Technology for treating road soft soil foundation by using geotextile bags Download PDFInfo
- Publication number
- CN112012064A CN112012064A CN202011047891.8A CN202011047891A CN112012064A CN 112012064 A CN112012064 A CN 112012064A CN 202011047891 A CN202011047891 A CN 202011047891A CN 112012064 A CN112012064 A CN 112012064A
- Authority
- CN
- China
- Prior art keywords
- soft soil
- geotextile
- bag
- bags
- soil
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000002689 soil Substances 0.000 title claims abstract description 81
- 239000004746 geotextile Substances 0.000 title claims description 42
- 238000005516 engineering process Methods 0.000 title abstract description 11
- 239000004744 fabric Substances 0.000 claims abstract description 13
- 238000000034 method Methods 0.000 claims description 15
- 238000010276 construction Methods 0.000 abstract description 9
- 230000000694 effects Effects 0.000 description 3
- 238000003475 lamination Methods 0.000 description 2
- 238000007789 sealing Methods 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 238000009958 sewing Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
- E01C3/003—Foundations for pavings characterised by material or composition used, e.g. waste or recycled material
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C3/00—Foundations for pavings
- E01C3/006—Foundations for pavings made of prefabricated single units
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
Abstract
The invention discloses a technology for treating a soft soil foundation of a road by using a soil engineering bag. In road construction, a soft soil layer of a roadbed is dug and replaced by gravels, so that the roadbed is called as 'replacement and filling', the deeper the soft soil layer is, the larger the replacement and filling amount is, and the higher the road construction cost is, and through years of research and tests, the invention provides a technology for treating a soft soil foundation of a road by using a soil engineering bag to replace 'replacement and filling', wherein the technology comprises a soil engineering bag pattern and a roadbed structure, the soil engineering bag is in a rectangular flat pattern, and the roadbed structure comprises a soil engineering cloth paved on the surface of the soft soil foundation and a plurality of layers of soil engineering bags paved on the soil engineering cloth.
Description
Technical Field
The invention relates to a technology for treating a soft soil foundation of a road by using a soil engineering bag.
Background
In road construction, the problem of soft soil roadbed treatment is often encountered, the common method is to dig out the soft soil layer of the roadbed, replace the soft soil layer with sand stones to serve as the roadbed, the roadbed is called as 'replacement and filling', the deeper the soft soil layer, the larger the replacement and filling amount is, and the higher the road construction cost is brought therewith, and in order to solve the problem, the invention provides a technology for treating the soft soil foundation of the road by using a soil engineering bag to replace 'replacement and filling'.
Disclosure of Invention
In order to solve the defects in the prior art, the invention aims to provide a technology for treating a soft soil foundation of a road by using a soil engineering bag, and aims to provide a new method for treating the soft soil foundation in road construction, replace the conventional 'replacement and filling' method and reduce the cost of road construction.
In order to achieve the purpose, the technical scheme of the invention is as follows: the utility model provides a technique of road soft soil foundation is handled with geotechnological bag, includes geotechnological bag pattern and roadbed structure, geotechnological bag shape be rectangle platykurtic pattern, roadbed structure include the geotechnological cloth of soft soil foundation surface laying and the multilayer geotechnological bag of laying on geotechnological cloth.
Preferably, the shape of the earth work bag is a rectangular flat shape, and the weight of the earth work bag after being filled with soil is between 200 and 600 kilograms.
Preferably, the geotextile laid on the surface of the soft soil foundation is a layer laid after the surface of the soft soil foundation is drained and leveled, and the layer is connected into a whole geotextile.
Preferably, the geotextile is paved with a plurality of geotextile bags, and the number of the geotextile bags is 4 to 6.
Preferably, the geotextile is provided with geotextile bags, and the long edge of each geotextile bag is perpendicular to the road direction.
Preferably, the geotextile bags are laid on the geotextile, and the gap between each layer of the geotextile bags and the periphery of the geotextile bags is about 10 cm.
Preferably, the geotextile bags are laid on the geotextile, and from the second layer, each geotextile bag is pressed at the cross-shaped joint of the next four geotextile bags, so that the staggered lamination effect is formed.
Preferably, the geotextile is paved with the geotextile, and after each layer of paved geotextile bags are compacted by a road roller, gaps among the geotextile bags are filled with loose soil.
The invention has the beneficial effects that: the technology for treating the soft soil foundation of the road by the geotextile bags is provided, aims to provide a new technology for treating the soft soil foundation in road construction, replaces the conventional method for replacing and filling the soft soil foundation of the road, is convenient and simple to construct, has social benefits of replacing stone with soil in terms of environmental protection, and can greatly reduce the road construction cost in terms of economic benefits.
Drawings
Fig. 1 is a schematic view of the geobag of the present invention.
Fig. 2 is a schematic view of the roadbed structure of the present invention.
Detailed Description
As shown in fig. 1 and 2, a technology for treating a soft soil foundation of a road by using a soil bag comprises a soil bag 1 type and a roadbed structure, wherein the soil bag 1 is in a rectangular flat type, the weight of the soil bag 2 after soil loading is between 200 and 600 kilograms, the roadbed structure comprises a soil cloth 4 laid on the surface of a soft soil foundation 3 and a plurality of layers of soil bags 2 laid on the soil cloth 4, the soil cloth 4 laid on the surface of the soft soil foundation is a layer of soil cloth 4 laid on the surface of the soft soil foundation 3 after drainage and leveling, the layer of soil cloth 4 laid on the surface of the soft soil foundation is connected into a whole, the plurality of layers of soil bags 2 laid on the soil cloth 4 have 4 to 6 layers in total, the long edge of each soil bag 2 is vertical to the direction of the road, a gap 5 between the soil bags 2 laid on the same layer is about 10 centimeters, and each soil bag 2 is pressed at a cross joint 6 of four bags on the next layer from the second layer, the effect of staggered lamination is formed, after each layer of the soil engineering bags 2 is well paved and compacted by a road roller, gaps 5 between the soil engineering bags 2 are filled with loose soil.
The specific implementation method comprises the following steps: bagging, namely filling the soil material into the soil engineering bag 1 to form a soil engineering bag 2, and sealing the opening of the bag by using a handheld sewing machine, or pre-filling and sealing for later use; the construction process comprises the steps of firstly draining and leveling a soft soil foundation 3, then paving a layer of geotextile 4 connected into a whole, horizontally and sequentially placing geotextile bags 2 on the paved geotextile 4 in a direction of a long edge perpendicular to a road, keeping a gap 5 between the geotextile bags 2 and the periphery of the geotextile bags about 10 centimeters, compacting by a road roller after a first layer is paved, filling the gap 5 between the geotextile bags with loose soil, pressing the geotextile bags 2 at cross joints 6 of four geotextile bags of the first layer when a second layer is paved to form the staggered and laminated effect of the two geotextile bags 2, then compacting by the road roller and filling the loose soil, repeating the steps for each layer until the number of paved layers is finished, thus finishing the treatment process of the soft soil foundation, and filling and building the road by using common soil.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents or improvements made within the spirit and principle of the present invention should be included in the scope of the present invention.
Claims (8)
1. The utility model provides a technique of road soft soil foundation is handled with geotechnological bag, includes geotechnological bag 1 pattern and roadbed structure, its characterized in that, geotechnological bag 1 shape be rectangle platykurtic pattern, roadbed structure include geotechnological cloth 4 and the geotechnological bag 2 of laying on geotechnological cloth 4 of 3 surface laying of soft soil foundation.
2. The technique for treating soft soil foundations on roads with geotextile bags as claimed in claim 1,
the weight of the geotextile bag 2 after the geotextile bag 1 is filled with soil is between 200 and 600 kilograms.
3. The technique for treating soft soil foundations on roads with geotextile bags as claimed in claim 1,
the geotextile 4 laid on the surface of the soft soil foundation 3 is a layer laid on the soft soil foundation 3 after the surface of the soft soil foundation 3 is drained and leveled, and is connected into a whole geotextile 4.
4. A technique for treating soft soil foundations on roads with geobags according to claim 1, wherein the geotextile 4 is laid with a plurality of geobags 2, from 4 to 6 layers.
5. A technique for treating soft soil foundations on roads with geobags according to claims 1 and 4, further characterized in that the geobags 2 are laid on the geotextile 4, and the long side of each bag is perpendicular to the road direction.
6. A technique for treating soft soil foundations on roads with geobags according to claims 1 and 4, further characterized in that the multilayer geobags 2 laid on the geotextile 4 have a gap 5 of about 10 cm between each layer of the bags and the periphery of the bags.
7. A technique for treating soft soil foundations on roadways with geobags according to claims 1 and 4, further characterized in that the multilayer geobags 2 laid on top of the geotextile 4, starting from the second layer, each geobag 2 is pressed at the cross seam 6 of the next four bags.
8. A technique for treating soft soil foundation of road with earthwork bag according to claims 1 and 4 wherein a plurality of earthwork bags 2 are laid on the earthwork cloth 4, and after each laid earthwork bag is compacted by a roller, the gap between the earthwork bags is filled with loose soil.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011047891.8A CN112012064A (en) | 2020-09-29 | 2020-09-29 | Technology for treating road soft soil foundation by using geotextile bags |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011047891.8A CN112012064A (en) | 2020-09-29 | 2020-09-29 | Technology for treating road soft soil foundation by using geotextile bags |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112012064A true CN112012064A (en) | 2020-12-01 |
Family
ID=73528233
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011047891.8A Pending CN112012064A (en) | 2020-09-29 | 2020-09-29 | Technology for treating road soft soil foundation by using geotextile bags |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112012064A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112853842A (en) * | 2021-01-15 | 2021-05-28 | 湖南尼塔建设发展股份有限公司 | Construction method for treating soft soil foundation of road based on geotextile bags |
CN114351729A (en) * | 2021-11-23 | 2022-04-15 | 王琪 | Assembly type ground firmware slope protection and cushion layer structure and laying method thereof |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102127907A (en) * | 2010-01-18 | 2011-07-20 | 刘斯宏 | Geotextile bag raft and application method thereof |
-
2020
- 2020-09-29 CN CN202011047891.8A patent/CN112012064A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102127907A (en) * | 2010-01-18 | 2011-07-20 | 刘斯宏 | Geotextile bag raft and application method thereof |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112853842A (en) * | 2021-01-15 | 2021-05-28 | 湖南尼塔建设发展股份有限公司 | Construction method for treating soft soil foundation of road based on geotextile bags |
CN112853842B (en) * | 2021-01-15 | 2022-07-05 | 湖南尼塔建设发展股份有限公司 | Construction method for treating soft soil foundation of road based on geotextile bags |
CN114351729A (en) * | 2021-11-23 | 2022-04-15 | 王琪 | Assembly type ground firmware slope protection and cushion layer structure and laying method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100510278C (en) | Ecological protection method for sand-filling road foundation hollow block | |
CN102704364B (en) | Clay serging tailings subgrade structure and construction method thereof | |
CN106283944B (en) | The method for pressing washer stone and/or block stone to reinforce shallow layer soft ground | |
CN109736291A (en) | One kind owing consolidation and blows on the base of alluvial plain that biological cement is reinforcing road bed and its construction method | |
CN206902488U (en) | A kind of soft soil foundation high-filled embankment of effectively control settlement after construction | |
CN109487653A (en) | A kind of construction technology carrying out roadbed precompressed using water bag | |
CN113445396B (en) | High-fill road foundation filling construction method for high liquid limit soil road section | |
CN110924254A (en) | Construction process for filling carbonaceous shale roadbed | |
CN107119520A (en) | The soft base combined type of coastal tidal, which is changed, fills out structure and Treatment Methods | |
CN206438358U (en) | A kind of highway soft soil widening of subgrade ruggedized construction | |
CN106836244A (en) | A kind of method of friction pile dative guest barricade joint protection steep slope subgrade high | |
CN209039896U (en) | The soft soil roadbed three-dimensional reinforced structure of convolution is knitted in a kind of stake- | |
CN112012064A (en) | Technology for treating road soft soil foundation by using geotextile bags | |
CN105804007A (en) | Reinforced soil bank wall structure based on beach soft foundation | |
CN104358196A (en) | Construction method for embankment settlement treatment structure of road open to traffic | |
CN109778625A (en) | A kind of express highway roadbed structure that dregs class building castoff fills | |
CN111691435A (en) | Expansive soil cutting slope protection method | |
CN110820456A (en) | Anti-settling and replacement-filling alternate airport runway and construction method thereof | |
CN108385651B (en) | Design and construction method for reinforcing soft foundation by using composite geotextile | |
CN109537389B (en) | EPS (expandable polystyrene) lower embankment structure and construction method thereof | |
AU2021102288A4 (en) | Composite Replacement Structure and Treatment for Soft Base of Coastal Mudflat | |
CN103276717A (en) | Method for treating soft soil foundations with composite geotechnical synthetic material reinforced cushions | |
CN206800092U (en) | The soft base combined type of coastal tidal, which is changed, fills out structure and Roadbed by offshore soft clay | |
CN110172988A (en) | A kind of piling formula composite concrete placement ground and its construction method | |
CN213143069U (en) | Pouring type impervious core earth-rock dam structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20201201 |
|
WD01 | Invention patent application deemed withdrawn after publication |