CN107100180A - Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering - Google Patents

Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering Download PDF

Info

Publication number
CN107100180A
CN107100180A CN201710512768.0A CN201710512768A CN107100180A CN 107100180 A CN107100180 A CN 107100180A CN 201710512768 A CN201710512768 A CN 201710512768A CN 107100180 A CN107100180 A CN 107100180A
Authority
CN
China
Prior art keywords
pull bar
anchorage
arm
breast boards
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710512768.0A
Other languages
Chinese (zh)
Inventor
刘杰
唐西娅
杨庆光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan University of Technology
Original Assignee
Hunan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan University of Technology filed Critical Hunan University of Technology
Priority to CN201710512768.0A priority Critical patent/CN107100180A/en
Publication of CN107100180A publication Critical patent/CN107100180A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses superelevation light supporting structure and improvement high roadbed, the method for high slope engineering, first it is vertically arranged king pile, secondary stake, then the bulkhead construction below cushion cap, banketing between stake and after stake answers placement in layers to be compacted, more than bearing platform construction, cushion cap help arm and bulkhead construction and steel pipe pre-buried, the construction of anchorage wall, banketed after breast boards more than cushion cap, the construction of grout injection in pull bar positioning, installation, tensioning, locking, sealing off and covering anchorage concrete and hole.Go for Protean site condition, when height of embankment is in 12.0m 24.0m, side slope total height has comparativity in 16.0m 30.0m with common retaining wall.When height of embankment is in 24.0m 30.0m, side slope total height has comparativity in 28.0m 34.0m with bridge, meanwhile, with load-bearing, anti-skid and earth-retaining triple functions.

