CN111997405A - Construction method for treating building cracks - Google Patents

Construction method for treating building cracks Download PDF

Info

Publication number
CN111997405A
CN111997405A CN202010850482.5A CN202010850482A CN111997405A CN 111997405 A CN111997405 A CN 111997405A CN 202010850482 A CN202010850482 A CN 202010850482A CN 111997405 A CN111997405 A CN 111997405A
Authority
CN
China
Prior art keywords
crack
construction method
treating
cut
cracks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010850482.5A
Other languages
Chinese (zh)
Inventor
刘让新
刘滔
罗泽红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yichanghengsheng Building Installation Co ltd
Original Assignee
Yichanghengsheng Building Installation Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yichanghengsheng Building Installation Co ltd filed Critical Yichanghengsheng Building Installation Co ltd
Priority to CN202010850482.5A priority Critical patent/CN111997405A/en
Publication of CN111997405A publication Critical patent/CN111997405A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0203Arrangements for filling cracks or cavities in building constructions

Abstract

A construction method for treating building cracks comprises the following steps: the first step is as follows: drilling a plurality of cut-off holes in the wall crack, and inserting cut-off pipes into the cut-off holes in an interference manner; the second step is that: two ends of the two cover plates are fixedly connected through a first screw rod arranged in the cut-off pipe, and the two cover plates seal the two sides of the crack; the third step: and filling structural adhesive into the cracks, and removing the cover plate after the structural adhesive is cured. The invention is used for solving the problems of secondary cracking and crack extension of buildings due to vibration.

Description

Construction method for treating building cracks
Technical Field
The invention relates to a construction method for treating a building crack.
Background
At present, cement mortar is poured into the cracks in a commonly-used repairing method for the building cracks, the phenomenon that the cement mortar leaks is caused on one hand, and on the other hand, the cement mortar is hard after being cured, so that secondary cracking is easily caused at the cracks when the building vibrates, and meanwhile, the cracks cannot be completely guaranteed not to continue to extend.
Disclosure of Invention
The invention aims to provide a construction method for treating a building crack, which is used for solving the problems of secondary cracking and crack extension of a building due to vibration.
In order to solve the above problems, the technical solution to be solved by the present invention is:
a construction method for treating building cracks comprises the following steps:
the first step is as follows: drilling a plurality of cut-off holes in the wall crack, and inserting cut-off pipes into the cut-off holes in an interference manner;
the second step is that: two ends of the two cover plates are fixedly connected through a first screw rod arranged in the cut-off pipe, and the two cover plates seal the two sides of the crack;
the third step: and filling structural adhesive into the cracks, and removing the cover plate after the structural adhesive is cured.
The wall body passes through multiunit tightening mechanism to be connected about the crack, tightening mechanism is equipped with the second screw rod respectively including seting up the grooving in the wall body both sides in the wall body both ends wall body about the grooving, and two second screw rod both ends are connected through straining device respectively, and straining device includes wire rope and the pull ring of fixed connection on the second screw rod, at pull ring one end fixedly connected with screwed pipe, wire rope one end and one of them screwed pipe fixed connection, other one end and screwed sleeve fixed connection, pass through double-end screw connection between screwed sleeve and the other screwed pipe.
The lengths of the two adjacent groups of tightening mechanisms are different.
One end of one of the screw pipes is in threaded connection with an end cover, a through hole is formed in the center of the end cover, one end of the steel wire rope penetrates through the through hole and then is fixedly connected with the tensioning block, a disc spring group is sleeved outside the steel wire rope, and two ends of the disc spring group are respectively abutted against the tensioning block and the end cover.
A plurality of glue injection holes are formed in the cover plate, and the glue injection holes are connected with glue injection joints in a threaded mode.
And filling structural adhesive into the crack from low to high through each glue filling joint in sequence.
After two sides of the crack are sealed by the two cover plates, one end of each cover plate is communicated with a tap water pipe through a glue filling joint, dust in the crack is cleaned by tap water, and after the cleaning is finished, structural glue is filled into the crack after water is dried.
The invention has the beneficial effects that:
1. the building crack tearing path is cut off through the cut-off holes at the two ends of the crack and the cut-off pipes, and the crack is prevented from extending.
2. The cracks are sealed through the cover plates on the two sides of the cracks, and structural glue is poured into the cracks, so that the structural glue is effectively prevented from being leaked.
3. Because some structural adhesives of solidification have flexible displacement ability to under the fixed cooperation of multiunit tightening mechanism, can effectually prevent the crack secondary fracture.
Drawings
The invention is further described below with reference to the accompanying drawings:
FIG. 1 is a schematic front view of the present invention,
FIG. 2 is a schematic cross-sectional view taken along line A-A in FIG. 1,
FIG. 3 is a schematic cross-sectional view taken along line B-B in FIG. 1,
fig. 4 is a schematic cross-sectional structure diagram of the tightening mechanism according to the present invention.
In the figure: the device comprises a cover plate 1, a first screw rod 2, a crack 3, a cutting groove 4, a tensioning device 5, a cut-off pipe 6, a wall 7, a glue filling joint 8, a second screw rod 9, a pull ring 51, a spiral pipe 52, a tensioning block 53, a disc spring group 54, an end cover 55, a head screw 56, a steel wire rope 57 and a double-screw sleeve 58.
Detailed Description
A construction method for treating building cracks comprises the following steps:
the first step is as follows: respectively drilling a cut-off hole at two ends of the crack 3 of the wall 7, knocking a PVC-U plastic pipe into each cut-off hole, and plugging one end of the crack 3 of the wall 7 by using the plastic pipes;
the second step is that: preparing two cover plates 1, covering the cover plates 1 with a PE film to facilitate the subsequent taking off of the cover plates 1, then covering the two cover plates 1 on two sides of a crack 3, fixedly connecting two ends of the two cover plates 1 through a first screw 2 arranged in a cut-off pipe 6, and sealing two sides of the crack 3 by the two cover plates 1;
the third step: and (3) filling structural adhesive into the crack 3 through the adhesive injection hole on the cover plate 1, and removing the cover plate 1 after the structural adhesive is cured.
The cut-off holes at the two ends of the crack 3 intercept the crack 3, so that the crack 3 can be effectively prevented from extending.
As shown in fig. 4, the upper wall 7 and the lower wall 7 of the crack 3 are connected by a plurality of sets of tightening mechanisms, each tightening mechanism includes a cutting groove 4 formed on two sides of the wall 7, second screws 9 are respectively arranged in the walls 7 at the upper end and the lower end of each cutting groove 4, two ends of each second screw 9 are respectively connected by a tightening device 5, each tightening device 5 includes a steel wire rope 57 and a pull ring 51 fixedly connected to the second screw 9, one end of each pull ring 51 is fixedly connected to a screw tube 52, one end of each steel wire rope 57 is fixedly connected to one of the screw tubes 52, the other end of each steel wire rope 57 is fixedly connected to a screw sleeve 58, the screw sleeve 58 is connected to the other screw tube 52 by a double-headed screw 56, the steel wire rope 57 is tightened by rotating the double-headed screw 56, as shown in fig. 3, both the tightening devices 5 and the second screws 9 are in. The upper wall body 7 and the lower wall body 7 of the crack 3 are connected through a plurality of groups of tightening mechanisms, so that the displacement of the upper building wall body 7 and the lower building wall body 7 is limited, the upper building wall body 7 and the lower building wall body 7 are combined into a whole, the strength of the building wall bodies 7 is improved, the packaging wall bodies 7 are safe to use, and meanwhile, the crack 3 is further prevented from extending.
As shown in fig. 1, the two adjacent sets of tightening mechanisms are different in length. The screw anchors are dispersed, so that the building wall 7 is uniformly stressed, and the building wall 7 is prevented from cracking at the anchors.
One end of one of the spiral tubes 52 is connected with an end cover 55 through a thread, a through hole is formed in the center of the end cover 55, one end of a steel wire rope 57 penetrates through the through hole and then is fixedly connected with the tensioning block 53, a disc spring group 54 is sleeved outside the steel wire rope 57, two ends of the disc spring group 54 are respectively abutted against the tensioning block 53 and the end cover 55, and the structure enables the tensioning device 5 to have certain elasticity. As shown in fig. 1, 3 and 4, when the wall 7 vibrates, a part of the tension generated by the vibration at the crack 3 is distributed to the disc spring group 54, so as to further prevent the crack 3 from cracking again, and on the other hand, reduce the load of the second screw 9, and further prevent the building wall 7 from cracking at the anchor point.
A plurality of glue injection holes are formed in the cover plate 1, and the glue injection holes are connected with glue injection joints 8 in a threaded mode. The glue filling joint 8 facilitates glue filling.
Structural adhesive is filled into the crack 3 from low to high through each glue filling joint 8. Which is advantageous for removing air from the cracks 3.
After two apron 1 seal crack 3 both sides, 1 one end glue-pouring joint 8 of apron and water pipe switch-on, the running water washs the interior dust of crack 3, washs the completion back, treats the water and does the back, fills into the structure again and glues in crack 3, makes the structure glue can be more firm bond crack 3 wall body 7 from top to bottom.

Claims (7)

1. A construction method for treating building cracks is characterized by comprising the following steps: the method comprises the following steps:
the first step is as follows: drilling a plurality of cut-off holes in the cracks (3) of the wall body (7), and inserting the cut-off pipes (6) into the cut-off holes in an interference manner;
the second step is that: the two sides of the crack (3) are respectively provided with a cover plate (1), the two ends of the two cover plates (1) are fixedly connected through a first screw (2) arranged in a cut-off pipe (6), and the two cover plates (1) seal the two sides of the crack (3);
the third step: and (5) filling structural adhesive into the crack (3), and removing the cover plate (1) after the structural adhesive is cured.
2. The construction method for treating the building cracks as claimed in claim 1, wherein the construction method comprises the following steps: wall body (7) are connected through multiunit tightening mechanism about crack (3), tightening mechanism is including offering grooving (4) in wall body (7) both sides, be equipped with second screw rod (9) in grooving (4) upper and lower both ends wall body (7) respectively, two second screw rod (9) both ends are connected through overspeed device tensioner (5) respectively, overspeed device tensioner (5) include wire rope (57) and pull ring (51) of fixed connection on second screw rod (9), at pull ring (51) one end fixedly connected with screwed pipe (52), wire rope (57) one end and one of them screwed pipe (52) fixed connection, other one end and swivel nut (58) fixed connection, be connected through double-headed screw (56) between swivel nut (58) and the other screwed pipe (52).
3. The construction method for treating the building cracks as claimed in claim 2, wherein the construction method comprises the following steps: the lengths of the two adjacent groups of tightening mechanisms are different.
4. The construction method for treating the building cracks as claimed in claim 2, wherein the construction method comprises the following steps: one end of one of the spiral tubes (52) is in threaded connection with an end cover (55), a through hole is formed in the center of the end cover (55), one end of a steel wire rope (57) penetrates through the through hole and then is fixedly connected with the tensioning block (53), a disc spring group (54) is sleeved outside the steel wire rope (57), and two ends of the disc spring group (54) are abutted against the tensioning block (53) and the end cover (55) respectively.
5. The construction method for treating the building cracks as claimed in any one of claims 1 to 4, wherein: a plurality of glue injection holes are formed in the cover plate (1), and glue injection joints (8) are connected in each glue injection hole in a threaded mode.
6. The construction method for treating the building cracks as claimed in claim 5, wherein the construction method comprises the following steps: structural adhesive is filled into the crack (3) from low to high through each glue filling joint (8).
7. The construction method for treating the building cracks as claimed in claim 5, wherein the construction method comprises the following steps: after two cover plates (1) seal two sides of the crack (3), one end of each cover plate (1) is communicated with a tap water pipe through a glue filling joint (8), dust in the crack (3) is cleaned by tap water, and after the cleaning is finished, structural glue is filled into the crack (3) after water is dried.
CN202010850482.5A 2020-08-21 2020-08-21 Construction method for treating building cracks Pending CN111997405A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010850482.5A CN111997405A (en) 2020-08-21 2020-08-21 Construction method for treating building cracks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010850482.5A CN111997405A (en) 2020-08-21 2020-08-21 Construction method for treating building cracks

