CN112030646A - Granular pile construction process for treating highway diseases - Google Patents

Granular pile construction process for treating highway diseases Download PDF

Info

Publication number
CN112030646A
CN112030646A CN202010144003.8A CN202010144003A CN112030646A CN 112030646 A CN112030646 A CN 112030646A CN 202010144003 A CN202010144003 A CN 202010144003A CN 112030646 A CN112030646 A CN 112030646A
Authority
CN
China
Prior art keywords
construction process
road
treating
granular
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010144003.8A
Other languages
Chinese (zh)
Inventor
温亮辉
白冬晓
王树信
郝欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Hongsen Highway Engineering Technology Co ltd
Original Assignee
Hebei Hongsen Highway Engineering Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Hongsen Highway Engineering Technology Co ltd filed Critical Hebei Hongsen Highway Engineering Technology Co ltd
Priority to CN202010144003.8A priority Critical patent/CN112030646A/en
Publication of CN112030646A publication Critical patent/CN112030646A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/0075Uses not provided for elsewhere in C04B2111/00 for road construction
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/72Repairing or restoring existing buildings or building materials
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Inorganic Chemistry (AREA)
  • Organic Chemistry (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Materials Engineering (AREA)
  • Paleontology (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Road Paving Structures (AREA)
  • Road Repair (AREA)

Abstract

本发明属于公路路面施工技术领域,提供了一种处治公路病害的粒料桩施工工艺,包括以下步骤:A、测量放样;B、钻孔;C、拌合;将砂料过筛子,将水泥和砂石料拌合,水泥:砂:石:添加剂重量比例为1:4:1:0.01,拌合后形成粒料;D、回填;将拌合好的粒料逐层定量向孔内回填,回填厚度为50‑100cm,E、夯扩成桩;使用夯锤对粒料进行逐层夯实;F、封孔;采用水泥混凝土封孔至路面齐平;G、路面调平;在路面沉陷一定长度的路面上铺筑沥青混凝土,使沉陷路面与其他路面平整;H、检测;施工完成后,在路面横断面设置沉降观测点,通过水准仪每间隔24小时观测一次,解决了现有的道路施工需要将道路完全封闭,严重影响道路通车的弊端。The invention belongs to the technical field of highway pavement construction, and provides a construction process for granular piles for treating highway diseases, comprising the following steps: A, measuring and setting out; B, drilling; C, mixing; Mixed with sand and gravel, the weight ratio of cement:sand:stone:additives is 1:4:1:0.01, and after mixing, it forms granules; D. Backfilling; quantitatively backfill the mixed granules into the hole layer by layer, The backfill thickness is 50-100cm, E, ram and expand into piles; use a rammer to compact the aggregates layer by layer; F, seal the hole; use cement concrete to seal the hole to the level of the road surface; G, level the road surface; Asphalt concrete is laid on the pavement with a long length to make the subsidence pavement smooth with other pavements; H. Inspection; after the construction is completed, set up settlement observation points on the cross section of the pavement, and observe it once every 24 hours through a level gauge, which solves the problem of existing road construction. The road needs to be completely closed, which seriously affects the drawbacks of the road opening to traffic.

Description

一种处治公路病害的粒料桩施工工艺A construction technology of granular piles for treating road diseases

技术领域technical field

本发明涉及公路路面施工技术领域,具体地说,是涉及一种处治公路病害 的粒料桩施工工艺。The present invention relates to the technical field of highway pavement construction, in particular, to a construction technique of aggregate piles for treating highway diseases.

背景技术Background technique

随着城市化进程的不断发展,高速公路里程的不断增加;然而,各种各样 的病害也随着通车时间的增加而出现,其中路面沉降是最为常见的路基填方路 段最容易出现的病害之一,沉降严重甚至局部伴有重度纵向裂缝,严重影响行 车安全,影响了道路的安全运营。With the continuous development of urbanization, the mileage of expressways continues to increase; however, various diseases also appear with the increase of traffic time, among which road subsidence is the most common disease in roadbed fill sections. One, the subsidence is severe or even partially accompanied by severe longitudinal cracks, which seriously affects the driving safety and the safe operation of the road.

水泥粒料桩复合路基中,水泥粒料桩起着竖向增强体的作用,它的强度直 接决定着复合地基的承载力。水泥粒料桩主要用于处治含水量较大,碎石含量≤ 30%,以土质为主的路基沉陷段,通过挤密路基,形成复合路基,以提高路基整 体强度。In the cement aggregate pile composite roadbed, the cement aggregate pile plays the role of vertical reinforcement, and its strength directly determines the bearing capacity of the composite foundation. Cement aggregate piles are mainly used to treat subsidence sections of subgrade with high water content and crushed stone content of ≤ 30% and mainly soil quality. By compacting the subgrade, a composite subgrade is formed to improve the overall strength of the subgrade.

水泥粒料挤密桩加固处治沉降路段,填方路基中碎石含量要小于20%-30%, 含水量要大于15%,土体处于软塑-可塑状态。在道路维修施工过程中,现有的 施工方法的工作半径较大,需要将道路完全封闭,严重影响道路通车,为此, 我们提出一种处治公路病害的粒料桩施工工艺。Cement granule compaction piles are used to treat settlement sections. The gravel content in the fill subgrade should be less than 20%-30%, the water content should be greater than 15%, and the soil body should be in a soft plastic-plastic state. In the process of road maintenance and construction, the existing construction method has a large working radius, and the road needs to be completely closed, which seriously affects the road opening.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于克服上述传统技术的不足之处,提供了一种处治公路病 害的粒料桩施工工艺,解决了现有的道路施工需要将道路完全封闭,严重影响 道路通车的弊端。The object of the present invention is to overcome the deficiencies of the above-mentioned traditional techniques, provide a kind of construction technology of granular piles for treating road diseases, solve the drawbacks that existing road construction needs to completely close the road and seriously affect the road opening to traffic.

本发明的技术方案是:The technical scheme of the present invention is:

一种处治公路病害的粒料桩施工工艺,包括以下步骤:A construction technique of granular piles for treating road diseases, comprising the following steps:

A、测量放样;根据孔隙比、含水率计算孔位间距,并根据计算布置孔位; 测放粒料桩的点位,在点位上做标记,以确定桩底相对于地面的深度;A. Measure the stakeout; calculate the hole spacing according to the void ratio and water content, and arrange the hole positions according to the calculation;

B、钻孔;按测量的桩位,将钻机钻尖中心对准桩位中点,通过悬挂在钻杆 导向架侧面的双面指示标调整钻机的水平和钻杆的垂直度;B. Drilling; according to the measured pile position, align the center of the drill tip with the midpoint of the pile position, and adjust the level of the drill rig and the verticality of the drill pipe through the double-sided indicator hanging on the side of the drill pipe guide frame;

C、拌合;将砂料过筛子,将水泥和砂石料拌合,水泥:砂:石:添加剂重 量比例为1:4:1:0.01,拌合后形成粒料;C. Mixing; pass the sand through a sieve, mix the cement and the sand, and the weight ratio of cement:sand:stone:additive is 1:4:1:0.01, and it forms granules after mixing;

D、回填;将拌合好的粒料逐层定量向孔内回填,回填厚度为50-100cm,D. Backfilling: quantitatively backfill the mixed pellets into the hole layer by layer, and the backfill thickness is 50-100cm.

E、夯扩成桩;使用夯锤对粒料进行逐层夯实,在夯击密实的同时粒料向水 平扩大,最终形成大于开孔直径的桩体。E. Consolidate and expand into piles; use rammers to compact the aggregates layer by layer, while compacting and compacting, the aggregates expand horizontally, and finally form a pile body larger than the diameter of the opening.

F、封孔;采用水泥混凝土封孔至路面齐平;F. Seal the hole; use cement concrete to seal the hole to the level of the road surface;

G、路面调平;在路面沉陷一定长度的路面上铺筑沥青混凝土,使沉陷路面 与其他路面平顺衔接;G. Pavement leveling; paving asphalt concrete on the pavement with a certain length of subsidence to make the subsidence pavement smoothly connect with other pavements;

H、检测;施工完成后,在路面横断面设置沉降观测点,通过水准仪每间隔24 小时观测一次。H. Detection: After the construction is completed, set up settlement observation points on the cross section of the pavement, and observe once every 24 hours through the leveling instrument.

作为一种优选的技术方案,步骤B中垂直度的容许偏差小于1%。As a preferred technical solution, the allowable deviation of the verticality in step B is less than 1%.

作为一种优选的技术方案,步骤C中拌合采用人工拌合,拌合次数为3次As a preferred technical solution, the mixing in step C adopts manual mixing, and the mixing times are 3 times

通过人工拌合的方式拌合混凝土,在拌合的过程中,混凝土搅拌在没有加 水以前,要用2-3把铁锹把水泥和砂石料对翻,水泥和砂石料要反过来翻过去混 合共3次,使干料均匀,然后加水,对翻4次,确保拌合的混合料饱和不夹生。The concrete is mixed by manual mixing. During the mixing process, before adding water, 2-3 shovels are used to turn the cement and sand and gravel materials in opposite directions. 3 times to make the dry ingredients uniform, then add water, and turn them in opposite directions 4 times to ensure that the mixed mixture is saturated and not trapped.

作为一种优选的技术方案,步骤C中拌合采用强制式混凝土搅拌机机械拌 合,搅拌时间为3分钟。As a kind of preferred technical scheme, in step C, mixing adopts forced concrete mixer mechanical mixing, and mixing time is 3 minutes.

通过强制式混凝土搅拌机械拌合混凝土,可加快出料速度,使搅拌更加彻 底,还具有可减少泥浆渗漏的优势。Mixing concrete with a forced concrete mixer can speed up the discharge speed, make the mixing more thorough, and also have the advantage of reducing mud leakage.

作为一种优选的技术方案,步骤E中使用夯锤的重量为180-240kg,落锤高 度为2-3米,每层粒料夯实10-15锤。在夯击密实的同时粒料向水平扩大,最终 形成大于开孔直径的桩体。As a kind of preferred technical scheme, in step E, the weight of using rammer is 180-240kg, and the height of drop weight is 2-3 meters, and every layer of granular material is tamped by 10-15 hammers. While compacting and compacting, the pellets expand horizontally, eventually forming a pile body larger than the diameter of the opening.

作为一种优选的技术方案,步骤E中使用夯锤的重量为180kg,落锤高度为2 米。每层终止夯击标准为连续3次沉降量小于2cm。As a preferred technical solution, the weight of the rammer used in step E is 180kg, and the height of the drop hammer is 2 meters. The standard for the termination of ramming of each layer is that the settlement amount is less than 2cm for 3 consecutive times.

作为一种优选的技术方案,步骤F中,水泥混凝土采用C30水泥混凝土。As a preferred technical solution, in step F, the cement concrete adopts C30 cement concrete.

作为一种优选的技术方案,步骤D中,粒料回填密实总量为孔内体积的2-5 倍。As a preferred technical solution, in step D, the total amount of backfill and compaction of the pellets is 2-5 times of the volume in the pores.

作为一种优选的技术方案,步骤E中,回填到离孔口100cm处,停止作业。As a preferred technical solution, in step E, backfill to a distance of 100 cm from the orifice, and stop the operation.

本发明由于采用了以上技术方案,具有以下优点:由于钻孔步骤中,钻孔 孔径仅有14厘米,对施工段路面结构破坏小;在夯击成桩步骤中,通过夯锤重 力夯击粒料,其密实的同时向水平扩大,最终形成大于开孔直径大的桩体,提 高路面的处理;在夯击成桩步骤中,夯锤的重量为180-240kg,不会造成路面结 构层破坏、隆起以及相邻两个粒料桩间土出现松动的情况;施工设备灵活,无 需将道路完全封闭,不会影响道路的通行。The present invention has the following advantages due to the adoption of the above technical solutions: in the drilling step, the hole diameter of the drilled hole is only 14 cm, and the damage to the pavement structure in the construction section is small; The material is compacted and expanded horizontally, and finally a pile body larger than the diameter of the opening is formed, which improves the treatment of the road surface; in the step of ramming the pile, the weight of the rammer is 180-240kg, which will not cause damage to the road structure layer. , uplift and loose soil between two adjacent aggregate piles; flexible construction equipment, no need to completely seal the road, and will not affect the passage of the road.

下面结合具体实施方式对本发明作进一步说明。The present invention will be further described below in conjunction with specific embodiments.

具体实施方式Detailed ways

为使本发明实施例的目的、技术方案和优点更加清楚,对本发明实施例中 的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实 施例,而不是全部的实施例。In order to make the purposes, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention are described clearly and completely. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all the implementations. example.

在本技术方案的描述中,需要理解的是,术语“中心”、“纵向”、“横 向”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、 “内”、“外”等指示的方位或位置关系仅是为了便于描述本发明和简化描述, 而不是只是指示或者暗示所指的装置或元件必须具有特定的方位、以特定的方 位构造和操作,因此不能理解为对本发明保护范围的限制,下面对本发明作进 一步说明。In the description of this technical solution, it should be understood that the terms "center", "portrait", "horizontal", "front", "rear", "left", "right", "vertical" and "horizontal" , "top", "bottom", "inner", "outer" and other indicated orientations or positional relationships are only for the convenience of describing the present invention and simplifying the description, rather than merely indicating or implying that the indicated device or element must have a specific The orientation, construction and operation in a specific orientation should not be construed as limiting the protection scope of the present invention, and the present invention will be further described below.

实施例1:一种处治公路病害的粒料桩施工工艺,包括以下步骤:Embodiment 1: a kind of construction technology of granule pile for treating road diseases, comprising the following steps:

A、测量放样;按照设计施工图布置桩位平面位置图;测放粒料桩的点位, 在点位上做标记,以确定桩底相对于地面的深度;A. Measure and stake out; arrange the pile position plan according to the design and construction drawing; measure and place the point position of the aggregate pile, and mark the point position to determine the depth of the pile bottom relative to the ground;

B、钻孔;按测量的桩位,将钻机钻尖中心对准桩位中点,通过悬挂在钻杆 导向架侧面的双面指示标调整钻机的水平和钻杆的垂直度;在钻孔过程中,每 根桩施工前均由技术人员进行桩位对中和垂直度检查,满足要求后才进行开钻, 随时观察双面指示标,确保钻机不偏斜。B. Drilling; according to the measured pile position, align the center of the drill point of the drilling rig with the midpoint of the pile position, and adjust the level of the drilling rig and the verticality of the drill pipe through the double-sided indicator hanging on the side of the drill pipe guide frame; During the process, before each pile is constructed, technicians will check the pile position and verticality, and then start drilling after meeting the requirements. Observe the double-sided indicator at any time to ensure that the drilling rig is not skewed.

C、拌合;将砂料过筛子,将水泥和砂石料拌合,水泥:砂:石:添加剂重 量比例为1:4:1:0.01,拌合后形成粒料;C. Mixing; pass the sand through a sieve, mix the cement and the sand, and the weight ratio of cement:sand:stone:additive is 1:4:1:0.01, and it forms granules after mixing;

D、回填;将拌合好的粒料逐层定量向孔内回填,回填厚度为50-100cm;D. Backfilling; quantitatively backfill the mixed granules layer by layer into the hole, and the backfill thickness is 50-100cm;

E、夯扩成桩;使用夯锤对粒料进行逐层夯实;在夯击密实的同时粒料向水 平扩大,最终形成比孔径大的桩。E. Ramming and expanding into piles; using rammers to compact the aggregates layer by layer; while compacting and compacting, the aggregates expand horizontally, and finally form a pile larger than the hole diameter.

F、封孔;采用水泥混凝土封孔至路面齐平;F. Seal the hole; use cement concrete to seal the hole to the level of the road surface;

G、路面调平;在路面沉陷一定长度的路面上铺筑沥青混凝土,使沉陷路面 与其他段路面衔接平顺;G. Pavement leveling; paving asphalt concrete on the pavement subsided for a certain length to make the subsidence pavement and other sections of pavement connect smoothly;

H、检测;施工完成后,在路面横断面设置沉降观测点,通过水准仪每间隔12 小时观测一次。H. Detection: After the construction is completed, set up settlement observation points on the cross section of the road surface, and observe once every 12 hours through the leveling instrument.

步骤B中垂直度的容许偏差小于1%。在钻机钻进过程中,随时观察双面 指示标,确保钻机不偏斜。The tolerance for squareness in step B is less than 1%. During the drilling process of the rig, observe the double-sided indicator at any time to ensure that the rig is not deflected.

步骤C中拌合采用人工拌合,拌合次数为3次。In step C, manual mixing is used for mixing, and the mixing frequency is 3 times.

在人工拌合的过程中,混凝土搅拌在没有加水以前,要用2-3把铁锹把水泥 和砂石料对翻,水泥和砂石料要反过来翻过去混合共3次,使干料均匀,然后 加水,对翻4次,确保拌合的混合料饱和不夹生。In the process of manual mixing, before the concrete is mixed without adding water, 2-3 shovels are used to turn the cement and sand and gravel materials in opposite directions. Add water and turn 4 times to ensure that the mixture is saturated and not smothered.

步骤E中使用夯锤的重量为180kg,落锤高度为2米,每层粒料夯实10-15 锤,直至连续3次夯击沉降量小于2cm。停止夯击。In step E, the weight of the rammer used is 180kg, the height of the drop weight is 2 meters, and each layer of granular material is tamped with 10-15 rams until the settlement amount is less than 2cm for 3 consecutive times of tamping. Stop ramming.

步骤F中,水泥混凝土采用C30水泥混凝土。In step F, the cement concrete adopts C30 cement concrete.

步骤D中,粒料回填总量为孔内体积的2-5倍。In step D, the total amount of pellet backfill is 2-5 times the volume in the pores.

步骤E中,回填到离孔口100cm处,停止作业。In step E, backfill to 100cm away from the orifice, and stop the operation.

步骤C中,筛子的筛孔不大于5mm。In step C, the mesh size of the sieve is not greater than 5mm.

实施例2:一种处治公路病害的粒料桩施工工艺,包括以下步骤:Embodiment 2: a kind of construction technology of granule pile for treating road diseases, comprising the following steps:

A、测量放样;按照设计施工图布置桩位平面位置图;测放粒料桩的点位, 在点位上做标记,确定好桩底相对于地面的深度;A. Measure and stake out; arrange the pile position plan according to the design and construction drawing; measure and place the point position of the aggregate pile, mark the point position, and determine the depth of the pile bottom relative to the ground;

B、钻孔;按测量的桩位,将钻机钻尖中心对准桩位中点,通过悬挂在钻杆 导向架侧面的双面指示标调整钻机的水平和钻杆的垂直度;在钻孔过程中,每 根桩施工前均由技术人员进行桩位对中和垂直度检查,满足要求后才进行开钻, 随时观察双面指示标,确保钻机不偏斜B. Drilling; according to the measured pile position, align the center of the drill point of the drilling rig with the midpoint of the pile position, and adjust the level of the drilling rig and the verticality of the drill pipe through the double-sided indicator hanging on the side of the drill pipe guide frame; During the process, before the construction of each pile, technicians will check the pile position and verticality, and then start drilling after meeting the requirements. Observe the double-sided indicator at any time to ensure that the drilling rig is not skewed.

C、拌合;将砂料过筛子,将水泥和砂石料拌合,水泥:砂:石:添加剂重 量比例为1:4:1:0.01,拌合后形成粒料;C. Mixing; pass the sand through a sieve, mix the cement and the sand, and the weight ratio of cement:sand:stone:additive is 1:4:1:0.01, and it forms granules after mixing;

D、回填;将拌合好的粒料逐层定量向孔内回填,回填厚度为50-100cm,D. Backfilling: quantitatively backfill the mixed pellets into the hole layer by layer, and the backfill thickness is 50-100cm.

E、夯扩成桩;使用夯锤对粒料进行逐层夯实;E. Ramming and expanding into piles; use rammers to compact the aggregates layer by layer;

F、封孔;采用水泥混凝土封孔至路面齐平;F. Seal the hole; use cement concrete to seal the hole to the level of the road surface;

G、路面调平;在路面沉陷一定长度的路面上铺筑沥青混凝土,使沉陷路面 与其他路面平整;G. Pavement leveling; paving asphalt concrete on the pavement subsided for a certain length to make the subsidence pavement level with other pavements;

H、检测;施工完成后,在路面横断面设置沉降观测点,通过水准仪每间隔24 小时观测一次。H. Detection: After the construction is completed, set up settlement observation points on the cross section of the pavement, and observe once every 24 hours through the leveling instrument.

步骤B中垂直度的容许偏差小于1%。The tolerance for squareness in step B is less than 1%.

步骤C中拌合采用强制式混凝土搅拌机机械拌合,搅拌时间为3分钟。强 制式混凝土搅拌机械具有由于搅拌铲与转动臂之间采用十字轴总成相连接,并 设置拉杆或螺杆调控搅拌铲的工作间隙,可防止硬质物料卡住现象,以降低运 转阻力,减少磨损。由于搅拌铲的工作面在垂直和水平二个方向上与前进方向 的夹角为钝角,因此可加强搅拌效果,提高搅拌质量。通过设在料筒侧壁的出 料口,料筒相对机架可横向摆动,并设置清料刮板,可加快出料,并更加彻底, 还具有可减少泥浆渗漏的优势。In step C, a forced concrete mixer is used for mechanical mixing, and the mixing time is 3 minutes. The forced concrete mixing machine has a cross shaft assembly connected between the mixing shovel and the rotating arm, and the working gap of the mixing shovel is controlled by a tie rod or a screw, which can prevent the hard materials from sticking, so as to reduce the running resistance and reduce wear and tear. . Since the angle between the working surface of the mixing shovel and the advancing direction is an obtuse angle in the vertical and horizontal directions, the mixing effect can be enhanced and the mixing quality can be improved. Through the discharge port on the side wall of the barrel, the barrel can swing laterally relative to the frame, and a cleaning scraper is provided, which can speed up the discharge and make it more thorough, and also has the advantage of reducing mud leakage.

步骤E中使用夯锤的重量为240kg,落锤高度为3米,每层粒料夯实15锤。 直至连续3次夯击沉降量小于2cm。停止夯击。In step E, the weight of the rammer used is 240kg, the height of the drop weight is 3 meters, and each layer of granular material is tamped with 15 rams. Until the ramming settlement amount is less than 2cm for 3 consecutive times. Stop ramming.

对水泥粒料而言,影响其强度的因素除了干密度以外,含水量也是一个主 要因素,含水量高于最佳含水量对其强度影响很大,所以施工中,填料的含水 量应尽量接近最佳含水量,因此,步骤E中使用夯锤的重量为180kg,落锤高度 为2米。For cement granules, in addition to dry density, water content is also a major factor that affects its strength. The water content is higher than the optimum water content, which has a great influence on its strength. Therefore, during construction, the water content of the filler should be as close as possible. The optimum water content, therefore, the weight of the rammer used in step E is 180kg, and the height of the drop hammer is 2 meters.

步骤F中,水泥混凝土采用C30水泥混凝土。In step F, the cement concrete adopts C30 cement concrete.

步骤D中,粒料回填总量为孔内体积的2-5倍。In step D, the total amount of pellet backfill is 2-5 times the volume in the pores.

步骤E中,回填到离孔口100cm处,停止作业。In step E, backfill to 100cm away from the orifice, and stop the operation.

步骤C中,筛子的筛孔不大于5mm。In step C, the mesh size of the sieve is not greater than 5mm.

以上各实施例仅用以说明本发明的技术方案,但是本发明并不限于此实施 方式,在所属技术领域的技术人员所具备的知识范围内,在不脱离本发明宗旨 的前提下,还可以做出各种变化。所属技术领域的技术人员从上述构思出发, 不经过创造性的劳动,所做出的种种变换,均落在本发明的保护范围内。The above embodiments are only used to illustrate the technical solutions of the present invention, but the present invention is not limited to this embodiment. Within the scope of knowledge possessed by those skilled in the art, and without departing from the spirit of the present invention, it is also possible to make various changes. Various transformations made by those skilled in the art from the above-mentioned concept without creative work all fall within the protection scope of the present invention.

Claims (9)

1. A granular pile construction process for treating highway diseases is characterized by comprising the following steps:
A. measuring and lofting; calculating hole site intervals according to the pore ratio and the water content, and arranging hole sites according to the calculation; measuring the point position of the granular material pile, and marking the point position to determine the depth of the pile bottom relative to the ground;
B. drilling; aligning the center of the drill point of the drilling machine to the midpoint of the pile position according to the measured pile position, and adjusting the level of the drilling machine and the verticality of the drill rod through a double-sided indicator hung on the side surface of the drill rod guide frame;
C. mixing; screening the sand material, mixing cement and sand material, and mixing cement: sand: stone: the weight ratio of the additive is 1: 4: 1: 0.01, mixing to form a mixture;
D. backfilling; the mixed granules are quantitatively backfilled into the holes layer by layer, the backfilling thickness is 50-100cm,
E. tamping and expanding to form a pile; tamping the granular materials layer by using a tamping hammer; the pile can be horizontally expanded while being tamped to be compact, and finally a pile with a diameter larger than the aperture is formed;
F. sealing holes; sealing holes with cement concrete until the pavement is level;
G. leveling a road surface; paving asphalt concrete on the pavement with a certain length of subsidence of the pavement to enable the subsidence pavement to be smoothly connected with other pavements;
H. detecting; after construction is finished, settlement observation points are arranged on the cross section of the road surface, and observation is carried out once every 24 hours by the level gauge.
2. The granular pile construction process for treating the road diseases according to claim 1, which is characterized in that: the tolerance of the verticality in step B is less than 1%.
3. The granular pile construction process for treating the road diseases according to claim 1, which is characterized in that: and C, manually stirring the mixture for 3 times.
4. The granular pile construction process for treating the road diseases according to claim 1, which is characterized in that: and C, mechanically stirring by adopting a forced concrete stirrer for 3 minutes.
5. The granular pile construction process for treating the road diseases according to claim 1, which is characterized in that: in the step E, the weight of a rammer is 180-240kg, the drop height of the rammer is 2-3 m, and each layer of the aggregates is tamped by 10-15 hammers.
6. The granular pile construction process for treating the road diseases as claimed in claim 5, wherein the granular pile construction process comprises the following steps: in the step E, the weight of the rammer used is 180kg, and the height of the drop hammer is 2 meters.
7. The granular pile construction process for treating the road diseases according to claim 1, which is characterized in that: in the step F, C30 cement concrete is adopted as the cement concrete.
8. The granular pile construction process for treating the road diseases according to claim 1, which is characterized in that: in the step D, the total backfilling amount of the granules is 2-5 times of the volume in the pores.
9. The granular pile construction process for treating the road diseases according to claim 1, which is characterized in that: and E, backfilling to a position 100cm away from the hole, and stopping operation.
CN202010144003.8A 2020-03-04 2020-03-04 Granular pile construction process for treating highway diseases Pending CN112030646A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010144003.8A CN112030646A (en) 2020-03-04 2020-03-04 Granular pile construction process for treating highway diseases

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010144003.8A CN112030646A (en) 2020-03-04 2020-03-04 Granular pile construction process for treating highway diseases

Publications (1)

Publication Number Publication Date
CN112030646A true CN112030646A (en) 2020-12-04

Family

ID=73578733

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010144003.8A Pending CN112030646A (en) 2020-03-04 2020-03-04 Granular pile construction process for treating highway diseases

Country Status (1)

Country Link
CN (1) CN112030646A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114763689A (en) * 2021-01-11 2022-07-19 新疆北新路桥集团股份有限公司 Rapid treatment method for highway diseases

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101109167A (en) * 2006-07-21 2008-01-23 河南万里路桥工程有限公司 Technique method for processing subgrade disease
CN101319500A (en) * 2008-07-21 2008-12-10 中铁七局集团第三工程有限公司 Construction method of static pressure compaction pile
RU2449075C1 (en) * 2010-11-26 2012-04-27 Общество с ограниченной ответственностью "Финансово-Строительная компания "МостГеоЦентр" Method to strengthen loose natural base for erection of road earth bed
CN103061326A (en) * 2013-01-25 2013-04-24 黑龙江省公路勘察设计院 Construction method for reinforcing island-shaped permafrost roadbed through water stable gravel piles
CN103590391A (en) * 2013-11-27 2014-02-19 温州宏源水电建设有限公司 Cement-fly-ash-gravel pile foundation reinforcing construction method
CN104131564A (en) * 2013-05-27 2014-11-05 北京振冲工程机械有限公司 Manufacturing process of vibration and powder-spraying gravel pile and vibrating equipment of process
CN109024544A (en) * 2018-07-02 2018-12-18 中国铁路总公司 The hydraulic high frequency compaction method of collapsible loess tunnel substrate

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101109167A (en) * 2006-07-21 2008-01-23 河南万里路桥工程有限公司 Technique method for processing subgrade disease
CN101319500A (en) * 2008-07-21 2008-12-10 中铁七局集团第三工程有限公司 Construction method of static pressure compaction pile
RU2449075C1 (en) * 2010-11-26 2012-04-27 Общество с ограниченной ответственностью "Финансово-Строительная компания "МостГеоЦентр" Method to strengthen loose natural base for erection of road earth bed
CN103061326A (en) * 2013-01-25 2013-04-24 黑龙江省公路勘察设计院 Construction method for reinforcing island-shaped permafrost roadbed through water stable gravel piles
CN104131564A (en) * 2013-05-27 2014-11-05 北京振冲工程机械有限公司 Manufacturing process of vibration and powder-spraying gravel pile and vibrating equipment of process
CN103590391A (en) * 2013-11-27 2014-02-19 温州宏源水电建设有限公司 Cement-fly-ash-gravel pile foundation reinforcing construction method
CN109024544A (en) * 2018-07-02 2018-12-18 中国铁路总公司 The hydraulic high frequency compaction method of collapsible loess tunnel substrate

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
卢小文: "《建筑地基基础工程施工与质量验收实用手册》", 29 February 2004, 北京:中国建材工业出版社 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114763689A (en) * 2021-01-11 2022-07-19 新疆北新路桥集团股份有限公司 Rapid treatment method for highway diseases

Similar Documents

Publication Publication Date Title
CN108797557A (en) A kind of lime-soil compaction pile constructing process in Collapsible Loess District end of the bridge section
CN104404838B (en) The above railway collapsible loess subgrade substrate treating method of speed 200km
CN109736346A (en) Structure and construction method of reinforced balance-weight retaining wall reinforced by steel anchor pipe in weathered rock formation
CN110453678B (en) Method for treating loess highway subgrade settlement by high-pressure jet grouting pile double-pipe method
CN103074882A (en) Construction method for reinforcing island-type perennial frozen-soil foundation by adopting gravel piles
CN103806432A (en) Method for treating foundations in slope filling and digging joint part of wet and soft zone in loess region
CN109914240A (en) A construction method for treating bridge head jumping by grouting polyurethane polymer under the condition of opening to traffic
CN108625244A (en) A kind of roadbed composite structure and its construction method
CN107417182A (en) Intumescent high polymer cement mortar, grouting and reinforcing device and grouting strengthening method
CN112144559B (en) Well construction method in high-water-rich loess sand pebble stratum pressure-variable pipe well
CN106522191A (en) Transformer substation foundation treatment method and application thereof
CN107938456A (en) Fill out river road construction method
CN203334154U (en) Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
CN114197261B (en) Road widening roadbed filling method for immersed road section
CN112030646A (en) Granular pile construction process for treating highway diseases
CN108439867B (en) Rockfill dam using seamless faceplate and construction method thereof
CN112554167A (en) Novel poured large-particle-size aggregate UHPC soft soil road foundation pile
CN218116005U (en) Ecological type half-digging and half-filling roadbed structure for mountain highway
CN110055845A (en) A kind of construction method that highway bridge and culvert two sides are soft soil roadbed
CN113235552B (en) Method for filling roadbed by using large-diameter broken stone through dynamic compaction
CN114439017A (en) A backfill structure using a new type of backfill material and its construction method
CN106703013A (en) Water-proof curtain for treating built loess roadbed subsidence damages
CN206554068U (en) Water seal curtain for punishing built loess subgrade depression disease
CN221072112U (en) Underpinning reinforcing structure for uneven settlement of highway soft foundation section
CN117026714B (en) Construction method of high embankment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Bai Dongxiao

Inventor after: Xu Yong

Inventor after: Wen Lianghui

Inventor after: Wang Shuxin

Inventor after: Ye Runzhong

Inventor after: Liu Zhiyuan

Inventor after: Hao Xin

Inventor before: Wen Lianghui

Inventor before: Bai Dongxiao

Inventor before: Wang Shuxin

Inventor before: Hao Xin

SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201204