Description

Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering
Technical field
The invention belongs to technical field of civil engineering, it is related to a kind of superelevation light supporting structure and administers high roadbed, flash The method of slope engineering.
Background technology
China《Highway subgrade design specification》(JTGD30-2004) the retaining structure type available for embankment side slope proposed And applicable elements have:1) gravity retaining wall (including balance weight retaining wall) is with being applied to general area, soaking district and earthquake The retaining engineerings such as curb, embankment and the cutting in area.Wall height is not more than 12.0m.2) half gravity retaining wall is applied to use On the higher or weak ground of the level of ground water of gravity retaining wall, wall is high not to be preferably greater than 12.0m.3) cantilever retaining wall preferably exists The relatively low embankment section of foundation bearing capacity is used, and wall height is no more than 5.0m.4) counterfort retaining wall preferably foundation bearing capacity compared with Low embankment section is used, although specification is pointed out up to 15.0m.But in actual applications, when wall height is more than 10.0m, to general Earthen foundation, antiskid and the stability against overturning of its foundation bearing capacity and retaining wall are difficult to meet to require, and baseplate width will connect Nearly wall is high.5) anchor plate retaining wall is preferably used in the inadequate regional curb wall of building stones or embankment formula retaining wall, and wall height should not surpass Cross 10.0m.The curb wall or embankment formula retaining walls height that reinforced earth retaining wall is used for general area are not more than 12.0m.Prop up above Keeping off the shortcoming of structure type is:One side supporting and retaining system height of embankment is limited, on the other hand only has earth-retaining function, no load-bearing and anti-skid Function, is not suitable for coming down, caves in, on soft soil foundation.
《High light-duty supporting and retaining system technology and application》The supporting and retaining system knot available for embankment side slope proposed in works such as (Zhang Yufang works) Structure type and applicable elements have:High light-duty Prestressed Anchor Cable Poling Board Wall is applied to the steep height of embankment 12.0m- of physical relief 16.0m embankment supporting and retaining system, the supporting construction has certain anti-skid function, but must possess after wall and be suitable for prestressed cable anchorage Stratum, and enough anchor forces can be provided, not be suitable for large-scale embankment location.High light anchorage plate retaining wall is applicable In height of embankment 12.0m-16.0m embankment supporting and retaining system, but it should not use in antiskid location.
With developing rapidly for the construction such as highway, railway, to adapt to Protean site condition and a wide range of high roadbed The need for (height of embankment is more than 16.0m, side slope total height more than 24.0m) slope supporting.Combined type retaining structure is exactly at this Plant turns into the hot issue that engineers and technicians pay close attention to again under foreign and domestic situation.
The content of the invention
In order to achieve the above object, the present invention provides a kind of superelevation light supporting structure, goes for Protean Site condition, when height of embankment is in 12.0m-24.0m, side slope total height has comparable in 16.0m-30.0m with common retaining wall Property.When height of embankment is in 24.0m-30.0m, side slope total height has comparativity in 28.0m-34.0m with bridge, meanwhile, have Load-bearing, anti-skid and earth-retaining triple functions.
It is a further object of the present invention to provide above-mentioned superelevation light supporting structure improvement high roadbed, the side of high slope engineering Method.
The technical solution adopted in the present invention is, superelevation light supporting structure, including vertical setting of being made of armored concrete King pile, secondary stake are put, cushion cap is provided with above king pile and secondary stake, between king pile and secondary stake, reinforced concrete is provided with king pile The breast boards that soil is made;The top of king pile and secondary stake, which is set, helps arm;The horizontal embedded steel tube on arm is helped;It is additionally provided with and is mixed by reinforcing bar Horizontal embedded steel tube on anchorage wall, anchorage wall is made in solidifying soil;Pull bar is passed through from the embedded steel tube on arm and anchorage wall is helped;Anchorage The end of the pull bar of wall is fixed with anchorage;Help on the outside of arm, fixed positioned at the end for the pull bar helped on arm with anchorage;Anchorage external application is mixed Solidifying grave anchor.
Another technical scheme of the present invention is to administer high roadbed, high slope work using superelevation light supporting structure The method of journey, is specifically followed the steps below:
Step 1, king pile, secondary stake are vertically arranged, king pile is made up with secondary stake of armored concrete, king pile and the pair of below ground King pile more than stake one-time cast-forming, ground uses multiple cast with secondary stake according to actual conditions, and joint part should first dabbing;
Step 2, the bulkhead construction below cushion cap:Breast boards is made up of armored concrete;
Step 3, banket between stake and after stake and answer placement in layers to be compacted, lift height is not more than 50cm, away from king pile and secondary stake and Breast boards banketing in the range of 1m is compacted with the baby roller or ramming machine less than 1 ton, and compactness is no less than 85%;
Step 4, bearing platform construction, king pile sets cushion cap to be made up of armored concrete with secondary stake upper horizontal, is poured using scene Note;
Step 5, more than cushion cap help arm and bulkhead construction and steel pipe pre-buried:Help arm with breast boards by armored concrete system Into, sandstone loaded filter is set after breast boards, should be according to design attitude before helping arm concrete to pour into a mould, level is pre- on arm is helped Steel pipe is buried, embedded steel tube internal diameter is determined according to the pull bar diameter of design;
Step 6, anchorage wall is constructed:Anchorage wall is made up of armored concrete, using cast-in-site, is poured in anchorage wall concrete , should be according to design attitude before note, the horizontal embedded steel tube on anchorage wall, pipe diameter according to pull bar diameter determine;
Step 7, banketed after breast boards more than cushion cap, banketed after breast boards and answer compaction in layers, lift height is not more than 50cm, away from the banketing with the baby roller or ramming machine pressure less than 1 ton in the range of 1m for helping arm, breast boards and anchorage wall Real, compactness is no less than 85%;Filling for soil should be installed, tensioning and locking handover are carried out according to pull bar set location with pull bar;
Step 8, in pull bar positioning, installation, tensioning, locking, sealing off and covering anchorage concrete and hole grout injection construction:Pull bar is determined Native handover of filling is carried out after position, installation and tensioning and breast boards, until designed elevation is pushed up on slope;Before pull bar installation, first embankment To pull bar design level height above 0.2m, embankment compactness reaches can start to install pull bar after regulation requirement;Pull bar is installed When, should be according to pull bar design plane position first in compacting embankment surface grooving, groove width 0.3m, depth ratio pull bar designed elevation is low 10cm;Pull bar is passed through from the embedded steel tube on arm and anchorage wall is helped, is embedded in the pull bar groove excavated;Anchorage will be located at The end of the pull bar of wall is good with anchorage installation, and is pointed on anchorage wall grout injection in embedded steel tube, while being located at The construction of sealing off and covering anchorage concrete on anchorage wall, pull bar groove fills compacting with soil or 37 lime earth, and pull bar is densified to continuing embankment During absolute altitude above 1m, helping positioned at helping the end of arm upper connecting rod to install on the outside of arm with anchorage, pull bar tensioning, tensioning classification, Tensile load, tensioning time are determined by design requirement, and the change of deformation and the embankment of helping arm is should be noted that during tensioning, is such as noted abnormalities Situation, should stop tensioning, ascertain the reason, take measures;Above step 8 is repeated until embankment is fully completed to slope top in embankment Afterwards, benefit tensioning is carried out to all pull bars by design requirement, and is pointed to help on arm grout injection in embedded steel tube, carried out simultaneously Positioned at the construction for helping sealing off and covering anchorage concrete on arm.
Further, in the step 1, king pile uses manually digging hole filling pile or mechanical hole perfusion post with secondary stake, main Stake is no less than 600mm with secondary stake stake footpath, and strength grade of concrete is not less than C25.
Further, in the step 2, breast boards is using cast-in-site or uses precast assembly;Earth-retaining below cushion cap Plate thickness is 120-200mm, and strength grade of concrete is not less than C25.
Further, in the step 4, cushion cap thickness is no less than 400mm, and strength grade of concrete is not less than C25.
Further, in the step 5, spilled water hole, sluicing pitch of holes 2-3m, aperture are reserved on breast boards more than cushion cap Earth-retaining plate thickness more than 50-100mm, cushion cap is 150-200mm.
Further, in the step 5, help arm thickness to be no less than 300mm, help arm spacing 2-3m, help arm and breast boards mixed Solidifying soil strength grade is not less than C25.
Further, in the step 6, anchorage wall thickness is no less than 300mm, and strength grade of concrete is not less than C25.
Further, in the step 8, pull bar uses deformed bar or steel strand wires.
Further, when the pull bar uses steel strand wires, made using non-bending steel cable, steel strand wires are attached except two intermediate plate Near outer, remainder first brushes twice of antifouling paint, then fills anti-corrosion grease, and outer casing internal diameter is 17mm, wall thickness not less than 1mm Hard plastic tube.
The beneficial effects of the invention are as follows combine cantilevered pile plate wall, double friction pile, high light-duty prestress anchorage cable peg board The technical characterstic of wall, high light anchorage plate retaining wall and counterfort retaining wall, has load-bearing concurrently, anti-skid and supporting and retaining system triple functions super High light supporting structure.Relative to traditional high roadbed, high slope, high light supporting structure, this supporting construction is in Deformation control Validity, structure type arrangement flexibility in terms of be able to embody well.The characteristics of it mainly has the following aspects:
1) layout pattern is flexible.Peg board and anchorage wall combining form maneuverability, strong adaptability.A) after can be according to retaining wall Anchorage wall is arranged to separate type (Fig. 1,2), monoblock type vertical and integral inclined formula by the banket position and orientation of the middle plane of fracture (Fig. 3,4).For separate type anchorage wall:Each anchorage wall independent effect, its set location is flexible but whole between each pull bar The body coordination ability is poor.For overall vertical anchorage wall:Construction is quick and easy, one-shot forming, the total tune between each pull bar Ability is good, but lower floor's pull bar length is big.For integral inclined formula anchorage wall:Can rationally it be determined according to the position and orientation of the plane of fracture The position of anchorage wall and gradient, so that the total tune ability reduced between lower floor's pull bar length, each pull bar is good, but anchorage wall After banket must first compaction in layers, and slope is formed according to anchorage wall gradient, construction is complicated.B) arm can will be helped to be arranged to anti-chair Formula (Fig. 2).Because anti-chair form is helped during the platform of arm is not disposed on and bankets, but on the outside of side slope, therefore can be according to actual feelings Condition plants flowers and plants etc. to coordinate surrounding landscape on platform.C) it can change cushion cap set location to adjust and assist according to actual conditions Adjust deformation and the internal force of top and the bottom structure.D) flexible reasonable Arrangement multilayer pull bar on arm can be helped each according to retaining wall height, So as to improve earth-retaining height, and adjust and the internal force for coordinating top and the bottom structure and deformation.E) can be reasonable according to landform geological conditions Flexible arrangement substructure (king pile below cushion cap, secondary stake), gives full play to load-bearing, anti-skid and supporting and retaining system triple functions.
2) cushion cap, king pile, secondary stake and pull bar constitute an indeterminate space structure, and integral rigidity and anti-skid ability are much larger than Single row pillars retaining structure, high light-duty Prestressed Anchor Cable Poling Board Wall, high light anchorage plate retaining wall.Due to the setting of pull bar so that Internal forces drastically decline, and its horizontal displacement is substantially reduced.Simultaneously can be by entering one to the appropriate application prestressing force of pull bar Step reduction Internal forces and its horizontal displacement, and adjust the distribution of cushion cap bottom vertical pressure, can supporting and retaining system than high light-duty prestressing force The higher embankment side slope of anchor cable pile plate wall, high light anchorage plate retaining wall.
3) cushion cap top is banketed after gravity makes the overall center of gravity of retaining structure and moves the ability for enhancing resistance soil pressure, is effectively carried The high resistance to overturning of retaining structure.Simultaneously as the setting of cushion cap makes pile foundation be acted on by vertical force, pile body is improved Shear-carrying capacity, and vertical load can be transferred to deeper soil layer.Therefore, either in terms of structure stress and settlement Control Better than other retaining structure patterns.
4) this retaining structure is indeterminate space structure, and the Internal forces distribution of energy adjust automatically is allowed to adapt to complicated and changeable Loading condition, also can adjust the horizontal displacement of Internal forces and retaining structure by applying prestressing force to pull bar.
5) when there is potential water use or inadequate foundation bearing capacity in native (rock) layer in bottom, bottom pile foundation play it is anti-skid, Load-bearing and earth-retaining triple functions.For steep slope region, effective anchor force is provided when there is good and hard stable rock-soil layer When, anchorage pull bar can be changed to anchor pole (rope), or the form being combined using anchor pole (rope) with anchorage pull bar.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is the accompanying drawing used required in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, can be with Other accompanying drawings are obtained according to these accompanying drawings.
Fig. 1 be use in the embodiment of the present invention help arm chair form pile plate wall to combine anchorage wall supporting construction figure.
Fig. 2 is that use in the embodiment of the present invention counter helps arm chair form pile plate wall to combine anchorage wall supporting construction figure.
Fig. 3 be use in the embodiment of the present invention help the overall vertical anchorage wall supporting construction of arm chair form pile plate wall joint Figure.
Fig. 4 be use in the embodiment of the present invention help arm chair form pile plate wall to combine integral inclined formula anchorage wall supporting construction Figure.
In figure, 1. king piles, 2. secondary stakes, 3. cushion caps, 4. breast boards, 5. help arm, and 6. embedded steel tubes, 7. anchorages, 8. sealing off and covering anchorages are mixed Solidifying soil, 9. cement mortars, 10. pull bars, 11. anchorage walls.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment, belongs to the scope of protection of the invention.
Superelevation light supporting structure, structure as shown in any forms of Fig. 1-4, including armored concrete be made it is vertical King pile 1, secondary stake 2 are set, cushion cap 3 is provided between the secondary top of stake 2, king pile 1 and secondary stake 2, reinforcing bar is provided with king pile 1 and is mixed The breast boards 4 that solidifying soil is made;The top of king pile 1 and secondary stake 2, which is set, helps arm 5;The horizontal embedded steel tube 6 on arm 5 is helped;It is additionally provided with Horizontal embedded steel tube 6 on anchorage wall 11, anchorage wall 11 is made by armored concrete;Pull bar 10 is from helping on arm 5 and anchorage wall 11 Passed through in embedded steel tube 6;The end anchorage 7 of the pull bar 10 of anchorage wall 11 is fixed;Help on the outside of arm, positioned at the pull bar helped on arm 5 10 end anchorage 7 is fixed;The external application sealing off and covering anchorage concrete eight of anchorage 7 is fixed.
As shown in Figure 1, 2, anchorage wall 11 can be using separate type, and is vertically arranged, can be according to specific environment, will King pile 1 sets the direction (such as Fig. 1) away from anchorage wall 11, and king pile 1 can be arranged close to the direction (such as Fig. 2) of anchorage wall 11; As shown in Figure 3,4, anchorage wall 11 can be specifically as follows (such as Fig. 3) being vertically arranged, or tilting using one (such as Fig. 4).
, can be according to any in Fig. 1-4 using superelevation light supporting structure improvement high roadbed, the method for high slope engineering Retaining structure, is specifically followed the steps below:
Step 1, king pile 1, secondary stake 2 are vertically arranged, king pile 1 is made up with secondary stake 2 of armored concrete, can use manually digging hole Bored concrete pile or mechanical hole perfusion post.More than the king pile 1 of below ground and the secondary one-time cast-forming of stake 2, ground king pile 1 and pair Stake 2 can be according to actual conditions using multiple cast, but joint part answers first dabbing, and splice should meet relevant code requirement.It is main Stake 1 is no less than 600mm with secondary 2 footpaths of stake, and strength grade of concrete is not less than C25, and pile foundation depth meets design requirement;
Step 2, breast boards 4 of the cushion cap below 3 is constructed, and breast boards 4 is made up of armored concrete, can use cast-in-site, Also precast assembly can be used.Breast boards 4 thickness of the cushion cap below 3 is 120-200mm, and strength grade of concrete is not less than C25;
Step 3, banket between stake and after stake and answer placement in layers to be compacted, lift height is not more than 50cm, away from king pile 1 and secondary stake 2 And the banketing in the range of 1.0m of breast boards 4 is compacted with baby roller (being less than 1 ton) or ramming machine, compactness is no less than 85%;
Step 4, cushion cap 3 is constructed, and king pile 1 sets cushion cap 3 to be made up of armored concrete with the secondary upper horizontal of stake 2, using existing Field cast.The thickness of cushion cap 3 is no less than 400mm, and strength grade of concrete is not less than C25;
Step 5, cushion cap more than 3 helps that arm 5 is constructed with breast boards 4 and steel pipe 6 is pre-buried, helps arm 5 with breast boards 4 by reinforced concrete Soil is made, using cast-in-site, and breast boards 4 can also use precast assembly.Spilled water hole, sluicing pitch of holes should be reserved on breast boards 4 2-3m, aperture 50-100mm, the thickness of more than 3 breast boards of cushion cap 4 are 150-200mm, and sandstone anti-filter should be set after breast boards 4 Layer.Help the thickness of arm 5 to be no less than 300mm, help the spacing 2-3m of arm 5, before helping the concrete of arm 5 to pour into a mould, should helped according to design attitude Horizontal embedded steel tube 6 on arm 5, the internal diameter of embedded steel tube 6 should be determined according to the pull bar diameter of design.Help arm 5 and the concrete of breast boards 4 Strength grade is not less than C25.
Step 6, anchorage wall 11 is constructed, and anchorage wall 11 is made up of armored concrete, using cast-in-site.It is mixed in anchorage wall 11 , should be according to design attitude before solidifying soil cast, the horizontal embedded steel tube 6 on anchorage wall 11, the internal diameter of steel pipe 6 should be according to the pull bar of design 10 diameter is determined.The thickness of anchorage wall 11 is no less than 300mm, and strength grade of concrete is not less than C25;
Step 7, banketed after the breast boards 4 of cushion cap more than 3, banketed after breast boards 4 and answer compaction in layers, lift height is not more than 50cm, away from the banketing with baby roller (being less than 1 ton) or beating in the range of 1.0m for helping arm 5, breast boards 4 and anchorage wall 11 Tamping machine is compacted, and compactness is no less than 85%.Filling for soil should be installed according to the set location of pull bar 10 with pull bar 10, tensioning and lock Determine handover progress;
Step 8, pull bar 10 position, install, tensioning, locking, in sealing off and covering anchorage concrete eight and hole grout injection 9 construction.Draw Bar 10 uses deformed bar or steel strand wires.Pull bar 10 positions, install and tensioning and breast boards 4 after it is native fill handover progress, directly Designed elevation is pushed up to slope.Before the installation of pull bar 10, first embankment to the design level height above 0.2m of pull bar 10, embankment compactness reaches It after to regulation requirement can start that pull bar 10 is installed., should be according to the design plane position of pull bar 10 first in compacting when pull bar 10 is installed The grooving of embankment surface, groove width 0.3m, the low 10cm of the designed elevation of depth ratio pull bar 10.The specification and quantity Ying Yushe of the material of pull bar 10 Meter requirement is consistent.When pull bar 10 is using prestress wire, it should be made using non-bending steel cable, steel strand wires are attached except two intermediate plate Near outer, remainder first brushes twice of antifouling paint, then fills anti-corrosion grease, and outer casing internal diameter is 17mm, wall thickness not less than 1mm Hard plastic tube.Pull bar 10 is passed through in the embedded steel tube 6 on arm 5 and anchorage wall 11 from helping, is embedded in the pull bar groove excavated.Will End anchorage 7 positioned at the pull bar 10 of anchorage wall 11 is installed, and is pointed on anchorage wall 11 cement injection in embedded steel tube 6 Slurry 9, while be located at the construction of sealing off and covering anchorage concrete eight on anchorage wall 11.The groove of pull bar 10 can fill pressure with soil or 37 lime earth It is real.When continuation embankment is densified to 10 absolute altitude above 1.0m of pull bar, the upper connecting rod 10 of arm 5 is helped helping with anchorage 7 to be located on the outside of arm End install.The tensioning of pull bar 10, tensioning classification, tensile load, tensioning time are determined by design requirement.It should be noted that during tensioning The change of deformation and the embankment of arm 5 is helped, such as be found the abnormal situation, tensioning should be stopped, being ascertained the reason, taken measures.
Above step 8 is repeated until embankment to slope is pushed up.After embankment is fully completed, all pull bars 10 are entered by design requirement Row mends tensioning, and is pointed to help on arm 5 grout injection 9 in embedded steel tube 6, and sealing off and covering anchorage concrete eight on arm 5 is helped while be located at Construction.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the scope of the present invention.It is all Any modification, equivalent substitution and improvements made within the spirit and principles in the present invention etc., are all contained in protection scope of the present invention It is interior.

Claims (10)

1. superelevation light supporting structure, it is characterised in that be vertically arranged king pile (1), secondary stake including what armored concrete was made (2) cushion cap (3), is provided between king pile (1) and secondary stake (2) top, king pile (1) and secondary stake (2), is set on king pile (1) There is the breast boards (4) that armored concrete is made;The top of king pile (1) and secondary stake (2), which is set, helps arm (5);The level on arm (5) is helped Embedded steel tube (6);It is additionally provided with and horizontal embedded steel tube (6) on anchorage wall (11), anchorage wall (11) is made by armored concrete;Draw Bar (10) is passed through in the embedded steel tube (6) on arm (5) and anchorage wall (11) from helping;Use the end of the pull bar (10) of anchorage wall (11) Anchorage (7) is fixed;Help on the outside of arm, fixed positioned at the end for the pull bar (10) helped on arm (5) with anchorage (7);Anchorage (7) external application is mixed Solidifying soil (8) sealing off and covering anchorage.
2. high roadbed, the method for high slope engineering are administered using superelevation light supporting structure, it is characterised in that specifically according to following Step is carried out:
Step 1, king pile (1), secondary stake (2) are vertically arranged, king pile (1) is made up with secondary stake (2) of armored concrete, below ground King pile (1) more than king pile (1) and secondary stake (2) one-time cast-forming, ground is used with secondary stake (2) according to actual conditions repeatedly to be poured Note, joint part should first dabbing;
Step 2, breast boards (4) construction of cushion cap (3) below:Breast boards (4) is made up of armored concrete;
Step 3, banket between stake and after stake and answer placement in layers to be compacted, lift height is not more than 50cm, away from king pile (1) and secondary stake (2) And breast boards (4) banketing in the range of 1m is compacted with the baby roller or ramming machine less than 1 ton, compactness is no less than 85%;
Step 4, cushion cap (3) is constructed, and king pile (1) sets cushion cap (3) to be made up of armored concrete with secondary stake (2) upper horizontal, adopts Use cast-in-site;
Step 5, more than cushion cap (3) help arm (5) and breast boards (4) construction and steel pipe (6) pre-buried:Help arm (5) and breast boards (4) by Armored concrete is made, and sandstone loaded filter is set afterwards in breast boards (4), before helping arm (5) concrete to pour into a mould, should be according to design position Put, the horizontal embedded steel tube (6) on arm (5) is helped, embedded steel tube (6) internal diameter is determined according to the pull bar diameter of design;
Step 6, anchorage wall (11) is constructed:Anchorage wall (11) is made up of armored concrete, using cast-in-site, in anchorage wall (11) Concrete cast before, should be according to design attitude, the horizontal embedded steel tube (6) on anchorage wall (11), steel pipe (6) internal diameter according to drawing The diameter of bar (10) is determined;
Step 7, banketed after breast boards (4) more than cushion cap (3), banketed after breast boards (4) and answer compaction in layers, lift height is little In 50cm, away from the banketing with the small-sized pressure road less than 1 ton in the range of 1m for helping arm (5), breast boards (4) and anchorage wall (11) Machine or ramming machine compacting, compactness are no less than 85%;Filling for soil should be pacified according to pull bar (10) set location with pull bar (10) Dress, tensioning and locking handover are carried out;
Step 8, in pull bar (10) positioning, installation, tensioning, locking, sealing off and covering anchorage concrete (8) and hole grout injection (9) construction: Pull bar (10) positioning, install and tensioning and breast boards (4) are native afterwards fills handover progress, until slope top designed elevation;In pull bar (10) before installing, first embankment to pull bar (10) design level height above 0.2m, embankment compactness reaches can after regulation requirement Start that pull bar (10) is installed;When pull bar (10) are installed, it should first be dug according to pull bar (10) design plane position on compacting embankment surface Groove, groove width 0.3m, depth ratio pull bar (10) low 10cm of designed elevation;By pull bar (10) from helping on arm (5) and anchorage wall (11) Embedded steel tube is passed through in (6), is embedded in the pull bar groove excavated;The end anchor of the pull bar (10) of anchorage wall (11) will be located at Tool (7) is installed, and is pointed to embedded steel tube (6) interior grout injection (9) on anchorage wall (11), while carrying out being located at anchorage wall (11) construction of sealing off and covering anchorage concrete (8) on, pull bar (10) groove fills compacting with soil or 37 lime earth, is densified to continuing embankment During pull bar (10) absolute altitude above 1m, the end of arm (5) upper connecting rod (10) is helped to install helping with anchorage (7) to be located on the outside of arm, Pull bar (10) tensioning, tensioning classification, tensile load, tensioning time are determined by design requirement, and the change for helping arm (5) is should be noted that during tensioning Shape and the change of embankment, such as found the abnormal situation, and should stop tensioning, ascertain the reason, take measures;
Above step 8 is repeated until embankment to slope is pushed up, after embankment is fully completed, by design requirement to all pull bars (10) progress Tensioning is mended, and is pointed to help embedded steel tube (6) interior grout injection (9) on arm (5), sealing off and covering anchorage on arm (5) is helped while be located at The construction of concrete (8).
3. use superelevation light supporting structure according to claim 2 administers high roadbed, the method for high slope engineering, it is special Levy and be, in the step 1, king pile (1) uses manually digging hole filling pile or mechanical hole perfusion post, king pile (1) with secondary stake (2) 600mm is no less than with secondary stake (2) stake footpath, strength grade of concrete is not less than C25.
4. use superelevation light supporting structure according to claim 2 administers high roadbed, the method for high slope engineering, it is special Levy and be, in the step 2, breast boards (4) is using cast-in-site or uses precast assembly;The breast boards (4) of cushion cap (3) below Thickness is 120-200mm, and strength grade of concrete is not less than C25.
5. use superelevation light supporting structure according to claim 2 administers high roadbed, the method for high slope engineering, it is special Levy and be, in the step 4, cushion cap (3) thickness is no less than 400mm, and strength grade of concrete is not less than C25.
6. use superelevation light supporting structure according to claim 2 administers high roadbed, the method for high slope engineering, it is special Levy and be, in the step 5, spilled water hole, sluicing pitch of holes 2-3m, aperture 50- are reserved on breast boards (4) more than cushion cap (3) Breast boards (4) thickness more than 100mm, cushion cap (3) is 150-200mm.
7. use superelevation light supporting structure according to claim 2 administers high roadbed, the method for high slope engineering, it is special Levy and be, in the step 5, help arm (5) thickness to be no less than 300mm, help arm (5) spacing 2-3m, help arm (5) and breast boards (4) Strength grade of concrete is not less than C25.
8. use superelevation light supporting structure according to claim 2 administers high roadbed, the method for high slope engineering, it is special Levy and be, in the step 6, anchorage wall (11) thickness is no less than 300mm, and strength grade of concrete is not less than C25.
9. use superelevation light supporting structure according to claim 2 administers high roadbed, the method for high slope engineering, it is special Levy and be, in the step 8, pull bar (10) uses deformed bar or steel strand wires.
10. use superelevation light supporting structure according to claim 9 administers high roadbed, the method for high slope engineering, its It is characterised by, when the pull bar (10) is using steel strand wires, made using non-bending steel cable, steel strand wires are except near the intermediate plate of two Outside, remainder first brushes twice of antifouling paint, then fills anti-corrosion grease, and outer casing internal diameter is 17mm, wall thickness is hard not less than 1mm Modeling pipe.
CN201710512768.0A 2017-06-29 2017-06-29 Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering Pending CN107100180A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710512768.0A CN107100180A (en) 2017-06-29 2017-06-29 Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710512768.0A CN107100180A (en) 2017-06-29 2017-06-29 Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering

Publications (1)

Publication Number Publication Date
CN107100180A true CN107100180A (en) 2017-08-29

Family

ID=59663935

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710512768.0A Pending CN107100180A (en) 2017-06-29 2017-06-29 Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering

Country Status (1)

Country Link
CN (1) CN107100180A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700500A (en) * 2017-09-14 2018-02-16 深圳百勤建设工程有限公司 Slope retaining structure and slope supporting draining integral system
CN108130917A (en) * 2017-12-25 2018-06-08 中国二十冶集团有限公司 Pile foundation earth-retaining wall construction method
CN108797636A (en) * 2018-09-06 2018-11-13 中铁二院北方勘察设计有限责任公司 A kind of upper font retaining wall structure and its construction method
CN109403321A (en) * 2018-09-14 2019-03-01 中国人民解放军陆军勤务学院 Construction method of filling slope prestressed anchor cable
CN110284432A (en) * 2019-06-04 2019-09-27 中交路桥建设有限公司 A kind of high roadbed area first applies fills out abutment construction method afterwards
CN110700291A (en) * 2019-10-23 2020-01-17 山东建筑大学 Combined retaining structure and construction method thereof
CN111291487A (en) * 2020-02-13 2020-06-16 中铁二院工程集团有限责任公司 Method for improving shear-resistant bearing capacity of existing weight-balanced retaining wall
CN111310265A (en) * 2020-02-13 2020-06-19 中铁二院工程集团有限责任公司 Method for improving shear-resisting bearing capacity of balance weight type retaining wall
CN111794268A (en) * 2020-06-01 2020-10-20 中铁大桥科学研究院有限公司 Composite retaining wall and construction method thereof
CN112796187A (en) * 2021-03-22 2021-05-14 余志鹏 Highway subgrade side slope antiskid
CN113513032A (en) * 2021-03-23 2021-10-19 深圳市工勘岩土集团有限公司 Three-row pile gravity dam combined retaining structure for filled high slope
CN114809035A (en) * 2022-04-18 2022-07-29 南京林业大学 Traction type slope re-strengthening and slope self-stabilizing device and working method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202730795U (en) * 2012-06-29 2013-02-13 深圳市工勘岩土工程有限公司 Pile supporting buttressed retaining wall structure
CN105201011A (en) * 2015-09-18 2015-12-30 山东大学 Complex anchored-plate retaining wall and construction method thereof
CN105735345A (en) * 2016-04-01 2016-07-06 自贡市城市规划设计研究院有限责任公司 Composite type supporting and retaining structure and construction method adopting supporting and retaining structure
CN206844132U (en) * 2017-06-29 2018-01-05 湖南工业大学 Superelevation light supporting structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202730795U (en) * 2012-06-29 2013-02-13 深圳市工勘岩土工程有限公司 Pile supporting buttressed retaining wall structure
CN105201011A (en) * 2015-09-18 2015-12-30 山东大学 Complex anchored-plate retaining wall and construction method thereof
CN105735345A (en) * 2016-04-01 2016-07-06 自贡市城市规划设计研究院有限责任公司 Composite type supporting and retaining structure and construction method adopting supporting and retaining structure
CN206844132U (en) * 2017-06-29 2018-01-05 湖南工业大学 Superelevation light supporting structure

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700500A (en) * 2017-09-14 2018-02-16 深圳百勤建设工程有限公司 Slope retaining structure and slope supporting draining integral system
CN107700500B (en) * 2017-09-14 2019-06-18 深圳百勤建设工程有限公司 Slope retaining structure and slope supporting drain integral system
CN108130917A (en) * 2017-12-25 2018-06-08 中国二十冶集团有限公司 Pile foundation earth-retaining wall construction method
CN108797636A (en) * 2018-09-06 2018-11-13 中铁二院北方勘察设计有限责任公司 A kind of upper font retaining wall structure and its construction method
CN109403321A (en) * 2018-09-14 2019-03-01 中国人民解放军陆军勤务学院 Construction method of filling slope prestressed anchor cable
CN110284432A (en) * 2019-06-04 2019-09-27 中交路桥建设有限公司 A kind of high roadbed area first applies fills out abutment construction method afterwards
CN110284432B (en) * 2019-06-04 2021-06-08 中交路桥建设有限公司 Construction method for filling bridge abutment in high-fill area after first construction
CN110700291A (en) * 2019-10-23 2020-01-17 山东建筑大学 Combined retaining structure and construction method thereof
CN111310265A (en) * 2020-02-13 2020-06-19 中铁二院工程集团有限责任公司 Method for improving shear-resisting bearing capacity of balance weight type retaining wall
CN111291487A (en) * 2020-02-13 2020-06-16 中铁二院工程集团有限责任公司 Method for improving shear-resistant bearing capacity of existing weight-balanced retaining wall
CN111310265B (en) * 2020-02-13 2022-03-25 中铁二院工程集团有限责任公司 Method for improving shear-resisting bearing capacity of balance weight type retaining wall
CN111291487B (en) * 2020-02-13 2022-06-14 中铁二院工程集团有限责任公司 Method for improving shear-resistant bearing capacity of existing weight-balanced retaining wall
CN111794268A (en) * 2020-06-01 2020-10-20 中铁大桥科学研究院有限公司 Composite retaining wall and construction method thereof
CN112796187A (en) * 2021-03-22 2021-05-14 余志鹏 Highway subgrade side slope antiskid
CN113513032A (en) * 2021-03-23 2021-10-19 深圳市工勘岩土集团有限公司 Three-row pile gravity dam combined retaining structure for filled high slope
CN114809035A (en) * 2022-04-18 2022-07-29 南京林业大学 Traction type slope re-strengthening and slope self-stabilizing device and working method

Similar Documents

Publication Publication Date Title
CN107100180A (en) Superelevation light supporting structure and improvement high roadbed, the method for high slope engineering
CN102296961B (en) Karst tunnel large-scale cavern processing method
CN102352632B (en) Anchor rod sheet pile combined structure and method for reinforcing high filling body on one side of slope
CN201722704U (en) Pre-stressed cantilever counter rib holding retaining wall
CN106638673B (en) A kind of construction method of compound retaining structure
CN105274922B (en) A kind of antiskid key steel-pipe pile composite construction and method for repairing landslide roadbed
CN101899839A (en) Counter-pulled type rib retaining wall of pre-stressing force cantilever
CN100580190C (en) Building foundation pit supporting construction
CN102828518A (en) Manual hole digging support pile prestress anchor cable anchoring structure and construction method of anchoring structure
CN104389320B (en) Construction method of pile foundation anchor rope prestress high retaining wall
CN108560349A (en) The high embankment retaining structure in soft clay area
CN110374111B (en) Slope releasing and steel pipe pile anchor cooperative supporting system
CN109371989B (en) A kind of combined type retaining structure and its construction method suitable for stability of slope supporting
CN105201011A (en) Complex anchored-plate retaining wall and construction method thereof
CN104631440B (en) A kind of existing large-section in-situ concrete pile strength core increases foundation pit supporting construction and constructional method
CN206844132U (en) Superelevation light supporting structure
CN111894023A (en) Construction method of steep-slope bridge foundation
CN105887948A (en) Inclination resetting, deviation correction and reinforcement method for anti-slide pile
CN208604438U (en) The high embankment retaining structure in soft clay area
CN204919602U (en) Compound anchored retaining wall by tie rods
CN101153494A (en) Underground Beam-Pile Frame Structure for Slope Reinforcement
CN201891130U (en) Flexible precast block retaining wall structure
CN109653242A (en) Composite foundation reinforcement arch box type barrier wall structure and construction method
CN107100179A (en) Light-duty combination retaining structure and the method for administering a wide range of tall earth fill engineering
CN101793027A (en) Core-grouted static pressure anchor rod pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination