CN111827678A - A hoisting method of truss steel structure at the top of a silo - Google Patents
A hoisting method of truss steel structure at the top of a silo Download PDFInfo
- Publication number
- CN111827678A CN111827678A CN202010584094.7A CN202010584094A CN111827678A CN 111827678 A CN111827678 A CN 111827678A CN 202010584094 A CN202010584094 A CN 202010584094A CN 111827678 A CN111827678 A CN 111827678A
- Authority
- CN
- China
- Prior art keywords
- silo
- truss
- steel structure
- hoisting
- lower chord
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
- B66C13/08—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H7/00—Construction or assembling of bulk storage containers employing civil engineering techniques in situ or off the site
- E04H7/22—Containers for fluent solids, e.g. silos, bunkers; Supports therefor
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
技术领域technical field
本发明属于钢结构施工方法领域,具体涉及一种筒仓顶部桁架钢结构吊装方法。The invention belongs to the field of steel structure construction methods, in particular to a hoisting method for a truss steel structure at the top of a silo.
背景技术Background technique
目前,筒仓顶钢结构安装,大多数直接采用地面组装后整体吊装的方式进行安装,采用整体吊装的方法,由于整体桁架在地面安装后,重量很重,需要大型吊装机械进行吊装,一方面,吊装过程中施工难度大,平稳度很难保证,影响安装质量,另一方面需要大型机械吊装,浪费人力物力。At present, most of the silo roof steel structure installations are installed directly by the way of overall hoisting after ground assembly. The overall hoisting method is adopted. Since the overall truss is very heavy after being installed on the ground, large-scale hoisting machinery is required for hoisting. On the one hand, , During the hoisting process, the construction is difficult, the stability is difficult to guarantee, which affects the installation quality. On the other hand, large-scale mechanical hoisting is required, which wastes manpower and material resources.
发明内容SUMMARY OF THE INVENTION
本发明所要解决的技术问题是:提供一种筒仓顶部桁架钢结构吊装方法,解决了现有技术中整体吊装施工难度大质量难保证的问题。The technical problem to be solved by the present invention is to provide a hoisting method for the truss steel structure on the top of the silo, which solves the problem of high difficulty in overall hoisting construction and difficult quality assurance in the prior art.
本发明为解决上述技术问题采用以下技术方案:The present invention adopts the following technical solutions for solving the above-mentioned technical problems:
一种筒仓顶部桁架钢结构吊装方法,预先将筒仓顶部桁架钢结构划分为若干段,然后在筒仓顶部搭设临时支架,依次从筒仓顶部土建基础上方开始分段吊装,并且借助筒仓顶部临时支架对各段的部件进行组装。A method for hoisting a truss steel structure at the top of a silo. The truss steel structure at the top of a silo is divided into several sections in advance, and then temporary supports are erected on the top of the silo. The top temporary bracket assembles the components of each segment.
每一段筒仓顶部桁架钢结构均包括立柱、下弦杆、上弦杆、腹杆、横梁、屋架,吊装时,先安装桁架两端受力立柱,将立柱安装在筒仓两侧的土建基础上作为基础立柱,再吊装与之相接的横梁和屋架各自形成门型框架,然后依次吊装并安装相邻段的下弦杆、横梁、中间立柱、腹杆、上弦杆、屋架,直至筒仓顶部桁架施工完成。The truss steel structure at the top of each section of the silo includes uprights, lower chords, upper chords, webs, beams, and roof trusses. When hoisting, install the force-bearing uprights at both ends of the truss first, and install the uprights on the civil foundations on both sides of the silo. The foundation column, and then the beam and the roof truss connected to it are hoisted to form a door frame, and then the lower chord, beam, middle column, web rod, upper chord, and roof truss of adjacent sections are hoisted and installed in turn, until the construction of the truss on the top of the silo Finish.
在下弦杆安装位置侧面设置水平参照线标识。Set the horizontal reference line mark on the side of the lower chord installation position.
所述水平参照线为钢线,下弦杆直线度以钢线作为参照进行调节,下弦杆的起拱度通过临时支架上的千斤顶调节。The horizontal reference line is a steel wire, the straightness of the lower chord is adjusted with the steel wire as a reference, and the camber of the lower chord is adjusted by the jack on the temporary support.
采用临时支架作为桁架安装的受力点,桁架全部安装完成,检查无误后拆除临时支架。Temporary brackets are used as the stress points for truss installation. All truss installations are completed. After checking, the temporary brackets are removed.
该吊装方法适用于双筒仓结构,用于双筒仓结构时,先吊装两个筒仓相邻筒壁上方的桁架钢结构分段,再吊装两端筒壁上方的桁架钢结构分段,然后吊装中间连接的分段。This hoisting method is suitable for double silo structure. When used in double silo structure, first hoist the truss steel structure segments above the adjacent cylinder walls of the two silos, and then hoist the truss steel structure segments above the cylinder walls at both ends. Then hoist the segment connected in the middle.
每一段筒仓顶部桁架钢结构均包括立柱、下弦杆、上弦杆、腹杆、横梁、屋架,吊装时,按照如下步骤操作:The truss steel structure at the top of each section of silo includes columns, lower chords, upper chords, webs, beams, and roof trusses. When hoisting, follow the steps below:
步骤1、吊装两个相邻筒仓壁顶部土建基础上的立柱,作为基础立柱;
步骤2、吊装基础立柱之间的部分横梁和屋架各自形成门型框架;
步骤3、依次吊装并安装相邻两个筒仓壁之间钢结构桁架段的下弦杆、横梁、中间立柱、腹杆、上弦杆、屋架;Step 3. Hoist and install the lower chord, beam, middle column, web, upper chord and roof truss of the steel structure truss section between two adjacent silo walls in turn;
步骤4、吊装两个筒仓另外两端顶部土建基础上的立柱,作为基础立柱;
步骤5、吊装相应部分的横梁和屋架各自形成门型框架;Step 5. The beams and roof trusses of the corresponding parts are hoisted to form door-shaped frames;
步骤6、借助临时支架作为受力支撑,吊装桁架中间部分下弦杆,连接成整体,再依次安装下弦杆上侧横梁、中间立柱、腹杆、上弦杆、屋架;Step 6. With the temporary support as the force support, hoist the lower chord of the middle part of the truss, connect it into a whole, and then install the upper beam of the lower chord, the middle column, the web rod, the upper chord, and the roof truss in sequence;
步骤7、借助临时支架上的千斤顶调节下弦杆起拱度,并安装其余构件,直至桁架钢结构安装完成,拆除临时支架。
步骤2与步骤3之间还包括采用型钢将两段暂时连接为一个整体的步骤。Between
土建基础上的立柱及门型框架安装好后,安装下弦杆时,将下弦杆的一端与固定好的立柱连接,另一端放在临时支架上,临时支架上部设置千斤顶。After the column and the door frame on the civil foundation are installed, when installing the lower chord, connect one end of the lower chord to the fixed column, and place the other end on the temporary support. The upper part of the temporary support is provided with a jack.
吊装中间部分时,将下弦杆放于临时支架上,并且在下方设置千斤顶,桁架钢结构安装完成后,拆除临时支架。When hoisting the middle part, put the lower chord on the temporary support, and set up a jack below. After the truss steel structure is installed, remove the temporary support.
与现有技术相比,本发明具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:
1、筒仓顶部桁架钢结构散件吊装方法,具有很好的经济性,降低了施工难度,提高施工效率和质量。1. The hoisting method of the truss steel structure on the top of the silo has good economy, reduces the construction difficulty, and improves the construction efficiency and quality.
2、借助临时支架进行散件吊装后再组装,仓顶桁架钢结构安装平稳,施工安全可靠。2. With the help of temporary brackets, the parts are hoisted and then assembled. The steel structure of the warehouse roof truss is installed smoothly and the construction is safe and reliable.
3、散件吊装,构件重量轻,可选用小型吊装机械,有效控制施工成本。3. Bulk hoisting, the components are light in weight, and small hoisting machinery can be selected to effectively control the construction cost.
附图说明Description of drawings
图1为本发明筒仓顶桁架钢结构布置示意图。Figure 1 is a schematic diagram of the arrangement of the silo roof truss steel structure of the present invention.
图2为本发明1#筒仓仓顶桁架分段示意图。Fig. 2 is a schematic diagram of a section of a silo roof truss of the 1# silo of the present invention.
图3为本发明2#筒仓仓顶桁架分段示意图。Fig. 3 is a schematic diagram of a segmented silo roof truss of the 2# silo of the present invention.
图4为图2中沿A-A剖视图。FIG. 4 is a cross-sectional view along A-A in FIG. 2 .
图5为本发明临时支撑架分布示意图。FIG. 5 is a schematic diagram of the distribution of the temporary support frame of the present invention.
图6为图5中沿B-B剖视图。FIG. 6 is a cross-sectional view taken along the line B-B in FIG. 5 .
其中,图中的标识为:1-立柱;2-下弦杆;3-上弦杆;4-腹杆;5-横梁;6-屋架;7-临时支撑架;8-千斤顶;9-桁架;10-筒仓顶部。Among them, the signs in the figure are: 1-column; 2-lower chord; 3-upper chord; 4-web; 5-beam; 6-roof; 7-temporary support frame; 8-jack; 9-truss; 10 - Silo top.
具体实施方式Detailed ways
下面结合附图对本发明的结构及工作过程作进一步说明。The structure and working process of the present invention will be further described below in conjunction with the accompanying drawings.
一种筒仓顶部桁架钢结构吊装方法,预先将筒仓顶部桁架钢结构划分为若干段,然后在筒仓顶部搭设临时支架,依次从筒仓顶部土建基础上方开始分段吊装,并且借助筒仓顶部临时支架对各段的部件进行组装。A method for hoisting a truss steel structure at the top of a silo. The truss steel structure at the top of a silo is divided into several sections in advance, and then temporary supports are erected on the top of the silo. The top temporary bracket assembles the components of each segment.
具体实施例一,Specific embodiment one,
一种筒仓顶部桁架钢结构吊装方法,预先将筒仓顶部桁架钢结构划分为若干段,每一段筒仓顶部桁架钢结构均包括立柱1、下弦杆2、上弦杆3、腹杆4、横梁5、屋架6,吊装时,先安装桁架两端受力立柱,将立柱1安装在筒仓两侧的土建基础上作为基础立柱,再吊装与之相接的横梁5和屋架6各自形成门型框架,然后依次吊装并安装相邻段的下弦杆、横梁、中间立柱、腹杆、上弦杆、屋架,直至筒仓顶部桁架9施工完成。A method for hoisting a truss steel structure at the top of a silo. The truss steel structure at the top of a silo is divided into several sections in advance, and each section of the truss steel structure at the top of a silo includes a
在下弦杆安装位置侧面设置水平参照线标识。Set the horizontal reference line mark on the side of the lower chord installation position.
所述水平参照线为钢线,下弦杆直线度以钢线作为参照进行调节,下弦杆的起拱度通过临时支架上的千斤顶8调节。The horizontal reference line is a steel wire, the straightness of the lower chord is adjusted with the steel wire as a reference, and the camber of the lower chord is adjusted by the jack 8 on the temporary support.
采用临时支架作为桁架安装的受力点,桁架全部安装完成,检查无误后拆除临时支架。Temporary brackets are used as the stress points for truss installation. All truss installations are completed. After checking, the temporary brackets are removed.
该吊装方法适用于双筒仓结构,用于双筒仓结构时,先吊装两个筒仓相邻筒壁上方的桁架钢结构分段,再吊装两端筒壁上方的桁架钢结构分段,然后吊装中间连接的分段。This hoisting method is suitable for double silo structure. When used in double silo structure, first hoist the truss steel structure segments above the adjacent cylinder walls of the two silos, and then hoist the truss steel structure segments above the cylinder walls at both ends. Then hoist the segment connected in the middle.
每一段筒仓顶部桁架钢结构均包括立柱、下弦杆、上弦杆、腹杆、横梁、屋架,吊装时,按照如下步骤操作:The truss steel structure at the top of each section of silo includes columns, lower chords, upper chords, webs, beams, and roof trusses. When hoisting, follow the steps below:
步骤1、吊装两个相邻筒仓壁顶部土建基础上的立柱,作为基础立柱;
步骤2、吊装基础立柱之间的部分横梁和屋架各自形成门型框架;
步骤3、依次吊装并安装相邻两个筒仓壁之间钢结构桁架段的下弦杆、横梁、中间立柱、腹杆、上弦杆、屋架;Step 3. Hoist and install the lower chord, beam, middle column, web, upper chord and roof truss of the steel structure truss section between two adjacent silo walls in turn;
步骤4、吊装两个筒仓另外两端顶部土建基础上的立柱,作为基础立柱;
步骤5、吊装相应部分的横梁和屋架各自形成门型框架;Step 5. The beams and roof trusses of the corresponding parts are hoisted to form door-shaped frames;
步骤6、借助临时支架作为受力支撑,吊装桁架中间部分下弦杆,连接成整体,再依次安装下弦杆上侧横梁、中间立柱、腹杆、上弦杆、屋架;Step 6. With the temporary support as the force support, hoist the lower chord of the middle part of the truss, connect it into a whole, and then install the upper beam of the lower chord, the middle column, the web rod, the upper chord, and the roof truss in sequence;
步骤7、借助临时支架上的千斤顶调节下弦杆起拱度,并安装其余构件,直至桁架钢结构安装完成,拆除临时支架。
具体实施例二,如图1至图6所示,Specific embodiment two, as shown in Figure 1 to Figure 6,
以双筒仓顶部桁架分段吊装为例对该方案进行详细的介绍。The scheme is introduced in detail by taking the sectioned hoisting of the top truss of double silos as an example.
筒仓顶部10桁架9从右往左分为9段进行吊装,每段之间以高强螺栓连接。The
先在加工厂制作立柱等桁架所有构件,标记好构件号,检查加工质量无误后运至现场;First make all the components of the truss such as columns in the processing plant, mark the component numbers, check the processing quality, and then transport them to the site;
依据图纸上构件的安装位置,将构件放在筒仓下地面上相应位置,便于吊装。According to the installation position of the components on the drawing, place the components in the corresponding position on the ground under the silo to facilitate hoisting.
在筒仓顶上做吊装的准备工作,加工并依据图纸设置临时支撑架7,并于支撑架上放置千斤顶8;在桁架安装底座旁拉设钢丝线作为吊装的控制线。Make preparations for hoisting on the top of the silo, process and set up a
吊装时用临时支撑架7承载桁架的重量,将下弦杆2放于临时支撑架7上,再依次于下弦杆上方安装立柱1、上弦杆3、腹杆4、横梁5、屋架6等构件,吊装时用千斤顶8调整桁架的起拱度。When hoisting, use the
操作过程如下:The operation process is as follows:
1)依据图纸,在桁架悬空立柱1安装位置下方放置临时支撑架7,临时支撑架7上安装千斤顶8,并在下弦杆2安装位置旁设置钢线。1) According to the drawings, place a
2)先吊装第三段和第四段位于土建基础上的立柱1,及横梁5、屋架6,各自形成门型框架。2) First hoist the
3)吊装第四段位于两个筒仓之间的部分,并用型钢将第四段和第三段暂时连接为一个整体。3) Hoist the part of the fourth section between the two silos, and temporarily connect the fourth section and the third section as a whole with section steel.
4)吊装第五段下弦杆2,一端与第四段立柱1连接,另一端放在临时支撑架7和千斤顶 8上,并依次吊装横梁,5,其余立柱1,腹杆4,上弦杆3,屋架6。4) Hoist the fifth section
5)吊装第三段下弦杆2,一端与第三段立柱1连接,另一端放在临时支撑架7和千斤顶 8上。并依次吊装横梁5,其余立柱1,腹杆4,上弦杆3,屋架6。5) Hoist the third section
6)吊装第八段、第九段和第一段位于土建基础上的立柱1,及横梁5、屋架6,各自形成门型框架。再将下弦杆2放于临时支撑架7和千斤顶8上面,并依次吊装横梁5,其余立柱1,腹杆4,上弦杆3,屋架6。6) Hoist the eighth, ninth and first sections of the
7)吊装仓顶中间部位的第二段、第六段和第七段,下弦杆2放于临时支撑架8和千斤顶8上面,并依次吊装横梁5,其余立柱1,腹杆4,上弦杆3,屋架6。7) Hoist the second, sixth and seventh sections of the middle part of the silo roof. The
上述各段下弦杆2和上弦杆3以高强螺栓连接为整体,下弦杆的起拱度通过千斤顶8来调节,弦杆直线度以钢线作为参照进行调节。The
构件吊装完成,检查连接紧固情况,无误后拆除临时支撑架。After the hoisting of the components is completed, check the connection and tightness, and remove the temporary support frame if there is no error.
采用该吊装方法具有如下优点:Using this hoisting method has the following advantages:
1、施工效率高,降低施工难度。1. High construction efficiency and reduce construction difficulty.
2、仓顶桁架钢结构安装平稳,施工安全可靠。2. The steel structure of the warehouse roof truss is installed smoothly, and the construction is safe and reliable.
3、散件吊装,构件重量轻,可选用小型吊装机械,经济性好。3. Bulk hoisting, the components are light in weight, small hoisting machinery can be selected, and the economy is good.
通过参照以下附图对非限制性实施例所作的详细描述,本发明及其特征、外形和优点将会变得更加明显。在全部附图中相同的标记指示相同的部分。并未可以按照比例绘制附图,重点在于示出本发明的主旨。The present invention and its features, features and advantages will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings. Like numbers refer to like parts throughout the drawings. The drawings may not be drawn to scale, emphasis instead being placed upon illustrating the subject matter of the present invention.
以上对本发明的较佳实施例进行了描述。需要理解的是,本发明并不局限于上述特定实施方式,其中未尽详细描述的设备和结构应该理解为用本领域中的普通方式予以实施;任何熟悉本领域的技术人员,在不脱离本发明技术方案范围情况下,都可利用上述揭示的方法和技术内容对本发明技术方案做出许多可能的变动和修饰,或修改为等同变化的等效实施例,这并不影响本发明的实质内容。因此,凡是未脱离本发明技术方案的内容,依据本发明的技术实质对以上实施例所做的任何简单修改、等同变化及修饰,均仍属于本发明技术方案保护的范围内。The preferred embodiments of the present invention have been described above. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in ordinary ways in the art; any person skilled in the art, without departing from the present invention Within the scope of the technical solution of the invention, many possible changes and modifications can be made to the technical solution of the present invention by using the methods and technical contents disclosed above, or modified into equivalent embodiments with equivalent changes, which does not affect the essence of the present invention. . Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solutions of the present invention still fall within the protection scope of the technical solutions of the present invention.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010584094.7A CN111827678A (en) | 2020-06-24 | 2020-06-24 | A hoisting method of truss steel structure at the top of a silo |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010584094.7A CN111827678A (en) | 2020-06-24 | 2020-06-24 | A hoisting method of truss steel structure at the top of a silo |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN111827678A true CN111827678A (en) | 2020-10-27 |
Family
ID=72898009
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010584094.7A Pending CN111827678A (en) | 2020-06-24 | 2020-06-24 | A hoisting method of truss steel structure at the top of a silo |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111827678A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112696033A (en) * | 2020-12-25 | 2021-04-23 | 中冶天工集团有限公司 | On-site bulk loading method for ultra-large steel structure truss |
| CN115506476A (en) * | 2022-10-31 | 2022-12-23 | 山西五建集团有限公司 | A structural installation method for long-distance steel frame traffic corridors |
| CN116062609A (en) * | 2023-03-16 | 2023-05-05 | 中国建筑第四工程局有限公司 | A self-adaptive vertical rotation lifting construction method for long-span steel structures |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202706298U (en) * | 2012-07-26 | 2013-01-30 | 中国神华能源股份有限公司 | Silo top with corridor |
| CN106401252A (en) * | 2016-11-22 | 2017-02-15 | 河南工大设计研究院 | Flat roof of large-diameter silo and silo |
| CN107143145A (en) * | 2017-04-19 | 2017-09-08 | 浙江中南建设集团钢结构有限公司 | A kind of steel truss structure segmentation overhead connection and synchronous discharging method |
| JP2018044318A (en) * | 2016-09-13 | 2018-03-22 | 大成建設株式会社 | Silo roof construction method and silo roof structure |
| CN208934503U (en) * | 2018-09-26 | 2019-06-04 | 中国电力工程顾问集团西北电力设计院有限公司 | A kind of silo top trestle supporting structure |
-
2020
- 2020-06-24 CN CN202010584094.7A patent/CN111827678A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202706298U (en) * | 2012-07-26 | 2013-01-30 | 中国神华能源股份有限公司 | Silo top with corridor |
| JP2018044318A (en) * | 2016-09-13 | 2018-03-22 | 大成建設株式会社 | Silo roof construction method and silo roof structure |
| CN106401252A (en) * | 2016-11-22 | 2017-02-15 | 河南工大设计研究院 | Flat roof of large-diameter silo and silo |
| CN107143145A (en) * | 2017-04-19 | 2017-09-08 | 浙江中南建设集团钢结构有限公司 | A kind of steel truss structure segmentation overhead connection and synchronous discharging method |
| CN208934503U (en) * | 2018-09-26 | 2019-06-04 | 中国电力工程顾问集团西北电力设计院有限公司 | A kind of silo top trestle supporting structure |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112696033A (en) * | 2020-12-25 | 2021-04-23 | 中冶天工集团有限公司 | On-site bulk loading method for ultra-large steel structure truss |
| CN115506476A (en) * | 2022-10-31 | 2022-12-23 | 山西五建集团有限公司 | A structural installation method for long-distance steel frame traffic corridors |
| CN116062609A (en) * | 2023-03-16 | 2023-05-05 | 中国建筑第四工程局有限公司 | A self-adaptive vertical rotation lifting construction method for long-span steel structures |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106836498B (en) | Hoisting construction method for steel truss of grand stand roof of super-large span stadium | |
| CN104929373B (en) | Large span Square Steel Tubes Truss and its accumulation slippage construction method | |
| CN103866986B (en) | Long span variable cross-section bolted spherical node net shell mounting method | |
| CN111827678A (en) | A hoisting method of truss steel structure at the top of a silo | |
| CN111794529A (en) | Modular construction hoisting method for arch type space pipe truss steel structure system | |
| CN221567819U (en) | Quick construction device for horizontal structure in super high-rise core tube | |
| CN114837440B (en) | Construction method of large-span arch-type steel truss roof | |
| CN219011920U (en) | Support system of floor-free template support | |
| CN108797350B (en) | Tower column inner and outer stiff skeleton device and construction method thereof | |
| CN111188281A (en) | Transverse moving support system for prefabricated beam frame facility working machinery and construction method | |
| CN217266885U (en) | Steel construction assembled landing stage convenient to integral hoisting | |
| CN117145268A (en) | Jig frame supporting system for steel structure sliding and steel structure construction method | |
| CN112411753B (en) | Construction method of large-span suspended steel truss girder structure | |
| CN210563531U (en) | Steel structure support for building protection | |
| CN112431431B (en) | Reinforcement construction method for steel structure factory building in crane beam dismantling | |
| CN212082851U (en) | Vertical static load test structure of bridge floor crane | |
| CN212612038U (en) | Assembled arch rib erects changes hoisting frame | |
| CN107237515A (en) | The support meanss and its application method of circular steel truss structure | |
| CN119243589B (en) | Large-span floor arch structure installation method with arch foot prestress balance cable | |
| CN218880592U (en) | An integrated platform for construction and protection of cover beams | |
| CN117211534B (en) | Driving sliding construction method for steel structure of roof grid in large garbage pond | |
| CN111535182A (en) | Tubular bridge girder erection method | |
| CN219621621U (en) | A detachable gate frame suitable for four-lane cantilever | |
| CN221941139U (en) | A fully welded steel box truss composite beam on-site out-of-place assembly device | |
| CN116657492B (en) | Large cantilever wing-spreading steel box girder hoisting construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20201027 |