CN111962402A - Lateral sliding installation method for steel box girder - Google Patents
Lateral sliding installation method for steel box girder Download PDFInfo
- Publication number
- CN111962402A CN111962402A CN202010799941.1A CN202010799941A CN111962402A CN 111962402 A CN111962402 A CN 111962402A CN 202010799941 A CN202010799941 A CN 202010799941A CN 111962402 A CN111962402 A CN 111962402A
- Authority
- CN
- China
- Prior art keywords
- steel box
- box girder
- sliding
- steel
- counter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/06—Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
- E01D2/04—Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
Abstract
The invention relates to a lateral sliding installation method of a steel box girder.A counterforce seat is arranged at the end part of a capping beam at one side of a pier, a bracket is erected at the other side of the pier, and sliding rails are transversely paved on the bracket and the top surface of the capping beam in a bridging way; a sliding device is welded at the bottom of the steel box girder in the transverse bridge direction, and an anchor plate is welded at one side of the steel box girder; the steel box girder is hung on a bracket, and a sliding device at the bottom of the steel box girder is supported on a sliding rail at the top of the bracket; and a steel strand is connected between the anchor pulling plate and the counter-force seat, a penetrating jack is arranged on one side of the counter-force seat, and the penetrating jack pulls the steel box girder to move to the upper part of the cover girder along the slide rail through the steel strand. The invention solves the problem that the lower layer steel box girder can not be directly hoisted when the steel box girders of the upper and lower layer bridges are constructed simultaneously, the installation of the lower layer steel box girder is not influenced by the upper layer, and the construction progress can be ensured.
Description
Technical Field
The invention belongs to the technical field of bridge construction, relates to steel box girder installation construction, and particularly relates to a method for installing a steel box girder in a sliding mode.
Background
In the construction process of the steel structure bridge, the steel box girder is generally hoisted by a crane. When the three-dimensional intercommunication bridge construction, in order to guarantee the construction progress, upper and lower floor's roof beam body often is under construction simultaneously, but at upper and lower floor's cross position, lower floor's steel box girder receives the upper strata influence, can't adopt loop wheel machine direct mount, consequently can only construct the lower floor earlier, constructs the upper strata after the lower floor construction is accomplished again, influences the construction progress.
Disclosure of Invention
The invention aims to solve the problems and provides a lateral sliding installation method of a steel box girder, which ensures the normal installation of the steel box girder under the condition that the hoisting clearance of the steel box girder is limited.
The technical scheme of the invention is as follows:
a steel box girder lateral sliding installation method is characterized by comprising the following steps:
(1) when the capping beam on each pier is constructed, an embedded part is arranged at the top of one end of the capping beam, and a counterforce seat is welded on the embedded part;
(2) pouring a concrete foundation on the ground on one side of each pier, erecting a support on the concrete foundation, and enabling the top surface of the support to be flush with the top surface of a capping beam on the pier;
(3) paving sliding rails on the support and the top surface of the cover beam in the transverse bridge direction; a vertical jack is arranged on the bent cap;
(4) two rows of sliding devices are welded at the bottom of the steel box girder in the transverse bridge direction, and the distance between the two rows of sliding devices is consistent with the distance between the sliding rails on two adjacent bent caps; welding two anchor plates on one side of the steel box girder, wherein the distance between the two anchor plates is consistent with the distance between the counter-force seats on the two adjacent bent girders;
(5) hoisting the steel box girder to the supports corresponding to the two adjacent piers by using a crane, and respectively supporting the two rows of sliding devices at the bottom of the steel box girder on the slide rails at the tops of the two supports;
(6) connecting a steel strand between the anchor plate and the counter-force seat, wherein one end of the steel strand is anchored with the anchor plate, the other end of the steel strand passes through the counter-force seat and then passes through a center-penetrating jack, and a base of the center-penetrating jack is supported on the side wall of the counter-force seat;
(7) starting the center-penetrating jack, and drawing the steel box girder to move above the cover girder along the slide rail through the steel strand;
(8) and starting a vertical jack on the cover beam to lift the steel box beam upwards, enabling a sliding device at the bottom of the steel box beam to leave the sliding rail, cutting off the sliding device, returning oil by the vertical jack, and dropping the steel box beam onto a support at the bottom of the cover beam to finish the installation of the steel box beam.
According to the invention, the steel box girders are installed in a lateral sliding mode, so that the problem that the lower layer steel box girder cannot be directly hoisted when the upper layer bridge steel box girder and the lower layer bridge steel box girder are constructed simultaneously is solved, the installation of the lower layer steel box girder is not influenced by the upper layer construction, and the construction progress can be ensured.
Drawings
FIG. 1 is a schematic transverse bridge direction diagram of a slippage system of a steel box girder;
FIG. 2 is a schematic view of a forward direction of a bridge at a pier;
fig. 3 is a schematic representation of the forward direction at the stent.
Detailed Description
As shown in fig. 1, 2 and 3, the embodiment of the present invention is as follows:
(1) when the bent cap 2 on each pier 1 is constructed, an embedded part 3 is arranged at the top of one end of the bent cap, and a counterforce seat 4 is welded on the embedded part;
(2) pouring a concrete foundation 5 on the ground on one side of each pier, erecting a support 6 on the concrete foundation 5, and enabling the top surface of the support 6 to be flush with the top surface of the cover beam 2 on the pier;
(3) a sliding rail 7 is paved on the support 5 and the top surface of the bent cap 2 in the transverse bridge direction; a vertical jack 8 is arranged on the bent cap;
(4) at 9 bottom cross bridges of steel case roof beam to two rows of sliding device 10 of welding, sliding device includes the backup pad and a pulley of two vertical settings, and the welding of the upper end of two backup pads is in the steel case roof beam bottom, and two backup pads have the determining deviation and be equipped with the shaft hole to wearing, the pulley is located between two backup pads, and the shaft both ends of pulley alternate respectively in the shaft hole of two backup pads.
The distance between the two rows of sliding devices 10 is consistent with the distance between the sliding rails on the two adjacent bent caps; two anchor plates 11 are welded on one side of the steel box girder 9, and the distance between the two anchor plates 11 is consistent with the distance between the counter force seats on the two adjacent bent caps;
(5) hoisting a steel box girder 9 onto supports 6 corresponding to two adjacent piers by using a crane, wherein two rows of sliding devices 10 at the bottom of the steel box girder are respectively supported on slide rails 7 at the tops of the two supports;
(6) a steel strand 12 is connected between the anchor plate 11 and the counter-force seat 4, one end of the steel strand 12 is anchored with the anchor plate 11, the other end of the steel strand passes through the counter-force seat 4 and then passes through a center-penetrating jack 13, and the base of the center-penetrating jack 13 is supported on the side wall of the counter-force seat 4;
(7) starting the center-penetrating jack 13, and drawing the steel box girder 9 to move above the cover girder 2 along the slide rail 7 through the steel strand 12;
(8) and starting a vertical jack 8 on the cover beam to lift the steel box beam 9 upwards, enabling the sliding device at the bottom of the steel box beam to leave the sliding rail, cutting off the sliding device, returning oil by the vertical jack, and dropping the steel box beam 9 onto a support 14 at the bottom of the cover beam to finish the installation of the steel box beam.
Claims (2)
1. A steel box girder lateral sliding installation method is characterized by comprising the following steps:
(1) when the capping beam on each pier is constructed, an embedded part is arranged at the top of one end of the capping beam, and a counterforce seat is welded on the embedded part;
(2) pouring a concrete foundation on the ground on one side of each pier, erecting a support on the concrete foundation, and enabling the top surface of the support to be flush with the top surface of a capping beam on the pier;
(3) paving sliding rails on the support and the top surface of the cover beam in the transverse bridge direction; a vertical jack is arranged on the bent cap;
(4) two rows of sliding devices are welded at the bottom of the steel box girder in the transverse bridge direction, and the distance between the two rows of sliding devices is consistent with the distance between the sliding rails on two adjacent bent caps; welding two anchor plates on one side of the steel box girder, wherein the distance between the two anchor plates is consistent with the distance between the counter-force seats on the two adjacent bent girders;
(5) hoisting the steel box girder to the supports corresponding to the two adjacent piers by using a crane, and respectively supporting the two rows of sliding devices at the bottom of the steel box girder on the slide rails at the tops of the two supports;
(6) connecting a steel strand between the anchor plate and the counter-force seat, wherein one end of the steel strand is anchored with the anchor plate, the other end of the steel strand passes through the counter-force seat and then passes through a center-penetrating jack, and a base of the center-penetrating jack is supported on the side wall of the counter-force seat;
(7) starting the center-penetrating jack, and drawing the steel box girder to move above the cover girder along the slide rail through the steel strand;
(8) and starting a vertical jack on the cover beam to lift the steel box beam upwards, enabling a sliding device at the bottom of the steel box beam to leave the sliding rail, cutting off the sliding device, returning oil by the vertical jack, and dropping the steel box beam onto a support at the bottom of the cover beam to finish the installation of the steel box beam.
2. The lateral sliding installation method of the steel box girder according to claim 1, characterized in that: the sliding device comprises two vertically arranged supporting plates and a pulley, the upper ends of the two supporting plates are welded at the bottom of the steel box girder, the two supporting plates have a certain distance and are provided with through shaft holes, the pulley is positioned between the two supporting plates, and the two ends of the wheel shaft of the pulley are respectively inserted into the shaft holes of the two supporting plates.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010799941.1A CN111962402A (en) | 2020-08-11 | 2020-08-11 | Lateral sliding installation method for steel box girder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010799941.1A CN111962402A (en) | 2020-08-11 | 2020-08-11 | Lateral sliding installation method for steel box girder |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111962402A true CN111962402A (en) | 2020-11-20 |
Family
ID=73365095
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010799941.1A Pending CN111962402A (en) | 2020-08-11 | 2020-08-11 | Lateral sliding installation method for steel box girder |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111962402A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113026522A (en) * | 2021-03-22 | 2021-06-25 | 北京市政建设集团有限责任公司 | Bridge steel box girder installation structure and construction process |
CN114808720A (en) * | 2022-05-05 | 2022-07-29 | 广西路桥工程集团有限公司 | Steel box girder installation construction platform |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4306040A1 (en) * | 1993-02-26 | 1994-09-01 | Walter Dipl Ing Komm | Method and device for transverse displacement of bridge construction elements produced with a camber |
CN102182147A (en) * | 2011-03-31 | 2011-09-14 | 中铁港航局集团第二工程有限公司 | Steel box girder erection method |
CN102650118A (en) * | 2012-05-18 | 2012-08-29 | 科达集团股份有限公司 | Construction device and method for erecting prefabricated beam by slip method |
CN105350459A (en) * | 2015-11-20 | 2016-02-24 | 中建交通建设集团有限公司 | Large steel beam gliding device and construction method thereof |
CN105442452A (en) * | 2015-11-13 | 2016-03-30 | 中铁大桥局集团第一工程有限公司 | Device and method for splicing double width bridge steel girder |
CN206034293U (en) * | 2016-08-24 | 2017-03-22 | 广西长长路桥建设有限公司 | Whole sideslip device of cast -in -place support |
CN108798331A (en) * | 2018-06-14 | 2018-11-13 | 河北喜德来家具实业有限公司 | A kind of sliding door cabinet lower sheave and sliding rail improved structure |
KR20190006671A (en) * | 2017-07-11 | 2019-01-21 | 한국철도기술연구원 | Structural continuation method of reinforcing concrete structure and earth transitional zone |
CN111206513A (en) * | 2020-01-13 | 2020-05-29 | 成都高源工程勘察设计有限公司 | Bridge translation construction structure and device and construction method for crossing existing line bridge |
-
2020
- 2020-08-11 CN CN202010799941.1A patent/CN111962402A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4306040A1 (en) * | 1993-02-26 | 1994-09-01 | Walter Dipl Ing Komm | Method and device for transverse displacement of bridge construction elements produced with a camber |
CN102182147A (en) * | 2011-03-31 | 2011-09-14 | 中铁港航局集团第二工程有限公司 | Steel box girder erection method |
CN102650118A (en) * | 2012-05-18 | 2012-08-29 | 科达集团股份有限公司 | Construction device and method for erecting prefabricated beam by slip method |
CN105442452A (en) * | 2015-11-13 | 2016-03-30 | 中铁大桥局集团第一工程有限公司 | Device and method for splicing double width bridge steel girder |
CN105350459A (en) * | 2015-11-20 | 2016-02-24 | 中建交通建设集团有限公司 | Large steel beam gliding device and construction method thereof |
CN206034293U (en) * | 2016-08-24 | 2017-03-22 | 广西长长路桥建设有限公司 | Whole sideslip device of cast -in -place support |
KR20190006671A (en) * | 2017-07-11 | 2019-01-21 | 한국철도기술연구원 | Structural continuation method of reinforcing concrete structure and earth transitional zone |
CN108798331A (en) * | 2018-06-14 | 2018-11-13 | 河北喜德来家具实业有限公司 | A kind of sliding door cabinet lower sheave and sliding rail improved structure |
CN111206513A (en) * | 2020-01-13 | 2020-05-29 | 成都高源工程勘察设计有限公司 | Bridge translation construction structure and device and construction method for crossing existing line bridge |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113026522A (en) * | 2021-03-22 | 2021-06-25 | 北京市政建设集团有限责任公司 | Bridge steel box girder installation structure and construction process |
CN114808720A (en) * | 2022-05-05 | 2022-07-29 | 广西路桥工程集团有限公司 | Steel box girder installation construction platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101914897B (en) | Construction method of single main cable inclined-suspender earth anchored suspension bridge | |
CN102477717B (en) | A kind of bridge pushing construction method | |
CN206146751U (en) | A loading device for monospar static test | |
CN107653781A (en) | Big steel pipe truss and construction method for bent cap cast-in-place construction | |
CN111962402A (en) | Lateral sliding installation method for steel box girder | |
CN112854008A (en) | Prefabricated bridge pier and beam integrated bridge girder erection machine and construction method thereof | |
CN110219242B (en) | Mounting construction method for inner lifting beam of double-layer synchronous beam | |
CN111236089A (en) | Uneven jacking system and uneven jacking construction method for existing bridge superstructure | |
CN207032062U (en) | Tower with suspended cable available for Large-span Steel Box Beam construction | |
CN203866711U (en) | Large span cable-stayed bridge tower beam three-way temporary consolidation structure | |
CN209428958U (en) | A kind of flow type bridge erecting machine | |
CN109554961B (en) | Height-adjustable railway roadbed structure and implementation method thereof | |
CN100497834C (en) | Construction equipment for integral roof-holding highway bridge top structure | |
CN206015523U (en) | The built-in steel anchor beam accurate positioning device of free-standing Sarasota | |
CN101899815A (en) | Device for preventing bridging machine from rolling-over in installation process of bridge transition cross T-shaped boundary beam of bridging machine | |
CN214423168U (en) | Bridge girder erection machine support frame for installing and splicing wide bridge | |
CN111005324B (en) | Support-free suspension and locking construction method for assembled type segmental box girder | |
CN211735114U (en) | A antidumping reinforced structure for rectangle single-column mound bridge | |
CN205741794U (en) | A kind of reparation structure for switch area plate-type ballastless track | |
CN201738242U (en) | Rigid supporting device for mounting of bridge transitional span T-shaped edge beam | |
CN220166687U (en) | Cast-in-situ construction arch frame for upper beam of cable tower | |
CN204715219U (en) | Distribution beam hanging apparatus | |
CN110552294A (en) | Bridge girder erection machine reverse beam erection construction platform and construction method thereof | |
CN106480793B (en) | A kind of prefabricated floating plate ballast construction method | |
CN214939311U (en) | Prefabricated bridge pier and beam integrated bridge girder erection machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20201120 |
|
RJ01 | Rejection of invention patent application after publication |