扎安装,完成钢筋绑扎后,按照设计给定的尺寸进行支立模板并用铆钉及时进行加固,模板在基础坑中支立的同时考虑需支立起与底层挡土墙预制块底部的榫槽相对应大小的榫头孔位,以便灌注混凝土时形成榫头,并与底层挡土墙直接连接安装,在完成模板支立后,进行混凝土的浇筑,为了加快施工进度,在混凝土中加入速凝剂,按重量份速凝剂掺量为混凝土重量的5%,基础混凝土灌注统一采用混凝土搅拌站集中拌制后用混凝土搅拌车运输至基础槽位前进行浇筑,混凝土强度要求为C30,混凝土灌入基础槽位前,在入口位置固定好溜筒进料口,并且续接溜筒至浇筑仓面位置并固定牢固,灌注混凝土时,一边将混凝土溜入仓面,然后用插入式软轴振捣器平仓、振捣,直至灌注完毕,并将表面混凝土收平、压光;Step 3. Pouring of foundation concrete: Before excavating the foundation slot in step 2, process several forming templates and shaping supports according to the requirements of the engineering construction drawings, so as to facilitate the erection of the template on site; in step 2, open the foundation slot. After excavation, it is necessary to measure the excavation groove. After the measurement is qualified, the reinforcement construction is carried out. First, after the main reinforcement is welded, install the main reinforcement at the four corners of the foundation and all the stirrups, and bind them firmly with 20 # iron wire. Binding, steel bar binding shall be bound and installed in strict accordance with the quantity and specifications required by the design. After the steel bar binding is completed, the formwork shall be erected according to the size given by the design and reinforced in time with rivets. When the formwork is erected in the foundation pit, consider the need for support. The tenon hole position corresponding to the tenon and groove at the bottom of the precast block of the bottom retaining wall is erected, so that the tenon can be formed when pouring concrete, and the tenon can be directly connected and installed with the bottom retaining wall. After the formwork is erected, the concrete is poured. In order to speed up the construction progress, an accelerator is added to the concrete. The amount of the accelerator is 5% of the weight of the concrete by weight. The foundation concrete is poured uniformly by a concrete batching station and then transported to the foundation tank by a concrete mixer truck. For pouring, the concrete strength is required to be C30. Before pouring the concrete into the foundation groove, fix the feeding port of the chute at the entrance, and connect the chute to the position of the pouring silo and fix it firmly. Enter the warehouse surface, and then use the plug-in flexible shaft vibrator to level and vibrate until the filling is completed, and the surface concrete is flattened and calendered; 步骤四、装配式挡土墙的施工:在步骤三中基础混凝土达到设计强度后,进行装配式挡土墙的施工,装配式挡土墙采用吊车吊装,人工配合,挡土墙安装通过上层预留榫槽与下层预留榫头并以“错位拼接”方式拼接,就位后加以稳固支撑,防止倾覆,每层挡土墙安装高度需高于本层锚固体设计高度,以便更好的发挥锚固体所提供的抗拔承载力作用;Step 4. Construction of the prefabricated retaining wall: After the foundation concrete reaches the design strength in step 3, the construction of the prefabricated retaining wall is carried out. The prefabricated retaining wall is hoisted by crane and manually coordinated. The tenon groove and the tenon on the lower layer are reserved and spliced in a "displacement splicing" method. After they are in place, they are firmly supported to prevent overturning. The installation height of each retaining wall should be higher than the design height of the anchoring body of this layer, so as to better perform the anchoring. The uplift bearing capacity provided by the body; 步骤五、挡土墙后方填土施工并压实:在每层挡土墙安装完毕后,待基础混凝土强度达到85%时,进行挡土墙后部的回填土的施工,采用人工回填,蛙式打夯机打夯的方法进行土方的回填,蛙式打夯机在打夯之前,对回填土进行初步平整,打夯机依次夯打,一夯压半夯,夯夯相接,行行相连,两遍纵横交叉,打夯不留间隙,行夯路线由周边开始,然后再夯向中间,填方施工必须按规定分层夯压密实,填方施工后要对每层回填土进行检验,用换砂法取样测定土的干密度,求出土的密实度,符合设计要求后,才能填筑上层,每层压实后的回填土高度应与该层锚固体设计高度齐平;Step 5. Backfill construction and compaction at the rear of the retaining wall: After the installation of each retaining wall is completed, when the strength of the foundation concrete reaches 85%, the construction of the backfill at the rear of the retaining wall is carried out. The backfill of earthwork is carried out by the method of ramming with a type rammer. Before ramming, the frog rammer will preliminarily level the backfilled soil. Connected, cross vertically and horizontally twice, ramming without leaving gaps, the ramming route starts from the periphery, and then rams to the middle. The filling construction must be compacted and compacted in layers according to the regulations. After the filling construction, the backfill soil of each layer shall be inspected. , use the sand-changing method to sample and measure the dry density of the soil, and find out the compactness of the soil. Only after meeting the design requirements can the upper layer be filled. The backfill height of each layer after compaction should be flush with the design height of the anchoring body of the layer; 步骤六、开挖锚固体、锚索和连接杆的槽位:在每层填方施工完成后,在压实平整的填方表面采用人工开挖的方法,进行锚固体、锚索和连接杆槽位的开挖,槽位开挖时确保开挖断面尺寸符合锚固体、锚索和连接杆的尺寸大小且槽位底部平直,槽内无塌方,无积水;Step 6. Excavate the slots for anchors, cables and connecting rods: After the construction of each layer of fill is completed, manually excavate the surface of the compacted and flat fill to carry out anchors, cables and connecting rods. When excavating the slot, ensure that the size of the excavation section conforms to the size of the anchor body, anchor cable and connecting rod, and the bottom of the slot is straight, and there is no collapse or water accumulation in the slot; 步骤七、安装锚固体、设置横向和竖向连接锚索,同层锚固体的连接杆的焊接:在步骤六中锚固体、锚索和连接杆的槽位开挖完成后,首先在设定锚固体的槽位处安装锚固体,再将锚索安装在锚索的槽位处,锚索的后端与锚固体通过锚具锁定,锚索的前端穿过挡土墙暂不进行锁定,土方回填完成后再进行锚索端头的封锚,待同层锚固体安装完毕后,同层锚固体之间通过连接杆进行连接,连接杆与锚固体之间通过焊接进行固定,使同层锚固体连接成一个整体,能够提供更大的承载力;Step 7: Install the anchors, set up the horizontal and vertical connecting cables, and weld the connecting rods of the same layer of anchors: After excavating the slots for the anchors, cables and connecting rods in step 6, first set the Install the anchor at the slot of the anchor, and then install the anchor cable in the slot of the anchor cable. The rear end of the anchor cable and the anchor are locked by the anchor, and the front end of the anchor cable passes through the retaining wall and is temporarily locked. After the earthwork is backfilled, the end of the anchor cable is sealed and anchored. After the installation of the anchors on the same layer is completed, the anchors on the same layer are connected by connecting rods, and the connecting rods and the anchors are fixed by welding. The anchors are connected as a whole, which can provide greater bearing capacity; 步骤八、重复上述步骤四至步骤七,上级锚固体安装时,应对下级锚固体进行初张拉:进行上层锚固体安装施工时,应对下层锚固体进行初张拉,在第一层初张拉完成后,可继续向上层进行挡土墙的砌筑及挡土墙后部的土方回填,达到第二层锚固体高度时,按第一层锚固体的施工方法重复上述施工;Step 8. Repeat the above steps 4 to 7. When the upper-level anchors are installed, the lower-level anchors should be initially tensioned: when the upper-level anchors are installed and constructed, the lower-level anchors should be initially tensioned. After that, the masonry of the retaining wall and the earthwork backfilling at the rear of the retaining wall can be continued to the upper layer. When the height of the second layer of anchors is reached, the above construction shall be repeated according to the construction method of the first layer of anchors; 步骤九、按设计层数要求,对竖向连接锚索张拉锁定:在步骤八中所述的锚固体完成初张拉后,根据设计层数要求,对数层锚固体竖向之间的连接锚索进行张拉,张拉荷载为设计荷载的10%,张拉时监测竖向锚固体的变化及回填土的变形,如果出现异常情况,立即停止张拉,查明原因,采取措施后再次进行张拉,待数层锚固体之间的连接锚索张拉完成后进行竖向锁定;Step 9. Tension and lock the vertical connection anchor cable according to the design layer requirements: after the initial tension of the anchor body described in step 8 is completed, according to the design layer number requirements Connect the anchor cable for tensioning. The tensioning load is 10% of the design load. During tensioning, monitor the change of the vertical anchor and the deformation of the backfill. If there is an abnormal situation, stop the tensioning immediately, find out the cause, and take measures. Tension is carried out again, and vertical locking is carried out after the tensioning of the connecting anchor cables between several layers of anchors is completed; 步骤十、重复上述步骤四至步骤九至挡土墙砌筑达到设计高度,按设计荷载对水平向锚索进行分级张拉:水平向锚索分级张拉荷载为设计荷载的10%,张拉时监测竖向锚固体的变化及回填土的变形,如果出现异常情况,立即停止张拉,查明原因,采取措施后再次进行张拉,直至所有水平向锚索张拉完成;Step 10. Repeat the above steps 4 to 9 until the retaining wall is built to the design height, and the horizontal anchor cables are graded and tensioned according to the design load: the graded tension load of the horizontal anchor cables is 10% of the design load. Monitor the change of the vertical anchor and the deformation of the backfill. If there is an abnormal situation, stop the tension immediately, find out the reason, and take measures to tension again until all the horizontal anchor cables are tensioned; 步骤十一、检查调试,锚头封锚,施工完成。Step 11. Check and debug, seal the anchor head, and complete the construction. 6.根据权利要求5所述的一种装配式轻型支挡结构的施工方法,其特征在于:所述的锚索采用预应力钢绞线制成,锚索的端头采用标准锚具紧固安装,再用千斤顶进行张拉调试,张拉按设计要求进行,在锚索分级张拉调试完成后即对穿过挡土墙处的锚索的端头进行锁定封锚。6 . The construction method of an assembled light-duty support structure according to claim 5 , wherein the anchor cable is made of prestressed steel strands, and the ends of the anchor cable are fastened with standard anchors. 7 . After installation, the jack is used for tensioning and debugging. The tensioning is carried out according to the design requirements. After the graded tensioning and debugging of the anchor cable is completed, the end of the anchor cable passing through the retaining wall is locked and anchored. 7.根据权利要求5所述的一种装配式轻型支挡结构的施工方法,其特征在于:所述的步骤一中使用“全站仪”进行定位时最少确定六个定位桩,测量定位所用的“全站仪”、“经纬仪”、“水准仪”及控制质量检测设备在使用周期内的计量器具按二级计量标准进行计量标定控制。7. The construction method of an assembled light-duty retaining structure according to claim 5, wherein in the step 1, at least six positioning piles are determined when using a "total station" for positioning, and the measuring and positioning used The "total station", "theodolite", "level instrument" and the measuring instruments of the control quality testing equipment in the service cycle are measured and calibrated according to the secondary measurement standard. 8.根据权利要求5所述的一种装配式轻型支挡结构的施工方法,其特征在于:所述的步骤三中的模板支立完成后进行吊点检测,模板之间偏差小于2cm,在模板完成支立后,将模板底部与基础槽位底部缝隙密封严密。8. The construction method of an assembled light-duty support structure according to claim 5, characterized in that: after the template is erected in the step 3, the lifting point is detected, and the deviation between the templates is less than 2cm, and the After the formwork is erected, seal the gap between the bottom of the formwork and the bottom of the foundation slot tightly. 9.根据权利要求5所述的一种装配式轻型支挡结构的施工方法,其特征在于:所述的步骤五中的填方施工用人力翻斗车运土,由最低处开始回填,至下而上分层进行回填,每层回填土厚度不大于50cm,当天所回填土方必须在当天压实,以免漏夯,每回填50cm,压实一次,回填土方压实系数不小于0.97。9 . The construction method of an assembled light-duty support structure according to claim 5 , wherein the filling construction in the step 5 is carried out with a manpower dump truck to carry soil, and the backfilling starts from the lowest point and reaches the bottom. 10 . The upper layer is backfilled, and the thickness of each layer of backfill is not more than 50cm. The backfill soil must be compacted on the same day to avoid leakage of compaction. Every 50cm of backfill should be compacted once. 10.根据权利要求5所述的一种装配式轻型支挡结构的施工方法,其特征在于:所述的步骤十一中的封锚采用C30混凝土对锚索的端头进行密封,保护层厚度为100mm。10. The construction method of an assembled light-duty retaining structure according to claim 5, characterized in that: the sealing anchor in the eleventh step is to use C30 concrete to seal the end of the anchor cable, and the thickness of the protective layer is is 100mm.
CN202010999455.4A 2020-09-22 2020-09-22 Assembly type light supporting and retaining structure and construction method Pending CN112031018A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010999455.4A CN112031018A (en) 2020-09-22 2020-09-22 Assembly type light supporting and retaining structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010999455.4A CN112031018A (en) 2020-09-22 2020-09-22 Assembly type light supporting and retaining structure and construction method

Publications (1)

Publication Number Publication Date
CN112031018A true CN112031018A (en) 2020-12-04

Family

ID=73574137

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010999455.4A Pending CN112031018A (en) 2020-09-22 2020-09-22 Assembly type light supporting and retaining structure and construction method

Country Status (1)

Country Link
CN (1) CN112031018A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114561962A (en) * 2022-02-16 2022-05-31 哈尔滨工业大学 Double-wall retaining wall-injection type vacuum anchor cable cooperative slope protection system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5468098A (en) * 1993-07-19 1995-11-21 Babcock; John W. Segmental, anchored, vertical precast retaining wall system
KR20100084390A (en) * 2009-01-16 2010-07-26 (주)한도엔지니어링 The natural stone retaining structure using blasted rocks and concrete resistance blocks and its construction technique
CN107100180A (en) * 2017-06-29 2017-08-29 湖南工业大学 Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering
CN209429163U (en) * 2018-09-18 2019-09-24 中铁二院工程集团有限责任公司 Assembled green ecological anchor slab retaining wall construction
CN110700291A (en) * 2019-10-23 2020-01-17 山东建筑大学 Combined retaining structure and construction method thereof
CN212316984U (en) * 2020-09-22 2021-01-08 仲恺农业工程学院 Light-duty retaining structure of assembled suitable for fill engineering

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5468098A (en) * 1993-07-19 1995-11-21 Babcock; John W. Segmental, anchored, vertical precast retaining wall system
KR20100084390A (en) * 2009-01-16 2010-07-26 (주)한도엔지니어링 The natural stone retaining structure using blasted rocks and concrete resistance blocks and its construction technique
CN107100180A (en) * 2017-06-29 2017-08-29 湖南工业大学 Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering
CN209429163U (en) * 2018-09-18 2019-09-24 中铁二院工程集团有限责任公司 Assembled green ecological anchor slab retaining wall construction
CN110700291A (en) * 2019-10-23 2020-01-17 山东建筑大学 Combined retaining structure and construction method thereof
CN212316984U (en) * 2020-09-22 2021-01-08 仲恺农业工程学院 Light-duty retaining structure of assembled suitable for fill engineering

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114561962A (en) * 2022-02-16 2022-05-31 哈尔滨工业大学 Double-wall retaining wall-injection type vacuum anchor cable cooperative slope protection system

Similar Documents

Publication Publication Date Title
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN107542108B (en) A kind of reverse construction method of building basement structure
CN110106868B (en) Karst geology large-diameter pile foundation pore-forming process method
CN112593559A (en) Construction method for deep foundation pit supporting of micro-pile prestressed anchor cable composite soil nailing wall
CN106930319A (en) A kind of high slope framed revetment and its construction method
CN112575670B (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
US11959243B2 (en) Method for constructing large-span station with two-wing open type half-cover excavation and half-reverse construction
CN111705795A (en) A prefabricated anchor pier reinforced by a side slope and an integral construction method for the assembly of a post-cast lattice beam
CN111254966A (en) Bridge abutment and pier-column foundation structure in mountainous area and its construction method
CN100513705C (en) Underground Beam-Pile Frame Structure for Slope Reinforcement
CN114411761A (en) Advanced pre-support system for planned subway tunnel during construction of newly-built building and pre-support construction method
CN110644509A (en) A kind of vertical anchor and balance weight type pile-slab wall and its construction method
CN110306989B (en) Non-open-cut assembled pipe trench excavation supporting and reinforcing method
CN112031018A (en) Assembly type light supporting and retaining structure and construction method
CN101476338B (en) Construction technology of micro-steel pipe piles to reinforce subsidence foundation
CN212270945U (en) Existing railway line foundation pit supporting system
CN212316984U (en) Light-duty retaining structure of assembled suitable for fill engineering
CN111549789A (en) Reinforcing structure for foundation pit support and construction method thereof
CN217896563U (en) Anchor-spraying type pile plate retaining wall for rocky slope of platform building
CN212052850U (en) Bridge abutment and pier-column infrastructure in mountainous areas
CN112627002B (en) Continuous beam bridge suitable for tunnel to pass through giant karst cave and construction technical method thereof
CN115506382A (en) Construction method for pile plate wall of island building platform
CN212561573U (en) Combined protective structure for side slope retaining wall and steel pipe pile
CN115012947A (en) Reverse method prefabricated shaft and its construction method
CN210712916U (en) Combined anchoring road shoulder retaining wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination