CN103452332A - Method for repairing construction engineering floor slab crack - Google Patents

Method for repairing construction engineering floor slab crack Download PDF

Info

Publication number
CN103452332A
CN103452332A CN2013104105934A CN201310410593A CN103452332A CN 103452332 A CN103452332 A CN 103452332A CN 2013104105934 A CN2013104105934 A CN 2013104105934A CN 201310410593 A CN201310410593 A CN 201310410593A CN 103452332 A CN103452332 A CN 103452332A
Authority
CN
China
Prior art keywords
crack
floor slab
shaped groove
repairing
cracks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013104105934A
Other languages
Chinese (zh)
Inventor
郭海
王力尚
余涛
程亚楠
朱建潮
田三川
彭飞
吴鸣
李健
王建英
李树江
李方升
李焱
高洁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Construction Engineering Corp Middle East LLC
Original Assignee
China State Construction Engineering Corp Middle East LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Construction Engineering Corp Middle East LLC filed Critical China State Construction Engineering Corp Middle East LLC
Priority to CN2013104105934A priority Critical patent/CN103452332A/en
Publication of CN103452332A publication Critical patent/CN103452332A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a method for repairing a construction engineering floor slab crack. The method comprises the following implementation steps that a through floor slab crack is chiseled into a V-shaped groove, a row of steel bar planting holes is drilled at the two sides of the V-shaped groove respectively, the polyurethane caulked joint adhesive is adopted to fill the crack at the lower part of the V-shaped groove, embedded steel bars glue is filled and Phi12 staple-shaped reinforcing steel bars are implanted, high-strength repair mortar is used for filling the V-shaped groove till the surface of a floor slab, and a grouting port is embedded, and mortar is injected at high pressure from the surface of the floor slab to block the crack of the V-shaped groove as well as other tiny cracks. By adopting the method, the crack inside the structure is prevented from further extending after repair, and an obvious crack mark does not exist on the surface of the structure. The crack and the floor slab at the two sides are combined into a whole by repairing the surface with the high-strength repair mortar, reinforcement is realized on the crack. Construction quality acceptance is passed, and normal use of the floor slab is not influenced.

Description

A kind of construction work cracks on floor slab method for repairing and mending
Technical field
The invention belongs to construction engineering technical field, be particularly related to a kind of construction work cracks on floor slab method for repairing and mending, specifically, the crack produced due to a variety of causes in Building Construction externally under loading environment (construction heaped load or prestressed stretch-draw) draw logical broadening, exceed the crack repairing that designs allowed band.
Background technology
Under the scorching environment of high temperature or other severe environment for use, in concreting process, because the raw material of agitator feed or match ratio, site operation tissue or all kinds of factors such as improper operation, concrete shrinkage and creep cause that concrete produces crack.Under the impact of the local loading such as construction heaped load or prestressed stretch-draw, irregular local cracks may will progressively be drawn logical broadening, and exceeds the scope that the design crack allows, so that can't pass through delivery receiving acceptance, even affects structure and uses.
Summary of the invention
The present invention is to provide a kind of construction work cracks on floor slab method for repairing and mending, it is characterized in that, adopts the Bar Anchorage method to be repaired producing cracks on floor slab in Building Construction; The implementation step of this method for repairing and mending is as follows:
1) pick the forming V-shape groove along the structural cracks cutter;
2) respectively bore row's bar planting hole along the V-shaped groove both sides, and use polyurethane caulking glue to fill the crack, bottom;
3) fill anchoring adhesive and implant φ 12 " staple " shape reinforcing bar;
4) use conventional high-strength mending mortar to fill up V-shaped groove to slab surfaces, and while preparing structure surface detail gap, and imbed grouting nozzle.
5) high-pressure slip-casting, separately used slurry filling machine to carry out pressure and annotate high-strength mending mortar and repaired, and packed configuration interior detail gap, carry out repairing treatment to the grouting nozzle place after slip casting completes.
Described bar planting pitch-row is from each 50mm of V-shaped groove both sides, and pitch of holes is 100mm.
The invention has the beneficial effects as follows this method for repairing and mending of application guarantee to repair rear inside configuration crack no longer further expands and body structure surface without obvious crack vestige.Through high-strength mending mortar floor top layer, fill up, making Chu Yu both sides, crack floor melt is a place, as the reinforcement at place, crack; Check and accept by construction quality, do not affect floor slab structure and normally use.
The accompanying drawing explanation
Fig. 1 is the implementation step schematic diagram of Bar Anchorage method in cracks on floor slab is repaired.
1. structure floors in figure, 2. through crack and cutter pick the forming V-shape groove, 3. the filled polyurethane filleting, 4. bore double bar planting hole, 5. implant staple shape reinforcing bar, 6. high-strength mending mortar is filled up through crack, 7. high-pressure slip-casting packed configuration interior detail gap, 8. body structure surface fine cracks.
The specific embodiment
The present invention is to provide a kind of construction work cracks on floor slab method for repairing and mending, adopts the Bar Anchorage method to be repaired producing cracks on floor slab in Building Construction; Below in conjunction with accompanying drawing, be explained.
Figure 1 shows that implementation step a, b, c, the d schematic diagram of Bar Anchorage method in cracks on floor slab is repaired.The implementation step of reinforcement bolt anchoring method is as follows:
1) the through crack cutter along structure floor 1 picks forming V-shape groove 2(as shown in Figure 1a);
2) along the V-shaped groove both sides, a row bar planting hole 4 is bored at each 50mm place, and pitch of holes is 100mm; And use polyurethane caulking glue 3 to fill crack, bottom (as shown in Figure 1 b);
3) fill anchoring adhesive and implant φ 12 " staple " shape reinforcing bar (as shown in Fig. 1 c);
4) use conventional high-strength mending mortar 6 to fill up the through crack cutter and pick forming V-shape groove 2 to slab surfaces, and while preparing structure surface detail gap, and imbed grouting nozzle (as shown in Fig. 1 c);
5) high-pressure slip-casting, need separately to use slurry filling machine to carry out pressure to inject high-strength mending mortar and repaired, and packed configuration interior detail gap, carry out repairing treatment (as shown in Fig. 1 d) to the grouting nozzle place after slip casting completes.
In slab surfaces, use high-strength mending mortar filling run through large fracture 2 and repair surface detail gap 8, re-use high-pressure slip-casting blockage structure interior detail gap, make its slab surfaces without obvious crack vestige (as shown in Fig. 1 d), reach the construction quality acceptance criteria.
  

Claims (2)

1. a construction work cracks on floor slab method for repairing and mending, is characterized in that, adopts the Bar Anchorage method to be repaired producing cracks on floor slab in Building Construction; The implementation step of reinforcement bolt anchoring method is as follows:
1) pick the forming V-shape groove along the structural cracks cutter;
2) respectively bore row's bar planting hole along the V-shaped groove both sides, and use polyurethane caulking glue to fill the crack, bottom;
3) fill anchoring adhesive and implant φ 12 " staple " shape reinforcing bar;
4) use conventional high-strength mending mortar to fill up V-shaped groove to slab surfaces, and while preparing structure surface detail gap, and imbed grouting nozzle;
5) high-pressure slip-casting packed configuration interior detail gap, carry out repairing treatment to the grouting nozzle place after slip casting completes.
2. a kind of construction work cracks on floor slab method for repairing and mending according to claim 1, is characterized in that, described bar planting pitch-row is from each 50mm of V-shaped groove both sides, and pitch of holes is 100mm.
?
CN2013104105934A 2013-09-11 2013-09-11 Method for repairing construction engineering floor slab crack Pending CN103452332A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013104105934A CN103452332A (en) 2013-09-11 2013-09-11 Method for repairing construction engineering floor slab crack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013104105934A CN103452332A (en) 2013-09-11 2013-09-11 Method for repairing construction engineering floor slab crack

Publications (1)

Publication Number Publication Date
CN103452332A true CN103452332A (en) 2013-12-18

Family

ID=49735128

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013104105934A Pending CN103452332A (en) 2013-09-11 2013-09-11 Method for repairing construction engineering floor slab crack

Country Status (1)

Country Link
CN (1) CN103452332A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104193406A (en) * 2014-08-27 2014-12-10 天津大学 Repair method of construction engineering reinforced concrete structure
CN104196131A (en) * 2014-09-11 2014-12-10 山东建筑大学 Method for plugging cast-in-situ concrete slab or base-plate crack with microbe-sedimented calcium carbonate
CN104358422A (en) * 2014-11-29 2015-02-18 宋双阳 Prestress working device and prestress working method for reinforcing wall crack
CN105603855A (en) * 2016-01-05 2016-05-25 杭州修路人科技有限公司 Method for repairing concrete pavement cracks
CN106426569A (en) * 2016-10-25 2017-02-22 叶明俤 Repair structure and method for stone plate
CN106760602A (en) * 2016-12-26 2017-05-31 怀宁县三禾保洁服务有限公司 A kind of lintel renovates construction technology
CN107083848A (en) * 2017-06-20 2017-08-22 上海城建市政工程(集团)有限公司 The repair process method in beam crack is sealed on prestressed flat plate without beam
CN107724706A (en) * 2017-10-24 2018-02-23 广东广达建设集团有限公司 A kind of Cracks On Concrete Floors reinforcement process
CN107829569A (en) * 2017-10-31 2018-03-23 中国冶集团有限公司 Masonry panel fracture unit method
CN108330849A (en) * 2018-04-28 2018-07-27 洛阳理工学院 A kind of road and bridge crack ruggedized construction device
CN111550070A (en) * 2020-05-09 2020-08-18 上海橡树装饰工程有限公司 Deep seam repairing construction method
CN111608684A (en) * 2020-05-08 2020-09-01 中铁三局集团第四工程有限公司 Crack reinforcing method for subway tunnel construction
CN111997405A (en) * 2020-08-21 2020-11-27 宜昌恒生建筑安装有限公司 Construction method for treating building cracks
CN113294008A (en) * 2021-05-29 2021-08-24 重庆海发工程项目管理咨询有限公司 Building crack repairing method
CN113290207A (en) * 2021-04-30 2021-08-24 宁波明凌科技有限公司 Large sand mold crack repairing method
CN113323442A (en) * 2021-06-10 2021-08-31 中国十九冶集团有限公司 Method for treating upper crack of fabricated floor slab

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0978847A (en) * 1995-09-14 1997-03-25 I Retsuku:Kk Repairing method of crack on concrete surface
JPH10159348A (en) * 1996-11-29 1998-06-16 Natl House Ind Co Ltd Crack repairing method for cement board
KR20100055656A (en) * 2008-11-18 2010-05-27 김지현 The method of repair using armature for nonstructural crack filling on the concrete floor
CN101942905A (en) * 2010-09-09 2011-01-12 新蒲建设集团有限公司 Method for treating assembly-type floorslab cracks

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0978847A (en) * 1995-09-14 1997-03-25 I Retsuku:Kk Repairing method of crack on concrete surface
JPH10159348A (en) * 1996-11-29 1998-06-16 Natl House Ind Co Ltd Crack repairing method for cement board
KR20100055656A (en) * 2008-11-18 2010-05-27 김지현 The method of repair using armature for nonstructural crack filling on the concrete floor
CN101942905A (en) * 2010-09-09 2011-01-12 新蒲建设集团有限公司 Method for treating assembly-type floorslab cracks

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张泳材: "混合结构楼板裂缝的分析与处理", 《闽西职业大学学报》, no. 2, 30 June 2001 (2001-06-30) *
金行洲,史东波: "现浇砼楼板裂缝的原因及治理", 《职大学报》, no. 2, 30 April 2004 (2004-04-30) *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104193406B (en) * 2014-08-27 2016-05-18 天津大学 A kind of method for repairing and mending of architectural engineering reinforced concrete structure
CN104193406A (en) * 2014-08-27 2014-12-10 天津大学 Repair method of construction engineering reinforced concrete structure
CN104196131A (en) * 2014-09-11 2014-12-10 山东建筑大学 Method for plugging cast-in-situ concrete slab or base-plate crack with microbe-sedimented calcium carbonate
CN104358422A (en) * 2014-11-29 2015-02-18 宋双阳 Prestress working device and prestress working method for reinforcing wall crack
CN105603855A (en) * 2016-01-05 2016-05-25 杭州修路人科技有限公司 Method for repairing concrete pavement cracks
CN106426569A (en) * 2016-10-25 2017-02-22 叶明俤 Repair structure and method for stone plate
CN106760602A (en) * 2016-12-26 2017-05-31 怀宁县三禾保洁服务有限公司 A kind of lintel renovates construction technology
CN107083848B (en) * 2017-06-20 2019-05-03 上海城建市政工程(集团)有限公司 The repair process method in beam crack is sealed on prestressed flat plate without beam
CN107083848A (en) * 2017-06-20 2017-08-22 上海城建市政工程(集团)有限公司 The repair process method in beam crack is sealed on prestressed flat plate without beam
CN107724706A (en) * 2017-10-24 2018-02-23 广东广达建设集团有限公司 A kind of Cracks On Concrete Floors reinforcement process
CN107829569A (en) * 2017-10-31 2018-03-23 中国冶集团有限公司 Masonry panel fracture unit method
CN108330849A (en) * 2018-04-28 2018-07-27 洛阳理工学院 A kind of road and bridge crack ruggedized construction device
CN111608684A (en) * 2020-05-08 2020-09-01 中铁三局集团第四工程有限公司 Crack reinforcing method for subway tunnel construction
CN111550070A (en) * 2020-05-09 2020-08-18 上海橡树装饰工程有限公司 Deep seam repairing construction method
CN111997405A (en) * 2020-08-21 2020-11-27 宜昌恒生建筑安装有限公司 Construction method for treating building cracks
CN113290207A (en) * 2021-04-30 2021-08-24 宁波明凌科技有限公司 Large sand mold crack repairing method
CN113294008A (en) * 2021-05-29 2021-08-24 重庆海发工程项目管理咨询有限公司 Building crack repairing method
CN113323442A (en) * 2021-06-10 2021-08-31 中国十九冶集团有限公司 Method for treating upper crack of fabricated floor slab

Similar Documents

Publication Publication Date Title
CN103452332A (en) Method for repairing construction engineering floor slab crack
CN102493821B (en) Support method for high stress roadway coal-rock mass
CN107762532A (en) Tunnel vault band mould grouting construction method
CN111119935B (en) Multi-layer grouting reinforcement method for surrounding rock of soft and broken roadway structure
CN105201530A (en) Repairing and strengthening method for large cracks on rock tunnel lining
CN104405411B (en) Oversized variable cross section tunnel supporting structure
CN107701200A (en) A kind of section of jurisdiction crack restorative procedure
CN104404844A (en) Method for repairing and reinforcing open joint of filling layer of slab ballastless track
CN109681235B (en) Method for repairing highway tunnel lining cavity with poor surrounding rock
CN110284889A (en) A kind of flat pilot tunnel Enlargement excavation method of TBM
CN203488189U (en) Tunnel structure for emptying renovation
CN104533451A (en) Tunnel advance pre-supporting technology used in discrete gravelly soil and broken surrounding rock
CN103334779A (en) Method for constructing isotropic surrounding rock soft rock roadway support
CN103089276A (en) Deep-shallow hole and high-low pressure coupling grouting technology
CN204435906U (en) Planting reinforced bar into concrete device
CN105350988A (en) Tunnel base reinforcing method
CN103147778A (en) Method for lane development and support in extremely crushed rock stratum
CN102619536A (en) Deep coal mine roadway grout body maintenance method
CN102505582A (en) Method for repairing filling layer of high-speed railway slab ballastless track
CN105040989A (en) Anchoring device for anchoring prefabricated laminated slab and prefabricated component and construction method of anchoring device
JP6570170B2 (en) Repair method of repair wall, repair ceiling and trowel finish face
CN103437770A (en) Supporting method for excitation gap pressure relief soft rock roadway
CN105019427A (en) Bolting-grouting integrated treatment method for railway tunnel base disease
CN202170802U (en) Slip-casting anchor cable
CN105201525B (en) A kind of recoverable preventing and treating pucking method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131218