Publications (1)

Publication Number Publication Date
CN111997405A true CN111997405A (en) 2020-11-27

Family

ID=73473171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010850482.5A Pending CN111997405A (en) 2020-08-21 2020-08-21 Construction method for treating building cracks

Country Status (1)

Country Link
CN (1) CN111997405A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0942054A1 (en) * 1998-03-11 1999-09-15 Minnesota Mining And Manufacturing Company Multilayer adhesive construction
CN1576497A (en) * 2003-07-07 2005-02-09 M&S工业株式会社 Reinforced material for concrete building repairing ,repairing and reinforcing technology for concrete building
CN103452332A (en) * 2013-09-11 2013-12-18 中建中东有限责任公司 Method for repairing construction engineering floor slab crack
CN204326567U (en) * 2014-11-14 2015-05-13 中大建设有限公司 A kind of reinforced concrete wall runs through large fracture preparing structure
CN208996220U (en) * 2018-07-16 2019-06-18 至高建设集团有限公司 A kind of wall body slit plugging device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0942054A1 (en) * 1998-03-11 1999-09-15 Minnesota Mining And Manufacturing Company Multilayer adhesive construction
CN1576497A (en) * 2003-07-07 2005-02-09 M&S工业株式会社 Reinforced material for concrete building repairing ,repairing and reinforcing technology for concrete building
CN103452332A (en) * 2013-09-11 2013-12-18 中建中东有限责任公司 Method for repairing construction engineering floor slab crack
CN204326567U (en) * 2014-11-14 2015-05-13 中大建设有限公司 A kind of reinforced concrete wall runs through large fracture preparing structure
CN208996220U (en) * 2018-07-16 2019-06-18 至高建设集团有限公司 A kind of wall body slit plugging device

Similar Documents

Publication Publication Date Title
US4986862A (en) Sealant injection method and an apparatus therefor
CN111997405A (en) Construction method for treating building cracks
CN108532837A (en) The double sleeve anchorages of combined type for FRP tendons and its anchoring process
CN209323369U (en) A kind of compound anchorage of CFRP tendons pre-extrusion
CN206800186U (en) A kind of road and bridge cement mortar joint filling device
CN211735826U (en) Outer wall screw rod eyelet shutoff waterproof construction
CN111720149A (en) Mining anchor rope of cavity slip casting
CN106480880B (en) Recoverable soil nailing and the construction method for using recoverable soil nail
CN209099538U (en) A kind of buildings waterproof structure that crack resistance is strong
CN108999352A (en) Roof leakage leak detection and method for repairing and mending based on high pressure water
CN101463926A (en) Water-proof method for pipeline crossing full-packaging waterproof layer
CN208280964U (en) A kind of telescoping steel form zigzag end head formwork device
CN212223864U (en) Novel bird's nest formula slip casting anchor rope
JP7178861B2 (en) Concrete wall reinforcement method
CN109252518B (en) Variable-diameter anchor rod and anchoring method thereof
CN207419713U (en) A kind of built-in connection
JP2021055479A (en) Low-pressure injection device and method of repairing reinforced concrete structure
CN220224974U (en) Prestressed pipeline exhaust device
CN211515026U (en) Prefabricated PC component transportation crack repair curing means
CN205637590U (en) Template fixed knot of wrong platform constructs between anti -shear power wall floor
CN211701425U (en) Underground cable sealer
CN110778028A (en) Grouting sleeve assembly and construction method thereof
CN210737381U (en) Bridge seals anchor prestressing force mounting
CN215888638U (en) Quick leak repairing device for filling pipe
CN219993134U (en) Water stop screw rod connecting piece penetrating basement outer wall waterproof layer and waterproof device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201127

RJ01 Rejection of invention patent application after publication