CN108278115A - A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop - Google Patents

A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop Download PDF

Info

Publication number
CN108278115A
CN108278115A CN201711054349.3A CN201711054349A CN108278115A CN 108278115 A CN108278115 A CN 108278115A CN 201711054349 A CN201711054349 A CN 201711054349A CN 108278115 A CN108278115 A CN 108278115A
Authority
CN
China
Prior art keywords
tunnel
arch
steel
arch springing
big
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711054349.3A
Other languages
Chinese (zh)
Inventor
雷明锋
陈家旺
施成华
林大涌
曹豪荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Original Assignee
Central South University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University filed Critical Central South University
Priority to CN201711054349.3A priority Critical patent/CN108278115A/en
Publication of CN108278115A publication Critical patent/CN108278115A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop, apply short tube canopy, with advance reinforcement and supporting front of tunnel heading country rock by tunnel construction with no workroom technology in hole respectively;With the big arch springing of setting at every level-one step base;Under above-mentioned double control measure, three steps of tunnel cross section point excavate successively, and detailed process is:First short barrel vault advanced support is applied along a certain range of tunnel arch;It is wrong away from upper, middle and lower step is excavated successively, preliminary bracing is applied immediately after the completion of each bench excavation, and big arch springing pattern is designed as at preliminary bracing footing;When getting out of a predicament or an embarrassing situation with previous 1 times of hole diameter of circulation secondary lining cutting distance, inverted arch, abutment wall, filled layer and secondary lining are applied.The present invention not only solves the problem of tunnel deformation control hardly possible under the conditions of Shallow-Buried Soft Rock, while also overcoming the shortcomings of conventional construction method branch under square one is more, process is numerous, construction is slow, gib is more.

Description

A kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop and Structure
Technical field
The present invention relates to constructing tunnel field, more particularly to a kind of three step tunnel of big arch springing based on pre-timbering with tubular prop is fast Fast construction method and structure.
Background technology
In recent years, there are more and more Tunnel Engineering in greatly developing with China's infrastructure construction.At some It passes through in the shallow tunnel of weak surrounding rock, preliminary bracing strain cracking is invaded the limit even large deformation problems such as collapse and cave-in and seen repeatly not It is fresh, the construction safety and progress in tunnel are seriously affected, to increase project cost.
For the above situation, the generation of large deformation disaster in order to prevent is adopted mostly both at home and abroad at present with ensureing construction safety It is that the complicated partial excavation method of various processes is constructed, wherein most commonly seen with CRD methods and two side-wall pilot tunnel. Although such construction method is more apparent for the effect for controlling ground settlement, due to its working procedure is numerous, each portion constructs phase It mutually interferes that larger, speed of application is slow, causes the closing time of entire excavated section long, be unfavorable for controlling tunnel to a certain extent Deformation, while gib dosage is big, increases engineering cost.
Therefore, tunnel deformation how is efficiently controlled, while ensureing the rapid construction in tunnel, is currently urgently to be resolved hurrily ask Topic.
Invention content
The technical problem to be solved by the present invention is to be the deficiency for above-mentioned construction method, providing one kind can control Tunnel deformation ensures construction safety, and can accelerate construction progress the method for tunnel construction and structure for reducing construction cost.
In order to solve the above technical problem, the present invention provides a kind of, and the three step tunnel of big arch springing based on pre-timbering with tubular prop is fast Fast construction method and structure apply short tube canopy, with advance reinforcement and supporting area by tunnel construction with no workroom technology in hole Square country rock in front, by the way that big arch springing is arranged at every level-one step base, to increase substrate-loading area, to reduce tunnel knot Structure and surrouding rock deformation;Under above-mentioned double control measure, three steps of tunnel cross section point excavate successively.
In order to achieve the above technical purposes, the technical scheme is that,
A kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop, includes the following steps:
Mistake before tunnel excavation, applies short tube canopy to three steps of tunnel cross section point along tunnel arch first away from excavation successively Advance support;Then wrong successively to be recycled as one away from excavation upper, middle and lower step, and each step in a cycle is opened Corresponding preliminary bracing is applied immediately after the completion of digging, and big arch springing type is set as at the footing of preliminary bracing;When under secondary cycle excavation When step and the secondary lining distance of previous cycle are 1 times of hole diameter, inverted arch, abutment wall, filled layer and secondary lining are applied.
A kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop, the short tube canopy are super Preceding supporting is made of using tunnel construction with no workroom in hole, the short tube canopy the steel pipe of more diameter 75mm, long 6~8m, Part of the steel pipe in being deep into country rock is equipped with for setting the aperture for finishing grouting behind shaft or drift lining in short tube boron steel pipe, in tunnel cross section On, steel pipe is evenly arranged in the spacing of 0.3~0.8m within the scope of 120 °~180 ° of tunnel arch, in tunnel profile direction On, steel pipe is inserted upwardly into front of tunnel heading country rock with 6 °~8 ° of oblique cutting angle, and longitudinal lap joint length is 1~2m.
A kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop, it is short in work progress Pipe canopy by 6 °~8 ° oblique cutting angles and pipe canopy by designing the 1m long that spacing is embedded in advance in the gunite concrete of previous cycle Guide pipe reach the last necromancer body, to realize tunnel construction with no workroom in hole.
A kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop, the preliminary bracing Include the system anchor bolt radially squeezed into country rock along tunnel, the bar-mat reinforcement that hang on tunnel arch, erected along tunnel cross section Steel arch-shelf, the lock foot anchoring stock squeezed into country rock and be supported on steel arch-shelf bottom, the big arch springing being arranged at steel arch-shelf bottom and It sprays in the gunite concrete of tunnel arch.
A kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop, the big arch springing are The triangle being welded by I-steel, the bottom edge of big arch springing and the bevel edge by country rock side weld on I-steel again respectively The steel plate of 1.6cm thickness 0.5m wide, bottom edge steel plate is vertical with the contour line of tunnel excavation, when the substrate of any step enters basement rock When, then cancel big arch springing.
A kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop, upper, middle and lower step point The 1/3 of tunnel cross section is not accounted for, and mutually wrong away from 5m~1 times hole diameter, each cyclic advance is 1~1.5m.
A kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop, including short barrel vault advanced support knot Structure, upper, middle and lower step, preliminary bracing structure, inverted arch, abutment wall, filled layer and the secondary lining for constituting tunnel excavation part;
Tunnel arch of the short barrel vault advanced support structure setting before tunnel excavation part is with to tunnel excavation Part forms protection, the described upper, middle and lower step respectively it is wrong away from;The preliminary bracing structure is respectively arranged at upper, middle and lower The tunnel arch of stepped locations;Inverted arch, abutment wall, filled layer and secondary lining are respectively arranged at top, the side that part is completed in tunnel Wall, bottom;
Preliminary bracing structure includes the system anchor bolt radially squeezed into country rock along tunnel, hang on the reinforcing bar of tunnel arch Net, along tunnel cross section erect steel arch-shelf, squeeze into country rock and be supported on steel arch-shelf bottom lock foot anchoring stock, be arranged in steel Big arch springing and injection at arch bottom is in the gunite concrete of tunnel arch.
A kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop, the short tube canopy are super Preceding supporting construction includes the steel pipe composition of more diameter 75mm, long 6~8m, and part of the steel pipe in being deep into country rock is equipped with and is used for The aperture for finishing grouting behind shaft or drift lining is set in short tube boron steel pipe, on tunnel cross section, steel pipe is evenly arranged with the spacing of 0.3~0.8m Within the scope of 120 °~180 ° of tunnel arch, on tunnel profile direction, steel pipe is inserted upwardly into the palm with 6 °~8 ° of oblique cutting angle Square country rock in face of son, longitudinal lap joint length are 1~2m.
A kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop, the upper, middle and lower Step accounts for the 1/3 of tunnel cross section respectively, and mutually mistake is away from 5m~1 times hole diameter, and excavates upper, middle and lower platform when tunnel excavation successively Rank recycles as one, and each cyclic advance is 1~1.5m.
A kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop, the big arch springing are The triangle being welded by I-steel, the bottom edge of big arch springing and the bevel edge by country rock side weld on I-steel again respectively The steel plate of 1.6cm thickness 0.5m wide, bottom edge steel plate is vertical with the contour line of tunnel excavation, when the substrate of any step enters basement rock When, then it is not provided with big arch springing.
The technical effects of the invention are that:
(1) traditional Pipe Roofing Construction Technology needs to dig 0.6~0.8m to outer diameter to form pipe canopy work along tunnel contour line Make room, although being conducive to the construction of large scale piperoof, since the excavation area of tunnel cross-section expands, not only further releases and enclose Rock pressure power leads to place's stress concentration of caunching, and also adds the quantities such as the cubic metre of earth and stone, preliminary bracing to extend construction work Phase causes engineering cost to increase.The present invention considers the advanced drilling depth length of top bar and builder's staging height in construction, rationally Ground devises pipe canopy length and the outer limb of pipe canopy, and the conventional operating rooms Guan Peng are eliminated by pre-buried guide pipe, realize no work Make the safely and fast construction of pipe canopy when the condition of room.
(2) traditional partial excavation construction method leads to initial stage in work progress due to having carried out piecemeal to tunnel cross-section Supporting cannot close in time cyclization and reach best supporting effect, thus arch preliminary bracing structure just must by its two The reaction of bearing of side ground ensures stable structure.For traditional partial excavation construction method since piecemeal is more, pressure from surrounding rock is primary Property discharges smaller, therefore big arch springing structure is not designed specially, but in practice of construction, due to the actual bearing capacity of tunnel surrounding It is poor, often it can all cause tunnel the problem of Deformation control hardly possible occur to a certain extent.The present invention is by being arranged the big arch springing in both sides Structure increases the contact area of arch springing and ground, has disperseed the load that preliminary bracing structure is transferred to arch springing ground, to control Structure and surrouding rock deformation play crucial effect.
(3) traditional partial excavation construction method branch is more, process is numerous, construction is slow, gib is more.It is opened between each branch The conversion of excavation method and the allotment of equipment have significantly delayed construction speed, gib are usually provided between branch, not only Quantities is increased, while the Secondary Disturbance of country rock can be increased in removing temporary supports, is unfavorable for the stabilization of country rock and structure.This hair Three bench excavation methods of bright offer are equally applicable to Shallow-Buried Soft Rock location, pass through above-mentioned tunnel construction with no workroom technology And the big arch springing structure of setting, the deformation of country rock and structure has been efficiently controlled, construction safety has been ensure that, substantially reduces simultaneously Construction period simultaneously reduces gib dosage, improves project benefit.
In conclusion the present invention can quickly and easily carry out barrel vault advanced support and the construction of big arch springing, largely On control the deformation of tunnel top and the sedimentation of earth's surface, can solve that branch existing for existing traditional construction engineering method is more, process The problems such as numerous, construction is slowly, gib is more, there is higher social and economic benefit.
Invention is further explained with example below in conjunction with the accompanying drawings.
Description of the drawings
Fig. 1 is rapid constructing method three-dimensional provided by the present invention construction step schematic diagram.
Fig. 2 is that the cross-section surface construction of rapid constructing method provided by the present invention walks schematic diagram.
Fig. 3 is rapid constructing method vertical section provided by the present invention construction step schematic diagram.
Fig. 4 is tunnel construction with no workroom installation diagram of the present invention.
Fig. 5 is the big arch springing structural schematic diagram of substrate in preliminary bracing of the present invention.
In figure:100,200 and 300 be tunnel partial excavation each section, wherein 100 be top bar, 200 be middle step, 300 be to get out of a predicament or an embarrassing situation.
1 is pipe canopy guide pipe.
2 be leading pre-supporting short tube canopy.
301,302 be respectively the radial anchor pole of exponent part and middle step part tunnel peripheral wall of appearing on the stage.
401,402,403 be respectively the bar-mat reinforcement for excavating and being hung after upper, middle and lower step part.
501,502,503 be respectively the steel arch-shelf for excavating and being erected after upper, middle and lower step part.
601,602 be respectively steel arch-shelf 501 and 502 big arch springing structure.
701,702 be respectively steel arch-shelf 501 and the lock foot anchoring stock (bar) that 502 bottoms are welded.
801,802,803 be respectively upper, middle and lower step part gunite concrete preliminary bracing.
901 it is inverted arch and abutment wall, 902 is secondary lining.
10 be tunnel bottom Concrete Filled layer.
11 be the I20b I-steel diagonal braces close to country rock side in big arch springing structure.
12 be the lateral steel plate that size is 50*50*1.6cm in big arch springing structure.
13 be the I20b I-steel stulls close to country rock bottom in big arch springing structure.
14 be the bottom steel plate that size is 100*50*1.6cm in big arch springing structure.
Specific implementation mode
The method of the present embodiment includes the following steps:Mistake is away from excavation successively for three steps of tunnel cross section point, in tunnel excavation Before, first short barrel vault advanced support is applied along tunnel arch;It is then wrong successively to be recycled as one away from excavation upper, middle and lower step, And corresponding preliminary bracing is applied immediately after the completion of each bench excavation in a cycle, it is set as at the footing of preliminary bracing Big arch springing type.Due to dividing bench excavation, the top bar excavation that excavates and get out of a predicament or an embarrassing situation is completed, and after erecting steel arch-shelf, is existed Footing.When it is secondary cycle excavate get out of a predicament or an embarrassing situation with the secondary lining of previous cycle distance be 1 times of hole diameter when, apply inverted arch, abutment wall, fill out Fill layer and secondary lining.
Short barrel vault advanced support is using tunnel construction with no workroom in hole, and short tube canopy is by more diameter 75mm, long 6~8m Steel pipe form, part of the steel pipe in being deep into country rock be equipped with for setting the aperture for finishing grouting behind shaft or drift lining in short tube boron steel pipe, On tunnel cross section, steel pipe is evenly arranged in the spacing of 0.3~0.8m within the scope of 120 °~180 ° of tunnel arch, vertical in tunnel On section direction, steel pipe is inserted upwardly into front of tunnel heading country rock with 6 °~8 ° of oblique cutting angle, and longitudinal lap joint length is 1~2m.
In work progress, short tube canopy by pressing 6 °~8 ° oblique cutting angles and pipe in advance in the gunite concrete of previous cycle The guide pipe of the 1m long of canopy design spacing embedment is reached the last necromancer body, to realize tunnel construction with no workroom in hole.Existing hole Interior tunnel construction with no workroom is required to carry out a small amount of dig.And the present embodiment passes through the guiding in the previous pre-buried 1m long of cycle Pipe squeezes into Guan Peng, realizes without the pipe roof construction under the premise of any dig.
Preliminary bracing in the present embodiment includes the system anchor bolt radially squeezed into country rock along tunnel, hang on tunnel arch Bar-mat reinforcement, along tunnel cross section erect steel arch-shelf, squeeze into country rock and be supported on steel arch-shelf bottom lock foot anchoring stock, set It sets the big arch springing at steel arch-shelf bottom and sprays in the gunite concrete of tunnel arch.Wherein big arch springing is to be welded by I-steel Made of triangle, be welded by I-steel identical with steel arch-shelf, the bottom edge of big arch springing and by country rock side bevel edge distinguish The steel plate that 1.6cm thickness 0.5m wide is welded on I-steel again is built up one's resistance to disease with increasing the forced area of substrate and country rock side, Reduce Supporting Structure deformation.Its insole binding steel plate is vertical with the contour line of tunnel excavation, when the substrate of any step enters basement rock When, then cancel big arch springing.Wherein substrate, that is, footing position, that is, refer to the foundation position of steel arch-shelf erection.
In the present embodiment, upper, middle and lower step accounts for the 1/3 of tunnel cross section respectively, and mutually mistake is away from 5m~1 times hole diameter, often One cyclic advance is 1~1.5m.
Three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop in the present embodiment, including short tube canopy are advanced Supporting construction, upper, middle and lower step, preliminary bracing structure, inverted arch, abutment wall, filled layer and the secondary lining for constituting tunnel excavation part It builds;
Tunnel arch of the short barrel vault advanced support structure setting before tunnel excavation part is with to tunnel excavation part shape At protection, upper, middle and lower step respectively it is wrong away from;Preliminary bracing structure is respectively arranged at the tunnel arch of upper, middle and lower stepped locations; Inverted arch, abutment wall, filled layer and secondary lining are respectively arranged at top, side wall, the bottom that part is completed in tunnel;
Preliminary bracing structure includes the system anchor bolt radially squeezed into country rock along tunnel, hang on the reinforcing bar of tunnel arch Net, along tunnel cross section erect steel arch-shelf, squeeze into country rock and be supported on steel arch-shelf bottom lock foot anchoring stock, be arranged in steel Big arch springing and injection at arch bottom is in the gunite concrete of tunnel arch.
Short barrel vault advanced support structure includes the steel pipe composition of more diameter 75mm, long 6~8m, steel in the present embodiment structure Part of the pipe in being deep into country rock is equipped with for setting the aperture for finishing grouting behind shaft or drift lining in short tube boron steel pipe, in tunnel cross section On, steel pipe is evenly arranged in the spacing of 0.3~0.8m within the scope of 120 °~180 ° of tunnel arch, in tunnel profile direction On, steel pipe is inserted upwardly into front of tunnel heading country rock with 6 °~8 ° of oblique cutting angle, and longitudinal lap joint length is 1~2m.
In the present embodiment structure, upper, middle and lower step accounts for the 1/3 of tunnel cross section respectively, and mutually mistake is away from 5m~1 times hole Diameter, and excavate upper, middle and lower step when tunnel excavation successively and recycled as one, each cyclic advance is 1~1.5m.
In the present embodiment structure, big arch springing is the triangle being welded by I-steel, the bottom edge of big arch springing and leans on country rock The bevel edge of side welds the steel plate of 1.6cm thickness 0.5m wide on I-steel again respectively, to increase the forced area of substrate and country rock side, It builds up one's resistance to disease, reduces Supporting Structure deformation.Bottom edge steel plate is vertical with the contour line of tunnel excavation, when any step substrate into When entering basement rock, then big arch springing is not provided with.
This method applies short tube canopy using tunnel construction with no workroom technology in hole, before advance reinforcement and supporting face Square country rock;By the way that big arch springing is arranged at every level-one step base, to increase substrate-loading area, to reduce tunnel structure with Surrouding rock deformation.Under above-mentioned deformation-controlling measures, three steps of tunnel cross section point excavate successively, and Specific construction process is:Along tunnel Short barrel vault advanced support is applied in a certain range of road arch;Wrong away from upper, middle and lower step is excavated successively, each bench excavation is completed It applies preliminary bracing immediately afterwards, big arch springing pattern is designed as at preliminary bracing footing;Get out of a predicament or an embarrassing situation with previous circulation secondary lining cutting away from When from 1 times of hole diameter, inverted arch, abutment wall, filled layer and secondary lining are applied.
For this example in Specific construction, used steps are as follows:
(1) referring to Fig. 1, Fig. 2, Fig. 3, before carrying out tunnel excavation construction, according to the transverse shape of Tunnel Design, by tunnel Entire cross section be divided into the part of upper, middle and lower three, each partly account for about 1/3 or so of entire tunnel cross section.
(2) referring to Fig. 4, by the previous jacking construction for recycling the guide pipe 1 applied and carrying out pre support short tube canopy 2, then Grouting and reinforcing is carried out, and applies subsequent cycle guide pipe.Guide pipe 1, pipe canopy 2 and the angle of horizontal plane are 8 °.
(3) excavation of top bar 100 is carried out, immediately first pneumatically placed concrete, then with the circumferential spacing Vertical tunnel of 0.6m week Wall squeezes into the system anchor bolt 301 of long 4m, Φ 22, and in tunnel, peripheral wall hangs bar-mat reinforcement 401, erects exponent part steel arch-shelf 501 of appearing on the stage, Lock foot anchoring stock 601 and big arch springing structure 701 at the arch springing of both sides are applied, multiple pneumatically placed concrete to design thickness forms complete initial stage branch Shield 801.Big arch springing structure is referring to Fig. 5, wherein 11,13 be respectively I20b I-steel diagonal brace and stull, 12,14 be respectively 1.6cm The steel plate of thick 0.5m wide.
(4) top bar 100 excavate 5m after, the excavation of step 200 in progress, immediately just pneumatically placed concrete, then with 0.6m's Circumferential spacing Vertical tunnel peripheral wall squeezes into the system anchor bolt 302 of long 4m, Φ 22, and in tunnel, peripheral wall hangs bar-mat reinforcement 402, in erection Step steel arch-shelf 502 is simultaneously welded with top bar steel arch-shelf 501, applies lock foot anchoring stock 602 and big arch springing steel construction at the arch springing of both sides 702, multiple pneumatically placed concrete to design thickness forms complete preliminary bracing 802.
(5) after step 200 excavates 5m in, get out of a predicament or an embarrassing situation 300 excavation, first pneumatically placed concrete immediately, then in tunnel week Wall hanging sets bar-mat reinforcement 403, step steel arch-shelf 503 and is welded with middle step steel arch-shelf 502 in erection, and multiple pneumatically placed concrete is to designing Thickness forms complete preliminary bracing 803.
(6) inverted arch, abutment wall 901 are applied, after inverted arch concrete initial set, it is high to design that placing inverted arch fills layer concrete 10 Degree.
(7) secondary lining 902 is applied.
(8) after completing entire construction cycle, the construction of subsequent cycle is carried out until the construction of Shallow-Buried Soft Rock section finishes.

Claims (10)

1. a kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop, which is characterized in that including following step Suddenly:
Before tunnel excavation, it is advanced to apply short tube canopy away from excavation to three steps of tunnel cross section point along tunnel arch first for mistake successively Supporting;Then wrong successively to be recycled as one away from excavation upper, middle and lower step, and each bench excavation in a cycle is complete It applies corresponding preliminary bracing immediately after, big arch springing type is set as at the footing of preliminary bracing;When what secondary cycle was excavated gets out of a predicament or an embarrassing situation When secondary lining distance with previous cycle is 1 times of hole diameter, inverted arch, abutment wall, filled layer and secondary lining are applied.
2. a kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop according to claim 1, It is characterized in that, the short barrel vault advanced support is using tunnel construction with no workroom in hole, and the short tube canopy is by more diameters The steel pipe composition of 75mm, long 6~8m, steel pipe are equipped in the part in being deep into country rock for after short tube boron steel pipe is set The aperture of slip casting, on tunnel cross section, steel pipe is evenly arranged in 120 °~180 ° of tunnel arch model with the spacing of 0.3~0.8m In enclosing, on tunnel profile direction, steel pipe is inserted upwardly into front of tunnel heading country rock with 6 °~8 ° of oblique cutting angle, and longitudinal lap joint is long Degree is 1~2m.
3. a kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop according to claim 2, Be characterized in that, in work progress, short tube canopy by the gunite concrete of previous cycle in advance press 6 °~8 ° oblique cutting angles and The guide pipe of the 1m long of pipe canopy design spacing embedment is reached the last necromancer body, to realize tunnel construction with no workroom in hole.
4. a kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop according to claim 1, It is characterized in that, the preliminary bracing includes the system anchor bolt radially squeezed into country rock along tunnel, hang on the steel of tunnel arch Muscle net exists along the steel arch-shelf of tunnel cross section erection, the lock foot anchoring stock squeezed into country rock and be supported on steel arch-shelf bottom, setting Big arch springing and injection at steel arch-shelf bottom is in the gunite concrete of tunnel arch.
5. a kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop according to claim 1, It is characterized in that, the big arch springing is the triangle being welded by I-steel, the bottom edge of big arch springing and the bevel edge by country rock side Weld the steel plate of 1.6cm thickness 0.5m wide on I-steel again respectively, bottom edge steel plate is vertical with the contour line of tunnel excavation, when any When the substrate of step enters basement rock, then cancel big arch springing.
6. a kind of three step Rapid Construction of Tunnels method of big arch springing based on pre-timbering with tubular prop according to claim 1, It is characterized in that, upper, middle and lower step accounts for the 1/3 of tunnel cross section respectively, and mutually away from 5m~1 times hole diameter, each cyclic advance is mistake 1~1.5m.
7. a kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop, which is characterized in that including short tube canopy Advance support structure, upper, middle and lower step, preliminary bracing structure, inverted arch, abutment wall, the filled layer and two for constituting tunnel excavation part Secondary lining cutting;
Tunnel arch of the short barrel vault advanced support structure setting before tunnel excavation part is with to tunnel excavation part Form protection, the described upper, middle and lower step respectively it is wrong away from;The preliminary bracing structure is respectively arranged at upper, middle and lower step The tunnel arch of position;Inverted arch, abutment wall, filled layer and secondary lining are respectively arranged at top, side wall, the bottom that part is completed in tunnel Portion;
Preliminary bracing structure includes the system anchor bolt radially squeezed into country rock along tunnel, hang on tunnel arch bar-mat reinforcement, edge The steel arch-shelf of tunnel cross section erection, is arranged in steel arch-shelf the lock foot anchoring stock squeezed into country rock and be supported on steel arch-shelf bottom Big arch springing and injection at bottom is in the gunite concrete of tunnel arch.
8. a kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop according to claim 7, It is characterized in that, the short barrel vault advanced support structure includes the steel pipe composition of more diameter 75mm, long 6~8m, and steel pipe is in depth The part entered into country rock is equipped with for setting the aperture for finishing grouting behind shaft or drift lining, on tunnel cross section, steel pipe in short tube boron steel pipe Be evenly arranged within the scope of 120 °~180 ° of tunnel arch with the spacing of 0.3~0.8m, on tunnel profile direction, steel pipe with 6 °~8 ° of oblique cutting angle is inserted upwardly into front of tunnel heading country rock, and longitudinal lap joint length is 1~2m.
9. a kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop according to claim 7, It is characterized in that, the upper, middle and lower step accounts for the 1/3 of tunnel cross section respectively, and mutually mistake is away from 5m~1 times hole diameter, and tunnel is opened Upper, middle and lower step is excavated when digging successively to recycle as one, each cyclic advance is 1~1.5m.
10. a kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop according to claim 7, It is characterized in that, the big arch springing is the triangle being welded by I-steel, the bottom edge of big arch springing and the bevel edge by country rock side Weld the steel plate of 1.6cm thickness 0.5m wide on I-steel again respectively, bottom edge steel plate is vertical with the contour line of tunnel excavation, when any When the substrate of step enters basement rock, then big arch springing is not provided with.
CN201711054349.3A 2017-10-31 2017-10-31 A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop Pending CN108278115A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711054349.3A CN108278115A (en) 2017-10-31 2017-10-31 A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711054349.3A CN108278115A (en) 2017-10-31 2017-10-31 A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop

Publications (1)

Publication Number Publication Date
CN108278115A true CN108278115A (en) 2018-07-13

Family

ID=62801293

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711054349.3A Pending CN108278115A (en) 2017-10-31 2017-10-31 A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop

Country Status (1)

Country Link
CN (1) CN108278115A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109268030A (en) * 2018-12-04 2019-01-25 湖南省交通规划勘察设计院有限公司 A kind of multistage set arch structure, pipe canopy set arch structure and its construction method for tunnel portal supporting
CN109339828A (en) * 2018-11-29 2019-02-15 中南大学 A kind of tunnel prestressing force inverted arch structure and its construction method
CN109538250A (en) * 2019-01-28 2019-03-29 中南大学 Device and method for branch at the beginning of tunnel with mould gunite concrete rapid construction
CN109578027A (en) * 2019-01-14 2019-04-05 中铁十局集团有限公司 Upper-soft lower-hard ground tunnel excavation support structure and tunnel excavation construction method
CN110005434A (en) * 2019-04-19 2019-07-12 中国矿业大学(北京) A kind of constant resistance and large deformation anchor cable control method of soft rock tunnel country rock large deformation disaster
CN110566236A (en) * 2019-10-18 2019-12-13 赤峰柴胡栏子黄金矿业有限公司 Pipe shed and steel support combined supporting device and supporting method
CN111188626A (en) * 2020-03-13 2020-05-22 长安大学 Open-type soft rock heading machine advance support system and use method thereof
CN112127900A (en) * 2020-09-07 2020-12-25 中国水利水电第十四工程局有限公司 Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body
CN112127910A (en) * 2020-09-21 2020-12-25 北京市市政工程研究院 Tunnel construction extra-front supporting sheath arch structure
CN112761675A (en) * 2021-01-26 2021-05-07 中铁八局集团昆明铁路建设有限公司 Construction method of composite support system for extremely-small-clear-distance obliquely downward-penetrating existing subway tunnel
CN112796769A (en) * 2020-12-24 2021-05-14 中铁十八局集团第五工程有限公司 Construction method of water-rich weak surrounding rock stratum tunnel
CN112963177A (en) * 2021-04-19 2021-06-15 山东建筑大学 Supporting method and structure for weak stratum shallow-buried large-section tunnel with hole
CN113175331A (en) * 2021-04-06 2021-07-27 中南大学 Weak surrounding rock fiber net pre-support structure and rapid construction equipment and method
CN114320311A (en) * 2021-12-31 2022-04-12 北京住总集团有限责任公司 Interval underground excavation method and support framework based on surrounding rock grade
WO2022122052A1 (en) * 2021-05-06 2022-06-16 中铁九局集团第七工程有限公司 Comprehensive construction method for shallow buried section of tunnel using urban railway mine tunneling method
CN115263322A (en) * 2022-08-09 2022-11-01 中铁十六局集团路桥工程有限公司 Construction method suitable for ultra-large cross-tunnel door hiding room of weak surrounding rock

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101614125A (en) * 2009-07-23 2009-12-30 中铁九局集团有限公司 V level surrounding rock tunnel job practices
CN101994513A (en) * 2010-10-30 2011-03-30 中铁十二局集团第二工程有限公司 Method for constructing tunnel by finishing full section curtain grouting from upper-half section
CN102226399A (en) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 Soft rock four-line large-span tunnel three-bench cable-bracing excavation construction method
CN102562074A (en) * 2012-02-03 2012-07-11 中铁四局集团第二工程有限公司 Construction method for composite stratum with hard top and soft bottom of large-section tunnel
CN104389618A (en) * 2014-10-13 2015-03-04 中铁二院重庆勘察设计研究院有限责任公司 Method for constructing multiple-arch tunnel hole body large room-free pipe shed support
CN104818991A (en) * 2015-03-30 2015-08-05 中铁二十四局集团福建铁路建设有限公司 Construction method of residual slope wash tunnel with shallow cover and unsymmetrical pressure
CN105298517A (en) * 2015-11-21 2016-02-03 中铁二十局集团第二工程有限公司 Soft and weak wall rock tunnel advance reinforced support construction method
CN207892615U (en) * 2017-10-31 2018-09-21 中南大学 A kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101614125A (en) * 2009-07-23 2009-12-30 中铁九局集团有限公司 V level surrounding rock tunnel job practices
CN101994513A (en) * 2010-10-30 2011-03-30 中铁十二局集团第二工程有限公司 Method for constructing tunnel by finishing full section curtain grouting from upper-half section
CN102226399A (en) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 Soft rock four-line large-span tunnel three-bench cable-bracing excavation construction method
CN102562074A (en) * 2012-02-03 2012-07-11 中铁四局集团第二工程有限公司 Construction method for composite stratum with hard top and soft bottom of large-section tunnel
CN104389618A (en) * 2014-10-13 2015-03-04 中铁二院重庆勘察设计研究院有限责任公司 Method for constructing multiple-arch tunnel hole body large room-free pipe shed support
CN104818991A (en) * 2015-03-30 2015-08-05 中铁二十四局集团福建铁路建设有限公司 Construction method of residual slope wash tunnel with shallow cover and unsymmetrical pressure
CN105298517A (en) * 2015-11-21 2016-02-03 中铁二十局集团第二工程有限公司 Soft and weak wall rock tunnel advance reinforced support construction method
CN207892615U (en) * 2017-10-31 2018-09-21 中南大学 A kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张婧;: "浅谈浅埋暗挖法隧道施工", 科技创新与应用, no. 13, pages 201 *
李季森;: "十堰四号隧道浅埋软弱围岩施工技术", 岩土工程界, no. 07, pages 1066 - 1070 *
柳长奔;张树;: "无工作室管棚技术的研究与应用", 现代隧道技术, no. 03, pages 98 - 102 *

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339828A (en) * 2018-11-29 2019-02-15 中南大学 A kind of tunnel prestressing force inverted arch structure and its construction method
CN109339828B (en) * 2018-11-29 2024-01-30 中南大学 Tunnel prestress inverted arch structure and construction method thereof
CN109268030A (en) * 2018-12-04 2019-01-25 湖南省交通规划勘察设计院有限公司 A kind of multistage set arch structure, pipe canopy set arch structure and its construction method for tunnel portal supporting
CN109268030B (en) * 2018-12-04 2024-03-22 湖南省交通规划勘察设计院有限公司 Multistage sleeve arch structure for tunnel portal support, pipe shed sleeve arch structure and construction method of pipe shed sleeve arch structure
CN109578027A (en) * 2019-01-14 2019-04-05 中铁十局集团有限公司 Upper-soft lower-hard ground tunnel excavation support structure and tunnel excavation construction method
CN109538250A (en) * 2019-01-28 2019-03-29 中南大学 Device and method for branch at the beginning of tunnel with mould gunite concrete rapid construction
CN109538250B (en) * 2019-01-28 2023-09-15 中南大学 Device and method for quick construction of tunnel primary support with mould sprayed concrete
CN110005434A (en) * 2019-04-19 2019-07-12 中国矿业大学(北京) A kind of constant resistance and large deformation anchor cable control method of soft rock tunnel country rock large deformation disaster
CN110566236B (en) * 2019-10-18 2024-03-08 赤峰柴胡栏子黄金矿业有限公司 Combined supporting device and supporting method for pipe shed and steel support
CN110566236A (en) * 2019-10-18 2019-12-13 赤峰柴胡栏子黄金矿业有限公司 Pipe shed and steel support combined supporting device and supporting method
CN111188626B (en) * 2020-03-13 2024-05-28 长安大学 Advanced support system of open type soft rock heading machine and application method of advanced support system
CN111188626A (en) * 2020-03-13 2020-05-22 长安大学 Open-type soft rock heading machine advance support system and use method thereof
CN112127900A (en) * 2020-09-07 2020-12-25 中国水利水电第十四工程局有限公司 Construction method for hidden half-wall and half-arch protection structure of exposed arch of shallow-buried bias tunnel penetrating through accumulation body
CN112127910A (en) * 2020-09-21 2020-12-25 北京市市政工程研究院 Tunnel construction extra-front supporting sheath arch structure
CN112127910B (en) * 2020-09-21 2022-11-08 北京市市政工程研究院 Tunnel construction extra-front supporting sheath arch structure
CN112796769A (en) * 2020-12-24 2021-05-14 中铁十八局集团第五工程有限公司 Construction method of water-rich weak surrounding rock stratum tunnel
CN112761675A (en) * 2021-01-26 2021-05-07 中铁八局集团昆明铁路建设有限公司 Construction method of composite support system for extremely-small-clear-distance obliquely downward-penetrating existing subway tunnel
CN113175331A (en) * 2021-04-06 2021-07-27 中南大学 Weak surrounding rock fiber net pre-support structure and rapid construction equipment and method
CN113175331B (en) * 2021-04-06 2023-12-19 中南大学 Rapid construction equipment and method for weak surrounding rock fiber net pre-supporting structure
CN112963177A (en) * 2021-04-19 2021-06-15 山东建筑大学 Supporting method and structure for weak stratum shallow-buried large-section tunnel with hole
WO2022122052A1 (en) * 2021-05-06 2022-06-16 中铁九局集团第七工程有限公司 Comprehensive construction method for shallow buried section of tunnel using urban railway mine tunneling method
CN114320311A (en) * 2021-12-31 2022-04-12 北京住总集团有限责任公司 Interval underground excavation method and support framework based on surrounding rock grade
CN115263322A (en) * 2022-08-09 2022-11-01 中铁十六局集团路桥工程有限公司 Construction method suitable for ultra-large cross-tunnel door hiding room of weak surrounding rock
CN115263322B (en) * 2022-08-09 2024-04-19 中铁十六局集团路桥工程有限公司 Construction method suitable for super-large-span tunnel storage door-to-door construction of weak surrounding rock

Similar Documents

Publication Publication Date Title
CN108278115A (en) A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop
CN207892615U (en) A kind of three step Rapid Construction of Tunnels structure of big arch springing based on pre-timbering with tubular prop
CN106337686B (en) Three layers of subway station canopy structure of rocky stratum tunneling and construction method
CN205742213U (en) Foundation pit supporting construction
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN110905530B (en) Stability control construction method for water-rich soft rock tunnel penetrating fault fracture zone
CN101864963A (en) Large-section loess tunnel construction method
CN111502696A (en) Dense-mesh type advanced support system of underground excavation tunnel and construction method
CN108487911A (en) The compound crossing method construction method of longspan tunnel bilateral wall under complex geological condition
CN110541721A (en) Support system and construction method for fully weathered surrounding rock tunnel in water-rich quicksand stratum
CN108457656A (en) A kind of unearthed method for tunnel construction
CN105909256A (en) Large-span weak surrounding rock tunnel construction method adopting face pre-reinforcement core soil reserving three-step temporary inverted arch technology
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN109973122A (en) A kind of tunnel reinforcement control method of wall rock loosening or soft rock large deformation
CN109056810A (en) The transverse direction that open cut or lid dig underground main structure below existing building digs construction and its construction method
CN109139018A (en) The method for tunnel construction and system that deep hole sleeve valve barrel grouting is combined with horizontal jet grouting
CN112855225B (en) Soft rock tunnel supporting construction method with high safety
CN107401411A (en) Step excavation construction method is strengthened in a kind of interim perpendicular support for being applied to IV grade of country rock Shallow depth bored tunnel
CN107060778B (en) Pass through super high-rise building group back filled region method for tunnel construction
CN104131566A (en) Method for constructing basement foundation pit without horizontal braces
CN207047867U (en) Shaped steel formula double-row pile foundation pit supporting system is inserted after outer row
CN206888994U (en) A kind of inclined shaft two serves as a contrast and pilot tunnel caunches device
CN104863613A (en) High-side-wall anchored primary support structure for rock strata underground excavation underground structure, and construction method of high-side-wall anchored primary support structure
CN115467690B (en) New structure system of shallow-buried large-span underground excavation subway station and construction method thereof
CN107503355A (en) Shaped steel formula double-row pile foundation pit supporting system and its construction method are inserted after outer row

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination