CN111828050B - A construction method for a small-section traffic tunnel entering a diversion lock chamber with a thin, tall and special-shaped space structure - Google Patents

A construction method for a small-section traffic tunnel entering a diversion lock chamber with a thin, tall and special-shaped space structure Download PDF

Info

Publication number
CN111828050B
CN111828050B CN202010737662.2A CN202010737662A CN111828050B CN 111828050 B CN111828050 B CN 111828050B CN 202010737662 A CN202010737662 A CN 202010737662A CN 111828050 B CN111828050 B CN 111828050B
Authority
CN
China
Prior art keywords
lock chamber
construction
special
thin
chamber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010737662.2A
Other languages
Chinese (zh)
Other versions
CN111828050A (en
Inventor
刘泽
刘星源
黄根茂
蒲晓容
刘彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Erju 1st Engineering Co Ltd
Original Assignee
China Railway No 2 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 2 Engineering Group Co Ltd filed Critical China Railway No 2 Engineering Group Co Ltd
Priority to CN202010737662.2A priority Critical patent/CN111828050B/en
Publication of CN111828050A publication Critical patent/CN111828050A/en
Application granted granted Critical
Publication of CN111828050B publication Critical patent/CN111828050B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明涉及建筑施工技术领域,具体涉及一种小断面交通洞进瘦高异型空间结构引水闸室施工方法,其步骤如下:步骤1,施工过渡段:主干挑顶施工过渡段,对过渡段的拱顶及边墙进行初期支护;步骤2,施工闸室:过渡段挑顶施工闸室,对闸室拱顶及边墙进行初期支护,闸室上部采用台阶法施工,闸室中部采用分层分块法施工;步骤3,开挖支干:平挑开挖支干,使支干贯通闸室下部。施工过程将整个闸室分割为上、中、下三个区域分别挖掘,闸室上部采用台阶法施工,闸室中部采用分层分块法挖掘,最后施工支干使支干与闸室下部贯通,挖掘过程对周围的隧洞结构稳定影响较小,避免了瘦高异型复杂空间结构施工坍塌的风险,提高了施工过程中的安全性。

Figure 202010737662

The invention relates to the technical field of building construction, in particular to a construction method for a small-section traffic hole entering a diversion lock chamber with a thin, tall and special-shaped space structure. Do initial support for the vault and side walls; Step 2, construction of the lock chamber: construct the lock chamber by lifting the roof in the transition section, and perform initial support for the vault and side walls of the lock chamber. Construction by layered and block method; Step 3, excavate the branch trunk: horizontally lift and excavate the branch trunk, so that the branch trunk runs through the lower part of the lock chamber. During the construction process, the entire sluice chamber is divided into upper, middle and lower areas for excavation. The upper part of the sluice chamber is constructed by the step method, and the middle part of the sluice chamber is excavated by the layered and block method. , the excavation process has little influence on the stability of the surrounding tunnel structure, avoids the risk of construction collapse of the thin, tall and special-shaped complex space structure, and improves the safety during the construction process.

Figure 202010737662

Description

一种小断面交通洞进瘦高异型空间结构引水闸室施工方法A construction method for a small-section traffic tunnel entering a diversion lock chamber with a thin, tall and special-shaped space structure

技术领域technical field

本发明涉及建筑施工技术领域,特别是一种小断面交通洞进瘦高异型空间结构引水闸室施工方法。The invention relates to the technical field of building construction, in particular to a construction method for a small-section traffic hole entering a diversion lock chamber with a thin, high and special-shaped space structure.

背景技术Background technique

随着引水工程建设的快速发展,众多的引水隧洞穿越复杂地质,引水隧洞一般长度较长,断面较小,在主干与支干交叉口通常需要设置进水闸室实现分流,为了通行需要,通常还需要设置三岔口过渡段,主干进入过渡段后再依次进入各个支干,其中进水闸室由于设备安装需要,其结构断面高度较引水隧洞更高,三岔口的闸室同时连通过渡段和支干,施工困难,传统的方法是采用过渡段挑高进入闸室,然后进行扩挖施工,即首先挖出闸室雏形,再将闸室逐步向周围进行扩挖达到预设尺寸,这样闸室的内轮廓在施工过程中一直处于变动状态,不便于对闸室内进行支护搭设,同时扩挖施工对整个闸室内的空间都有一定震荡,容易造成坍塌事故。With the rapid development of water diversion engineering construction, many water diversion tunnels pass through complex geology. Generally, water diversion tunnels are long in length and small in cross section. At the intersection of main trunk and branch trunk, it is usually necessary to set up an intake lock chamber to realize diversion. It is necessary to set up a transition section at the Sanchakou. The main trunk enters the transition section and then enters each branch in turn. The intake lock chamber has a higher structural section height than the diversion tunnel due to equipment installation requirements. The lock chamber at the Sanchakou connects the transition section and the branch at the same time. , the construction is difficult, the traditional method is to use the transition section to lift into the sluice chamber, and then carry out the expansion and excavation construction, that is, first excavate the prototype of the sluice chamber, and then gradually expand the sluice chamber to the surrounding area to reach the preset size, so that the sluice chamber is fully excavated. The inner contour has been in a state of change during the construction process, which is inconvenient for the support and erection of the sluice chamber. At the same time, the expansion and excavation construction will have a certain degree of shock to the entire sluice chamber, which is likely to cause collapse accidents.

所以,目前需要一种技术方案,以解决现有技术在引水隧洞的三岔口施工时,由过渡段进入闸室后,闸室施工过程中,容易出现坍塌事故的技术问题。Therefore, there is currently a need for a technical solution to solve the technical problem that collapse accidents are prone to occur during the construction of the lock chamber after the transition section enters the lock chamber during the construction of the three forks of the diversion tunnel in the prior art.

发明内容SUMMARY OF THE INVENTION

本发明的发明目的在于:针对现有技术存在引水隧洞的三岔口施工时,由过渡段进入闸室后,闸室施工过程中,容易出现坍塌事故的技术问题,提供一种小断面交通洞进瘦高异型空间结构引水闸室施工方法。The purpose of the invention of the present invention is to: aiming at the technical problem that collapse accidents are prone to occur during the construction of the lock chamber after entering the lock chamber from the transition section during the construction of the three-way entrance of the diversion tunnel in the prior art, to provide a small-section traffic tunnel entrance Construction method of diversion lock chamber with thin and tall special-shaped space structure.

为了实现上述目的,本发明采用的技术方案为:In order to achieve the above object, the technical scheme adopted in the present invention is:

一种小断面交通洞进瘦高异型空间结构引水闸室施工方法,其步骤如下:A construction method for a small-section traffic hole entering a diversion lock chamber with a thin, tall and special-shaped space structure, the steps of which are as follows:

步骤1,施工过渡段:主干挑顶施工过渡段,对过渡段的拱顶及边墙进行初期支护;Step 1, construction transition section: the main trunk canopy construction transition section, and initial support for the vault and side walls of the transition section;

步骤2,施工闸室:过渡段挑顶施工闸室,对闸室拱顶及边墙进行初期支护,闸室上部采用台阶法施工,闸室中部采用分层分块法施工;Step 2, construction of the sluice chamber: the construction of the sluice chamber is carried out by lifting the roof in the transition section, and the initial support for the dome and side walls of the sluice chamber is carried out.

步骤3,开挖支干:平挑开挖支干,使支干贯通闸室下部。Step 3, excavate the branch trunk: excavate the branch trunk horizontally, so that the branch trunk runs through the lower part of the lock chamber.

本发明一种小断面交通洞进瘦高异型空间结构引水闸室施工方法,施工过程中同时对隧洞的拱顶边墙位置进行初期支护,加强引水隧洞的结构强度,在施工闸室时由过渡段挑顶进入闸室上部,将整个闸室分割为上、中、下三个区域分别挖掘,闸室上部采用台阶法施工,从上到下逐步开挖,闸室中部采用分层分块法挖掘,在高度方向上将闸室中部分割成若干层,在每一层将闸室中部分割为若干区块,这样挖掘对周围的隧洞结构稳定影响较小,同时也便于观察每一层、每一块的地质情况,便于预防突发事件,提高了施工过程中的安全性,闸室的下部与支干贯通,最后施工支干并使支干与闸室下部贯通,避免了因闸室下部强度不足而造成闸室坍塌等现象。The invention provides a construction method for a small-section traffic tunnel entering a diversion lock chamber with a thin, high and special-shaped space structure. During the construction process, initial support is performed on the position of the vault side wall of the tunnel to strengthen the structural strength of the water diversion tunnel. The transition section is lifted into the upper part of the lock chamber, and the entire lock chamber is divided into upper, middle and lower areas to be excavated respectively. The upper part of the lock chamber is constructed by the step method, which is gradually excavated from top to bottom, and the middle part of the lock chamber is divided into layers and blocks. The middle of the lock chamber is divided into several layers in the height direction, and the middle part of the lock chamber is divided into several blocks in each layer, so that the excavation has less influence on the stability of the surrounding tunnel structure, and it is also convenient to observe the characteristics of each layer, The geological conditions of each block are convenient for preventing emergencies and improving the safety during construction. Insufficient strength, resulting in the collapse of the lock chamber and other phenomena.

作为本发明的优选方案,所述步骤1还包括步骤1.1,优化过渡段形状:所述过渡段上设有若干闸室接口,所述闸室接口的轴线垂直于闸室侧壁设置。使得在过渡段进入闸室过程中也不需要转换掌子面,提高了施工效率。As a preferred solution of the present invention, the step 1 further includes step 1.1, optimizing the shape of the transition section: the transition section is provided with a plurality of sluice chamber interfaces, and the axis of the sluice chamber interface is perpendicular to the side wall of the sluice chamber. Therefore, it is not necessary to convert the face during the process of entering the lock chamber in the transition section, which improves the construction efficiency.

作为本发明的优选方案,所述初期支护包括在拱顶及边墙上喷射混凝土,以及安装若干个支撑架。通过在隧洞的拱顶及边墙上喷射混凝土对隧洞进行加固,同时在隧洞内安装支撑架对拱顶及边墙进行支撑,使隧洞在施工过程中能够保持足够的强度,以承受施工过程中的各种施工操作所带来的破坏力。As a preferred solution of the present invention, the initial support includes spraying concrete on the vault and side walls, and installing several support frames. The tunnel is reinforced by spraying concrete on the vault and side walls of the tunnel, and at the same time, a support frame is installed in the tunnel to support the vault and side walls, so that the tunnel can maintain sufficient strength during the construction process to withstand the construction process. The destructive force caused by various construction operations.

作为本发明的优选方案,所述支撑架包括与拱顶形状适配的弧形杆,所述弧形杆两端分别设有立柱。弧形杆和两个立柱连接形成门字形结构,使得支撑架在隧洞内安装后能够与隧洞的拱顶和边墙紧靠,从而对隧洞的拱顶及边墙形成支撑。As a preferred solution of the present invention, the support frame includes an arc-shaped rod adapted to the shape of the dome, and two ends of the arc-shaped rod are respectively provided with uprights. The arc-shaped rod and the two uprights are connected to form a gate-shaped structure, so that the support frame can abut against the vault and side wall of the tunnel after being installed in the tunnel, thereby forming support for the vault and side wall of the tunnel.

作为本发明的优选方案,所述分层分块法包括:首先将闸室中部沿闸室高度方向分割为若干个挖掘层,再将每一个挖掘层分割为若干个挖掘块,选择一个挖掘块进行挖掘,再对其他挖掘块依次进行挖掘,每次挖掘的高度与挖掘层的高度相同。As a preferred solution of the present invention, the layered block method includes: firstly dividing the middle of the lock chamber into several excavation layers along the height direction of the lock chamber, then dividing each excavation layer into several excavation blocks, and selecting one excavation block Excavate, and then excavate other excavation blocks in sequence, and the height of each excavation is the same as the height of the excavation layer.

作为本发明的优选方案,对于每一层的若干挖掘块,其第一个开挖的挖掘块采用垂向浅眼爆破,其他挖掘块采用预裂爆破。其中垂向浅眼爆破是指在爆破区域上端设置爆破孔进行爆破,预裂爆破是指从爆破区域侧壁上设置爆破孔进行爆破,在一个挖掘层上的一个挖掘块进行垂向浅眼爆破后形成台阶,再对该层挖掘层的其他挖掘块进行预裂爆破,这样减小爆破对隧洞周壁的扰动,提高了施工过程的安全性。As a preferred solution of the present invention, for several excavation blocks of each layer, the first excavated excavation block is blasted with vertical shallow hole, and the other excavated blocks are blasted with pre-split blasting. Among them, vertical shallow-hole blasting refers to setting blasting holes at the upper end of the blasting area for blasting, pre-splitting blasting refers to setting blasting holes on the side wall of the blasting area for blasting, and performing vertical shallow-hole blasting at an excavation block on an excavation layer After forming a step, pre-split blasting is performed on other excavated blocks of the excavation layer, which reduces the disturbance of the blasting to the surrounding wall of the tunnel and improves the safety of the construction process.

作为本发明的优选方案,在所述步骤2中,在闸室中部施工完成后,在闸室中部侧壁上开设有注浆孔,并在注浆孔中设置注浆锚管。通过闸室中部侧壁上的注浆孔向岩层中灌注浆液,以提高隧洞周壁的结构强度,为后面闸室下部施工做准备。As a preferred solution of the present invention, in the step 2, after the construction in the middle of the sluice chamber is completed, a grouting hole is opened on the side wall of the middle part of the sluice chamber, and a grouting anchor pipe is arranged in the grouting hole. The grout is injected into the rock formation through the grouting hole on the side wall in the middle of the sluice chamber to improve the structural strength of the surrounding wall of the tunnel and prepare for the construction of the lower part of the sluice chamber.

作为本发明的优选方案,所述注浆孔斜向下设置。通过斜向下设置的注浆孔将浆液输送到闸室下部,使闸室下部的周围岩层得到加强,确保在闸室下部爆破施工的安全性。As a preferred solution of the present invention, the grouting holes are arranged obliquely downward. The grout is transported to the lower part of the sluice chamber through the grouting holes set obliquely downward, so that the surrounding rock formations in the lower part of the sluice chamber are strengthened, and the safety of blasting construction in the lower part of the sluice chamber is ensured.

作为本发明的优选方案,在所述步骤3中,在支干进入闸室下部施工中,支干底板、边墙、及拱顶均采用放大外插角爆破进行施工。其中放大外插角爆破是指在支干进入闸室时,在隧洞周壁上设置斜向隧洞外的爆破孔进行爆破,由于闸室下部的两侧边墙之间的间距较支干的两侧边墙间距更大,并且闸室底部也低于支干底部,故采用放大外插角爆破进行施工能够减少后期的修正工作,提高施工效率。As a preferred solution of the present invention, in the step 3, when the branch trunk enters the lower part of the sluice chamber, the bottom plate, side wall, and vault of the branch trunk are all constructed by blasting with enlarged external angle. Among them, blasting with enlarged outside angle means that when the branch trunk enters the sluice chamber, blasting holes are set on the peripheral wall of the tunnel obliquely outside the tunnel for blasting. The distance between the side walls is larger, and the bottom of the sluice chamber is also lower than the bottom of the branch trunk. Therefore, blasting at the enlarged outer angle for construction can reduce the later correction work and improve the construction efficiency.

作为本发明的优选方案,在所述步骤3中,在挖掘的过程中,从支干进入闸室下部时,支干与闸室净空突变处采用人工修整。其中净空突变处是指支干与闸室交界处,净空突变处施工量较小不易采用大型设备和爆破方式进行施工,采用人工修整施工能够提高施工精度,而且有利于确保施工安全。As a preferred solution of the present invention, in the step 3, in the process of excavation, when entering the lower part of the sluice chamber from the branch trunk, manual trimming is used for the sudden change of the clearance between the branch trunk and the sluice chamber. Among them, the sudden change of clearance refers to the junction of the branch trunk and the lock chamber. The construction volume at the sudden change of clearance is small, and it is difficult to use large-scale equipment and blasting for construction. The use of manual trimming construction can improve the construction accuracy and help ensure construction safety.

作为本发明的优选方案,在所述步骤3中,在支干底部设置连接杆,所述连接杆与闸室内的支撑架可拆卸式连接。具体的每个所述支撑架底部设有横杆,所述横杆两端分别与两个所述立柱连接,所述连接杆与所述横杆可拆卸式连接,更具体的,为了保证对闸室上部及中部设置的支撑架形成稳定支撑,每个所述支撑架下方设有两个所述连接杆,两个所述连接杆分别设置在所述闸室两侧。As a preferred solution of the present invention, in the step 3, a connecting rod is arranged at the bottom of the support trunk, and the connecting rod is detachably connected to the support frame in the lock chamber. Specifically, the bottom of each support frame is provided with a cross bar, the two ends of the cross bar are respectively connected with the two upright columns, and the connecting bar and the cross bar are detachably connected. The support frames arranged in the upper part and the middle part of the lock chamber form a stable support, two connecting rods are arranged under each support frame, and the two connecting rods are respectively arranged on both sides of the lock chamber.

综上所述,由于采用了上述技术方案,本发明的有益效果是:To sum up, due to the adoption of the above-mentioned technical solutions, the beneficial effects of the present invention are:

本发明一种小断面交通洞进瘦高异型空间结构引水闸室施工方法,施工过程中同时对隧洞的拱顶边墙位置进行初期支护,加强引水隧洞的结构强度,在施工闸室时由过渡段挑顶进入闸室上部,将整个闸室分割为上、中、下三个区域分别挖掘,闸室上部采用台阶法施工,从上到下逐步开挖,闸室中部采用分层分块法挖掘,在高度方向上将闸室中部分割成若干层,在每一层将闸室中部分割为若干区块,这样挖掘对周围的隧洞结构稳定影响较小,同时也便于观察每一层、每一块的地质情况,便于预防突发事件,提高了施工过程中的安全性,闸室的下部与支干贯通,最后施工支干使支干与闸室下部贯通,避免了因闸室下部强度不足而造成闸室坍塌等现象。The invention provides a construction method for a small-section traffic tunnel entering a diversion lock chamber with a thin, high and special-shaped space structure. During the construction process, initial support is performed on the position of the vault side wall of the tunnel to strengthen the structural strength of the water diversion tunnel. The transition section is lifted into the upper part of the lock chamber, and the entire lock chamber is divided into upper, middle and lower areas to be excavated respectively. The upper part of the lock chamber is constructed by the step method, which is gradually excavated from top to bottom, and the middle part of the lock chamber is divided into layers and blocks. The middle of the lock chamber is divided into several layers in the height direction, and the middle part of the lock chamber is divided into several blocks in each layer, so that the excavation has less influence on the stability of the surrounding tunnel structure, and it is also convenient to observe the characteristics of each layer, The geological conditions of each block are convenient for preventing emergencies and improving the safety during construction. Insufficient, resulting in the collapse of the lock chamber and other phenomena.

附图说明Description of drawings

图1是本发明一种小断面交通洞进瘦高异型空间结构引水闸室施工方法的施工流程图;Fig. 1 is the construction flow chart of a kind of construction method of the present invention that a small-section traffic tunnel enters a diversion lock chamber with a thin, high and special-shaped space structure;

图2为本发明所述的主干、支干、过渡段和闸室的布置图;Fig. 2 is the layout diagram of trunk, branch trunk, transition section and lock chamber according to the present invention;

图3为本发明所述的闸室和支干的位置关系图;Fig. 3 is the positional relationship diagram of the lock chamber and the branch trunk according to the present invention;

图4为本发明所述的分层分块施工示意图;4 is a schematic diagram of the layered and block construction according to the present invention;

图5为本发明所述的支撑架的结构示意图;Fig. 5 is the structural schematic diagram of the support frame of the present invention;

图6为发明所述步骤3的施工示意图;Fig. 6 is the construction schematic diagram of step 3 of the invention;

图中标记:1-主干,2-支干,3-闸室,31-挖掘层,311-挖掘快,4-过渡段,41-闸室接口,5-支撑架,51-弧形杆,52-立柱,53-横杆,54-连接杆,6-爆破孔。Marked in the figure: 1- main trunk, 2- branch trunk, 3- lock chamber, 31- excavation layer, 311- excavation fast, 4- transition section, 41- lock chamber interface, 5- support frame, 51- arc rod, 52-column, 53-crossbar, 54-connecting rod, 6-blasting hole.

具体实施方式Detailed ways

下面结合附图,对本发明作详细的说明。The present invention will be described in detail below with reference to the accompanying drawings.

为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明。In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention, but not to limit the present invention.

实施例1Example 1

如图1-图6所示,本发明一种小断面交通洞进瘦高异型空间结构引水闸室施工方法,其步骤如下:As shown in Fig. 1-Fig. 6, a construction method of a small-section traffic hole entering a diversion lock chamber with a thin, tall and special-shaped space structure of the present invention, the steps are as follows:

步骤1.1,优化过渡段形状:所述过渡段4上设有若干闸室接口41,所述闸室接口41的轴线垂直于闸室3侧壁设置,使得在过渡段4进入闸室3过程中也不需要转换掌子面,提高了施工效率。Step 1.1, optimize the shape of the transition section: the transition section 4 is provided with a number of lock chamber interfaces 41, and the axis of the lock chamber interface 41 is set perpendicular to the side wall of the lock chamber 3, so that in the process of the transition section 4 entering the lock chamber 3 There is also no need to convert the palm face, which improves the construction efficiency.

步骤1,施工过渡段:主干1挑顶施工过渡段4,主干1逐级挑高进入过渡段,对过渡段4的拱顶及边墙进行初期支护,过渡段4高于主干1,主干1挑顶进入过渡段4标高位置后,过渡段采用台阶法进行挖掘,所述台阶法为将待挖区域分层若干层,从上到下依次挖掘,其中主干1逐级挑高进入过渡段,避免了破坏过渡段4设计形状,从而避免了因过度开挖而造成的需要对过渡段4进行混凝土回填;Step 1, construction transition section: trunk 1 lifts the roof to construct transition section 4, trunk 1 is lifted step by step into the transition section, and the vault and side walls of transition section 4 are initially supported. Transition section 4 is higher than trunk 1, and the trunk 1. After the roof is lifted into the elevation position of the transition section 4, the transition section is excavated by the step method. The step method is to layer the area to be excavated into several layers and excavate sequentially from top to bottom, in which the trunk 1 is lifted step by step and enters the transition section. , to avoid damaging the design shape of the transition section 4, thereby avoiding the need for concrete backfilling of the transition section 4 caused by excessive excavation;

步骤2,施工闸室:过渡段4挑顶施工闸室3,过渡段4逐级挑高进入闸室3,对闸室3拱顶及边墙进行初期支护,闸室3上部采用台阶法施工,闸室3中部采用分层分块法施工,过渡段4逐级挑高进入闸室3,避免了破坏闸室3设计形状,从而避免了因过度开挖而造成的需要对闸室3进行混凝土回填;Step 2, construction of the lock chamber: the transition section 4 is lifted from the roof to construct the lock chamber 3, and the transition section 4 is lifted into the lock chamber 3 step by step, and the vault and side walls of the lock chamber 3 are initially supported. The upper part of the lock chamber 3 adopts the step method During the construction, the middle part of the lock chamber 3 is constructed by the layered and block method, and the transition section 4 is lifted into the lock chamber 3 step by step, so as to avoid damaging the design shape of the lock chamber 3, thus avoiding the need for the lock chamber 3 due to excessive excavation. Concrete backfill;

步骤3,开挖支干:平挑开挖支干2,使支干2贯通闸室3下部。Step 3, excavate the branch trunk: horizontally lift and excavate the branch trunk 2, so that the branch trunk 2 passes through the lower part of the lock chamber 3.

具体的,初期支护包括在拱顶及边墙上喷射混凝土,以及安装若干个支撑架5,若干所述支撑架沿隧洞的长度方向均匀布置,通过在隧洞的拱顶及边墙上喷射混凝土对隧洞进行加固,在过渡段4和闸室3的拱顶及边墙上喷射C20混凝土,厚度20cm,同时在隧洞内安装支撑架5对拱顶及边墙进行支撑,使隧洞在施工过程中能够保持足够的强度,以承受施工过程中的各种施工操作所带来的破坏力,其中支撑架5包括与拱顶形状适配的弧形杆51,所述弧形杆51两端分别设有立柱52,弧形杆51和两个立柱51连接形成门字形结构,使得支撑架5在隧洞内安装后能够与隧洞的拱顶和边墙紧靠,从而对隧洞的拱顶及边墙形成支撑;Specifically, the initial support includes spraying concrete on the vault and side walls, and installing a number of support frames 5, which are evenly arranged along the length of the tunnel, by spraying concrete on the vault and side walls of the tunnel Reinforce the tunnel, spray C20 concrete on the vault and side wall of transition section 4 and lock chamber 3, with a thickness of 20cm, and install support frame 5 in the tunnel to support the vault and side wall, so that the tunnel can be constructed during the construction process. It can maintain sufficient strength to withstand the destructive force caused by various construction operations during the construction process, wherein the support frame 5 includes an arc-shaped rod 51 that is adapted to the shape of the dome, and the two ends of the arc-shaped rod 51 are respectively provided. There are uprights 52, and the arc-shaped rod 51 and the two uprights 51 are connected to form a gate-shaped structure, so that the support frame 5 can abut against the vault and side walls of the tunnel after being installed in the tunnel, thereby forming the vault and side walls of the tunnel. support;

所述分层分块法包括:首先将闸室4中部沿闸室4高度方向分割为若干个挖掘层31,再将每一个挖掘层31分割为若干个挖掘块311,选择一个挖掘块311进行挖掘,再对其他挖掘块311依次进行挖掘,每次挖掘的高度与挖掘层31的高度相同,这样使得每一次施工对闸室周围结构影响较小,同时也便于观察每一挖掘块311、每一层挖掘层31的地质情况,能够预防突发事件,对于每一层的若干挖掘块311,其第一个开挖的挖掘块311采用垂向浅眼爆破,其他挖掘块采用预裂爆破,其中垂向浅眼爆破是指在爆破区域上端设置爆破孔进行爆破,预裂爆破是指从爆破区域侧壁上设置爆破孔进行爆破,在一个挖掘层31上的一个挖掘块311进行垂向浅眼爆破后形成台阶,再对该层挖掘层31的其他挖掘块311进行预裂爆破,这样减小爆破对隧洞周壁的扰动,提高了施工过程的安全性。The layered and block method includes: first, dividing the middle of the lock chamber 4 into several excavation layers 31 along the height direction of the lock chamber 4, and then dividing each excavation layer 31 into a number of excavation blocks 311, and selecting one excavation block 311 to carry out the process. Excavate, and then excavate the other excavation blocks 311 in sequence, and the height of each excavation is the same as the height of the excavation layer 31, so that each construction has less impact on the structure around the lock chamber, and it is also convenient to observe each excavation block 311, each The geological conditions of the first excavation layer 31 can prevent emergencies. For several excavation blocks 311 in each layer, the first excavated excavation block 311 is blasted with vertical shallow holes, and the other excavated blocks are blasted with pre-split blasting. Among them, vertical shallow hole blasting refers to setting blasting holes at the upper end of the blasting area for blasting, pre-split blasting refers to setting blasting holes on the side wall of the blasting area for blasting, and performing vertical shallow blasting at an excavation block 311 on an excavation layer 31 After the eye is blasted, a step is formed, and then the other excavation blocks 311 of the excavation layer 31 are pre-split and blasted, which reduces the disturbance of the blasting to the surrounding wall of the tunnel and improves the safety of the construction process.

进一步的,在所述步骤2中,在闸室3中部施工完成后,在闸室3中部侧壁上开设有注浆孔,并在注浆孔中设置注浆锚管,通过闸室3中部侧壁上的注浆孔向岩层中灌注浆液,以提高隧洞周壁的结构强度,为后面闸室3下部施工做准备,再进一步的,所述注浆孔斜向下设置,通过斜向下设置的注浆孔将浆液输送到闸室下部,使闸室下部的周围岩层得到加强,确保在闸室下部爆破施工的安全性。Further, in the step 2, after the construction in the middle part of the lock chamber 3 is completed, a grouting hole is opened on the side wall of the middle part of the lock chamber 3, and a grouting anchor pipe is set in the grouting hole, passing through the middle part of the lock chamber 3. The grouting holes on the side walls pour grout into the rock formation to improve the structural strength of the surrounding wall of the tunnel and prepare for the construction of the lower part of the sluice chamber 3. Further, the grouting holes are set obliquely downward. The grouting hole in the sluice chamber transports the slurry to the lower part of the sluice chamber, so that the surrounding rock formations in the lower part of the sluice chamber are strengthened, and the safety of blasting construction in the lower part of the sluice chamber is ensured.

进一步的,在所述步骤3中,在支干2进入闸室3下部施工中,支干底板、边墙、及拱顶均采用放大外插角爆破进行施工,其中放大外插角爆破是指在支干2进入闸室3时,在隧洞周壁上设置斜向隧洞外的爆破孔6进行爆破,由于闸室3下部的两侧边墙之间的间距较支干2的两侧边墙间距更大,并且闸室3底部也低于支干2底部,故采用放大外插角爆破进行施工能够减少后期的修正工作,提高施工效率。Further, in the step 3, in the construction of the lower part of the support stem 2 entering the lock chamber 3, the support stem bottom plate, the side wall, and the vault are all constructed by using magnified outside angle blasting, wherein the enlarged outside insert angle blasting refers to the construction. When the branch trunk 2 enters the lock chamber 3, blasting holes 6 are set on the peripheral wall of the tunnel obliquely to the outside of the tunnel for blasting. It is larger and the bottom of the lock chamber 3 is also lower than the bottom of the branch trunk 2, so the use of enlarged external angle blasting for construction can reduce the later correction work and improve the construction efficiency.

进一步的,在所述步骤3中,在挖掘的过程中,从支干2进入闸室3下部时,支干2与闸室3净空突变处采用人工修整,其中净空突变处是指支干2与闸室3交界处,净空突变处施工量较小不易采用大型设备和爆破方式进行施工,采用人工修整施工能够提高施工精度,而且有利于确保施工安全。Further, in the step 3, in the process of excavation, when entering the lower part of the lock chamber 3 from the branch trunk 2, manual trimming is adopted at the sudden change of clearance between the branch trunk 2 and the lock chamber 3, wherein the sudden change of clearance refers to the branch trunk 2. At the junction with lock chamber 3, the construction volume at the sudden change of clearance is small, and it is difficult to use large-scale equipment and blasting for construction. The use of manual trimming construction can improve construction accuracy and help ensure construction safety.

进一步的,在所述步骤3中,在支干2底部设置连接杆54,所述连接杆54与闸室3内的支撑架5可拆卸式连接,具体的每个所述支撑架5底部设有横杆53,所述横杆53两端分别与两个所述立柱52连接,所述连接杆54与所述横杆53可拆卸式连接,更具体的,为了保证对闸室5上部及中部设置的支撑架5形成稳定支撑,每个所述支撑架5下方设有两个所述连接杆54,两个所述连接杆54分别设置在所述闸室3两侧,在支干贯通闸室下部时,支撑架与连接杆连接,从而实现了支撑架的长度延伸,使支撑架能够在支干贯通闸室下部后依然起到支撑作用。Further, in the step 3, a connecting rod 54 is provided at the bottom of the support trunk 2, and the connecting rod 54 is detachably connected with the support frame 5 in the lock chamber 3. Specifically, the bottom of each support frame 5 is provided with There is a cross bar 53, the two ends of the cross bar 53 are respectively connected with the two uprights 52, and the connecting bar 54 is detachably connected with the cross bar 53. The supporting frame 5 arranged in the middle forms a stable support, and two connecting rods 54 are arranged under each supporting frame 5, and the two connecting rods 54 are respectively arranged on both sides of the lock chamber 3 and pass through the support trunk. When the lower part of the lock chamber is connected, the support frame is connected with the connecting rod, thereby realizing the extension of the length of the support frame, so that the support frame can still play a supporting role after the branch trunk penetrates through the lower part of the lock chamber.

本发明一种小断面交通洞进瘦高异型空间结构引水闸室施工方法,施工过程中同时对隧洞的拱顶边墙位置进行初期支护,加强引水隧洞的结构强度,在施工闸室3时由过渡段挑4顶进入闸室3上部,将整个闸室3分割为上、中、下三个区域分别挖掘,闸室3上部采用台阶法施工,从上到下逐步开挖,闸室中部采用分层分块法挖掘,在高度方向上将闸室3中部分割成若干层,在每一层将闸室中部分割为若干区块,这样挖掘对周围的隧洞结构稳定影响较小,同时也便于观察每一层、每一块的地质情况,便于预防突发事件,提高了施工过程中的安全性,闸室3的下部与支干2贯通,最后施工支干2使支干2与闸室3下部贯通,避免了因闸室3下部强度不足而造成闸室3坍塌等现象。The invention provides a construction method for a small-section traffic tunnel entering a diversion lock chamber with a thin, high and special-shaped space structure. During the construction process, the position of the vault side wall of the tunnel is initially supported to strengthen the structural strength of the water diversion tunnel. The top of the sluice chamber 3 is lifted into the upper part of the sluice chamber 3 from the transition section, and the entire sluice chamber 3 is divided into upper, middle and lower areas for excavation respectively. The layered and block method is used for excavation, and the middle of the lock chamber 3 is divided into several layers in the height direction, and the middle of the lock chamber is divided into several blocks at each layer, so that the excavation has less influence on the stability of the surrounding tunnel structure, and also It is convenient to observe the geological conditions of each layer and each block, to prevent emergencies, and to improve the safety in the construction process. The lower part of 3 is penetrated to avoid the collapse of the lock chamber 3 due to insufficient strength of the lower part of the lock chamber 3 .

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention shall be included in the protection of the present invention. within the range.

Claims (10)

1.一种小断面交通洞进瘦高异型空间结构引水闸室施工方法,其特征在于,包括:1. a small-section traffic hole into a thin, high and special-shaped space structure diversion lock chamber construction method, is characterized in that, comprises: 步骤1,施工过渡段:主干(1)挑顶施工过渡段(4),对过渡段(4)的拱顶及边墙进行初期支护;Step 1, construction transition section: the trunk (1) lifts the roof to construct the transition section (4), and performs initial support for the vault and side walls of the transition section (4); 步骤2,施工闸室:过渡段(4)挑顶施工闸室(3),对闸室(3)拱顶及边墙进行初期支护,闸室(3)上部采用台阶法施工,闸室(3)中部采用分层分块法施工;Step 2. Construction of the sluice chamber: the transition section (4) lifts the roof to construct the sluice chamber (3), and the dome and side walls of the sluice chamber (3) are initially supported. The upper part of the sluice chamber (3) is constructed by the step method. (3) The middle part is constructed by layered and block method; 步骤3,开挖支干:平挑开挖支干(2),使支干(2)贯通闸室(3)下部。Step 3, excavate the branch trunk: excavate the branch trunk (2) horizontally, so that the branch trunk (2) penetrates the lower part of the lock chamber (3). 2.根据权利要求1所述的小断面交通洞进瘦高异型空间结构引水闸室施工方法,其特征在于,所述步骤1还包括步骤1.1,优化过渡段形状:所述过渡段(4)上设有若干闸室接口(41),所述闸室接口(41)的轴线垂直于闸室(3)侧壁设置。2. The method for constructing a small-section traffic tunnel into a diversion lock chamber with a thin, high, and special-shaped space structure according to claim 1, wherein the step 1 further comprises a step 1.1, optimizing the shape of the transition section: the transition section (4) A plurality of lock chamber interfaces (41) are arranged thereon, and the axes of the lock chamber interfaces (41) are arranged perpendicular to the side walls of the lock chamber (3). 3.根据权利要求1所述的小断面交通洞进瘦高异型空间结构引水闸室施工方法,其特征在于,所述初期支护包括在拱顶及边墙上喷射混凝土,以及安装若干个支撑架(5)。3. The construction method for the diversion lock chamber of a small-section traffic hole entering a thin, high and special-shaped space structure according to claim 1, wherein the initial support comprises spraying concrete on the dome and the side wall, and installing several supports rack (5). 4.根据权利要求3所述的小断面交通洞进瘦高异型空间结构引水闸室施工方法,其特征在于,所述支撑架(5)包括与拱顶形状适配的弧形杆(51),所述弧形杆(51)两端分别设有立柱(52)。4. The method for constructing a small-section traffic hole into a diversion lock chamber with a thin, high and special-shaped space structure according to claim 3, wherein the support frame (5) comprises an arc-shaped rod (51) adapted to the shape of the vault , the two ends of the arc rod (51) are respectively provided with uprights (52). 5.根据权利要求1所述的小断面交通洞进瘦高异型空间结构引水闸室施工方法,其特征在于,所述分层分块法包括:首先将闸室(3)中部沿闸室(3)高度方向分割为若干个挖掘层(31),再将每一个挖掘层(31)分割为若干个挖掘块(311),选择一个挖掘块(311)进行挖掘,再对其他挖掘块(311)依次进行挖掘,每次挖掘的高度与挖掘层(31)的高度相同。5. The method for constructing a small-section traffic tunnel into a diversion lock chamber with a thin, tall, and special-shaped space structure according to claim 1, wherein the layered and block method comprises: first, placing the middle part of the lock chamber (3) along the lock chamber (3). 3) The height direction is divided into several mining layers (31), and then each mining layer (31) is divided into several mining blocks (311), one mining block (311) is selected for mining, and other mining blocks (311) are selected for mining. ) are excavated in sequence, and the height of each excavation is the same as the height of the excavation layer (31). 6.根据权利要求5所述的小断面交通洞进瘦高异型空间结构引水闸室施工方法,其特征在于,对于每一层的若干挖掘块(311),其第一个开挖的挖掘块(311)采用垂向浅眼爆破,其他挖掘块(311)采用预裂爆破。6. The method for constructing a small-section traffic hole into a diversion lock chamber with a thin, tall, and special-shaped space structure according to claim 5, characterized in that, for several excavated blocks (311) on each floor, the first excavated excavated block (311) adopts vertical shallow hole blasting, and other excavation blocks (311) adopt pre-split blasting. 7.根据权利要求1-6任一所述的小断面交通洞进瘦高异型空间结构引水闸室施工方法,其特征在于,在所述步骤2中,在闸室(3)中部施工完成后,在闸室(3)中部侧壁上开设有注浆孔,并在注浆孔中设置注浆锚管。7. The method for constructing a small-section traffic hole into a diversion lock chamber with a thin, tall, and special-shaped space structure according to any one of claims 1-6, characterized in that, in the step 2, after the construction in the middle of the lock chamber (3) is completed , a grouting hole is opened on the side wall of the middle part of the lock chamber (3), and a grouting anchor pipe is arranged in the grouting hole. 8.根据权利要求1-6任一所述的小断面交通洞进瘦高异型空间结构引水闸室施工方法,其特征在于,在所述步骤3中,在支干(2)进入闸室(3)下部施工中,支干(2)底板、边墙、及拱顶均采用放大外插角爆破进行施工。8. The construction method for a small-section traffic hole entering a diversion lock chamber with a thin, tall and special-shaped space structure according to any one of claims 1-6, wherein in the step 3, the branch trunk (2) enters the lock chamber ( 3) In the construction of the lower part, the bottom plate, side wall, and vault of the support trunk (2) are all constructed by blasting with enlarged external angle. 9.根据权利要求1-6任一所述的小断面交通洞进瘦高异型空间结构引水闸室施工方法,其特征在于,在所述步骤3中,在挖掘的过程中,从支干(2)进入闸室(3)下部时,支干(2)与闸室(3)净空突变处采用人工修整。9. The construction method for a small-section traffic hole entering a diversion lock chamber with a thin, tall and special-shaped space structure according to any one of claims 1-6, wherein in the step 3, in the process of excavation, from the branch trunk ( 2) When entering the lower part of the lock chamber (3), manual trimming is used for the sudden change of clearance between the branch trunk (2) and the lock chamber (3). 10.根据权利要求1-6任一所述的小断面交通洞进瘦高异型空间结构引水闸室施工方法,其特征在于,在所述步骤3中,在支干(2)底部设置连接杆(54),所述连接杆(54)与闸室(3)内的支撑架(5)可拆卸式连接。10. The construction method for a small-section traffic hole entering a diversion lock chamber with a thin, high and special-shaped space structure according to any one of claims 1-6, wherein in the step 3, a connecting rod is arranged at the bottom of the branch trunk (2). (54), the connecting rod (54) is detachably connected with the support frame (5) in the lock chamber (3).
CN202010737662.2A 2020-07-28 2020-07-28 A construction method for a small-section traffic tunnel entering a diversion lock chamber with a thin, tall and special-shaped space structure Active CN111828050B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010737662.2A CN111828050B (en) 2020-07-28 2020-07-28 A construction method for a small-section traffic tunnel entering a diversion lock chamber with a thin, tall and special-shaped space structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010737662.2A CN111828050B (en) 2020-07-28 2020-07-28 A construction method for a small-section traffic tunnel entering a diversion lock chamber with a thin, tall and special-shaped space structure

Publications (2)

Publication Number Publication Date
CN111828050A CN111828050A (en) 2020-10-27
CN111828050B true CN111828050B (en) 2022-04-08

Family

ID=72926446

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010737662.2A Active CN111828050B (en) 2020-07-28 2020-07-28 A construction method for a small-section traffic tunnel entering a diversion lock chamber with a thin, tall and special-shaped space structure

Country Status (1)

Country Link
CN (1) CN111828050B (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677892A (en) * 2018-07-27 2018-10-19 中国电建集团成都勘测设计研究院有限公司 Diversion tunnel working tunnel is used as reconstruction structure of the ecology for water hole
CN111236240A (en) * 2020-01-13 2020-06-05 中国水利水电第七工程局有限公司 Narrow rock wall crane beam excavation method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677892A (en) * 2018-07-27 2018-10-19 中国电建集团成都勘测设计研究院有限公司 Diversion tunnel working tunnel is used as reconstruction structure of the ecology for water hole
CN111236240A (en) * 2020-01-13 2020-06-05 中国水利水电第七工程局有限公司 Narrow rock wall crane beam excavation method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
乌东德泄洪洞工作闸室变形稳定分析及加固处理;康旭升等;《中国水利》;20171231;第78-81、95页 *
瀑布沟水电站地下厂房三大洞室开挖分层及施工程序;胡金志等;《四川水力发电》;20070815;第26卷(第4期);第26-30、41页 *

Also Published As

Publication number Publication date
CN111828050A (en) 2020-10-27

Similar Documents

Publication Publication Date Title
CN111188629B (en) Construction method for sudden change of tunnel bifurcation section and expanding excavation
CN108278115A (en) A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop
CN204729099U (en) Rock quality layer tunneling three layers of subway station canopy structure
CN103615273A (en) Square steel confined concrete arch center wall back filling bolting-grouting support system and construction method
CN112443331B (en) Disturbance sensitive stratum ultra-small clear distance large section group-hole parallel subway tunnel construction method
CN103982188A (en) Supporting structure system of rock stratum large-section deep vertical shaft and construction method of supporting structure system
CN207892615U (en) A kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop
CN110004981A (en) A composite assembled underground structure and reverse construction method
CN109779653B (en) Construction method for crossing of soft rock large-section tunnel
CN112302686B (en) Vertical jacking construction method for entering tunnel inclined shaft into main tunnel
CN109594995B (en) Weak surrounding rock tunnel perturbation motive machinery subsection tunneling construction method
CN111810184A (en) A kind of variable section tunnel construction method
CN114382106B (en) A construction method for a high-drop pipe well concrete structure with pipelines laid inside
CN111828050B (en) A construction method for a small-section traffic tunnel entering a diversion lock chamber with a thin, tall and special-shaped space structure
CN207761667U (en) A kind of supporting construction for tunnel reconstruction and extension project
CN112942374A (en) Open-cut and hidden-support foundation pit supporting structure and construction method thereof
CN112302687A (en) Support-changing and jacking construction method for entering main tunnel of tunnel inclined shaft
CN205636749U (en) A excavation supporting system for sandy gravel boulder geological stratification
CN111852502B (en) Conversion structure between double-layer TBM tunnel and single-layer TBM tunnel and its construction method
CN112081176A (en) Pressure-bearing water layer vertical shaft construction method based on non-dewatering drainage
CN112647978A (en) Construction method for leading small pilot tunnel of soft rock large-deformation tunnel
CN112282771A (en) Rapid construction method for super-large-span highway tunnel
CN218786853U (en) Underground excavation pile foundation underpinning system with closely-adhered lower penetrating existing structure
CN211038640U (en) Loess tunnel three-step excavation construction structure
CN119434833B (en) A mechanized construction method for underground passages in complex strata

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20241015

Address after: 550007 Jinpeng Building, No. 3, Sitong Street, Nanming District, Guiyang City, Guizhou Province

Patentee after: CHINA RAILWAY ERJU 1ST ENGINEERING Co.,Ltd.

Country or region after: China

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee before: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right