CN105603855A - Method for repairing concrete pavement cracks - Google Patents

Method for repairing concrete pavement cracks Download PDF

Info

Publication number
CN105603855A
CN105603855A CN201610007900.8A CN201610007900A CN105603855A CN 105603855 A CN105603855 A CN 105603855A CN 201610007900 A CN201610007900 A CN 201610007900A CN 105603855 A CN105603855 A CN 105603855A
Authority
CN
China
Prior art keywords
crack
road surface
concrete
concrete road
restorative procedure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610007900.8A
Other languages
Chinese (zh)
Inventor
陈勇
章玺
吴方政
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Roadmender Technology Co Ltd
Original Assignee
Hangzhou Roadmender Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Roadmender Technology Co Ltd filed Critical Hangzhou Roadmender Technology Co Ltd
Priority to CN201610007900.8A priority Critical patent/CN105603855A/en
Publication of CN105603855A publication Critical patent/CN105603855A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C23/00Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
    • E01C23/06Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road
    • E01C23/09Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for forming cuts, grooves, or recesses, e.g. for making joints or channels for markings, for cutting-out sections to be removed; for cleaning, treating, or filling cuts, grooves, recesses, or fissures; for trimming paving edges
    • E01C23/0966Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for forming cuts, grooves, or recesses, e.g. for making joints or channels for markings, for cutting-out sections to be removed; for cleaning, treating, or filling cuts, grooves, recesses, or fissures; for trimming paving edges for filling or priming, with or without working the surface of the filling or applying particulate material thereto, e.g. for filling the joints of stone-sett paving
    • E01C23/0973Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for forming cuts, grooves, or recesses, e.g. for making joints or channels for markings, for cutting-out sections to be removed; for cleaning, treating, or filling cuts, grooves, recesses, or fissures; for trimming paving edges for filling or priming, with or without working the surface of the filling or applying particulate material thereto, e.g. for filling the joints of stone-sett paving with liquid or semi-liquid materials, e.g. crack sealants

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Repair (AREA)

Abstract

The invention discloses a method for repairing concrete pavement cracks. The method includes the steps that in the crack direction, inclined holes are drilled in a cross mode at certain intervals, all the inclined holes penetrate through crack cross sections, and then grouting is conducted on the inclined holes, so that the crack cross sections are filled with grout materials; or after the inclined holes are drilled, reinforcing steel bars are placed into the inclined holes, and then grouting is conducted. By means of the method, the pavement where cracks are generated can be repaired into a whole again, breakage maintenance is not needed, a lot of manpower and materials are saved, large mechanical equipment is not needed, and the novel repairing method is environmentally friendly, economical and effective.

Description

A kind of concrete road surface crack restorative procedure
Technical field
The invention belongs to cement concrete road surface recovery technique field, relate to a kind of concrete roadFacial cleft seam restorative procedure.
Background technology
The restorative procedure of traditional concrete road surface mainly contains two kinds, when concrete road surface breakageWhen serious, take directly to abolish and clear up former concrete slab, then cast in place concrete plate againRestorative procedure; Though there is the diseases such as cracking when concrete road surface, still have certain making hardWhen energy, generally take direct fracture to carry out the restorative procedure of the cementation of fissures or slip casting.
But the first restorative procedure need expend a large amount of artificial and materials, and abolish, clearlyManaging, stir, building or lifting all needs heavy mechanical equipment, and rehabilitation expense is high; The second is repaiiedCompound method is due to technological problems, and grout material cannot fully be filled crack, only fracture faces shapeBecome false confining bed, actual repairing effect is very limited. Therefore, proposing one more encirclesProtect, economical, effectively concrete road surface crack restorative procedure is necessary.
Summary of the invention
The object of the invention is the shortcoming in order to solve conventional concrete road facial cleft seam restorative procedureAnd deficiency, a kind of novel, environmental protection, economy are proposed, effectively repair in concrete road surface crackCompound method, this restorative procedure has maximally utilised former concrete road surface, will occur crackXoncrete structure again repair as a wholely, whole repair process only needs 2~3 workmansWith a small amount of special material, without heavy mechanical equipment.
According to on-site actual situations, and the instructions for use that after repairing, road face need reach, the methodMaster operation is to hole alternately in the both sides in crack, directly in bored hole slip casting orSlip casting again after first placing reinforcing bar in bored hole, described boring is the side direction from crackOffside rat holing, inclined hole is through crack section.
In technique scheme, described inclined hole and the angle of concrete road surface be 15 °-75 °; The crosspoint of described inclined hole and crack section is positioned under the mid point of concrete slab thickness of slabSide; The bottom of described inclined hole is positioned at concrete slab bottom top 3-8mm; Described reinforcing barIt can be Ribbed Bar.
Concrete construction method can be divided into:
1, rat holing → slip casting
1. rat holing
Along fractuer direction, intersect at a certain distance rat holing, at the coagulation of crack one sideOn soil plate, select first boring point A, then select second from the concrete slab of crack opposite sideBoring point B, by that analogy. By (15 ° of inclined angle alpha (angle of Kong Yudao face) rat holings75 ° of < α <), inclined hole is through crack section, and its intersection point is a little less than 1/2 concrete slab thickness of slab,The distance of boring point A and surface crack is L1, and inclined hole can not run through concrete slab, at the bottom of inclined holeEnd is H (being preferably 5mm left and right) with the distance at the bottom of concrete slab plate, boring point A and BBe L2 along fracture interval, concrete road surface crack repair schematic diagram see Fig. 1 and Fig. 2.
2. slip casting
Slip casting makes grout material directly arrive and fill near the splitting of inclined hole and concrete slab crosspointSeam section; Traditional grout material paste-making method is directly to start downward injection from surface crack, noteSlurry can not fully be filled crack; In the time adopting rat holing slip casting, owing to breaking in inclined hole and crackFace crosspoint is positioned at the middle part of concrete slab, can improve greatly the accuracy of slip casting, makesThe through crack of grout material section, reaches better filling section and the effect of the section that bonds; NoteSlip preferably adopts Workable, microdilatancy, the material that adhesion strength is high, early strong, high-strengthMaterial.
2, rat holing → placement reinforcing bar → slip casting
Adopt after said method rat holing, in inclined hole, first place the steel of diameter and suitable lengthMuscle, then slip casting.
Front a kind of operation (i.e. boring after directly slip casting) be mainly applicable to breakage light, repairThe not high general concrete road face of rear instructions for use is repaired; Rear a kind of operation (is placed after boringReinforcing bar is slip casting again) be mainly applicable to badly broken, the high concrete road of instructions for use after repairingFace is repaired.
Method of the present invention, for existing road surface repair method, can will produce crackRoad face again repair into as a whole, without abolishing maintenance, save a large amount of artificial andMaterial, without heavy mechanical equipment, and repairing effect is good, is a kind of environmental protection, economy, hasThe novel restorative procedure of effect.
Brief description of the drawings
Profile when Fig. 1 is the reparation of concrete road surface crack;
Fig. 2 is that Shi road face top view is repaired in concrete road surface crack.
Detailed description of the invention
Case study on implementation 1
Preparation 150mm*150mm*550mm concrete test block, average rupture strength is4.5MPa, by the placement of again aliging of the concrete test block section after fractureing, and by crack sectionBottom and two side-closed, on the concrete test block of crack one side, select first boringPoint A, then select second boring point B, two borings from the concrete slab of crack opposite sidePoint is 5cm from concrete test block edge, with L1=8cm, and L2=5cm, α=45 °, boreGet two cross one another inclined holes, inclined hole diameter is 2cm, and inclined hole is long is 15cm, then adoptsInjecting paste material (as the Hangzhou Special grouting material that people Science and Technology Ltd. produces of repairing the roads) is to tiltedlySlip casting is carried out in hole, until the slurry that overflows appears in fracture faces, after maintenance 2h, 1d, 7d, enters respectivelyRow bending test, the rupture strength of surveying in table 1.
Table 1 case study on implementation 1 is repaired rear concrete sample rupture strength
Case study on implementation 2
Bore mode, with case study on implementation 1, is placed diameter 12mm in inclined hole after boring, longThe Ribbed Bar of 11cm, then adopt Hangzhou repair the roads people Science and Technology Ltd. produce extraordinary slip castingMaterial carries out slip casting to inclined hole, until there is the slurry that overflows in fracture faces, difference maintenance 2h, 1d,After 7d, carry out bending test, the rupture strength of surveying in table 2.
Table 2 case study on implementation 2 is repaired rear concrete sample rupture strength
Comprehensive the above, use directly slip casting after rat holing, or rat holing is placed reinforcing bar againThis kind of restorative procedure of grouting behind shaft or drift lining, can make concrete road surface crack be repaired well effectReally, the method, without abolishing maintenance, can be saved a large amount of artificial and materials, without large scale computerTool equipment is a kind of environmental protection, economy, effective novel restorative procedure.

Claims (5)

1. a concrete road surface crack restorative procedure, is characterized in that, comprises following technique:Hole alternately in the both sides in crack, directly slip casting or first in bored hole in bored holeSlip casting again after interior placement reinforcing bar, described boring is the side direction offside rat holing from crack,Inclined hole is through crack section.
2. concrete road surface according to claim 1 crack restorative procedure, is characterized in that,Described inclined hole and the angle of concrete road surface are 15 °-75 °.
3. concrete road surface according to claim 1 crack restorative procedure, is characterized in that,The crosspoint of described inclined hole and crack section is positioned at the mid point below of concrete slab thickness of slab.
4. concrete road surface according to claim 1 crack restorative procedure, is characterized in that,The bottom of described inclined hole is positioned at concrete slab bottom top 3-8mm.
5. concrete road surface according to claim 1 crack restorative procedure, is characterized in that,Described reinforcing bar is Ribbed Bar.
CN201610007900.8A 2016-01-05 2016-01-05 Method for repairing concrete pavement cracks Pending CN105603855A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610007900.8A CN105603855A (en) 2016-01-05 2016-01-05 Method for repairing concrete pavement cracks

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610007900.8A CN105603855A (en) 2016-01-05 2016-01-05 Method for repairing concrete pavement cracks

Publications (1)

Publication Number Publication Date
CN105603855A true CN105603855A (en) 2016-05-25

Family

ID=55984165

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610007900.8A Pending CN105603855A (en) 2016-01-05 2016-01-05 Method for repairing concrete pavement cracks

Country Status (1)

Country Link
CN (1) CN105603855A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106498834A (en) * 2016-12-30 2017-03-15 成都圭目机器人有限公司 A kind of Athey wheel road face repair robot system and road surface repair method
CN106514607A (en) * 2016-12-30 2017-03-22 成都圭目机器人有限公司 Four-wheel drive road face repairing robot system and road face repairing method
CN106522077A (en) * 2016-11-10 2017-03-22 曹立强 Rapid compounding repair method of pavement
CN107461196A (en) * 2016-06-03 2017-12-12 中国矿业大学(北京) The step-like restorative procedure collapsed in colliery
CN108386005A (en) * 2018-04-08 2018-08-10 中国电建集团成都勘测设计研究院有限公司 Repairing concrete crack structure and method for repairing and mending
CN108952206A (en) * 2018-09-07 2018-12-07 中铁十四局集团第四工程有限公司 A kind of restorative procedure in the discontinuous crack of concrete construction body
CN109853347A (en) * 2019-01-24 2019-06-07 杭州垠杉建设有限公司 A kind of pot hole method for repairing and mending
CN110161047A (en) * 2019-06-14 2019-08-23 汕头大学 A kind of road and bridge Crack Detection and repair integrated robot
CN114703854A (en) * 2022-03-22 2022-07-05 光华建设集团有限公司 Construction method of dam in hydraulic and hydroelectric engineering

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0950761B1 (en) * 1998-04-15 2002-02-27 Mulch Seal, LLC Method of repairing cracks in roadways
CA2695333A1 (en) * 2010-03-04 2011-09-04 Gary Fielding Aggregate repair method and product
CN103452332A (en) * 2013-09-11 2013-12-18 中建中东有限责任公司 Method for repairing construction engineering floor slab crack
CN104233939A (en) * 2014-08-29 2014-12-24 华南理工大学 Maintenance method for crossed and oblique embedded steel bars of concrete pavement
CN104343077A (en) * 2014-10-23 2015-02-11 中国二十冶集团有限公司 Asphalt concrete pavement reflection crack treatment method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0950761B1 (en) * 1998-04-15 2002-02-27 Mulch Seal, LLC Method of repairing cracks in roadways
CA2695333A1 (en) * 2010-03-04 2011-09-04 Gary Fielding Aggregate repair method and product
CN103452332A (en) * 2013-09-11 2013-12-18 中建中东有限责任公司 Method for repairing construction engineering floor slab crack
CN104233939A (en) * 2014-08-29 2014-12-24 华南理工大学 Maintenance method for crossed and oblique embedded steel bars of concrete pavement
CN104343077A (en) * 2014-10-23 2015-02-11 中国二十冶集团有限公司 Asphalt concrete pavement reflection crack treatment method

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107461196A (en) * 2016-06-03 2017-12-12 中国矿业大学(北京) The step-like restorative procedure collapsed in colliery
CN107461196B (en) * 2016-06-03 2019-11-15 中国矿业大学(北京) The step-like restorative procedure collapsed of coal mine
CN106522077A (en) * 2016-11-10 2017-03-22 曹立强 Rapid compounding repair method of pavement
CN106498834A (en) * 2016-12-30 2017-03-15 成都圭目机器人有限公司 A kind of Athey wheel road face repair robot system and road surface repair method
CN106514607A (en) * 2016-12-30 2017-03-22 成都圭目机器人有限公司 Four-wheel drive road face repairing robot system and road face repairing method
CN108386005A (en) * 2018-04-08 2018-08-10 中国电建集团成都勘测设计研究院有限公司 Repairing concrete crack structure and method for repairing and mending
CN108952206A (en) * 2018-09-07 2018-12-07 中铁十四局集团第四工程有限公司 A kind of restorative procedure in the discontinuous crack of concrete construction body
CN109853347A (en) * 2019-01-24 2019-06-07 杭州垠杉建设有限公司 A kind of pot hole method for repairing and mending
CN109853347B (en) * 2019-01-24 2020-10-16 杭州垠杉建设有限公司 Road surface pothole repairing method
CN110161047A (en) * 2019-06-14 2019-08-23 汕头大学 A kind of road and bridge Crack Detection and repair integrated robot
CN114703854A (en) * 2022-03-22 2022-07-05 光华建设集团有限公司 Construction method of dam in hydraulic and hydroelectric engineering
CN114703854B (en) * 2022-03-22 2023-12-08 光华建设集团有限公司 Construction method of dam in water conservancy and hydropower engineering

Similar Documents

Publication Publication Date Title
CN105603855A (en) Method for repairing concrete pavement cracks
CN106012697B (en) Ballastless track roadbed high polymer grouting lifting method
CN105133487B (en) Construction method for using combined type bridge temporary support to rapidly build continuous beams
CN102180645B (en) Concrete ingredient and fast hardening concrete
CN108103939A (en) Oblique section steel trestle construction composite reinforcement mode and construction technology
CN103225257B (en) Cantilever beam structure of antique plank road along cliff and construction technology thereof
CN111577334B (en) Operating tunnel inverted arch repairing method
CN110468725B (en) Rear mounting construction method for side pier support of swivel bridge
CN106284414A (en) Anti-grand supporting construction
CN107816056A (en) Filled type concrete gravity retaining wall and its construction technology
CN205243528U (en) Lining cutting fracture reinforced structure is subsided to tunnel bottom
CN106837382A (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
CN205134392U (en) Chemistry electric osmose method is united pile foundation and is consolidated side slope model test device
CN112127925A (en) Tunnel structure defect repairing system and construction method
CN104452502A (en) Construction method for renovating horizontal deformation hazards of terminal spines of ballastless tracks
CN103276645B (en) Precast pile, beam and slab renovation technology for diseases of existing line tunnel base
CN103790176A (en) Embedded short strut structure and construction method thereof
CN105804060A (en) Construction method for digging pile foundation hole manually
CN105220582B (en) Solid concrete roabed and tunnel bottom Disease Treatment method based on combined support and slip casting template
CN111980734A (en) Tunnel deformation rapid construction and reinforcement method based on constant-resistance large-deformation anchor rod
CN110963765A (en) Foam concrete and method for repairing pavement subsidence by adopting same
CN106401276A (en) Construction method for wall column binding bars of frame type building block enclosing wall
CN205035732U (en) Interim support of combined type bridge
CN213013834U (en) Multi-angle oblique crossing reinforcing structure for crack space of old cement pavement
CN108130825A (en) Subgrade of metro concrete replacement technique in special limiting condition

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160525

RJ01 Rejection of invention patent application after publication